DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 101 (May 24, 2018)

Page Range24094-24094
FR Document2018-11177

Federal Register, Volume 83 Issue 101 (Thursday, May 24, 2018)
[Federal Register Volume 83, Number 101 (Thursday, May 24, 2018)]
[Notices]
[Page 24094]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-11177]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP16-121-000]


Notice of Revised Schedule for Environmental Review of the Fields 
Point Liquefaction Project, National Grid LNG, LLC

May 18, 2018.
    This notice identifies the Federal Energy Regulatory Commission 
staff's revised schedule for the completion of the environmental 
assessment (EA) for National Grid LNG, LLC's (National Grid) Fields 
Point Liquefaction Project. The original notice of schedule, issued on 
September 15, 2017, identified March 30, 2018, as the EA issuance date. 
Due to staff's request for supplemental engineering information that 
was recently filed by National Grid, staff has revised the schedule for 
issuance of the EA.

Schedule for Environmental Review

Issuance of EA--June 25, 2018
90-Day Federal Authorization Decision Deadline--September 23, 2018
    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP16-121), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.

Kimberly D. Bose,
 Secretary.
[FR Doc. 2018-11177 Filed 5-23-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                24094                         Federal Register / Vol. 83, No. 101 / Thursday, May 24, 2018 / Notices

                                                   Total Estimated Number of Annual                     DEPARTMENT OF ENERGY                                  such as orders, notices, and rule
                                                Burden Hours: 121,900.                                                                                        makings.
                                                                                                        Federal Energy Regulatory
                                                   Abstract: The ED 524B form and                                                                             Kimberly D. Bose,
                                                                                                        Commission
                                                instructions are used in order for                                                                            Secretary.
                                                grantees to meet Department of                                                                                [FR Doc. 2018–11177 Filed 5–23–18; 8:45 am]
                                                Education (ED) deadline dates for                       [Docket No. CP16–121–000]
                                                                                                                                                              BILLING CODE 6717–01–P
                                                submission of performance reports for                   Notice of Revised Schedule for
                                                ED discretionary grant programs.                        Environmental Review of the Fields
                                                Recipients of multi-year discretionary                  Point Liquefaction Project, National                  DEPARTMENT OF ENERGY
                                                grants must submit an annual                            Grid LNG, LLC
                                                performance report for each year                                                                              Federal Energy Regulatory
                                                funding has been approved in order to                   May 18, 2018.                                         Commission
                                                receive a continuation award. The                          This notice identifies the Federal
                                                annual performance report should                        Energy Regulatory Commission staff’s                  [Docket No. EL18–115–000]
                                                demonstrate whether substantial                         revised schedule for the completion of
                                                progress has been made toward meeting                   the environmental assessment (EA) for                 Notice of Filing: Startrans IO, LLC
                                                the approved goals and objectives of the                National Grid LNG, LLC’s (National                       Take notice that on May 14, 2018,
                                                project. ED program offices may also                    Grid) Fields Point Liquefaction Project.              Startrans IO, L.L.C. submitted a
                                                require recipients of ‘‘forward funded’’                The original notice of schedule, issued               response to the March 15, 2018 Show
                                                grants that are awarded funds for their                 on September 15, 2017, identified                     Cause Order.1
                                                entire multi-year project up-front in a                 March 30, 2018, as the EA issuance
                                                                                                                                                                 Any person desiring to intervene or to
                                                single grant award to submit the ED                     date. Due to staff’s request for
                                                                                                                                                              protest this filing must file in
                                                524B on an annual basis. In addition,                   supplemental engineering information
                                                                                                                                                              accordance with Rules 211 and 214 of
                                                ED program offices may also require                     that was recently filed by National Grid,
                                                                                                                                                              the Commission’s Rules of Practice and
                                                                                                        staff has revised the schedule for
                                                recipients to use the ED 524B to submit                                                                       Procedure (18 CFR 385.211, 385.214).
                                                                                                        issuance of the EA.
                                                their final performance reports to                                                                            Protests will be considered by the
                                                demonstrate project success, impact and                 Schedule for Environmental Review                     Commission in determining the
                                                outcomes. In both the annual and final                                                                        appropriate action to be taken, but will
                                                                                                        Issuance of EA—June 25, 2018
                                                performance reports, grantees are                                                                             not serve to make protestants parties to
                                                                                                        90-Day Federal Authorization Decision                 the proceeding. Any person wishing to
                                                required to provide data on established
                                                                                                           Deadline—September 23, 2018                        become a party must file a notice of
                                                performance measures for the grant
                                                program (e.g., Government Performance                      If a schedule change becomes                       intervention or motion to intervene, as
                                                                                                        necessary, additional notice will be                  appropriate. Such notices, motions, or
                                                and Results Act measures) and on
                                                                                                        provided so that the relevant agencies                protests must be filed on or before the
                                                project performance measures that were
                                                                                                        are kept informed of the project’s                    comment date. Anyone filing a motion
                                                included in the grantee’s approved grant                progress.
                                                application. The ED 524B also contains                                                                        to intervene or protest must serve a copy
                                                                                                        Additional Information                                of that document on the Applicant.
                                                a number of questions related to project
                                                financial data such as Federal and non-                                                                          The Commission encourages
                                                                                                           In order to receive notification of the            electronic submission of protests and
                                                Federal expenditures and indirect cost                  issuance of the EA and to keep track of               interventions in lieu of paper using the
                                                information. Performance reporting                      all formal issuances and submittals in                ‘‘eFiling’’ link at http://www.ferc.gov.
                                                requirements are found in 34 CFR 74.51,                 specific dockets, the Commission offers               Persons unable to file electronically
                                                75.118, 75.253, 75.590 and 80.40 of the                 a free service called eSubscription. This             should submit an original and 5 copies
                                                Education Department General                            can reduce the amount of time you                     of the protest or intervention to the
                                                Administrative Regulations.                             spend researching proceedings by                      Federal Energy Regulatory Commission,
                                                   The 524B is being revised to collect                 automatically providing you with                      888 First Street NE, Washington, DC
                                                additional information to sufficiently                  notification of these filings, document               20426.
                                                monitor states on data security                         summaries, and direct links to the                       This filing is accessible on-line at
                                                requirements for grant programs.                        documents. Go to www.ferc.gov/docs-                   http://www.ferc.gov, using the
                                                                                                        filing/esubscription.asp.                             ‘‘eLibrary’’ link and is available for
                                                  Dated: May 21, 2018.                                     Additional information about the                   review in the Commission’s Public
                                                Stephanie Valentine,                                    project is available from the                         Reference Room in Washington, DC.
                                                Acting Director, Information Collection                 Commission’s Office of External Affairs               There is an ‘‘eSubscription’’ link on the
                                                Clearance Division, Office of the Chief Privacy         at (866) 208–FERC or on the FERC                      website that enables subscribers to
                                                Officer, Office of Management.                          website (www.ferc.gov). Using the                     receive email notification when a
                                                [FR Doc. 2018–11105 Filed 5–23–18; 8:45 am]             ‘‘eLibrary’’ link, select ‘‘General Search’’          document is added to a subscribed
                                                BILLING CODE 4000–01–P                                  from the eLibrary menu, enter the                     docket(s). For assistance with any FERC
                                                                                                        selected date range and ‘‘Docket                      Online service, please email
                                                                                                        Number’’ excluding the last three digits              FERCOnlineSupport@ferc.gov, or call
                                                                                                        (i.e., CP16–121), and follow the
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                                                                              (866) 208–3676 (toll free). For TTY, call
                                                                                                        instructions. For assistance with access              (202) 502–8659.
                                                                                                        to eLibrary, the helpline can be reached                 Comment Date: 5:00 p.m. Eastern time
                                                                                                        at (866) 208–3676, TTY (202) 502–8659,                on June 4, 2018.
                                                                                                        or at FERCOnlineSupport@ferc.gov. The
                                                                                                        eLibrary link on the FERC website also                  1 Alcoa Power Generation, Inc.—Long Sault
                                                                                                        provides access to the texts of formal                Division, et al., 162 FERC ¶ 61,224 (2018) (Show
                                                                                                        documents issued by the Commission,                   Cause Order).



                                           VerDate Sep<11>2014   18:10 May 23, 2018   Jkt 244001   PO 00000   Frm 00014   Fmt 4703   Sfmt 4703   E:\FR\FM\24MYN1.SGM   24MYN1



Document Created: 2018-05-24 00:05:15
Document Modified: 2018-05-24 00:05:15
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 24094 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR