83_FR_24196 83 FR 24095 - Notice of Schedule for Environmental Review of the Lambertville East Expansion Project: Texas Eastern Transmission, LP

83 FR 24095 - Notice of Schedule for Environmental Review of the Lambertville East Expansion Project: Texas Eastern Transmission, LP

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 101 (May 24, 2018)

Page Range24095-24095
FR Document2018-11178

Federal Register, Volume 83 Issue 101 (Thursday, May 24, 2018)
[Federal Register Volume 83, Number 101 (Thursday, May 24, 2018)]
[Notices]
[Page 24095]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-11178]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-26-000]


Notice of Schedule for Environmental Review of the Lambertville 
East Expansion Project: Texas Eastern Transmission, LP

May 18, 2018.
    On December 7, 2017, Texas Eastern Transmission, LP (Texas Eastern) 
filed an application in Docket No. CP18-26-000 requesting a Certificate 
of Public Convenience and Necessity pursuant to sections 7(b) and 7(c) 
of the Natural Gas Act to abandon, construct, and operate certain 
natural gas pipeline facilities at its existing Lambertville Compressor 
Station in Hunterdon County, New Jersey. The proposed project is known 
as the Lambertville East Expansion Project (Project), and would provide 
about 60 million cubic feet of natural gas per day of incremental 
pipeline transportation service to existing city gates in New Jersey.
    On December 20, 2017, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA) for the Project. This instant notice 
identifies the FERC staff's planned schedule for the completion of the 
EA for the Project.

Schedule for Environmental Review

Issuance of EA--July 24, 2018
90-day Federal Authorization Decision Deadline--October 22, 2018

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Texas Eastern proposes to abandon by removal two 5,000 horsepower 
natural gas-fired turbine compressor units and appurtenant facilities, 
and replace these units with two new 8,600 horsepower natural gas-fired 
turbine compressor units and appurtenant facilities at its existing 
Lambertville Compressor Station in Hunterdon County, New Jersey. In 
addition to the incremental pipeline transportation service, the 
Project is also proposed to comply with new air emissions regulations 
under the New Jersey Reasonably Achievable Control Technology program.

Background

    On January 10, 2018, the Commission issued a Notice of Intent to 
Prepare an Environmental Assessment for the Proposed Lambertville East 
Expansion Project and Request for Comments on Environmental Issues 
(NOI). The NOI was sent to affected landowners; federal, state, and 
local government agencies; elected officials; Native American tribes; 
other interested parties; and local libraries and newspapers. In 
response to the NOI, the Commission received comments from the U.S. 
Environmental Protection Agency (EPA), the Township of West Amwell, and 
seven residents. The EPA commented that the EA should include a full 
discussion of purpose and need of the Project; an evaluation of 
alternatives; a general conformity applicability analysis; and an 
analysis of cumulative, indirect, and secondary impacts, and 
environmental justice. The Township of West Amwell expressed Project 
concerns about increases in toxic air emissions and pollutants and 
impacts on residents from construction and operation of the compressor 
station. The seven residents also expressed Project concerns about the 
following:
     Impacts on air quality, nearby high consequence areas, and 
health;
     compressor type and size;
     effects on local communities, nearby properties, and 
property rights and values;
     direct harm to commercial, cultural, and historical 
interests and open space;
     water quality impacts;
     contaminated groundwater and soil;
     traffic impacts;
     impacts on tourism; and
     effects on quality of life.
    All substantive comments will be addressed in the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP18-26), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rulemakings.

Kimberly D. Bose,
 Secretary.
[FR Doc. 2018-11178 Filed 5-23-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                                              Federal Register / Vol. 83, No. 101 / Thursday, May 24, 2018 / Notices                                                    24095

                                                  Dated: May 18, 2018.                                  units and appurtenant facilities at its                  Additional information about the
                                                Kimberly D. Bose,                                       existing Lambertville Compressor                      Project is available from the
                                                Secretary.                                              Station in Hunterdon County, New                      Commission’s Office of External Affairs
                                                [FR Doc. 2018–11154 Filed 5–23–18; 8:45 am]             Jersey. In addition to the incremental                at (866) 208–FERC or on the FERC
                                                BILLING CODE 6717–01–P                                  pipeline transportation service, the                  website (www.ferc.gov). Using the
                                                                                                        Project is also proposed to comply with               ‘‘eLibrary’’ link, select ‘‘General Search’’
                                                                                                        new air emissions regulations under the               from the eLibrary menu, enter the
                                                DEPARTMENT OF ENERGY                                    New Jersey Reasonably Achievable                      selected date range and ‘‘Docket
                                                                                                        Control Technology program.                           Number’’ excluding the last three digits
                                                Federal Energy Regulatory                                                                                     (i.e., CP18–26), and follow the
                                                Commission                                              Background
                                                                                                                                                              instructions. For assistance with access
                                                [Docket No. CP18–26–000]
                                                                                                           On January 10, 2018, the Commission                to eLibrary, the helpline can be reached
                                                                                                        issued a Notice of Intent to Prepare an               at (866) 208–3676, TTY (202) 502–8659,
                                                Notice of Schedule for Environmental                    Environmental Assessment for the                      or at FERCOnlineSupport@ferc.gov. The
                                                Review of the Lambertville East                         Proposed Lambertville East Expansion                  eLibrary link on the FERC website also
                                                Expansion Project: Texas Eastern                        Project and Request for Comments on                   provides access to the texts of formal
                                                Transmission, LP                                        Environmental Issues (NOI). The NOI                   documents issued by the Commission,
                                                                                                        was sent to affected landowners; federal,             such as orders, notices, and
                                                May 18, 2018.                                           state, and local government agencies;                 rulemakings.
                                                   On December 7, 2017, Texas Eastern                   elected officials; Native American tribes;
                                                Transmission, LP (Texas Eastern) filed                  other interested parties; and local                   Kimberly D. Bose,
                                                an application in Docket No. CP18–26–                   libraries and newspapers. In response to              Secretary.
                                                000 requesting a Certificate of Public                  the NOI, the Commission received                      [FR Doc. 2018–11178 Filed 5–23–18; 8:45 am]
                                                Convenience and Necessity pursuant to                   comments from the U.S. Environmental                  BILLING CODE 6717–01–P
                                                sections 7(b) and 7(c) of the Natural Gas               Protection Agency (EPA), the Township
                                                Act to abandon, construct, and operate                  of West Amwell, and seven residents.
                                                certain natural gas pipeline facilities at              The EPA commented that the EA should                  DEPARTMENT OF ENERGY
                                                its existing Lambertville Compressor                    include a full discussion of purpose and
                                                Station in Hunterdon County, New                        need of the Project; an evaluation of                 Federal Energy Regulatory
                                                Jersey. The proposed project is known                   alternatives; a general conformity                    Commission
                                                as the Lambertville East Expansion                      applicability analysis; and an analysis of            [Docket Nos. EL18–68–000; EL18–69–000]
                                                Project (Project), and would provide                    cumulative, indirect, and secondary
                                                about 60 million cubic feet of natural                  impacts, and environmental justice. The               Notice of Filing: Transource Maryland,
                                                gas per day of incremental pipeline                     Township of West Amwell expressed                     LLC; Transource Pennsylvania, LLC
                                                transportation service to existing city                 Project concerns about increases in toxic
                                                gates in New Jersey.                                    air emissions and pollutants and                         Take notice that on May 10, 2018,
                                                   On December 20, 2017, the Federal                    impacts on residents from construction                Transource Maryland, LLC and
                                                Energy Regulatory Commission                            and operation of the compressor station.              Transource Pennsylvania, LLC
                                                (Commission or FERC) issued its Notice                  The seven residents also expressed                    submitted a response to the March 15,
                                                of Application for the Project. Among                   Project concerns about the following:                 2018 Show Cause Order.1
                                                other things, that notice alerted agencies                 • Impacts on air quality, nearby high                 Any person desiring to intervene or to
                                                issuing federal authorizations of the                   consequence areas, and health;                        protest this filing must file in
                                                requirement to complete all necessary                      • compressor type and size;                        accordance with Rules 211 and 214 of
                                                reviews and to reach a final decision on                   • effects on local communities,                    the Commission’s Rules of Practice and
                                                a request for a federal authorization                   nearby properties, and property rights                Procedure (18 CFR 385.211, 385.214).
                                                within 90 days of the date of issuance                  and values;                                           Protests will be considered by the
                                                of the Commission staff’s Environmental                    • direct harm to commercial, cultural,             Commission in determining the
                                                Assessment (EA) for the Project. This                   and historical interests and open space;              appropriate action to be taken, but will
                                                instant notice identifies the FERC staff’s                 • water quality impacts;                           not serve to make protestants parties to
                                                planned schedule for the completion of                     • contaminated groundwater and soil;               the proceeding. Any person wishing to
                                                the EA for the Project.                                    • traffic impacts;                                 become a party must file a notice of
                                                                                                           • impacts on tourism; and                          intervention or motion to intervene, as
                                                Schedule for Environmental Review                          • effects on quality of life.                      appropriate. Such notices, motions, or
                                                Issuance of EA—July 24, 2018                               All substantive comments will be                   protests must be filed on or before the
                                                90-day Federal Authorization Decision                   addressed in the EA.                                  comment date. Anyone filing a motion
                                                   Deadline—October 22, 2018                                                                                  to intervene or protest must serve a copy
                                                                                                        Additional Information
                                                   If a schedule change becomes                                                                               of that document on the Applicant.
                                                necessary, additional notice will be                       In order to receive notification of the               The Commission encourages
                                                provided so that the relevant agencies                  issuance of the EA and to keep track of               electronic submission of protests and
                                                are kept informed of the Project’s                      all formal issuances and submittals in                interventions in lieu of paper using the
                                                progress.                                               specific dockets, the Commission offers               ‘‘eFiling’’ link at http://www.ferc.gov.
                                                                                                        a free service called eSubscription. This
sradovich on DSK3GMQ082PROD with NOTICES




                                                Project Description                                                                                           Persons unable to file electronically
                                                                                                        can reduce the amount of time you                     should submit an original and 5 copies
                                                  Texas Eastern proposes to abandon by                  spend researching proceedings by                      of the protest or intervention to the
                                                removal two 5,000 horsepower natural                    automatically providing you with                      Federal Energy Regulatory Commission,
                                                gas-fired turbine compressor units and                  notification of these filings, document
                                                appurtenant facilities, and replace these               summaries, and direct links to the                      1 Alcoa Power Generation, Inc.—Long Sault
                                                units with two new 8,600 horsepower                     documents. Go to www.ferc.gov/docs-                   Division, et al., 162 FERC ¶ 61,224 (2018) (Show
                                                natural gas-fired turbine compressor                    filing/esubscription.asp.                             Cause Order).



                                           VerDate Sep<11>2014   18:10 May 23, 2018   Jkt 244001   PO 00000   Frm 00015   Fmt 4703   Sfmt 4703   E:\FR\FM\24MYN1.SGM   24MYN1



Document Created: 2018-05-24 00:05:13
Document Modified: 2018-05-24 00:05:13
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 24095 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR