On May 14, 2018, the U.S. Nuclear Regulatory Commission (NRC) solicited comments on Draft Regulatory Guide (DG), DG-5048, ``Standard Format and Content of Physical Security Plans, Training and Qualifications Plans, and Safeguards Contingency Plans for Nuclear Power Plants.'' The public comment period was originally scheduled to close on July 13, 2018. The NRC has decided to extend the public comment period by 30 days to allow more time for members of the public to develop and submit their comments.

Federal Register, Volume 83 Issue 103 (Tuesday, May 29, 2018)
[Federal Register Volume 83, Number 103 (Tuesday, May 29, 2018)]
[Notices]
[Pages 24510-24511]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-11460]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2018-0092]


Standard Format and Content of Physical Security Plans, Training 
and Qualifications Plans, and Safeguards Contingency Plans for Nuclear 
Power Plants

AGENCY: Nuclear Regulatory Commission.

ACTION: Draft regulatory guide; extension of comment period.

-----------------------------------------------------------------------

SUMMARY: On May 14, 2018, the U.S. Nuclear Regulatory Commission (NRC) 
solicited comments on Draft Regulatory Guide (DG), DG-5048, ``Standard 
Format and Content of Physical Security Plans, Training and 
Qualifications Plans, and Safeguards Contingency Plans for Nuclear 
Power Plants.'' The public comment period was originally scheduled to 
close on July 13, 2018. The NRC has decided to extend the public 
comment period by 30 days to allow more time for members of the public 
to develop and submit their comments.

DATES: The due date for comments requested in the document published on 
May 14, 2018 (83 FR 22297), is extended. Comments should be filed no 
later than August 13, 2018. Comments received after this date will be 
considered, if it is practical to do so, but

[[Page 24511]]

the Commission is able to ensure consideration only for comments 
received on or before this date.

ADDRESSES: You may submit comments by any of the following methods:
     Federal Rulemaking website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0092. Address 
questions about NRC dockets to Jennifer Borges; telephone: 301-287-
9127; email: Jennifer.Borges@nrc.gov. For technical questions, contact 
the individuals listed in the FOR FURTHER INFORMATION CONTACT section 
of this document.
     Mail comments to: May Ma, Office of Administration, Mail 
Stop: TWFN 7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001. For additional direction on obtaining information and 
submitting comments, see ``Obtaining Information and Submitting 
Comments'' in the SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Dennis Gordon, Office of Nuclear 
Security and Incident Response, telephone: 301-287-3633, email: 
Dennis.Gordon@nrc.gov and Mekonen Bayssie, Office of Nuclear Regulatory 
Research; telephone: 301-415-1699, email: Mekonen.Bayssie@nrc.gov. Both 
are staff of the U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001.

SUPPLEMENTARY INFORMATION: 

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2018-0092 when contacting the NRC 
about the availability of information regarding this action. You may 
obtain publically-available information related to this action, by any 
of the following methods:
     Federal Rulemaking website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0092.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. DG-
5048 is available in ADAMS under Accession No. ML17124A490.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments

    Please include Docket ID NRC-2018-0092 in your comment submission. 
The NRC cautions you not to include identifying or contact information 
that you do not want to be publicly disclosed in your comment 
submission. The NRC will post all comment submissions at http://www.regulations.gov as well as enters the comment submissions into 
ADAMS. The NRC does not routinely edit comment submissions to remove 
identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment submissions into ADAMS.

II. Background

    On May 14, 2018 (83 FR 22297), the NRC solicited comments on DG-
5048, ``Standard Format and Content of Physical Security Plans, 
Training and Qualifications Plans, and Safeguards Contingency Plans for 
Nuclear Power Plants'' (ADAMS Accession No. ML17124A490). The public 
comment period was originally scheduled to end on July 13, 2018. On May 
14, 2018, the Nuclear Energy Institute (NEI) requested that the comment 
period be extended, stating that ``the change would allow NEI and its 
members' sufficient time to perform a thorough review of the document 
consistent with other work priorities'' (ADAMS Accesion No. 
ML18136A546). The NRC agreed to the request because of the length and 
comprehensiveness of this DG. Accordingly, the NRC is extending the 
public comment period on this document until August 13, 2018, to allow 
more time for members of the public to submit their comments.

    Dated at Rockville, Maryland, this 23rd day of May, 2018.

    For the Nuclear Regulatory Commission.
Thomas H. Boyce,
Chief, Regulatory Guidance and Generic Issues Branch, Division of 
Engineering, Office of Nuclear Regulatory Research.
[FR Doc. 2018-11460 Filed 5-25-18; 8:45 am]
 BILLING CODE 7590-01-P



                                               24510                          Federal Register / Vol. 83, No. 103 / Tuesday, May 29, 2018 / Notices

                                               procedures, especially their                            preferability; waste prevention; and                  determination of whether such
                                               participation in agency Accident                        ultimate disposal, if appropriate;                    proceedings or representations are
                                               Review Boards (ARBs) and safety and                        c. Developing and implementing an                  appropriate in a given case, are
                                               health training.                                        agency plan for energy conservation                   delegated exclusively to the Solicitor.
                                                  f. Providing employees appropriate                   through changes in procurement                           9. Reservation of Secretary’s Authority
                                               personal protective and safety/                         practices, investment in energy efficient             and Responsibility.
                                               occupational health equipment.                          technology, and reduction of demand;                     A. The submission of reports and
                                                  g. Conducting analyses of Agency jobs                   d. Designating an Agency Recycling                 recommendations to the President and
                                               and ensuring that all workplaces are                    Coordinator to coordinate the                         the Congress is reserved to the
                                               surveyed to identify and eliminate or                   development of an effective agency                    Secretary.
                                               minimize possible ergonomic risk                        waste reduction and recycling program,                   B. This Secretary’s Order does not
                                               factors.                                                and emphasize agency purchase and use                 affect the authorities and
                                                  h. Acquiring, to the extent practicable,             of recycled and environmentally                       responsibilities of the Office of
                                               tools, equipment, and computer                          preferable products and services;                     Inspector General under the Inspector
                                               accessory furniture that is adjustable                     e. Providing data and information on               General Act of 1978, as amended, or
                                               and adaptable to those using them.                      agency activity for incorporation into                under Secretary’s Order 4–2006.
                                                  i. Assuring that agency employees                    Departmental reports;                                    10. Re-delegation of Authority. Unless
                                               participate in educational and training                    f. Designating facility energy                     identified as non-delegable under this
                                               experiences necessary to carry out their                supervisors in Department-operated                    Order, authorities delegated within this
                                               assigned duties in a safe and healthful                 facilities and ensuring a sufficient                  Order may be re-delegated, provided,
                                               manner.                                                 number of trained energy managers                     however, that re-delegation shall in no
                                                  j. Assuring, through partnership with                throughout the Department to                          way diminish the delegating official’s
                                               appropriate unions, that employee                       implement the provisions of law and                   responsibility.
                                               representatives have the opportunity to                 regulation relating to energy and water                  11. Effective Date. This order is
                                               participate in educational training                     conservation;                                         effective on May 27, 2018.
                                                                                                          g. Where programs include a project                  Dated: May 14, 2018.
                                               experiences necessary to carry out their
                                                                                                       or activity involving construction or
                                               responsibilities.                                                                                             R. Alexander Acosta,
                                                                                                       leasing of property, ensuring that the
                                                  4. Accessibility within Department of                                                                      Secretary of Labor.
                                                                                                       responsible program manager conducts
                                               Labor Buildings. Adhering to the                                                                              [FR Doc. 2018–11126 Filed 5–25–18; 8:45 am]
                                                                                                       an environmental assessment; and,
                                               policies, standards, and directives
                                                                                                       analyzes findings of environmental                    BILLING CODE 4510–04–P
                                               established by the ASAM in accordance
                                                                                                       assessments and makes final decisions
                                               with paragraph 6.D.(1), above relating to
                                                                                                       regarding the significance of
                                               accessibility within Department of                                                                            NUCLEAR REGULATORY
                                                                                                       environmental consequences;
                                               Labor buildings and spaces occupied by                     8. Voluntary Health and Wellness                   COMMISSION
                                               agency offices.                                         Programs. Supporting the Department’s
                                                  5. Records Management                                                                                      [NRC–2018–0092]
                                                                                                       voluntary health and occupational
                                                  a. Developing and implementing                       wellness programs and drug-free
                                               effective Records Management Programs                                                                         Standard Format and Content of
                                                                                                       workplace program.                                    Physical Security Plans, Training and
                                               within their respective organizations                      9. Commercial Services Management
                                               that are consistent with Departmental                                                                         Qualifications Plans, and Safeguards
                                                                                                       (formerly Competitive Sourcing).                      Contingency Plans for Nuclear Power
                                               policy and directives.                                     a. Establishing agency procedures
                                                  b. Assigning an Agency Records                                                                             Plants
                                                                                                       necessary to carry out the provisions of
                                               Officer for the management and                          the law, regulation, and Departmental                 AGENCY: Nuclear Regulatory
                                               execution of the Agency’s Records                       directives relating to commercial                     Commission.
                                               Management Program.                                     services management.                                  ACTION: Draft regulatory guide;
                                                  c. Ensuring that the appropriate                        b. Designating an agency official as               extension of comment period.
                                               Agency staff receives adequate records                  the central point of contact for
                                               management training and participates in                 commercial services management and                    SUMMARY:   On May 14, 2018, the U.S.
                                               Departmental as well as Agency training                 ensuring the timely and appropriate                   Nuclear Regulatory Commission (NRC)
                                               and awareness activities.                               completion of required activities and                 solicited comments on Draft Regulatory
                                                  6. Printing. Assuring compliance with                notices.                                              Guide (DG), DG–5048, ‘‘Standard
                                               all Government Printing Office                             8. The Solicitor of Labor. The Solicitor           Format and Content of Physical Security
                                               regulations and directives and adhering                 of Labor is delegated authority and                   Plans, Training and Qualifications
                                               to the policies, standards, and directives              assigned responsibility for providing                 Plans, and Safeguards Contingency
                                               established by the ASAM relating to                     legal advice and assistance to all officers           Plans for Nuclear Power Plants.’’ The
                                               printing operations.                                    of the Department relating to the                     public comment period was originally
                                                  7. Environmental Stewardship                         administration of all of the elements of              scheduled to close on July 13, 2018. The
                                                  a. Promoting waste reduction and                     this Order and the statutory provisions,              NRC has decided to extend the public
                                               recycling of reusable materials within                  regulations, and Executive Orders listed              comment period by 30 days to allow
                                               their agencies;                                         above. The Solicitor of Labor shall have              more time for members of the public to
                                                  b. Requiring consideration of the                    responsibility for legal advice and                   develop and submit their comments.
daltland on DSKBBV9HB2PROD with NOTICES




                                               following factors in acquisition                        assistance through rulings and                        DATES: The due date for comments
                                               planning for all agency procurement                     interpretations of applicable laws and                requested in the document published on
                                               actions, and in the evaluation and                      regulations and for drafting services.                May 14, 2018 (83 FR 22297), is
                                               award of contracts: Elimination of virgin               The bringing of legal proceedings under               extended. Comments should be filed no
                                               material requirements; use of recovered                 those authorities, the representation of              later than August 13, 2018. Comments
                                               materials; reuse of products; life cycle                the Secretary and other officials of the              received after this date will be
                                               costs; recyclability; environmental                     Department of Labor, and the                          considered, if it is practical to do so, but


                                          VerDate Sep<11>2014   16:39 May 25, 2018   Jkt 244001   PO 00000   Frm 00054   Fmt 4703   Sfmt 4703   E:\FR\FM\29MYN1.SGM   29MYN1


                                                                              Federal Register / Vol. 83, No. 103 / Tuesday, May 29, 2018 / Notices                                            24511

                                               the Commission is able to ensure                        the NRC’s PDR, Room O1–F21, One                       NUCLEAR REGULATORY
                                               consideration only for comments                         White Flint North, 11555 Rockville                    COMMISSION
                                               received on or before this date.                        Pike, Rockville, Maryland 20852.
                                                                                                                                                             [Docket Nos. 52–025 and 52–026; NRC–
                                               ADDRESSES: You may submit comments
                                                                                                       B. Submitting Comments                                2008–0252]
                                               by any of the following methods:
                                                  • Federal Rulemaking website: Go to                    Please include Docket ID NRC–2018–                  Southern Nuclear Operating Company,
                                               http://www.regulations.gov and search                   0092 in your comment submission. The                  Inc.; Vogtle Electric Generating Plant,
                                               for Docket ID NRC–2018–0092. Address                    NRC cautions you not to include                       Units 3 and 4 Main Control Room
                                               questions about NRC dockets to Jennifer                 identifying or contact information that               Emergency Habitability System
                                               Borges; telephone: 301–287–9127;                        you do not want to be publicly                        Changes
                                               email: Jennifer.Borges@nrc.gov. For                     disclosed in your comment submission.
                                               technical questions, contact the                        The NRC will post all comment                         AGENCY:  Nuclear Regulatory
                                               individuals listed in the FOR FURTHER                   submissions at http://                                Commission.
                                               INFORMATION CONTACT section of this                     www.regulations.gov as well as enters                 ACTION: Exemption and combined
                                               document.                                               the comment submissions into ADAMS.                   license amendment; issuance.
                                                  • Mail comments to: May Ma, Office                   The NRC does not routinely edit
                                               of Administration, Mail Stop: TWFN 7–                   comment submissions to remove                         SUMMARY:    The U.S. Nuclear Regulatory
                                               A60M, U.S. Nuclear Regulatory                           identifying or contact information.                   Commission (NRC) has issued an
                                               Commission, Washington, DC 20555–                         If you are requesting or aggregating                exemption to allow a departure from the
                                               0001. For additional direction on                       comments from other persons for                       certification information of Tier 1 of the
                                               obtaining information and submitting                    submission to the NRC, then you should                generic design control document and
                                               comments, see ‘‘Obtaining Information                   inform those persons not to include                   issued License Amendment Nos. 108
                                               and Submitting Comments’’ in the                        identifying or contact information that               and 107 to Combined License (COL)
                                               SUPPLEMENTARY INFORMATION section of                    they do not want to be publicly                       Nos. NPF–91 and NPF–92, respectively.
                                               this document.                                          disclosed in their comment submission.                The COLs were issued to Southern
                                               FOR FURTHER INFORMATION CONTACT:                        Your request should state that the NRC                Nuclear Operating Company, Inc., and
                                               Dennis Gordon, Office of Nuclear                        does not routinely edit comment                       Georgia Power Company; Oglethorpe
                                               Security and Incident Response,                         submissions to remove such information                Power Corporation; MEAG Power
                                               telephone: 301–287–3633, email:                         before making the comment                             SPVM, LLC; MEAG Power SPVJ, LLC;
                                               Dennis.Gordon@nrc.gov and Mekonen                       submissions available to the public or                MEAG Power SPVP, LLC; and the City
                                               Bayssie, Office of Nuclear Regulatory                   entering the comment submissions into                 of Dalton, Georgia (the licensee), for
                                               Research; telephone: 301–415–1699,                      ADAMS.                                                construction and operation of the Vogtle
                                               email: Mekonen.Bayssie@nrc.gov. Both                                                                          Electric Generating Plant (VEGP), Units
                                                                                                       II. Background                                        3 and 4, located in Burke County,
                                               are staff of the U.S. Nuclear Regulatory
                                               Commission, Washington, DC 20555–                          On May 14, 2018 (83 FR 22297), the                 Georgia.
                                               0001.                                                   NRC solicited comments on DG–5048,                       The granting of the exemption allows
                                                                                                       ‘‘Standard Format and Content of                      the changes to Tier 1 information asked
                                               SUPPLEMENTARY INFORMATION:
                                                                                                       Physical Security Plans, Training and                 for in the amendment. Because the
                                               I. Obtaining Information and                            Qualifications Plans, and Safeguards                  acceptability of the exemption was
                                               Submitting Comments                                     Contingency Plans for Nuclear Power                   determined in part by the acceptability
                                               A. Obtaining Information                                Plants’’ (ADAMS Accession No.                         of the amendment, the exemption and
                                                                                                       ML17124A490). The public comment                      amendment are being issued
                                                  Please refer to Docket ID NRC–2018–                  period was originally scheduled to end                concurrently.
                                               0092 when contacting the NRC about                      on July 13, 2018. On May 14, 2018, the
                                               the availability of information regarding                                                                     DATES:  The exemption and amendment
                                                                                                       Nuclear Energy Institute (NEI) requested              were issued on February 1, 2018.
                                               this action. You may obtain publically-                 that the comment period be extended,
                                               available information related to this                                                                         ADDRESSES: Please refer to Docket ID
                                                                                                       stating that ‘‘the change would allow
                                               action, by any of the following methods:                                                                      NRC–2008–0252 when contacting the
                                                                                                       NEI and its members’ sufficient time to
                                                  • Federal Rulemaking website: Go to                  perform a thorough review of the
                                                                                                                                                             NRC about the availability of
                                               http://www.regulations.gov and search                                                                         information regarding this document.
                                                                                                       document consistent with other work
                                               for Docket ID NRC–2018–0092.                                                                                  You may obtain publicly-available
                                                                                                       priorities’’ (ADAMS Accesion No.
                                                  • NRC’s Agencywide Documents                         ML18136A546). The NRC agreed to the
                                                                                                                                                             information related to this document
                                               Access and Management System                                                                                  using any of the following methods:
                                                                                                       request because of the length and
                                               (ADAMS): You may obtain publicly-                                                                               • Federal Rulemaking website: Go to
                                                                                                       comprehensiveness of this DG.
                                               available documents online in the                                                                             http://www.regulations.gov and search
                                                                                                       Accordingly, the NRC is extending the
                                               ADAMS Public Documents collection at                                                                          for Docket ID NRC–2008–0252. Address
                                                                                                       public comment period on this
                                               http://www.nrc.gov/reading-rm/                                                                                questions about NRC dockets to Jennifer
                                                                                                       document until August 13, 2018, to
                                               adams.html. To begin the search, select                                                                       Borges telephone: 301–287–9127; email:
                                                                                                       allow more time for members of the
                                               ‘‘ADAMS Public Documents’’ and then                                                                           Jennifer.Borges@nrc.gov. For technical
                                                                                                       public to submit their comments.
                                               select ‘‘Begin Web-based ADAMS                                                                                questions, contact the individual listed
                                               Search.’’ For problems with ADAMS,                         Dated at Rockville, Maryland, this 23rd day        in the FOR FURTHER INFORMATION
                                               please contact the NRC’s Public                         of May, 2018.                                         CONTACT section of this document.
daltland on DSKBBV9HB2PROD with NOTICES




                                               Document Room (PDR) reference staff at                     For the Nuclear Regulatory Commission.               • NRC’s Agencywide Documents
                                               1–800–397–4209, 301–415–4737, or by                     Thomas H. Boyce,                                      Access and Management System
                                               email to pdr.resource@nrc.gov. DG–5048                  Chief, Regulatory Guidance and Generic                (ADAMS): You may obtain publicly-
                                               is available in ADAMS under Accession                   Issues Branch, Division of Engineering, Office        available documents online in the
                                               No. ML17124A490.                                        of Nuclear Regulatory Research.                       ADAMS Public Documents collection at
                                                  • NRC’s PDR: You may examine and                     [FR Doc. 2018–11460 Filed 5–25–18; 8:45 am]           http://www.nrc.gov/reading-rm/
                                               purchase copies of public documents at                  BILLING CODE 7590–01–P                                adams.html. To begin the search, select


                                          VerDate Sep<11>2014   16:39 May 25, 2018   Jkt 244001   PO 00000   Frm 00055   Fmt 4703   Sfmt 4703   E:\FR\FM\29MYN1.SGM   29MYN1



Document Created: 2018-05-26 00:48:07
Document Modified: 2018-05-26 00:48:07
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionDraft regulatory guide; extension of comment period.
DatesThe due date for comments requested in the document published on May 14, 2018 (83 FR 22297), is extended. Comments should be filed no later than August 13, 2018. Comments received after this date will be considered, if it is practical to do so, but the Commission is able to ensure consideration only for comments received on or before this date.
ContactDennis Gordon, Office of Nuclear Security and Incident Response, telephone: 301-287-3633, email: [email protected] and Mekonen Bayssie, Office of Nuclear Regulatory Research; telephone: 301-415-1699, email: [email protected] Both are staff of the U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.