83_FR_30855 83 FR 30729 - ANR Pipeline Company; Notice of Request Under Blanket Authorization

83 FR 30729 - ANR Pipeline Company; Notice of Request Under Blanket Authorization

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 126 (June 29, 2018)

Page Range30729-30730
FR Document2018-13959

Federal Register, Volume 83 Issue 126 (Friday, June 29, 2018)
[Federal Register Volume 83, Number 126 (Friday, June 29, 2018)]
[Notices]
[Pages 30729-30730]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-13959]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-503-000]


ANR Pipeline Company; Notice of Request Under Blanket 
Authorization

    Take notice that on June 14, 2018, ANR Pipeline Company (ANR), 700 
Louisiana Street, Suite 700, Houston, Texas 77002-2700, filed in Docket 
No. CP18-503-000 a prior notice request pursuant to sections 157.205, 
157.208, and 157.216 of the Commission's regulations under the Natural 
Gas Act (NGA), and ANR's blanket certificate issued in Docket No. CP82-
480-000, to abandon 20 injection/withdrawal wells, one observation 
well, and related appurtenances in its Winfield Storage Field, located 
in Mecosta and Montcalm Counties Michigan (Winfield Storage Field Wells 
Abandonment Project).
    ANR states that the well integrity risk assessments for these wells 
revealed integrity weaknesses, and to maintain these wells would 
require some form of remediation, the cost of which would likely exceed 
the cost of plugging, as well as exceed the value provided by the wells 
to storage operations. ANR claims many of the wells proposed for 
abandonment are poor performers in comparison with other wells in the 
Winfield Storage Field, contributing approximately 2.8 percent of the 
total field deliverability. Therefore, ANR concludes that plugging and 
abandoning the wells is the best course of action to maintain field 
integrity and efficiency. ANR affirms that there will be no change to 
the field's total inventory, reservoir pressure, reservoir and buffer 
boundaries, or the certificated capacity as a result of the proposed 
Winfield Storage Field Wells Abandonment Project. ANR estimates the 
cost of the Project to be approximately $2.8 million, all as more fully 
set forth in the application which is on file with the Commission and 
open to public inspection. The filing may also be viewed on the web at 
http://www.ferc.gov using the eLibrary link.

[[Page 30730]]

Enter the docket number excluding the last three digits in the docket 
number field to access the document. For assistance, please contact 
FERC Online Support at [email protected] or toll free at (866) 
208-3676, or TTY, contact (202) 502-8659.
    Any questions concerning this application may be directed to Linda 
Farquhar, Manager, Project Determinations & Regulatory Administration, 
ANR Pipeline Company, 700 Louisiana Street, Suite 700, Houston, Texas 
77002-2700, by telephone at (832) 320-5685, by facsimile at (832) 320-
6685, or by email at [email protected].
    Any person or the Commission's staff may, within 60 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to section 157.205 of 
the regulations under the NGA (18 CFR 157.205), a protest to the 
request. If no protest is filed within the time allowed therefore, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the allowed time for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to section 7 of the NGA.
    Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9), 
within 90 days of this Notice, the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the EA for this proposal. The filing of the EA in the Commission's 
public record for this proceeding or the issuance of a Notice of 
Schedule for Environmental Review will serve to notify federal and 
state agencies of the timing for the completion of all necessary 
reviews, and the subsequent need to complete all federal authorizations 
within 90 days of the date of issuance of the Commission staff's EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters, will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
http://www.ferc.gov. Persons unable to file electronically should 
submit an original and seven copies of the protest or intervention to 
the Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426.

    Dated: June 22, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-13959 Filed 6-28-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                  Federal Register / Vol. 83, No. 126 / Friday, June 29, 2018 / Notices                                                    30729

                                                                                  Date and time                                                                            Location

                                                August 1, 2018 (4:00 p.m.–7:00 p.m. CST) .............................................   Cameron Parish School Board, Educational Conference Center, 510
                                                                                                                                           Marshall Street, Cameron, Louisiana 70631, (337) 775–5784.



                                                   The primary goal of this comment                        Commission’s decisions. Any person                        Dated: June 22, 2018.
                                                session is to have you identify the                        may seek to intervene on environmental                  Nathaniel J. Davis, Sr.,
                                                specific environmental issues and                          grounds and thereby become a party to                   Deputy Secretary.
                                                concerns with the draft EIS. Individual                    this proceeding by filing a motion to                   [FR Doc. 2018–13958 Filed 6–28–18; 8:45 am]
                                                verbal comments will be taken on a one-                    intervene that complies with the                        BILLING CODE 6717–01–P
                                                on-one basis with a court reporter. This                   requirements in Rule 214 of the
                                                format is designed to receive the                          Commission’s Rules of Practice and
                                                maximum amount of verbal comments,                         Procedures (18 CFR Part 385.214). Any                   DEPARTMENT OF ENERGY
                                                in a convenient way during the                             such intervention must be filed within
                                                timeframe allotted.                                        the comment period for the draft EIS to                 Federal Energy Regulatory
                                                   The comment session is scheduled                        be deemed timely. Motions to intervene                  Commission
                                                from 4 p.m. to 7 p.m. CST. You may                         that are filed after the comment due date               [Docket No. CP18–503–000]
                                                arrive at any time after 4 p.m. There will                 for the draft EIS are untimely and may
                                                not be a formal presentation by                            be denied. Any late-filed motion to                     ANR Pipeline Company; Notice of
                                                Commission staff when the session                          intervene must show good cause why                      Request Under Blanket Authorization
                                                opens. If you wish to speak, the                           the time limitation should be waived
                                                Commission staff will hand out                             and provide justification by reference to                  Take notice that on June 14, 2018,
                                                numbers in the order of your arrival;                                                                              ANR Pipeline Company (ANR), 700
                                                                                                           factors set forth in Rule 214(d) of the
                                                distribution of numbers will be                                                                                    Louisiana Street, Suite 700, Houston,
                                                                                                           Commission’s Rules of Practice and
                                                discontinued at 6 p.m. However, if no                                                                              Texas 77002–2700, filed in Docket No.
                                                                                                           Procedures (18 CFR part 385.214(b)(3)
                                                additional numbers have been handed                                                                                CP18–503–000 a prior notice request
                                                                                                           and (d)). The Commission strongly
                                                out and all individuals who wish to                                                                                pursuant to sections 157.205, 157.208,
                                                                                                           encourages electronic filing of
                                                provide comments have had an                                                                                       and 157.216 of the Commission’s
                                                                                                           interventions in lieu of paper using the
                                                opportunity to do so, staff may conclude                                                                           regulations under the Natural Gas Act
                                                                                                           eFiling feature described above, and
                                                                                                                                                                   (NGA), and ANR’s blanket certificate
                                                the session at 6 p.m. Please see                           available at http://www.ferc.gov. Persons
                                                                                                                                                                   issued in Docket No. CP82–480–000, to
                                                appendix 1 for additional information                      unable to file electronically may submit
                                                                                                                                                                   abandon 20 injection/withdrawal wells,
                                                on the session format and conduct.1                        a paper copy of the intervention to the
                                                  Your verbal comments will be                                                                                     one observation well, and related
                                                                                                           Federal Energy Regulatory Commission,                   appurtenances in its Winfield Storage
                                                recorded by the court reporter (with                       888 First Street NE, Washington, DC
                                                FERC staff or representative present)                                                                              Field, located in Mecosta and Montcalm
                                                                                                           20426.                                                  Counties Michigan (Winfield Storage
                                                and become part of the public record for
                                                                                                           Questions?                                              Field Wells Abandonment Project).
                                                this proceeding. Transcripts will be
                                                                                                                                                                      ANR states that the well integrity risk
                                                publicly available on FERC’s eLibrary                         Additional information about the                     assessments for these wells revealed
                                                system (see below for instructions on                      project is available from the                           integrity weaknesses, and to maintain
                                                using eLibrary). If a significant number                   Commission’s Office of External Affairs,                these wells would require some form of
                                                of people are interested in providing                      at (866) 208–FERC, or on the FERC                       remediation, the cost of which would
                                                verbal comments in the one-on-one                          website (www.ferc.gov) using the                        likely exceed the cost of plugging, as
                                                settings, a time limit of 5 minutes may                    eLibrary link. Click on the eLibrary link,              well as exceed the value provided by
                                                be implemented for each commentor.                         click on General Search, and enter the                  the wells to storage operations. ANR
                                                  It is important to note that verbal                      docket number in the Docket Number                      claims many of the wells proposed for
                                                comments hold the same weight as                           field, excluding the last three digits (i.e.,           abandonment are poor performers in
                                                written or electronically submitted                        CP15–550; CP15–551). Be sure you have                   comparison with other wells in the
                                                comments. Although there will not be a                     selected an appropriate date range. For                 Winfield Storage Field, contributing
                                                formal presentation, Commission staff                      assistance, please contact FERC Online                  approximately 2.8 percent of the total
                                                will be available throughout the                           Support at FercOnlineSupport@ferc.gov                   field deliverability. Therefore, ANR
                                                comment session to answer your                             or toll free at (866) 208–3676; or for                  concludes that plugging and abandoning
                                                questions about the environmental                          TTY, contact (202) 502–8659. The                        the wells is the best course of action to
                                                review process.                                            eLibrary link also provides access to the               maintain field integrity and efficiency.
                                                  Filing environmental comments will                       texts of all formal documents issued by                 ANR affirms that there will be no
                                                not give you intervenor status, but you                    the Commission, such as orders, notices,                change to the field’s total inventory,
                                                do not need intervenor status to have                      and rulemakings.                                        reservoir pressure, reservoir and buffer
                                                your comments considered. However,                            In addition, the Commission offers a                 boundaries, or the certificated capacity
                                                only intervenors have the right to seek                    free service called eSubscription that                  as a result of the proposed Winfield
                                                rehearing or judicial review of the                        allows you to keep track of all formal                  Storage Field Wells Abandonment
                                                                                                           issuances and submittals in specific                    Project. ANR estimates the cost of the
sradovich on DSK3GMQ082PROD with NOTICES




                                                  1 The appendices referenced in this notice will

                                                not appear in the Federal Register. Copies of the
                                                                                                           dockets. This can reduce the amount of                  Project to be approximately $2.8
                                                appendices were sent to all those receiving this           time you spend researching proceedings                  million, all as more fully set forth in the
                                                notice in the mail and are available at www.ferc.gov       by automatically providing you with                     application which is on file with the
                                                using the link called eLibrary or from the                 notification of these filings, document                 Commission and open to public
                                                Commission’s Public Reference Room, 888 First
                                                Street NE, Washington, DC 20426, or call (202) 502–
                                                                                                           summaries, and direct links to the                      inspection. The filing may also be
                                                8371. For instructions on connecting to eLibrary,          documents. Go to www.ferc.gov/docs-                     viewed on the web at http://
                                                refer to the last page of this notice.                     filing/esubscription.asp.                               www.ferc.gov using the eLibrary link.


                                           VerDate Sep<11>2014    17:58 Jun 28, 2018   Jkt 244001   PO 00000    Frm 00047    Fmt 4703    Sfmt 4703   E:\FR\FM\29JNN1.SGM   29JNN1


                                                30730                           Federal Register / Vol. 83, No. 126 / Friday, June 29, 2018 / Notices

                                                Enter the docket number excluding the                   copies of the environmental documents,                   2018, Contact: Paul Willard 509–682–
                                                last three digits in the docket number                  and will be notified of meetings                         4960
                                                field to access the document. For                       associated with the Commission’s                       EIS No. 20180142, Draft, BLM, AZ, San
                                                assistance, please contact FERC Online                  environmental review process.                            Pedro Riparian National Conservation
                                                Support at FERCOnlineSupport@                           Environmental commenters will not be                     Area Resource Management Plan and
                                                ferc.gov or toll free at (866) 208–3676, or             required to serve copies of filed                        Environmental Impact Statement,
                                                TTY, contact (202) 502–8659.                            documents on all other parties.                          Comment Period Ends: 09/27/2018,
                                                   Any questions concerning this                        However, the non-party commenters,                       Contact: Amy Markstein 520–258–
                                                application may be directed to Linda                    will not receive copies of all documents                 7231
                                                Farquhar, Manager, Project                              filed by other parties or issued by the                EIS No. 20180143, Adoption, DHS, SC,
                                                Determinations & Regulatory                             Commission (except for the mailing of                    Charleston Naval Complex (CNC)
                                                Administration, ANR Pipeline                            environmental documents issued by the                    Proposed Construction of a Marine
                                                Company, 700 Louisiana Street, Suite                    Commission) and will not have the right                  Container Terminal Cooper River in
                                                700, Houston, Texas 77002–2700, by                      to seek court review of the                              Charleston Harbor, City of North
                                                telephone at (832) 320–5685, by                         Commission’s final order.                                Charleston, Charleston County, SC,
                                                facsimile at (832) 320–6685, or by email                   The Commission strongly encourages                    Review Period Ends: 07/30/2018,
                                                at linda_farquhar@transcanada.com.                      electronic filings of comments, protests                 Contact: Mark Harvison 912–267–
                                                   Any person or the Commission’s staff                 and interventions in lieu of paper using                 3239
                                                may, within 60 days after issuance of                   the eFiling link at http://www.ferc.gov.               EIS No. 20180144, Final, FERC, OK,
                                                the instant notice by the Commission,                   Persons unable to file electronically                    Midcontinent Supply Header
                                                file pursuant to Rule 214 of the                        should submit an original and seven                      Interstate Pipeline Project, Review
                                                Commission’s Procedural Rules (18 CFR                   copies of the protest or intervention to                 Period Ends: 07/30/2018, Contact:
                                                385.214) a motion to intervene or notice                the Federal Energy Regulatory                            Elaine Baum 202–502–6467
                                                of intervention and pursuant to section                 Commission, 888 First Street NE,                       EIS No. 20180145, Final, FHWA, NV,
                                                157.205 of the regulations under the                    Washington, DC 20426.                                    Pyramid Highway/US 395
                                                NGA (18 CFR 157.205), a protest to the                                                                           Connection, Review Period Ends:
                                                request. If no protest is filed within the                Dated: June 22, 2018.
                                                                                                                                                                 07/30/2018, Contact: Abdelmoez
                                                time allowed therefore, the proposed                    Nathaniel J. Davis, Sr.,                                 Abdalla 775–687–1231
                                                activity shall be deemed to be                          Deputy Secretary.                                      EIS No. 20180146, Final, USFS, WA,
                                                authorized effective the day after the                  [FR Doc. 2018–13959 Filed 6–28–18; 8:45 am]              LeClerc Creek Grazing Allotment
                                                time allowed for filing a protest. If a                 BILLING CODE 6717–01–P                                   Management Planning, Review Period
                                                protest is filed and not withdrawn                                                                               Ends: 08/13/2018, Contact: Gayne
                                                within 30 days after the allowed time                                                                            Sears 509–447–7300
                                                for filing a protest, the instant request               ENVIRONMENTAL PROTECTION                               EIS No. 20180148, Final, USACE, SC,
                                                shall be treated as an application for                  AGENCY                                                   Navy Base Intermodal Container
                                                authorization pursuant to section 7 of                                                                           Transfer Facility, Review Period Ends:
                                                the NGA.                                                [ER–FRL–9040–1]                                          07/30/2018, Contact: Shawn Boone
                                                   Pursuant to section 157.9 of the                                                                              843–329–8044
                                                Commission’s rules (18 CFR 157.9),                      Environmental Impact Statements;
                                                                                                                                                               EIS No. 20190147, Draft, FERC, LA,
                                                within 90 days of this Notice, the                      Notice of Availability
                                                                                                                                                                 Calcasieu Pass Project, Comment
                                                Commission staff will either: Complete                    Responsible Agency: Office of Federal                  Period Ends: 08/13/2018, Contact:
                                                its environmental assessment (EA) and                   Activities, General Information (202)                    Shannon Crosley 202–502–8853
                                                place it into the Commission’s public                   564–7156 or https://www2.epa.gov/                        Dated: June 26, 2018.
                                                record (eLibrary) for this proceeding; or               nepa/.                                                 Robert Tomiak,
                                                issue a Notice of Schedule for
                                                                                                        Weekly receipt of Environmental Impact                 Director, Office of Federal Activities.
                                                Environmental Review. If a Notice of
                                                                                                          Statements                                           [FR Doc. 2018–14003 Filed 6–28–18; 8:45 am]
                                                Schedule for Environmental Review is
                                                                                                        Filed 06/18/2018 Through 06/22/2018
                                                issued, it will indicate, among other                                                                          BILLING CODE 6560–50–P
                                                                                                        Pursuant to 40 CFR 1506.9.
                                                milestones, the anticipated date for the
                                                Commission staff’s issuance of the EA                     Section 309(a) of the Clean Air Act
                                                for this proposal. The filing of the EA                 requires that EPA make public its                      DEPARTMENT OF HEALTH AND
                                                in the Commission’s public record for                   comments on EISs issued by other                       HUMAN SERVICES
                                                this proceeding or the issuance of a                    Federal agencies. EPA’s comment letters
                                                Notice of Schedule for Environmental                    on EISs are available at: https://                     Centers for Disease Control and
                                                Review will serve to notify federal and                 cdxnodengn.epa.gov/cdx-enepa-public/                   Prevention
                                                state agencies of the timing for the                    action/eis/search.
                                                completion of all necessary reviews, and                EIS No. 20180140, Draft, DOI, OK, Draft                Board of Scientific Counselors,
                                                the subsequent need to complete all                       Environmental Impact Statement for                   National Center for Environmental
                                                federal authorizations within 90 days of                  the Proposed Habitat Conservation                    Health/Agency for Toxic Substances
                                                the date of issuance of the Commission                    Plan for the Endangered American                     and Disease Registry (BSC, NCEH/
                                                staff’s EA.                                               Burying Beetle for American Electric                 ATSDR); Notice of Charter Renewal
                                                   Persons who wish to comment only                       Power in Oklahoma, Arkansas, and
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                                                                               AGENCY: Centers for Disease Control and
                                                on the environmental review of this                       Texas, Comment Period Ends: 08/13/                   Prevention (CDC), Department of Health
                                                project should submit an original and                     2018, Contact: Adam Zerrenner 512–                   and Human Services (HHS).
                                                two copies of their comments to the                       490–0057                                             ACTION: Notice of charter renewal.
                                                Secretary of the Commission.                            EIS No. 20180141, Final Supplement,
                                                Environmental commenters will be                          USFS, WA, Pack and Saddle Stock                      SUMMARY:  This gives notice under the
                                                placed on the Commission’s                                Outfitter-Guide Special Use Permit                   Federal Advisory Committee Act of
                                                environmental mailing list, will receive                  Issuance, Review Period Ends: 08/20/                 October 6, 1972, that the Board of


                                           VerDate Sep<11>2014   17:58 Jun 28, 2018   Jkt 244001   PO 00000   Frm 00048   Fmt 4703   Sfmt 4703   E:\FR\FM\29JNN1.SGM   29JNN1



Document Created: 2018-06-29 01:14:09
Document Modified: 2018-06-29 01:14:09
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 30729 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR