83_FR_32239 83 FR 32106 - ISO New England Inc.; Notice of Institution of Section 206 Proceeding and Refund Effective Date

83 FR 32106 - ISO New England Inc.; Notice of Institution of Section 206 Proceeding and Refund Effective Date

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 133 (July 11, 2018)

Page Range32106-32107
FR Document2018-14773

Federal Register, Volume 83 Issue 133 (Wednesday, July 11, 2018)
[Federal Register Volume 83, Number 133 (Wednesday, July 11, 2018)]
[Notices]
[Pages 32106-32107]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-14773]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL18-182-000]


ISO New England Inc.; Notice of Institution of Section 206 
Proceeding and Refund Effective Date

    On July 2, 2018, the Commission issued an order in Docket No. EL18-
182-000, pursuant to section 206 of the Federal Power Act (FPA), 16 
U.S.C. 824e (2012), instituting an investigation into whether ISO New 
England Inc.'s Transmission, Markets and Services Tariff is unjust and 
unreasonable. ISO New England Inc., 164 FERC ] 61,003 (2018).
    The refund effective date in Docket No. EL18-182-000, established 
pursuant to section 206(b) of the FPA, will be the date of publication 
of this notice in the Federal Register.
    Any interested person desiring to be heard in Docket No. EL18-182-
000 must file a notice of intervention or motion to intervene, as 
appropriate, with the Federal Energy Regulatory Commission, 888 First 
Street NE, Washington, DC 20426, in accordance with Rule 214 of the 
Commission's Rules of Practice and Procedure, 18 CFR

[[Page 32107]]

385.214, within 21 days of the date of issuance of the order.

    Dated: July 2, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-14773 Filed 7-10-18; 8:45 am]
 BILLING CODE 6717-01-P



                                               32106                        Federal Register / Vol. 83, No. 133 / Wednesday, July 11, 2018 / Notices

                                                  h. Applicant Contact: Arturo Silva,                   An existing 797-foot-long, 38-inch                    protests must set forth their evidentiary
                                               Interim Assistant General Manager—                       diameter welded steel penstock; (2) an                basis and otherwise comply with the
                                               Power Supply, City of Pasadena Water                     existing powerhouse containing one                    requirements of 18 CFR 4.34(b). All
                                               and Power Development, 85 East State                     generating unit having an installed                   comments, motions to intervene, or
                                               Street, Pasadena, California 91101–                      capacity of 3 megawatts; (3) an existing              protests should relate to project works
                                               3418, telephone: (626) 744–4568.                         148-foot-long, 136-inch-wide                          which are the subject of the license
                                                  i. FERC Contact: Robert Bell,                         underground tailrace; and (4)                         amendment. Agencies may obtain
                                               telephone (202) 502–6062 or email:                       appurtenant facilities. The City of                   copies of the application directly from
                                               robert.bell@ferc.gov.                                    Pasadena, estimates the project would                 the applicant. A copy of any protest or
                                                  j. Deadline for filing comments,                      have an average annual generation of                  motion to intervene must be served
                                               motions to intervene, and protests: 60                   2,890 megawatt-hours that would be                    upon each representative of the
                                               days from the issuance date of this                      sold to a local utility.                              applicant specified in the particular
                                               notice by the Commission; reply                             l. Locations of the Application: This              application. If an intervener files
                                               comments are due 105 days from the                       filing may be viewed on the                           comments or documents with the
                                               issuance date of this notice by the                      Commission’s website at http://                       Commission relating to the merits of an
                                               Commission. The Commission strongly                      www.ferc.gov/docs-filing/elibrary.asp.                issue that may affect the responsibilities
                                               encourages electronic filing. Please file                Enter the docket number P–1250, or                    of a particular resource agency, they
                                               any motion to intervene, protest,                        P–14836 in the docket number field to                 must also serve a copy of the document
                                               comments, and/or recommendations                         access the documents. You may also                    on that resource agency. A copy of all
                                               using the Commission’s eFiling system                    register online at http://www.ferc.gov/               other filings in reference to this
                                               at http://www.ferc.gov/docs-filing/                      docs-filing/esubscription.asp to be                   application must be accompanied by
                                               efiling.asp. Commenters can submit                       notified via email of new filings and                 proof of service on all persons listed in
                                               brief comments up to 6,000 characters,                   issuances related to this or other                    the service list prepared by the
                                               without prior registration, using the                    pending projects. For assistance, call                Commission in this proceeding, in
                                               eComment system at http://                               1–866–208–3676 or email                               accordance with 18 CFR 4.34(b) and
                                               www.ferc.gov/docs-filing/                                FERCOnlineSupport@ferc.gov, for TTY,                  385.2010.
                                               ecomment.asp. You must include your                      call (202) 502–8659. A copy is also
                                               name and contact information at the end                  available for inspection and                            Dated: July 2, 2018.
                                               of your comments. For assistance,                        reproduction at the address in item (h)               Kimberly D. Bose,
                                               please contact FERC Online Support at                    above and at the Commission’s Public                  Secretary.
                                               FERCOnlineSupport@ferc.gov, (866)                        Reference Room, located at 888 First                  [FR Doc. 2018–14776 Filed 7–10–18; 8:45 am]
                                               208–3676 (toll free), or (202) 502–8659                  Street NE, Room 2A, Washington, DC                    BILLING CODE 6717–01–P
                                               (TTY). In lieu of electronic filing, please              20426, or by calling (202) 502–8371.
                                               send a paper copy to: Secretary, Federal                    m. Individuals desiring to be included
                                               Energy Regulatory Commission, 888                        on the Commission’s mailing list should               DEPARTMENT OF ENERGY
                                               First Street NE, Washington, DC 20426.                   so indicate by writing to the Secretary
                                               The first page of any filing should                      of the Commission.                                    Federal Energy Regulatory
                                               include docket numbers P–1250–020,                          n. Comments, Protests, or Motions to               Commission
                                               and P–14836–000.                                         Intervene: Anyone may submit
                                                  k. Description of request: In the                     comments, a protest, or a motion to                   [Docket No. EL18–182–000]
                                               application filed on December 29, 2016,                  intervene in accordance with the
                                               the City of Pasadena requests that the                   requirements of Rules of Practice and                 ISO New England Inc.; Notice of
                                               Commission issue an order granting the                   Procedure, 18 CFR 385.210, .211, .214.                Institution of Section 206 Proceeding
                                               Azusa Project an exemption from the                      In determining the appropriate action to              and Refund Effective Date
                                               licensing requirements of Part I of the                  take, the Commission will consider all
                                               Federal Power Act. The City of                           protests or other comments filed, but                    On July 2, 2018, the Commission
                                               Pasadena also requests administrative                    only those who file a motion to                       issued an order in Docket No. EL18–
                                               surrender of its license for the Azusa                   intervene in accordance with the                      182–000, pursuant to section 206 of the
                                               Project facilities excluded under FERC’s                 Commission’s Rules may become a                       Federal Power Act (FPA), 16 U.S.C.
                                               definition of a small conduit                            party to the proceeding. Any comments,                824e (2012), instituting an investigation
                                               hydroelectric facility.                                  protests, or motions to intervene must                into whether ISO New England Inc.’s
                                                  a. Licensed Facilities: The applicant                 be received on or before the specified                Transmission, Markets and Services
                                               requests a conduit exemption for the                     comment date for the particular                       Tariff is unjust and unreasonable. ISO
                                               Azusa Hydroelectric Project No. 1250.                    application.                                          New England Inc., 164 FERC ¶ 61,003
                                               The applicant proposes to remove the                        o. Filing and Service of Responsive                (2018).
                                               following project facilities from the                    Documents: Any filing must (1) bear in                   The refund effective date in Docket
                                               Commission’s jurisdiction: (1) The                       all capital letters the title                         No. EL18–182–000, established
                                               forebay; (2) the 24.4-kV generator leads,                ‘‘COMMENTS’’, ‘‘PROTEST’’, or                         pursuant to section 206(b) of the FPA,
                                               a 2.3/12-kV transformer, and a short                     ‘‘MOTION TO INTERVENE’’ as                            will be the date of publication of this
                                               transmission line; (3) an afterbay. The                  applicable; (2) set forth in the heading              notice in the Federal Register.
                                               aforementioned facilities would remain                   the name of the applicant and the                        Any interested person desiring to be
                                               operational as part of the water supply                  project number of the application to                  heard in Docket No. EL18–182–000
daltland on DSKBBV9HB2PROD with NOTICES




                                               facilities operated by the San Gabriel                   which the filing responds; (3) furnish                must file a notice of intervention or
                                               River Water Committee.                                   the name, address, and telephone                      motion to intervene, as appropriate,
                                                  b. Conduit Exemption: The applicant                   number of the person protesting or                    with the Federal Energy Regulatory
                                               proposes a conduit exemption for the                     intervening; and (4) otherwise comply                 Commission, 888 First Street NE,
                                               Azusa Project No. 14836. The proposed                    with the requirements of 18 CFR                       Washington, DC 20426, in accordance
                                               project would be located on its water                    385.2001 through 385.2005. All                        with Rule 214 of the Commission’s
                                               supply system and would consist of: (1)                  comments, motions to intervene, or                    Rules of Practice and Procedure, 18 CFR


                                          VerDate Sep<11>2014   16:26 Jul 10, 2018   Jkt 244001   PO 00000   Frm 00035   Fmt 4703   Sfmt 4703   E:\FR\FM\11JYN1.SGM   11JYN1


                                                                            Federal Register / Vol. 83, No. 133 / Wednesday, July 11, 2018 / Notices                                                  32107

                                               385.214, within 21 days of the date of         Filed Date: 7/2/18.                                                Docket Numbers: RP18–958–000.
                                               issuance of the order.                         Accession Number: 20180702–5054.                                   Applicants: Rockies Express Pipeline
                                                  Dated: July 2, 2018.                        Comments Due: 5 p.m. ET 7/16/18.                                LLC.
                                                                                              Docket Numbers: RP18–952–000.                                      Description: § 4(d) Rate Filing: Neg
                                               Kimberly D. Bose,
                                                                                              Applicants: Equitrans, L.P.                                     Rate 2018–07–03 BP (2Ks) to be
                                               Secretary.
                                                                                              Description: § 4(d) Rate Filing:                                effective 7/4/2018.
                                               [FR Doc. 2018–14773 Filed 7–10–18; 8:45 am]                                                                       Filed Date: 7/3/18.
                                                                                           Negotiated Capacity Release
                                               BILLING CODE 6717–01–P
                                                                                           Agreements—7/1/2018 to be effective                                   Accession Number: 20180703–5117.
                                                                                           7/1/2018.                                                             Comments Due: 5 p.m. ET 7/16/18.
                                                                                              Filed Date: 7/2/18.                                                Docket Numbers: RP18–959–000.
                                               DEPARTMENT OF ENERGY
                                                                                              Accession Number: 20180702–5127.                                   Applicants: Texas Eastern
                                               Federal Energy Regulatory                      Comments Due: 5 p.m. ET 7/16/18.                                Transmission, LP.
                                               Commission                                     Docket Numbers: RP18–953–000.                                      Description: Compliance filing TETLP
                                                                                              Applicants: Gulf South Pipeline                                 Notice Regarding Non-Jurisdictional
                                               Combined Notice of Filings                  Company, LP.                                                       Facilities.
                                                                                              Description: § 4(d) Rate Filing:                                   Filed Date: 7/3/18.
                                                  Take notice that the Commission has                                                                            Accession Number: 20180703–5158.
                                               received the following Natural Gas          Negotiated  Rate Agmt (Emera 49472) to
                                                                                                                                                                 Comments Due: 5 p.m. ET 7/16/18.
                                               Pipeline Rate and Refund Report filings: be effective 7/2/2018.                                                   The filings are accessible in the
                                                                                              Filed Date: 7/2/18.
                                               Filings Instituting Proceedings                Accession Number: 20180702–5251.                                Commission’s eLibrary system by
                                                  Docket Numbers: RP10–1398–000.              Comments Due: 5 p.m. ET 7/16/18.                                clicking on the links or querying the
                                                  Applicants: El Paso Natural Gas             Docket Numbers: RP18–954–000.                                   docket number.
                                               Company.                                       Applicants: Gulf South Pipeline                                    Any person desiring to intervene or
                                                  Description: Report Filing: Refund       Company, LP.                                                       protest in any of the above proceedings
                                               Report.                                        Description: § 4(d) Rate Filing:                                must file in accordance with Rules 211
                                                  Filed Date: 7/2/18.                      PermCapRel & CapRelNegRateAgmt                                     and 214 of the Commission’s
                                                  Accession Number: 20180702–5164.         (Pivotal 34691 >ETG 49785, then >So                                Regulations (18 CFR 385.211 and
                                                  Comments Due: 5 p.m. ET 7/16/18.         Jersey 49788) to be effective 7/1/2018.                            385.214) on or before 5:00 p.m. Eastern
                                                  Docket Numbers: RP15–1022–014.              Filed Date: 7/2/18.                                             time on the specified comment date.
                                                  Applicants: Alliance Pipeline L.P.          Accession Number: 20180702–5259.                                Protests may be considered, but
                                                  Description: Compliance filing              Comments Due: 5 p.m. ET 7/16/18.                                intervention is necessary to become a
                                               Settlement—Gas Processing to be                                                                                party to the proceeding.
                                                                                              Docket Numbers: RP18–955–000.                                      eFiling is encouraged. More detailed
                                               effective 8/1/2018.                            Applicants: Enable Mississippi River
                                                  Filed Date: 7/2/18.                                                                                         information relating to filing
                                                                                           Transmission, LLC.                                                 requirements, interventions, protests,
                                                  Accession Number: 20180702–5001.            Description: § 4(d) Rate Filing:
                                                  Comments Due: 5 p.m. ET 7/16/18.                                                                            service, and qualifying facilities filings
                                                                                           Negotiated Rate Filing—Ankor—July 1,                               can be found at: http://www.ferc.gov/
                                                  Docket Numbers: RP18–861–001.            2018 #6032 to be effective 7/1/2018.
                                                  Applicants: Equitrans, L.P.                                                                                 docs-filing/efiling/filing-req.pdf. For
                                                                                              Filed Date: 7/2/18.                                             other information, call (866) 208–3676
                                                  Description: Compliance filing              Accession Number: 20180702–5267.
                                               Scheduling Priority Exemption for                                                                              (toll free). For TTY, call (202) 502–8659.
                                                                                              Comments Due: 5 p.m. ET 7/16/18.
                                               Reservation Charge Credits Compliance                                                                            Dated: July 5, 2018.
                                                                                              Docket Numbers: RP18–891–001.
                                               Filing to be effective 7/1/2018.                                                                               Nathaniel J. Davis, Sr.,
                                                                                              Applicants: Eastern Shore Natural Gas
                                                  Filed Date: 7/2/18.                                                                                         Deputy Secretary.
                                                  Accession Number: 20180702–5102.         Company.
                                                  Comments Due: 5 p.m. ET 7/16/18.            Description: Tariff Amendment:                                  [FR Doc. 2018–14832 Filed 7–10–18; 8:45 am]
                                                                                           Amended Non-Conforming Letter                                      BILLING CODE 6717–01–P
                                                  Docket Numbers: RP18–940–001.            Agreements-Easton/CUC–MD to be
                                                  Applicants: Empire Pipeline, Inc.
                                                                                           effective 5/1/2018.
                                                  Description: Tariff Amendment: Errata                                                                       DEPARTMENT OF ENERGY
                                                                                              Filed Date: 7/3/18.
                                               Empire Rate Case—June 2018 to be
                                                                                              Accession Number: 20180703–5108.
                                               effective 1/1/2019.                                                                                            Federal Energy Regulatory
                                                  Filed Date: 7/2/18.                         Comments Due: 5 p.m. ET 7/16/18.
                                                                                                                                                              Commission
                                                  Accession Number: 20180702–5101.            Docket Numbers: RP18–956–000.
                                                  Comments Due: 5 p.m. ET 7/16/18.            Applicants: WTG Hugoton, LP.                                    [Docket No. CP18–504–000]
                                                  Docket Numbers: RP18–950–000.               Description: § 4(d) Rate Filing: Annual
                                                                                           Fuel Retention Percentage Filing 2018–                             Notice of Request Under Blanket
                                                  Applicants: Dominion Energy Cove                                                                            Authorization; Transwestern Pipeline
                                               Point LNG, LP.                              2019 to be effective 7/2/2018.
                                                                                              Filed Date: 7/3/18.                                             Company, LLC
                                                  Description: Compliance filing
                                               DECP—2018 Penalty Revenue                      Accession Number: 20180703–5000.                                  Take notice that on June 14, 2018,
                                               Distribution.                                  Comments Due: 5 p.m. ET 7/16/18.                                Transwestern Pipeline Company, LLC
                                                  Filed Date: 7/2/18.                         Docket Numbers: RP18–957–000.                                   (Transwestern), 1300 Main Street,
                                                  Accession Number: 20180702–5044.            Applicants: Midcontinent Express                                Houston, Texas 7700, filed a Prior
daltland on DSKBBV9HB2PROD with NOTICES




                                                  Comments Due: 5 p.m. ET 7/16/18.         Pipeline LLC.                                                      Notice Request pursuant to sections
                                                  Docket Numbers: RP18–951–000.               Description: § 4(d) Rate Filing:                                157.203, 157.205, and 157.216 of the
                                                  Applicants: Dominion Energy              Chesapeake/BCE-Mach LLC Negotiated                                 Commission’s regulations under the
                                               Transmission, Inc.                          Rate to be effective 7/1/2018.                                     Natural Gas Act (NGA) for authorization
                                                  Description: Compliance filing DETI—        Filed Date: 7/3/18.                                             to abandon in place the Atoka 3
                                               2018 Overrun and Penalty Revenue               Accession Number: 20180703–5045.                                Compressor Station consisting of five
                                               Distribution.                                  Comments Due: 5 p.m. ET 7/16/18.                                natural gas compressor engines,


                                          VerDate Sep<11>2014   16:26 Jul 10, 2018   Jkt 244001   PO 00000   Frm 00036   Fmt 4703   Sfmt 4703   E:\FR\FM\11JYN1.SGM   11JYN1



Document Created: 2018-07-10 23:54:11
Document Modified: 2018-07-10 23:54:11
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 32106 