83_FR_40186 83 FR 40030 - Pacific Gas and Electric Company and City of Santa Clara, California; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions

83 FR 40030 - Pacific Gas and Electric Company and City of Santa Clara, California; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 156 (August 13, 2018)

Page Range40030-40032
FR Document2018-17305

Federal Register, Volume 83 Issue 156 (Monday, August 13, 2018)
[Federal Register Volume 83, Number 156 (Monday, August 13, 2018)]
[Notices]
[Pages 40030-40032]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-17305]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 619-164]


Pacific Gas and Electric Company and City of Santa Clara, 
California; Notice of Application Accepted for Filing, Soliciting 
Motions To Intervene and Protests, Ready for Environmental Analysis, 
and Soliciting Comments, Recommendations, Preliminary Terms and 
Conditions, and Preliminary Fishway Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Major License.
    b. Project No.: 619-164.
    c. Date filed: December 12, 2016.
    d. Applicant: Pacific Gas and Electric Company (PG&E) and City of 
Santa Clara, California.
    e. Name of Project: Bucks Creek Hydroelectric Project.
    f. Location: The Bucks Creek Project is located on Bucks, Grizzly, 
and Milk Ranch Creeks in Plumas County, California. Portions of the 
project are located within the Plumas National Forest.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Alan Soneda, PG&E, Mail Code N13C, P. 0. Box 
770000, San Francisco, California 94177-0001; (415) 973-4054.
    i. FERC Contact: Alan Mitchnick at (202) 502-6074 or 
[email protected].
    j. Deadline for filing motions to intervene and protests, comments, 
recommendations, preliminary terms and conditions, and preliminary 
prescriptions: 60 days from the issuance date of this notice; reply 
comments are due 105 days from the issuance date of this notice.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene, protests, comments, recommendations, preliminary 
terms and conditions, and preliminary fishway prescriptions using the 
Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
http://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-619-164.

[[Page 40031]]

    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted for filing and is now ready 
for environmental analysis.
    l. Project Description:
Bucks Lake Dam and Reservoir (Bucks Creek Development)

    The Bucks Lake Dam consists of a rock-fill with concrete face dam. 
It has a structural height of 123 feet and a length of 1,320 feet. 
Bucks Creek Dam impounds Bucks Lake, which extends 5 miles from the 
dam. Total storage in the 1,827-acre reservoir is approximately 105,605 
acre-feet at the normal maximum water surface elevation of 
approximately 5,157 feet. From Bucks Lake, the project's water flow is 
released immediately downstream into Lower Bucks Lake.

Three Lakes Dam and Reservoir, and Milk Ranch Conduit (Bucks Creek 
Development)

    The Three Lakes dam consists of a rock-fill dam with a structural 
height of 30 feet and a length of 584 feet. Three Lakes Dam impounds 
the flow of Milk Ranch Creek, forming Upper Lake, Middle Lake, and 
Lower Lake, collectively known as Three Lakes Reservoir. These water 
bodies are hydraulically linked and are approximately 0.75 mile from 
the dam. Total storage in the 40-acre reservoir is approximately 605 
acre-feet at the normal maximum water surface elevation of 
approximately 6,078 feet.
    Milk Ranch Conduit conveys the project's water flow from Three 
Lakes Reservoir and feeder diversions to Lower Bucks Lake. The maximum 
capacity of the approximately 8-mile-long conduit is about 70 cubic 
foot per second (cfs). It collects additional flow from several 
diversions located on unnamed tributaries.

Lower Bucks Lake Dam and Reservoir (Bucks Creek Development)

    The Lower Bucks Lake Dam consists of a concrete arch dam with a 
structural height of 99 feet and a length of 500 feet. Lower Bucks 
Creek Dam impounds Lower Bucks Lake, which extends approximately 1.1 
miles from the dam. Total storage in the 136-acre reservoir is 
approximately 5,843 acre-feet at the normal maximum water surface 
elevation of approximately 5,022 feet. Water is conveyed from Lower 
Bucks Lake to the Grizzly Powerhouse by the Grizzly Powerhouse Tunnel.

Grizzly Powerhouse Tunnel (Grizzly Development)

    The 12,320-foot-long Grizzly Powerhouse Tunnel (including a 4,900-
foot-long buried penstock) conveys the water flow from Lower Bucks Lake 
to Grizzly Powerhouse. The maximum flow capacity is 400 cfs.

Grizzly Powerhouse (Grizzly Development)

    The Grizzly Powerhouse is a 65-foot-long by 55-foot-wide, steel 
frame and concrete building constructed from reinforced concrete. The 
powerhouse contains one turbine-generator with a maximum capacity of 20 
megawatts (MW). The powerhouse produces an average annual generation 
production of 47.4 gigawatt-hours (GWh). Grizzly Powerhouse discharges 
the project's water flow directly into the Grizzly Forebay.
    A 4.2-mile-long, 115-kilovolt (kV) transmission line transmits 
power from Grizzly Powerhouse to PG&E's 115-kV Caribou-Sycamore 
Transmission Line, part of the interconnected system.

Grizzly Forebay Dam and Reservoir (Bucks Creek Development)

    The Grizzly Forebay Dam consists of a concrete arch dam with a 
structural height of 98 feet and a length of 520 feet. Grizzly Forebay 
Dam impounds the Grizzly Forebay, forming the Grizzly Forebay Reservoir 
that extends approximately 0.8 mile. Total storage in the 38-acre 
reservoir is approximately 1,112 acre-feet at the normal maximum water 
surface elevation of approximately 4,316 feet.

Grizzly Forebay Tunnel (Bucks Creek Development)

    From Grizzly Forebay, the project's water flow is conveyed through 
the horseshoe-shaped Grizzly Forebay Tunnel. The tunnel is 9,575-foot-
long with two 4,786-foot-long penstocks leading to Bucks Creek 
Powerhouse. The maximum flow capacity is 400 cfs.

Bucks Creek Powerhouse (Bucks Creek Development)

    The project's water flow is conveyed through the Grizzly Forebay 
Tunnel to Bucks Creek Powerhouse. The Bucks Creek Powerhouse is a 47-
foot-long by 132-foot-wide, steel frame and concrete building 
constructed from reinforced concrete, containing two turbine-generators 
with a total maximum capacity of 65 MW. The powerhouse produces an 
average annual generation of 223.6 GWh.
    There are no associated transmission lines at the Bucks Creek 
Powerhouse. The powerhouse connects directly to the non-project 
switchyard adjacent to the powerhouse part of the interconnected 
transmission system.
    Bucks Creek Powerhouse discharges the project's water flow in the 
North Fork Feather River, 1 mile upstream of Rock Creek Powerhouse, 
part of PG&E's Rock Creek-Cresta Hydroelectric Project (FERC Project 
No. 1962).
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's website at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    Register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Anyone may submit comments, a protest, or a motion to intervene 
in accordance with the requirements of Rules of Practice and Procedure, 
18 CFR 385.210, .211, and .214. In determining the appropriate action 
to take, the Commission will consider all protests or other comments 
filed, but only those who file a motion to intervene in accordance with 
the Commission's Rules may become a party to the proceeding. Any 
comments, protests, or motions to intervene must be received on or 
before the specified comment date for the particular application.
    All filings must (1) bear in all capital letters the title 
``PROTEST'', ``MOTION TO INTERVENE'', ``COMMENTS,'' ``REPLY COMMENTS,'' 
``RECOMMENDATIONS,'' ``PRELIMINARY TERMS AND CONDITIONS,'' or 
``PRELIMINARY FISHWAY PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person protesting or intervening; and (4) otherwise 
comply with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, recommendations, terms and conditions or prescriptions must 
set forth their evidentiary basis and otherwise comply with the 
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
application directly from the applicant. A copy of any protest or

[[Page 40032]]

motion to intervene must be served upon each representative of the 
applicant specified in the particular application. A copy of all other 
filings in reference to this application must be accompanied by proof 
of service on all persons listed in the service list prepared by the 
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 
385.2010.
    o. Procedural Schedule: The application will be processed according 
to the following revised Hydro Licensing Schedule. Revisions to the 
schedule may be made as appropriate.

------------------------------------------------------------------------
                Milestone                           Target date
------------------------------------------------------------------------
Filing of recommendations, preliminary    October 2018.
 terms and conditions, and preliminary
 fishway prescriptions.
Commission issues Draft Environmental     April 2019.
 Statement (EIS).
Comments on draft EIS...................  June 2019.
Modified terms and conditions Commission  August 2019.
 issues final EIS.
------------------------------------------------------------------------

    p. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of this notice.
    q. A license applicant must file no later than 60 days following 
the date of issuance of the notice of acceptance and ready for 
environmental analysis provided for in 5.22: (1) a copy of the water 
quality certification; (2) a copy of the request for certification, 
including proof of the date on which the certifying agency received the 
request; or (3) evidence of waiver of water quality certification.

    Dated: August 6, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-17305 Filed 8-10-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                40030                                  Federal Register / Vol. 83, No. 156 / Monday, August 13, 2018 / Notices

                                                  m. Procedural Schedule: The                                            Licensing Schedule. Revisions to the
                                                application will be processed according                                  schedule will be made as appropriate.
                                                to the following preliminary Hydro

                                                                                                                               Milestone                                                                                              Target Date

                                                Notice of Acceptance/Notice of Ready for Environmental Analysis ..................................................................................                               October 2018.
                                                Filing of recommendations, preliminary terms and conditions, and fishway prescriptions ...............................................                                           December 2018.
                                                Commission issues EA ......................................................................................................................................................      April 2019.
                                                Comments on EA ...............................................................................................................................................................   May 2019.
                                                Modified Terms and Conditions .........................................................................................................................................          July 2019.



                                                  n. Final amendments to the                                                You may also register online at http://                               with the Commission and is available
                                                application must be filed with the                                       www.ferc.gov/docs-filing/                                                for public inspection.
                                                Commission no later than 30 days from                                    esubscription.asp to be notified via                                        a. Type of Application: Major License.
                                                the issuance date of the notice of ready                                 email of new filings and issuances                                          b. Project No.: 619–164.
                                                for environmental analysis.                                              related to this or other pending projects.                                  c. Date filed: December 12, 2016.
                                                                                                                         For assistance, contact FERC Online                                         d. Applicant: Pacific Gas and Electric
                                                  Dated: August 6, 2018.                                                                                                                          Company (PG&E) and City of Santa
                                                Kimberly D. Bose,
                                                                                                                         Support.
                                                                                                                            Any comments should be filed within                                   Clara, California.
                                                Secretary.                                                               30 days from the date of this notice.                                       e. Name of Project: Bucks Creek
                                                [FR Doc. 2018–17306 Filed 8–10–18; 8:45 am]                                 The Commission strongly encourages                                    Hydroelectric Project.
                                                BILLING CODE 6717–01–P                                                   electronic filing. Please file comments                                     f. Location: The Bucks Creek Project
                                                                                                                         using the Commission’s eFiling system                                    is located on Bucks, Grizzly, and Milk
                                                                                                                         at http://www.ferc.gov/docs-filing/                                      Ranch Creeks in Plumas County,
                                                DEPARTMENT OF ENERGY                                                     efiling.asp. Commenters can submit                                       California. Portions of the project are
                                                                                                                         brief comments up to 6,000 characters,                                   located within the Plumas National
                                                Federal Energy Regulatory                                                                                                                         Forest.
                                                                                                                         without prior registration, using the
                                                Commission                                                                                                                                           g. Filed Pursuant to: Federal Power
                                                                                                                         eComment system at http://
                                                                                                                                                                                                  Act, 16 U.S.C. 791(a)–825(r).
                                                                                                                         www.ferc.gov/docs-filing/
                                                [Project No. 1510–018]                                                                                                                               h. Applicant Contact: Alan Soneda,
                                                                                                                         ecomment.asp. You must include your                                      PG&E, Mail Code N13C, P. 0. Box
                                                City of Kaukauna, Wisconsin; Notice of                                   name and contact information at the end                                  770000, San Francisco, California
                                                Availability of Environmental                                            of your comments. For assistance,                                        94177–0001; (415) 973–4054.
                                                Assessment                                                               please contact FERC Online Support. In                                      i. FERC Contact: Alan Mitchnick at
                                                                                                                         lieu of electronic filing, please send a                                 (202) 502–6074 or alan.mitchnick@
                                                   In accordance with the National                                       paper copy to: Secretary, Federal Energy                                 ferc.gov.
                                                Environmental Policy Act of 1969 and                                     Regulatory Commission, 888 First Street                                     j. Deadline for filing motions to
                                                the Federal Energy Regulatory                                            NE, Washington, DC 20426. The first                                      intervene and protests, comments,
                                                Commission’s (Commission)                                                page of any filing should include docket                                 recommendations, preliminary terms
                                                regulations, 18 CFR part 380, the Office                                 number P–1510–018.                                                       and conditions, and preliminary
                                                of Energy Projects has reviewed the                                         For further information, contact Erin                                 prescriptions: 60 days from the issuance
                                                application for a new license for the                                    Kimsey at (202) 502–8621 or by email at                                  date of this notice; reply comments are
                                                Kaukauna Hydro Project, located on the                                   erin.kimsey@ferc.gov.                                                    due 105 days from the issuance date of
                                                Lower Fox River, in the City of                                            Dated: August 7, 2018.                                                 this notice.
                                                Kaukauna, Outagamie County,                                              Kimberly D. Bose,                                                           The Commission strongly encourages
                                                Wisconsin, and has prepared an                                                                                                                    electronic filing. Please file motions to
                                                                                                                         Secretary.
                                                Environmental Assessment (EA) for the                                                                                                             intervene, protests, comments,
                                                                                                                         [FR Doc. 2018–17290 Filed 8–10–18; 8:45 am]
                                                project.                                                                                                                                          recommendations, preliminary terms
                                                                                                                         BILLING CODE 6717–01–P
                                                   The EA contains staff’s analysis of the                                                                                                        and conditions, and preliminary
                                                potential environmental impacts of the                                                                                                            fishway prescriptions using the
                                                project and concludes that licensing the                                                                                                          Commission’s eFiling system at http://
                                                                                                                         DEPARTMENT OF ENERGY
                                                project, with appropriate environmental                                                                                                           www.ferc.gov/docs-filing/efiling.asp.
                                                protective measures, would not                                           Federal Energy Regulatory                                                Commenters can submit brief comments
                                                constitute a major federal action that                                   Commission                                                               up to 6,000 characters, without prior
                                                would significantly affect the quality of                                                                                                         registration, using the eComment system
                                                the human environment.                                                   [Project No. 619–164]
                                                                                                                                                                                                  at http://www.ferc.gov/docs-filing/
                                                   A copy of the EA is available for                                                                                                              ecomment.asp. You must include your
                                                                                                                         Pacific Gas and Electric Company and
                                                review at the Commission in the Public                                                                                                            name and contact information at the end
                                                                                                                         City of Santa Clara, California; Notice
                                                Reference Room or may be viewed on                                                                                                                of your comments. For assistance,
                                                                                                                         of Application Accepted for Filing,
                                                the Commission’s website at http://                                                                                                               please contact FERC Online Support at
                                                                                                                         Soliciting Motions To Intervene and
                                                www.ferc.gov using the ‘‘eLibrary’’ link.
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                                         Protests, Ready for Environmental                                        FERCOnlineSupport@ferc.gov, (866)
                                                Enter the docket number excluding the                                                                                                             208–3676 (toll free), or (202) 502–8659
                                                                                                                         Analysis, and Soliciting Comments,
                                                last three digits in the docket number                                                                                                            (TTY). In lieu of electronic filing, please
                                                                                                                         Recommendations, Preliminary Terms
                                                field to access the document. For                                                                                                                 send a paper copy to: Secretary, Federal
                                                                                                                         and Conditions, and Preliminary
                                                assistance, contact FERC Online                                                                                                                   Energy Regulatory Commission, 888
                                                                                                                         Fishway Prescriptions
                                                Support at FERCOnlineSupport@                                                                                                                     First Street NE, Washington, DC 20426.
                                                ferc.gov, (866) 208–3676 (toll free), or                                   Take notice that the following                                         The first page of any filing should
                                                (202) 502–8659 (TTY).                                                    hydroelectric application has been filed                                 include docket number P–619–164.


                                           VerDate Sep<11>2014        20:42 Aug 10, 2018         Jkt 244001      PO 00000       Frm 00050       Fmt 4703      Sfmt 4703      E:\FR\FM\13AUN1.SGM             13AUN1


                                                                             Federal Register / Vol. 83, No. 156 / Monday, August 13, 2018 / Notices                                             40031

                                                   The Commission’s Rules of Practice                   elevation of approximately 5,022 feet.                   There are no associated transmission
                                                require all intervenors filing documents                Water is conveyed from Lower Bucks                    lines at the Bucks Creek Powerhouse.
                                                with the Commission to serve a copy of                  Lake to the Grizzly Powerhouse by the                 The powerhouse connects directly to
                                                that document on each person on the                     Grizzly Powerhouse Tunnel.                            the non-project switchyard adjacent to
                                                official service list for the project.                  Grizzly Powerhouse Tunnel (Grizzly                    the powerhouse part of the
                                                Further, if an intervenor files comments                   Development)                                       interconnected transmission system.
                                                or documents with the Commission                                                                                 Bucks Creek Powerhouse discharges
                                                                                                           The 12,320-foot-long Grizzly                       the project’s water flow in the North
                                                relating to the merits of an issue that
                                                                                                        Powerhouse Tunnel (including a 4,900-                 Fork Feather River, 1 mile upstream of
                                                may affect the responsibilities of a
                                                                                                        foot-long buried penstock) conveys the                Rock Creek Powerhouse, part of PG&E’s
                                                particular resource agency, they must
                                                                                                        water flow from Lower Bucks Lake to                   Rock Creek-Cresta Hydroelectric Project
                                                also serve a copy of the document on
                                                                                                        Grizzly Powerhouse. The maximum                       (FERC Project No. 1962).
                                                that resource agency.
                                                   k. This application has been accepted                flow capacity is 400 cfs.                                m. A copy of the application is
                                                for filing and is now ready for                         Grizzly Powerhouse (Grizzly                           available for review at the Commission
                                                environmental analysis.                                    Development)                                       in the Public Reference Room or may be
                                                   l. Project Description:                                 The Grizzly Powerhouse is a 65-foot-               viewed on the Commission’s website at
                                                Bucks Lake Dam and Reservoir (Bucks                     long by 55-foot-wide, steel frame and                 http://www.ferc.gov using the
                                                   Creek Development)                                   concrete building constructed from                    ‘‘eLibrary’’ link. Enter the docket
                                                   The Bucks Lake Dam consists of a                     reinforced concrete. The powerhouse                   number excluding the last three digits in
                                                rock-fill with concrete face dam. It has                contains one turbine-generator with a                 the docket number field to access the
                                                a structural height of 123 feet and a                   maximum capacity of 20 megawatts                      document. For assistance, contact FERC
                                                length of 1,320 feet. Bucks Creek Dam                   (MW). The powerhouse produces an                      Online Support. A copy is also available
                                                impounds Bucks Lake, which extends 5                    average annual generation production of               for inspection and reproduction at the
                                                miles from the dam. Total storage in the                47.4 gigawatt-hours (GWh). Grizzly                    address in item h above.
                                                1,827-acre reservoir is approximately                   Powerhouse discharges the project’s                      Register online at http://
                                                105,605 acre-feet at the normal                         water flow directly into the Grizzly                  www.ferc.gov/docs-filing/
                                                maximum water surface elevation of                      Forebay.                                              esubscription.asp to be notified via
                                                approximately 5,157 feet. From Bucks                       A 4.2-mile-long, 115-kilovolt (kV)                 email of new filings and issuances
                                                Lake, the project’s water flow is released              transmission line transmits power from                related to this or other pending projects.
                                                immediately downstream into Lower                       Grizzly Powerhouse to PG&E’s 115-kV                   For assistance, contact FERC Online
                                                Bucks Lake.                                             Caribou-Sycamore Transmission Line,                   Support.
                                                                                                                                                                 n. Anyone may submit comments, a
                                                Three Lakes Dam and Reservoir, and                      part of the interconnected system.
                                                                                                                                                              protest, or a motion to intervene in
                                                   Milk Ranch Conduit (Bucks Creek                      Grizzly Forebay Dam and Reservoir                     accordance with the requirements of
                                                   Development)                                            (Bucks Creek Development)                          Rules of Practice and Procedure, 18 CFR
                                                   The Three Lakes dam consists of a                       The Grizzly Forebay Dam consists of                385.210, .211, and .214. In determining
                                                rock-fill dam with a structural height of               a concrete arch dam with a structural                 the appropriate action to take, the
                                                30 feet and a length of 584 feet. Three                 height of 98 feet and a length of 520 feet.           Commission will consider all protests or
                                                Lakes Dam impounds the flow of Milk                     Grizzly Forebay Dam impounds the                      other comments filed, but only those
                                                Ranch Creek, forming Upper Lake,                        Grizzly Forebay, forming the Grizzly                  who file a motion to intervene in
                                                Middle Lake, and Lower Lake,                            Forebay Reservoir that extends                        accordance with the Commission’s
                                                collectively known as Three Lakes                       approximately 0.8 mile. Total storage in              Rules may become a party to the
                                                Reservoir. These water bodies are                       the 38-acre reservoir is approximately                proceeding. Any comments, protests, or
                                                hydraulically linked and are                            1,112 acre-feet at the normal maximum                 motions to intervene must be received
                                                approximately 0.75 mile from the dam.                   water surface elevation of                            on or before the specified comment date
                                                Total storage in the 40-acre reservoir is               approximately 4,316 feet.                             for the particular application.
                                                approximately 605 acre-feet at the                                                                               All filings must (1) bear in all capital
                                                                                                        Grizzly Forebay Tunnel (Bucks Creek
                                                normal maximum water surface                                                                                  letters the title ‘‘PROTEST’’, ‘‘MOTION
                                                                                                           Development)
                                                elevation of approximately 6,078 feet.                                                                        TO INTERVENE’’, ‘‘COMMENTS,’’
                                                   Milk Ranch Conduit conveys the                          From Grizzly Forebay, the project’s                ‘‘REPLY COMMENTS,’’
                                                project’s water flow from Three Lakes                   water flow is conveyed through the                    ‘‘RECOMMENDATIONS,’’
                                                Reservoir and feeder diversions to                      horseshoe-shaped Grizzly Forebay                      ‘‘PRELIMINARY TERMS AND
                                                Lower Bucks Lake. The maximum                           Tunnel. The tunnel is 9,575-foot-long                 CONDITIONS,’’ or ‘‘PRELIMINARY
                                                capacity of the approximately 8-mile-                   with two 4,786-foot-long penstocks                    FISHWAY PRESCRIPTIONS;’’ (2) set
                                                long conduit is about 70 cubic foot per                 leading to Bucks Creek Powerhouse.                    forth in the heading the name of the
                                                second (cfs). It collects additional flow               The maximum flow capacity is 400 cfs.                 applicant and the project number of the
                                                from several diversions located on                      Bucks Creek Powerhouse (Bucks Creek                   application to which the filing
                                                unnamed tributaries.                                       Development)                                       responds; (3) furnish the name, address,
                                                Lower Bucks Lake Dam and Reservoir                         The project’s water flow is conveyed               and telephone number of the person
                                                   (Bucks Creek Development)                            through the Grizzly Forebay Tunnel to                 protesting or intervening; and (4)
                                                   The Lower Bucks Lake Dam consists                    Bucks Creek Powerhouse. The Bucks                     otherwise comply with the requirements
                                                of a concrete arch dam with a structural                Creek Powerhouse is a 47-foot-long by                 of 18 CFR 385.2001 through 385.2005.
sradovich on DSK3GMQ082PROD with NOTICES




                                                height of 99 feet and a length of 500 feet.             132-foot-wide, steel frame and concrete               All comments, recommendations, terms
                                                Lower Bucks Creek Dam impounds                          building constructed from reinforced                  and conditions or prescriptions must set
                                                Lower Bucks Lake, which extends                         concrete, containing two turbine-                     forth their evidentiary basis and
                                                approximately 1.1 miles from the dam.                   generators with a total maximum                       otherwise comply with the requirements
                                                Total storage in the 136-acre reservoir is              capacity of 65 MW. The powerhouse                     of 18 CFR 4.34(b). Agencies may obtain
                                                approximately 5,843 acre-feet at the                    produces an average annual generation                 copies of the application directly from
                                                normal maximum water surface                            of 223.6 GWh.                                         the applicant. A copy of any protest or


                                           VerDate Sep<11>2014   20:42 Aug 10, 2018   Jkt 244001   PO 00000   Frm 00051   Fmt 4703   Sfmt 4703   E:\FR\FM\13AUN1.SGM   13AUN1


                                                40032                                 Federal Register / Vol. 83, No. 156 / Monday, August 13, 2018 / Notices

                                                motion to intervene must be served                                      accompanied by proof of service on all                                     o. Procedural Schedule: The
                                                upon each representative of the                                         persons listed in the service list                                       application will be processed according
                                                applicant specified in the particular                                   prepared by the Commission in this                                       to the following revised Hydro
                                                application. A copy of all other filings                                proceeding, in accordance with 18 CFR                                    Licensing Schedule. Revisions to the
                                                in reference to this application must be                                4.34(b) and 385.2010.                                                    schedule may be made as appropriate.

                                                                                                                                     Milestone                                                                                                 Target date

                                                Filing of recommendations, preliminary terms and conditions, and preliminary fishway prescriptions ...........................................                                               October 2018.
                                                Commission issues Draft Environmental Statement (EIS) ...............................................................................................................                        April 2019.
                                                Comments on draft EIS ....................................................................................................................................................................   June 2019.
                                                Modified terms and conditions Commission issues final EIS ..........................................................................................................                         August 2019.



                                                   p. Final amendments to the                                             Description: § 4(d) Rate Filing: Cap                                   DEPARTMENT OF ENERGY
                                                application must be filed with the                                      Rel Neg Rate Agmt (EM Energy OH
                                                Commission no later than 30 days from                                   35451 to BP 37304) to be effective 8/3/                                  Federal Energy Regulatory
                                                the issuance date of this notice.                                       2018.                                                                    Commission
                                                   q. A license applicant must file no
                                                                                                                          Filed Date: 8/3/18.
                                                later than 60 days following the date of                                                                                                         [Docket No. IN18–7–000]
                                                issuance of the notice of acceptance and                                  Accession Number: 20180803–5133.
                                                ready for environmental analysis                                          Comments Due: 5 p.m. ET 8/15/18.                                       Footprint Power LLC; Footprint Power
                                                provided for in 5.22: (1) a copy of the                                                                                                          Salem Harbor Operations LLC; Notice
                                                water quality certification; (2) a copy of                                Docket Numbers: RP18–1047–000.
                                                                                                                                                                                                 of Designation of Commission Staff as
                                                the request for certification, including                                  Applicants: Global LNG S.A.S.,Total                                    Non-Decisional
                                                proof of the date on which the certifying                               Gas & Power North America, Inc.
                                                agency received the request; or (3)                                       Description: Joint Petition for                                           With respect to an order issued by the
                                                evidence of waiver of water quality                                     Temporary Waivers of Capacity Release                                    Commission in the above-captioned
                                                certification.                                                          Regulations and Policies, et al. of Global                               docket,1 with the exceptions noted
                                                  Dated: August 6, 2018.                                                LNG S.A.S., et al.                                                       below, the staff of the Office of
                                                Kimberly D. Bose,                                                         Filed Date: 8/3/18.                                                    Enforcement are designated as non-
                                                Secretary.                                                                                                                                       decisional in deliberations by the
                                                                                                                          Accession Number: 20180803–5158.                                       Commission in this docket.
                                                [FR Doc. 2018–17305 Filed 8–10–18; 8:45 am]
                                                BILLING CODE 6717–01–P
                                                                                                                          Comments Due: 5 p.m. ET 8/15/18.                                       Accordingly, pursuant to 18 CFR
                                                                                                                           The filings are accessible in the                                     385.2202 (2017), they will not serve as
                                                                                                                        Commission’s eLibrary system by                                          advisors to the Commission or take part
                                                DEPARTMENT OF ENERGY                                                                                                                             in the Commission’s review of any offer
                                                                                                                        clicking on the links or querying the
                                                                                                                        docket number.                                                           of settlement. Likewise, as non-
                                                Federal Energy Regulatory                                                                                                                        decisional staff, pursuant to 18 CFR
                                                Commission                                                                 Any person desiring to intervene or                                   385.2201 (2017), they are prohibited
                                                                                                                        protest in any of the above proceedings                                  from communicating with advisory staff
                                                Combined Notice of Filings                                              must file in accordance with Rules 211                                   concerning any deliberations in this
                                                  Take notice that the Commission has                                   and 214 of the Commission’s                                              docket.
                                                received the following Natural Gas                                      Regulations (18 CFR 385.211 and
                                                                                                                        385.214) on or before 5:00 p.m. Eastern                                     Exceptions to this designation as non-
                                                Pipeline Rate and Refund Report filings:
                                                                                                                        time on the specified comment date.                                      decisional are:
                                                Filings Instituting Proceedings                                         Protests may be considered, but                                          Jeremy Medovoy
                                                   Docket Numbers: RP10–996–000.                                        intervention is necessary to become a                                    Catherine Collins
                                                   Applicants: Dominion Cove Point                                      party to the proceeding.
                                                LNG, LP.                                                                                                                                         Katherine Walsh
                                                                                                                           eFiling is encouraged. More detailed
                                                   Description: Report Filing: DECP—                                                                                                             Mark Nagle
                                                2018 Report of Operational Sales and                                    information relating to filing
                                                                                                                        requirements, interventions, protests,                                   Benjamin Jarrett
                                                Purchases of Gas.
                                                   Filed Date: 7/31/18.                                                 service, and qualifying facilities filings                               John Karp
                                                   Accession Number: 20180731–5146.                                     can be found at: http://www.ferc.gov/
                                                                                                                                                                                                 Alfred Jasins
                                                   Comments Due: 5 p.m. ET 8/13/18.                                     docs-filing/efiling/filing-req.pdf. For
                                                                                                                        other information, call (866) 208–3676                                   Jorge Casillas
                                                   Docket Numbers: RP18–1045–000.
                                                   Applicants: Transcontinental Gas                                     (toll free). For TTY, call (202) 502–8659.                                 Dated: August 6, 2018.
                                                Pipe Line Company, LLC.                                                   Dated: August 7, 2018.                                                 Kimberly D. Bose,
                                                   Description: § 4(d) Rate Filing:                                     Nathaniel J. Davis, Sr.,                                                 Secretary.
                                                Pooling Charges—Zones 5 and 6 to be
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                                        Deputy Secretary.                                                        [FR Doc. 2018–17311 Filed 8–10–18; 8:45 am]
                                                effective 10/1/2018.
                                                                                                                        [FR Doc. 2018–17352 Filed 8–10–18; 8:45 am]                              BILLING CODE 6717–01–P
                                                   Filed Date: 8/3/18.
                                                   Accession Number: 20180803–5034.                                     BILLING CODE 6717–01–P
                                                   Comments Due: 5 p.m. ET 8/15/18.
                                                   Docket Numbers: RP18–1046–000.
                                                   Applicants: Texas Gas Transmission,                                                                                                             1 Footprint Power LLC, et al., 163 FERC ¶ 61,198

                                                LLC.                                                                                                                                             (2018).



                                           VerDate Sep<11>2014        20:42 Aug 10, 2018        Jkt 244001      PO 00000       Frm 00052       Fmt 4703      Sfmt 9990      E:\FR\FM\13AUN1.SGM             13AUN1



Document Created: 2018-08-11 00:27:22
Document Modified: 2018-08-11 00:27:22
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 40030 