83_FR_44846 83 FR 44676 - First Energy Corp.; First Energy Solutions; FirstEnergy Nuclear Generation; FirstEnergy Nuclear Operating Company

83 FR 44676 - First Energy Corp.; First Energy Solutions; FirstEnergy Nuclear Generation; FirstEnergy Nuclear Operating Company

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 83, Issue 170 (August 31, 2018)

Page Range44676-44677
FR Document2018-18923

The U.S. Nuclear Regulatory Commission (NRC) is giving notice that by petition dated March 27, 2018, Environmental Law and Policy Center (ELPC) (the petitioner) has requested that the NRC take enforcement action with regard to First Energy Corp. (FE), First Energy Solutions (FES), FirstEnergy Nuclear Generation (NG), and FirstEnergy Nuclear Operating Company (FENOC). The petitioner's requests are included in the SUPPLEMENTARY INFORMATION section of this document.

Federal Register, Volume 83 Issue 170 (Friday, August 31, 2018)
[Federal Register Volume 83, Number 170 (Friday, August 31, 2018)]
[Notices]
[Pages 44676-44677]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-18923]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-334, 50-412, 50-346, and 50-440; NRC-2018-0174]


First Energy Corp.; First Energy Solutions; FirstEnergy Nuclear 
Generation; FirstEnergy Nuclear Operating Company

AGENCY: Nuclear Regulatory Commission.

ACTION: 10 CFR 2.206 request; receipt.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is giving notice 
that by petition dated March 27, 2018, Environmental Law and Policy 
Center (ELPC) (the petitioner) has requested that the NRC take 
enforcement action with regard to First Energy Corp. (FE), First Energy 
Solutions (FES), FirstEnergy Nuclear Generation (NG), and FirstEnergy 
Nuclear Operating Company (FENOC). The petitioner's requests are 
included in the SUPPLEMENTARY INFORMATION section of this document.

ADDRESSES: Please refer to Docket ID NRC-2018-0174 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0174. Address 
questions about NRC dockets to Jennifer Borges; telephone: 301-287-
9127; email: [email protected]. For technical questions, contact 
the individuals listed in the FOR FURTHER INFORMATION CONTACT section 
of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to [email protected]. The ADAMS accession number for each 
document referenced (if it is available in ADAMS) is provided the first 
time that it is mentioned in this document. In addition, for the 
convenience of the reader, the ADAMS accession numbers are provided in 
a table in the ``Availability of Documents'' section of this document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Bhalchandra K. Vaidya, Office of 
Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001; telephone: 301-415-3308; email: 
[email protected]; or Perry Buckberg, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-1383; email: [email protected]. 
Both are staff of the U.S. Nuclear Regulatory Commission, Washington, 
DC 20555-0001.

SUPPLEMENTARY INFORMATION: On March 27, 2018, the petitioner requested 
that the NRC take enforcement action with regard to FE, FES, NG, and 
FENOC operations in Ohio and Pennsylvania at Beaver Valley Power 
Station (BVPS), Units 1 and 2; Davis-Besse Nuclear Power Station 
(DBNPS), Unit 1; and Perry Nuclear Power Plant (PNPP), Unit 1 (ADAMS 
Accession No. ML18094A642). The petitioner requested that the NRC take 
the following actions:

[[Page 44677]]

(A) Demands for Information

    (1) Promptly issue a Demand for Information to FE, FES, NG, and 
FENOC requesting site-specific decommissioning funding plans for the 
BVNPS, DBNPS, and PNPP;
    (2) Promptly issue a Demand for Information to FE, FES, NG, and 
FENOC regarding their reliance on external trust funds from FE and FES 
to satisfy their decommissioning financial obligations;
    (3) Promptly issue a Demand for Information to FE, FES, NG, and 
FENOC regarding their continued reliance on Parent Guarantees from FE 
to satisfy decommissioning funding obligations, including the ability 
of FE to satisfy the Parent Guarantee financial test under title 10 of 
the Code of Federal Regulations (10 CFR) part 30, appendix A;
    (4) Promptly issue a Demand for Information to FES, NG, and FENOC 
to the extent that they are relying on Parent Guarantees from FES to 
satisfy decommissioning funding obligations, including the ability of 
FES to satisfy the Parent Guarantee financial test under 10 CFR part 
30, appendix A;
    (5) Promptly issue a Demand for Information to FE, FES, NG, and 
FENOC regarding their proposed investment and financial contribution 
plans to make up the current decommissioning shortfall; and
    (6) Promptly issue a Demand for Information to FE and FES, 
respectively, regarding each of their commitments to guarantee NG and 
FENOC's decommissioning shortfall in the event of bankruptcy.

(B) Notice of Violation and Penalties

    (1) Promptly issue a Notice of Violation against FE, FES, NG, and 
FENOC for operating nuclear facilities without sufficient 
decommissioning funds in violation of 42 United States Code Annotated 
(U.S.C.A.), Section 2201(x)(1) and 10 CFR 50.75;
    (2) Promptly issue civil penalties against FE, FES, NG, and FENOC 
for operating nuclear facilities without sufficient decommissioning 
funds in violation of 42 U.S.C.A. Section 2201(x)(1) and 10 CFR 50.75; 
and
    (3) Promptly issue an Order to suspend NG, and FENOC's licenses for 
BVNPS, DBNPS, and PNPP.
    The ELPC also urges the NRC to prohibit NG and FENOC from placing 
their nuclear facilities into SAFSTOR for purely financial reasons. In 
addition, ELPC requests that this Petition be given immediate emergency 
consideration in light of FE's and FES' rapidly deteriorating financial 
conditions.
    The basis for ELPC's request is summarized below:
    1. NG and FENOC's decommissioning trust amounts are insufficient on 
their own to provide reasonable assurance of funding.
    2. FE cannot rely on rate increases forced on retail ratepayers to 
pay for the decommissioning trust fund shortfalls.
    3. The costs, including SAFSTOR costs, may still be much higher 
than expected due to significantly higher shortfalls as reported by the 
Callan Institute and recognized flaws in the NRC's cost estimate 
formula.
    4. On March 28, 2018, FES and FENOC announced that they would 
permanently retire all four of their reactors within the next 3 years. 
If plants close in 2020 and 2021, the funds cannot grow to levels that 
will pay for complete decommissioning.
    5. Parent companies FE and FES filed for bankruptcy on March 31, 
2018.
    The request is being treated pursuant to 10 CFR 2.206 of the 
Commission's regulations. The request has been referred to the Director 
of the Office of Nuclear Reactor Regulation. As provided by 10 CFR 
2.206, appropriate action will be taken on this petition within a 
reasonable time.
    The petitioner met with the Petition Review Board on June 19, 2018, 
to discuss the petition; the transcript of that meeting is a supplement 
to the petition (ADAMS Accession No. ML18194A395). The petition and the 
results of the discussion at the June 19, 2018, meeting would be 
considered in establishing the schedule for the review of the petition.

    Dated at Rockville, Maryland, this 27th day of August 2018.

    For the Nuclear Regulatory Commission.
Ho K. Nieh,
Director, Office of Nuclear Reactor Regulation.
[FR Doc. 2018-18923 Filed 8-30-18; 8:45 am]
 BILLING CODE 7590-01-P



                                               44676                         Federal Register / Vol. 83, No. 170 / Friday, August 31, 2018 / Notices

                                               Saturday, October 6, 2018, Conference                   available through the NRC Public                      You may obtain publicly-available
                                               Room 1C3 and 1C5, 11601 Landsdown                       Document Room at pdr.resource@                        information related to this document
                                               Street, North Bethesda, MD 20852                        nrc.gov, or by calling the PDR at 1–800–              using any of the following methods:
                                                  8:30 p.m.–12:00 p.m.: Preparation of                 397–4209, or from the Publicly                           • Federal Rulemaking website: Go to
                                               ACRS Report/Retreat (Open/Closed)—                      Available Records System (PARS)                       http://www.regulations.gov and search
                                               The Committee will continue its                         component of NRC’s document system                    for Docket ID NRC–2018–0174. Address
                                               discussion of the ACRS report and                       (ADAMS) which is accessible from the                  questions about NRC dockets to Jennifer
                                               potential retreat items. [NOTE: A                       NRC website at http://www.nrc.gov/                    Borges; telephone: 301–287–9127;
                                               portion of this meeting may be closed                   reading-rm/adams.html or http://                      email: Jennifer.Borges@nrc.gov. For
                                               pursuant to 5 U.S.C. 552b(c)(2) and (6)                 www.nrc.gov/reading-rm/doc-                           technical questions, contact the
                                               to discuss organizational and personnel                 collections/#ACRS/.                                   individuals listed in the FOR FURTHER
                                               matters that relate solely to internal                     Video teleconferencing service is                  INFORMATION CONTACT section of this
                                               personnel rules and practices of the                    available for observing open sessions of              document.
                                               ACRS, and information the release of                    ACRS meetings. Those wishing to use                      • NRC’s Agencywide Documents
                                               which would constitute a clearly                        this service should contact Mr. Theron                Access and Management System
                                               unwarranted invasion of personal                        Brown, ACRS Audio Visual Technician                   (ADAMS): You may obtain publicly-
                                               privacy]                                                (301–415–6702), between 7:30 a.m. and                 available documents online in the
                                                  Procedures for the conduct of and                    3:45 p.m. (ET), at least 10 days before               ADAMS Public Documents collection at
                                               participation in ACRS meetings were                     the meeting to ensure the availability of             http://www.nrc.gov/reading-rm/
                                               published in the Federal Register on                    this service. Individuals or                          adams.html. To begin the search, select
                                               October 4, 2017 (82 FR 46312). In                       organizations requesting this service                 ‘‘Begin Web-based ADAMS Search.’’ For
                                               accordance with those procedures, oral                  will be responsible for telephone line                problems with ADAMS, please contact
                                               or written views may be presented by                    charges and for providing the                         the NRC’s Public Document Room (PDR)
                                               members of the public, including                        equipment and facilities that they use to             reference staff at 1–800–397–4209, 301–
                                               representatives of the nuclear industry.                establish the video teleconferencing                  415–4737, or by email to pdr.resource@
                                               Persons desiring to make oral statements                link. The availability of video                       nrc.gov. The ADAMS accession number
                                               should notify Quynh Nguyen, Cognizant                   teleconferencing services is not                      for each document referenced (if it is
                                               ACRS Staff (Telephone: 301–415–5844,                    guaranteed.                                           available in ADAMS) is provided the
                                               Email: Quynh.Nguyen@nrc.gov), 5 days                      Dated: August 28, 2018.                             first time that it is mentioned in this
                                               before the meeting, if possible, so that                Russell E. Chazell,                                   document. In addition, for the
                                               appropriate arrangements can be made                    Federal Advisory Committee Management                 convenience of the reader, the ADAMS
                                               to allow necessary time during the                      Officer, Office of the Secretary.                     accession numbers are provided in a
                                               meeting for such statements. In view of                 [FR Doc. 2018–18933 Filed 8–30–18; 8:45 am]           table in the ‘‘Availability of Documents’’
                                               the possibility that the schedule for                   BILLING CODE 7590–01–P
                                                                                                                                                             section of this document.
                                               ACRS meetings may be adjusted by the                                                                             • NRC’s PDR: You may examine and
                                               Chairman as necessary to facilitate the                                                                       purchase copies of public documents at
                                               conduct of the meeting, persons                         NUCLEAR REGULATORY                                    the NRC’s PDR, Room O1–F21, One
                                               planning to attend should check with                    COMMISSION                                            White Flint North, 11555 Rockville
                                               the Cognizant ACRS staff if such                                                                              Pike, Rockville, Maryland 20852.
                                                                                                       [Docket Nos. 50–334, 50–412, 50–346, and
                                               rescheduling would result in major                      50–440; NRC–2018–0174]                                FOR FURTHER INFORMATION CONTACT:
                                               inconvenience. The bridgeline number                                                                          Bhalchandra K. Vaidya, Office of
                                               for the meeting is 866–822–3032,                        First Energy Corp.; First Energy                      Nuclear Reactor Regulation, U.S.
                                               passcode 8272423#.                                      Solutions; FirstEnergy Nuclear                        Nuclear Regulatory Commission,
                                                  Thirty-five hard copies of each                      Generation; FirstEnergy Nuclear                       Washington, DC 20555–0001; telephone:
                                               presentation or handout should be                       Operating Company                                     301–415–3308; email:
                                               provided 30 minutes before the meeting.                                                                       Bhalchandra.Vaidya@nrc.gov; or Perry
                                               In addition, one electronic copy of each                AGENCY:  Nuclear Regulatory
                                                                                                                                                             Buckberg, Office of Nuclear Reactor
                                               presentation should be emailed to the                   Commission.
                                                                                                                                                             Regulation, U.S. Nuclear Regulatory
                                               Cognizant ACRS Staff one day before                     ACTION: 10 CFR 2.206 request; receipt.                Commission, Washington, DC 20555–
                                               meeting. If an electronic copy cannot be                                                                      0001; telephone: 301–415–1383; email:
                                               provided within this timeframe,                         SUMMARY:   The U.S. Nuclear Regulatory
                                                                                                       Commission (NRC) is giving notice that                Perry.Buckberg@nrc.gov. Both are staff
                                               presenters should provide the Cognizant                                                                       of the U.S. Nuclear Regulatory
                                               ACRS Staff with a CD containing each                    by petition dated March 27, 2018,
                                                                                                       Environmental Law and Policy Center                   Commission, Washington, DC 20555–
                                               presentation at least 30 minutes before                                                                       0001.
                                               the meeting.                                            (ELPC) (the petitioner) has requested
                                                  In accordance with Subsection 10(d)                  that the NRC take enforcement action                  SUPPLEMENTARY INFORMATION:    On March
                                               of Public Law 92–463 and 5 U.S.C.                       with regard to First Energy Corp. (FE),               27, 2018, the petitioner requested that
                                               552b(c), certain portions of this meeting               First Energy Solutions (FES),                         the NRC take enforcement action with
                                               may be closed, as specifically noted                    FirstEnergy Nuclear Generation (NG),                  regard to FE, FES, NG, and FENOC
                                               above. Use of still, motion picture, and                and FirstEnergy Nuclear Operating                     operations in Ohio and Pennsylvania at
                                               television cameras during the meeting                   Company (FENOC). The petitioner’s                     Beaver Valley Power Station (BVPS),
daltland on DSKBBV9HB2PROD with NOTICES




                                               may be limited to selected portions of                  requests are included in the                          Units 1 and 2; Davis-Besse Nuclear
                                               the meeting as determined by the                        SUPPLEMENTARY INFORMATION section of                  Power Station (DBNPS), Unit 1; and
                                               Chairman. Electronic recordings will be                 this document.                                        Perry Nuclear Power Plant (PNPP), Unit
                                               permitted only during the open portions                 ADDRESSES: Please refer to Docket ID                  1 (ADAMS Accession No.
                                               of the meeting.                                         NRC–2018–0174 when contacting the                     ML18094A642). The petitioner
                                                  ACRS meeting agendas, meeting                        NRC about the availability of                         requested that the NRC take the
                                               transcripts, and letter reports are                     information regarding this document.                  following actions:


                                          VerDate Sep<11>2014   18:42 Aug 30, 2018   Jkt 244001   PO 00000   Frm 00115   Fmt 4703   Sfmt 4703   E:\FR\FM\31AUN1.SGM   31AUN1


                                                                             Federal Register / Vol. 83, No. 170 / Friday, August 31, 2018 / Notices                                          44677

                                               (A) Demands for Information                               1. NG and FENOC’s decommissioning                   Operating License Nos. NPF–37 and
                                                  (1) Promptly issue a Demand for                      trust amounts are insufficient on their               NPF–66, issued to Exelon Generation
                                               Information to FE, FES, NG, and FENOC                   own to provide reasonable assurance of                Company (EGC), LLC, for operation of
                                               requesting site-specific                                funding.                                              the Byron Station, Unit Nos. 1 and 2.
                                               decommissioning funding plans for the                     2. FE cannot rely on rate increases                 The proposed amendment extends the
                                               BVNPS, DBNPS, and PNPP;                                 forced on retail ratepayers to pay for the            Completion Time for Technical
                                                  (2) Promptly issue a Demand for                      decommissioning trust fund shortfalls.                Specification 3.8.1, ‘‘AC Sources-
                                               Information to FE, FES, NG, and FENOC                     3. The costs, including SAFSTOR                     Operating,’’ Required Action A.2, on a
                                               regarding their reliance on external trust              costs, may still be much higher than                  one-time, temporary basis based on a
                                               funds from FE and FES to satisfy their                  expected due to significantly higher                  risk-informed approach.
                                               decommissioning financial obligations;                  shortfalls as reported by the Callan                  DATES: Submit comments by October 1,
                                                  (3) Promptly issue a Demand for                      Institute and recognized flaws in the                 2018. Requests for a hearing or petition
                                               Information to FE, FES, NG, and FENOC                   NRC’s cost estimate formula.                          for leave to intervene must be filed by
                                               regarding their continued reliance on                     4. On March 28, 2018, FES and                       October 30, 2018.
                                               Parent Guarantees from FE to satisfy                    FENOC announced that they would                       ADDRESSES: You may submit comments
                                               decommissioning funding obligations,                    permanently retire all four of their                  by any of the following methods:
                                               including the ability of FE to satisfy the              reactors within the next 3 years. If                     • Federal Rulemaking website: Go to
                                               Parent Guarantee financial test under                   plants close in 2020 and 2021, the funds              http://www.regulations.gov and search
                                               title 10 of the Code of Federal                         cannot grow to levels that will pay for               for Docket ID NRC–2018–0186. Address
                                               Regulations (10 CFR) part 30, appendix                  complete decommissioning.                             questions about NRC dockets to Jennifer
                                               A;                                                        5. Parent companies FE and FES filed                Borges; telephone: 301–287–9127;
                                                  (4) Promptly issue a Demand for                      for bankruptcy on March 31, 2018.                     email: Jennifer.Borges@nrc.gov. For
                                               Information to FES, NG, and FENOC to                      The request is being treated pursuant               technical questions, contact the
                                               the extent that they are relying on                     to 10 CFR 2.206 of the Commission’s                   individual listed in the FOR FURTHER
                                               Parent Guarantees from FES to satisfy                   regulations. The request has been                     INFORMATION CONTACT section of this
                                               decommissioning funding obligations,                    referred to the Director of the Office of             document.
                                               including the ability of FES to satisfy                 Nuclear Reactor Regulation. As                           • Mail comments to: May Ma, Office
                                               the Parent Guarantee financial test                     provided by 10 CFR 2.206, appropriate                 of Administration, Mail Stop: TWFN–
                                               under 10 CFR part 30, appendix A;                       action will be taken on this petition
                                                  (5) Promptly issue a Demand for                                                                            A60M, U.S. Nuclear Regulatory
                                                                                                       within a reasonable time.                             Commission, Washington, DC 20555–
                                               Information to FE, FES, NG, and FENOC                     The petitioner met with the Petition
                                               regarding their proposed investment                                                                           0001.
                                                                                                       Review Board on June 19, 2018, to                        For additional direction on obtaining
                                               and financial contribution plans to                     discuss the petition; the transcript of
                                               make up the current decommissioning                                                                           information and submitting comments,
                                                                                                       that meeting is a supplement to the                   see ‘‘Obtaining Information and
                                               shortfall; and                                          petition (ADAMS Accession No.
                                                  (6) Promptly issue a Demand for                                                                            Submitting Comments’’ in the
                                                                                                       ML18194A395). The petition and the                    SUPPLEMENTARY INFORMATION section of
                                               Information to FE and FES, respectively,                results of the discussion at the June 19,
                                               regarding each of their commitments to                                                                        this document.
                                                                                                       2018, meeting would be considered in
                                               guarantee NG and FENOC’s                                                                                      FOR FURTHER INFORMATION CONTACT: Joel
                                                                                                       establishing the schedule for the review
                                               decommissioning shortfall in the event                  of the petition.                                      S. Wiebe, Office of Nuclear Reactor
                                               of bankruptcy.                                                                                                Regulation, U.S. Nuclear Regulatory
                                                                                                         Dated at Rockville, Maryland, this 27th day         Commission, Washington, DC 20555–
                                               (B) Notice of Violation and Penalties                   of August 2018.                                       0001; telephone: 301–415–6606, email:
                                                  (1) Promptly issue a Notice of                         For the Nuclear Regulatory Commission.              Joel.Wiebe@nrc.gov.
                                               Violation against FE, FES, NG, and                      Ho K. Nieh,                                           SUPPLEMENTARY INFORMATION:
                                               FENOC for operating nuclear facilities                  Director, Office of Nuclear Reactor
                                               without sufficient decommissioning                      Regulation.                                           I. Obtaining Information and
                                               funds in violation of 42 United States                  [FR Doc. 2018–18923 Filed 8–30–18; 8:45 am]           Submitting Comments
                                               Code Annotated (U.S.C.A.), Section                      BILLING CODE 7590–01–P                                A. Obtaining Information
                                               2201(x)(1) and 10 CFR 50.75;
                                                  (2) Promptly issue civil penalties                                                                            Please refer to Docket ID NRC–2018–
                                               against FE, FES, NG, and FENOC for                      NUCLEAR REGULATORY                                    0186 when contacting the NRC about
                                               operating nuclear facilities without                    COMMISSION                                            the availability of information for this
                                               sufficient decommissioning funds in                                                                           action. You may obtain publicly-
                                                                                                       [Docket Nos. 50–454 and 50–455; NRC–                  available information related to this
                                               violation of 42 U.S.C.A. Section                        2018–0186]
                                               2201(x)(1) and 10 CFR 50.75; and                                                                              action by any of the following methods:
                                                  (3) Promptly issue an Order to                                                                                • Federal Rulemaking website: Go to
                                                                                                       Exelon Generation Company, LLC;
                                               suspend NG, and FENOC’s licenses for                                                                          http://www.regulations.gov and search
                                                                                                       Byron Station, Unit Nos. 1 and 2
                                               BVNPS, DBNPS, and PNPP.                                                                                       for Docket ID NRC–2018–0186.
                                                  The ELPC also urges the NRC to                       AGENCY:  Nuclear Regulatory                              • NRC’s Agencywide Documents
                                               prohibit NG and FENOC from placing                      Commission.                                           Access and Management System
                                               their nuclear facilities into SAFSTOR                   ACTION: License amendment application;                (ADAMS): You may obtain publicly-
daltland on DSKBBV9HB2PROD with NOTICES




                                               for purely financial reasons. In addition,              opportunity to comment, request a                     available documents online in the
                                               ELPC requests that this Petition be given               hearing, and petition for leave to                    ADAMS Public Documents collection at
                                               immediate emergency consideration in                    intervene.                                            http://www.nrc.gov/reading-rm/
                                               light of FE’s and FES’ rapidly                                                                                adams.html. To begin the search, select
                                               deteriorating financial conditions.                     SUMMARY:  The U.S. Nuclear Regulatory                 ‘‘Begin Web-based ADAMS Search.’’ For
                                                  The basis for ELPC’s request is                      Commission (NRC) is considering                       problems with ADAMS, please contact
                                               summarized below:                                       issuance of amendments to Facility                    the NRC’s Public Document Room (PDR)


                                          VerDate Sep<11>2014   18:42 Aug 30, 2018   Jkt 244001   PO 00000   Frm 00116   Fmt 4703   Sfmt 4703   E:\FR\FM\31AUN1.SGM   31AUN1



Document Created: 2018-08-31 00:54:10
Document Modified: 2018-08-31 00:54:10
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Action10 CFR 2.206 request; receipt.
ContactBhalchandra K. Vaidya, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-3308; email: [email protected]; or Perry Buckberg, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-1383; email: [email protected] Both are staff of the U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
FR Citation83 FR 44676 