83_FR_45867 83 FR 45692 - Exelon Generation Company, LLC; Peach Bottom Atomic Power Station, Units 2 and 3

83 FR 45692 - Exelon Generation Company, LLC; Peach Bottom Atomic Power Station, Units 2 and 3

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 83, Issue 175 (September 10, 2018)

Page Range45692-45694
FR Document2018-19462

The U.S. Nuclear Regulatory Commission will conduct a scoping process to gather information necessary to prepare an environmental impact statement (EIS) to evaluate the environmental impacts for the subsequent license renewal of the operating licenses for Peach Bottom Atomic Power Station, Units 2 and 3 (Peach Bottom). The NRC is seeking stakeholder input on this action and has scheduled a public meeting.

Federal Register, Volume 83 Issue 175 (Monday, September 10, 2018)
[Federal Register Volume 83, Number 175 (Monday, September 10, 2018)]
[Notices]
[Pages 45692-45694]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-19462]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-277 and 50-278; NRC-2018-0130]


Exelon Generation Company, LLC; Peach Bottom Atomic Power 
Station, Units 2 and 3

AGENCY: Nuclear Regulatory Commission.

ACTION: Intent to conduct scoping process and prepare environmental 
impact statement; public meeting and request for comment.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission will conduct a scoping 
process to gather information necessary to prepare an environmental 
impact statement (EIS) to evaluate the environmental impacts for the 
subsequent license renewal of the operating licenses for Peach Bottom 
Atomic Power Station, Units 2 and 3 (Peach Bottom). The NRC is seeking 
stakeholder input on this action and has scheduled a public meeting.

DATES: Submit comments by October 10, 2018. Comments received after 
this date will be considered if it is practical to do so, but assurance 
of consideration cannot be given to comments received after this date.

ADDRESSES: You may submit comments by any of the following methods 
(unless this document describes a different method for submitting 
comments on a specific subject):
     Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0130. Address 
questions about regulations.gov docket IDs to Jennifer Borges; 
telephone: 301-287-9127; email: [email protected]. For technical 
questions, contact the individual listed in the FOR FURTHER INFORMATION 
CONTACT section of this document.
     Mail Comments to: May Ma, Office of Administration, Mail 
Stop TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001. For additional direction on obtaining information and 
submitting comments, see Obtaining Information and Submitting Comments 
in the SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: David Drucker, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 
20555-0001; telephone: 301-415-6223, email: [email protected].

SUPPLEMENTARY INFORMATION: 

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2018-0130 when contacting the NRC 
about the availability of information regarding this document. You may 
obtain publicly-available information related to this document by any 
of the following methods:
     Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0130.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the NRC 
Library at http://www.nrc.gov/reading-rm/adams.html. To begin the 
search, select ``Begin Web-based ADAMS Search.'' For problems with 
ADAMS, please contact the NRC's Public Document Room (PDR) reference 
staff at 1-800-397-4209, 301-415-4737, or by email to 
[email protected]. The ADAMS accession number for each document 
referenced in this document (if that document is available in ADAMS) is 
provided the first time that a document is referenced. Exelon's 
application for subsequent renewal of the Peach Bottom licenses can be 
found in ADAMS under Accession No. ML18193A689.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments

    Please include Docket ID NRC-2018-0130 in the subject line of your 
comment submission in order to ensure that the NRC is able to make your 
comment submission available to the public in this docket.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC will post all comment submissions at http://www.regulations.gov as well as enter the comment submissions into 
ADAMS. The NRC does not routinely edit comment submissions to remove 
identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment submissions into ADAMS.

II. Discussion

    By letter dated July 10, 2018 (ADAMS Package Accession No. 
ML18193A689), Exelon submitted to the NRC an application for subsequent 
license renewal of Facility Operating License Nos. DPR-44 and DPR-56 
for an additional 20 years of operation at Peach Bottom Atomic Power 
Station, Units 2 and 3. The Peach Bottom units are boiling water 
reactors designed by General Electric Company and are located in Delta, 
PA (17.9 miles south of Lancaster, PA). The current renewed operating 
license for Unit 2 expires at midnight on August 8, 2033, and the 
current renewed operating license for Unit 3 expires at midnight on 
July 2, 2034. The application for subsequent license renewal was 
submitted pursuant to part 54 of title 10 of the Code of Federal 
Regulations (10 CFR) and included an environmental report (ER). A 
notice of receipt and availability of the application was published in 
the Federal Register on August 1, 2018 (83 FR 37529). A separate notice 
of acceptance for docketing of the application and opportunity for 
hearing regarding subsequent license renewal of the facility operating 
licenses will be published in the Federal Register.

[[Page 45693]]

III. Request for Comments

    This notice informs the public of the NRC's intention to conduct 
scoping and prepare an EIS related to the subsequent license renewal 
application, and to provide the public an opportunity to participate in 
the environmental scoping process, as defined in 10 CFR 51.29.
    The regulations in 36 CFR 800.8, ``Coordination with the National 
Environmental Policy Act,'' allow agencies to use their National 
Environmental Policy Act of 1969 (NEPA) process to fulfill the 
requirements of Section 106 of the National Historic Preservation Act 
(NHPA). Therefore, pursuant to 36 CFR 800.8(c), the NRC intends to use 
its process and documentation for the preparation of the EIS on the 
proposed action to comply with Section 106 of the NHPA in lieu of the 
procedures set forth at 36 CFR 800.3 through 800.6.
    In accordance with 10 CFR 51.53(c) and 10 CFR 54.23, Exelon 
submitted the ER as part of the subsequent license renewal application. 
The ER was prepared pursuant to 10 CFR part 51 and is publicly 
available in ADAMS under Accession No. ML18193A689. The ER may also be 
viewed on the internet at https://www.nrc.gov/reactors/operating/licensing/renewal/applications/peach-bottom-subsequent.html. In 
addition, a paper copy of the SLR application including the ER are 
available for public review near the site at the Harford County Public 
Library: Whiteford Branch, 2407 Whiteford Road, Whiteford, MD 21160.
    The NRC intends to gather the information necessary to prepare a 
plant-specific supplement to the NRC's ``Generic Environmental Impact 
Statement (GEIS) for License Renewal of Nuclear Plants'' (NUREG-1437), 
related to the application for subsequent license renewal of the Peach 
Bottom operating licenses for an additional 20 years beyond the period 
specified in each of the current renewed licenses.
    Possible alternatives to the proposed action include the no action 
alternative and reasonable alternative energy sources. The NRC is 
required by 10 CFR 51.95 to prepare a supplement to the GEIS in 
connection with the renewal of an operating license. This notice is 
being published in accordance with NEPA and the NRC's regulations found 
at 10 CFR part 51.
    The NRC will first conduct scoping for the supplement to the GEIS 
and, as soon as practicable thereafter, will prepare a draft supplement 
to the GEIS for public comment. Participation in the scoping process by 
members of the public and local, State, Tribal, and Federal government 
agencies is encouraged. The scoping process for the supplement to the 
GEIS will be used to accomplish the following:
    a. Define the proposed action, which is to be the subject of the 
supplement to the GEIS;
    b. Determine the scope of the supplement to the GEIS and identify 
the significant issues to be analyzed in depth;
    c. Identify and eliminate from detailed study those issues that are 
peripheral or are not significant; or were covered by a prior 
environmental review;
    d. Identify any environmental assessments and other ElSs that are 
being or will be prepared that are related to, but are not part of, the 
scope of the supplement to the GEIS being considered;
    e. Identify other environmental review and consultation 
requirements related to the proposed action;
    f. Indicate the relationship between the timing of the preparation 
of the environmental analyses and the Commission's tentative planning 
and decision-making schedule;
    g. Identify any cooperating agencies and, as appropriate, allocate 
assignments for preparation and schedules for completing the supplement 
to the GEIS to the NRC and any cooperating agencies; and
    h. Describe how the supplement to the GEIS will be prepared, 
including any contractor assistance to be used.
    The NRC invites the following entities to participate in scoping:
    a. The applicant, Exelon;
    b. Any Federal agency that has jurisdiction by law or special 
expertise with respect to any environmental impact involved or that is 
authorized to develop and enforce relevant environmental standards;
    c. Affected State and local government agencies, including those 
authorized to develop and enforce relevant environmental standards;
    d. Any affected Indian tribe;
    e. Any person who requests or has requested an opportunity to 
participate in the scoping process; and
    f. Any person who has petitioned or intends to petition for leave 
to intervene under 10 CFR 2.309.

IV. Public Scoping Meeting

    In accordance with 10 CFR 51.26, the scoping process for an EIS may 
include a public scoping meeting to help identify significant issues 
related to a proposed activity and to determine the scope of issues to 
be addressed in an EIS. The NRC will hold a public meeting for the 
Peach Bottom subsequent license renewal supplement to the GEIS. The 
scoping meeting will be held on September 25, 2018. The meeting will be 
held from 6:00 p.m. to 8:00 p.m. at the Peach Bottom Inn, 6085 Delta 
Road, Delta, PA, 17314. There will be an open house one hour before the 
meeting for members of the public to meet with NRC staff and sign in to 
speak at the meeting.
    The meeting will be transcribed and will include: (1) An overview 
by the NRC staff of the NEPA environmental review process, the proposed 
scope of the supplement to the GEIS, and the proposed review schedule; 
and (2) the opportunity for interested government agencies, 
organizations, and individuals to submit comments or suggestions on the 
environmental issues or the proposed scope of the Peach Bottom 
subsequent license renewal supplement to the GEIS. To be considered, 
comments must be provided either at the transcribed public meeting or 
in writing, as discussed in the ADDRESSES section of this notice.
    Persons may register to attend or present oral comments at the 
meeting on the scope of the NEPA review by contacting the NRC Project 
Manager, Mr. David Drucker, by telephone at 301-415-6223, or by email 
at [email protected] no later than September 18, 2018. Members of 
the public may also register to speak during the registration period 
prior to the start of the meeting. Individual oral comments may be 
limited by the time available, depending on the number of persons who 
register. Members of the public who have not registered may also have 
an opportunity to speak if time permits. Public comments will be 
considered in the scoping process for the Peach Bottom subsequent 
license renewal supplement to the GEIS. Please contact Mr. David 
Drucker no later than September 18, 2018, if accommodations or special 
equipment is needed to attend or present information at the public 
meeting, so that the NRC staff can determine whether the request can be 
accommodated.
    Participation in the scoping process for the Peach Bottom 
subsequent license renewal supplement to the GEIS does not entitle 
participants to become parties to the proceeding to which the 
supplement to the GEIS relates. Matters related to participation in any 
hearing are outside the scope of matters to be discussed at this public 
meeting.

    Dated at Rockville, Maryland, this 4th day of September, 2018.


[[Page 45694]]


    For the Nuclear Regulatory Commission.
Eric R. Oesterle,
Chief, License Renewal Projects Branch, Division of Materials and 
License Renewal, Office of Nuclear Reactor Regulation.
[FR Doc. 2018-19462 Filed 9-7-18; 8:45 am]
 BILLING CODE 7590-01-P



                                               45692                     Federal Register / Vol. 83, No. 175 / Monday, September 10, 2018 / Notices

                                               information. For example, in some                       this document describes a different                   White Flint North, 11555 Rockville
                                               instances, individuals provide home                     method for submitting comments on a                   Pike, Rockville, Maryland 20852.
                                               addresses in order to demonstrate                       specific subject):
                                                                                                         • Federal Rulemaking Website: Go to                 B. Submitting Comments
                                               proximity to a facility or site. With
                                               respect to copyrighted works, except for                http://www.regulations.gov and search                   Please include Docket ID NRC–2018–
                                               limited excerpts that serve the purpose                 for Docket ID NRC–2018–0130. Address                  0130 in the subject line of your
                                               of the adjudicatory filings and would                   questions about regulations.gov docket                comment submission in order to ensure
                                               constitute a Fair Use application,                      IDs to Jennifer Borges; telephone: 301–               that the NRC is able to make your
                                               participants are requested not to include               287–9127; email: Jennifer.Borges@                     comment submission available to the
                                               copyrighted materials in their                          nrc.gov. For technical questions, contact             public in this docket.
                                               submission.                                             the individual listed in the FOR FURTHER                The NRC cautions you not to include
                                                 For further details with respect to this              INFORMATION CONTACT section of this                   identifying or contact information that
                                               action, see the application for license                 document.                                             you do not want to be publicly
                                               amendment dated August 24, 2018, as                       • Mail Comments to: May Ma, Office                  disclosed in your comment submission.
                                               supplemented August 31, 2018                            of Administration, Mail Stop TWFN–7–                  The NRC will post all comment
                                               (ADAMS Accession Nos. ML18236A383                       A60M, U.S. Nuclear Regulatory                         submissions at http://
                                               and ML18243A392, respectively).                         Commission, Washington, DC 20555–                     www.regulations.gov as well as enter the
                                                 Attorney for licensee: Ms. Kathryn M.                 0001. For additional direction on                     comment submissions into ADAMS.
                                               Sutton, Morgan, Lewis & Bockius LLP,                    obtaining information and submitting                  The NRC does not routinely edit
                                               1111 Pennsylvania Avenue NW,                            comments, see Obtaining Information                   comment submissions to remove
                                               Washington, DC 20004.                                   and Submitting Comments in the                        identifying or contact information.
                                                 NRC Branch Chief: Michael Markley.                    SUPPLEMENTARY INFORMATION section of                    If you are requesting or aggregating
                                                  Dated at Rockville, Maryland, this 5th day           this document.                                        comments from other persons for
                                               of September 2018.                                      FOR FURTHER INFORMATION CONTACT:                      submission to the NRC, then you should
                                                  For the Nuclear Regulatory Commission.               David Drucker, Office of Nuclear                      inform those persons not to include
                                               Michael Mahoney,                                        Reactor Regulation, U.S. Nuclear                      identifying or contact information that
                                               Project Manager, Plant Licensing Branch II–             Regulatory Commission, Washington DC                  they do not want to be publicly
                                               1, Division of Operating Reactor Licensing,             20555–0001; telephone: 301–415–6223,                  disclosed in their comment submission.
                                               Office of Nuclear Reactor Regulation.                   email: David.Drucker@nrc.gov.                         Your request should state that the NRC
                                               [FR Doc. 2018–19583 Filed 9–7–18; 8:45 am]              SUPPLEMENTARY INFORMATION:                            does not routinely edit comment
                                               BILLING CODE 7590–01–P                                                                                        submissions to remove such information
                                                                                                       I. Obtaining Information and
                                                                                                       Submitting Comments                                   before making the comment
                                                                                                                                                             submissions available to the public or
                                               NUCLEAR REGULATORY                                      A. Obtaining Information                              entering the comment submissions into
                                               COMMISSION
                                                                                                          Please refer to Docket ID NRC–2018–                ADAMS.
                                               [Docket Nos. 50–277 and 50–278; NRC–                    0130 when contacting the NRC about
                                               2018–0130]                                                                                                    II. Discussion
                                                                                                       the availability of information regarding
                                                                                                       this document. You may obtain                            By letter dated July 10, 2018 (ADAMS
                                               Exelon Generation Company, LLC;                                                                               Package Accession No. ML18193A689),
                                               Peach Bottom Atomic Power Station,                      publicly-available information related to
                                                                                                       this document by any of the following                 Exelon submitted to the NRC an
                                               Units 2 and 3                                                                                                 application for subsequent license
                                                                                                       methods:
                                               AGENCY:  Nuclear Regulatory                                • Federal Rulemaking Website: Go to                renewal of Facility Operating License
                                               Commission.                                             http://www.regulations.gov and search                 Nos. DPR–44 and DPR–56 for an
                                               ACTION: Intent to conduct scoping                       for Docket ID NRC–2018–0130.                          additional 20 years of operation at
                                               process and prepare environmental                          • NRC’s Agencywide Documents                       Peach Bottom Atomic Power Station,
                                               impact statement; public meeting and                    Access and Management System                          Units 2 and 3. The Peach Bottom units
                                               request for comment.                                    (ADAMS): You may obtain publicly-                     are boiling water reactors designed by
                                                                                                       available documents online in the NRC                 General Electric Company and are
                                               SUMMARY:    The U.S. Nuclear Regulatory                 Library at http://www.nrc.gov/reading-                located in Delta, PA (17.9 miles south of
                                               Commission will conduct a scoping                       rm/adams.html. To begin the search,                   Lancaster, PA). The current renewed
                                               process to gather information necessary                 select ‘‘Begin Web-based ADAMS                        operating license for Unit 2 expires at
                                               to prepare an environmental impact                      Search.’’ For problems with ADAMS,                    midnight on August 8, 2033, and the
                                               statement (EIS) to evaluate the                         please contact the NRC’s Public                       current renewed operating license for
                                               environmental impacts for the                           Document Room (PDR) reference staff at                Unit 3 expires at midnight on July 2,
                                               subsequent license renewal of the                       1–800–397–4209, 301–415–4737, or by                   2034. The application for subsequent
                                               operating licenses for Peach Bottom                     email to pdr.resource@nrc.gov. The                    license renewal was submitted pursuant
                                               Atomic Power Station, Units 2 and 3                     ADAMS accession number for each                       to part 54 of title 10 of the Code of
                                               (Peach Bottom). The NRC is seeking                      document referenced in this document                  Federal Regulations (10 CFR) and
                                               stakeholder input on this action and has                (if that document is available in                     included an environmental report (ER).
                                               scheduled a public meeting.                             ADAMS) is provided the first time that                A notice of receipt and availability of
                                               DATES: Submit comments by October 10,                   a document is referenced. Exelon’s                    the application was published in the
daltland on DSKBBV9HB2PROD with NOTICES




                                               2018. Comments received after this date                 application for subsequent renewal of                 Federal Register on August 1, 2018 (83
                                               will be considered if it is practical to do             the Peach Bottom licenses can be found                FR 37529). A separate notice of
                                               so, but assurance of consideration                      in ADAMS under Accession No.                          acceptance for docketing of the
                                               cannot be given to comments received                    ML18193A689.                                          application and opportunity for hearing
                                               after this date.                                           • NRC’s PDR: You may examine and                   regarding subsequent license renewal of
                                               ADDRESSES: You may submit comments                      purchase copies of public documents at                the facility operating licenses will be
                                               by any of the following methods (unless                 the NRC’s PDR, Room O1–F21, One                       published in the Federal Register.


                                          VerDate Sep<11>2014   17:54 Sep 07, 2018   Jkt 244001   PO 00000   Frm 00099   Fmt 4703   Sfmt 4703   E:\FR\FM\10SEN1.SGM   10SEN1


                                                                         Federal Register / Vol. 83, No. 175 / Monday, September 10, 2018 / Notices                                               45693

                                               III. Request for Comments                               public and local, State, Tribal, and                  meeting for the Peach Bottom
                                                  This notice informs the public of the                Federal government agencies is                        subsequent license renewal supplement
                                               NRC’s intention to conduct scoping and                  encouraged. The scoping process for the               to the GEIS. The scoping meeting will
                                               prepare an EIS related to the subsequent                supplement to the GEIS will be used to                be held on September 25, 2018. The
                                               license renewal application, and to                     accomplish the following:                             meeting will be held from 6:00 p.m. to
                                               provide the public an opportunity to                       a. Define the proposed action, which               8:00 p.m. at the Peach Bottom Inn, 6085
                                               participate in the environmental                        is to be the subject of the supplement to             Delta Road, Delta, PA, 17314. There will
                                               scoping process, as defined in 10 CFR                   the GEIS;                                             be an open house one hour before the
                                                                                                          b. Determine the scope of the                      meeting for members of the public to
                                               51.29.
                                                  The regulations in 36 CFR 800.8,                     supplement to the GEIS and identify the               meet with NRC staff and sign in to speak
                                               ‘‘Coordination with the National                        significant issues to be analyzed in                  at the meeting.
                                               Environmental Policy Act,’’ allow                       depth;
                                                                                                          c. Identify and eliminate from                        The meeting will be transcribed and
                                               agencies to use their National                                                                                will include: (1) An overview by the
                                                                                                       detailed study those issues that are
                                               Environmental Policy Act of 1969                                                                              NRC staff of the NEPA environmental
                                                                                                       peripheral or are not significant; or were
                                               (NEPA) process to fulfill the                                                                                 review process, the proposed scope of
                                                                                                       covered by a prior environmental
                                               requirements of Section 106 of the                                                                            the supplement to the GEIS, and the
                                                                                                       review;
                                               National Historic Preservation Act                                                                            proposed review schedule; and (2) the
                                                                                                          d. Identify any environmental
                                               (NHPA). Therefore, pursuant to 36 CFR                                                                         opportunity for interested government
                                                                                                       assessments and other ElSs that are
                                               800.8(c), the NRC intends to use its                                                                          agencies, organizations, and individuals
                                                                                                       being or will be prepared that are
                                               process and documentation for the                                                                             to submit comments or suggestions on
                                                                                                       related to, but are not part of, the scope
                                               preparation of the EIS on the proposed                                                                        the environmental issues or the
                                                                                                       of the supplement to the GEIS being
                                               action to comply with Section 106 of the                                                                      proposed scope of the Peach Bottom
                                                                                                       considered;
                                               NHPA in lieu of the procedures set forth                   e. Identify other environmental                    subsequent license renewal supplement
                                               at 36 CFR 800.3 through 800.6.                          review and consultation requirements                  to the GEIS. To be considered,
                                                  In accordance with 10 CFR 51.53(c)
                                                                                                       related to the proposed action;                       comments must be provided either at
                                               and 10 CFR 54.23, Exelon submitted the                     f. Indicate the relationship between               the transcribed public meeting or in
                                               ER as part of the subsequent license                    the timing of the preparation of the                  writing, as discussed in the ADDRESSES
                                               renewal application. The ER was                         environmental analyses and the
                                               prepared pursuant to 10 CFR part 51                                                                           section of this notice.
                                                                                                       Commission’s tentative planning and
                                               and is publicly available in ADAMS                                                                               Persons may register to attend or
                                                                                                       decision-making schedule;
                                               under Accession No. ML18193A689.                                                                              present oral comments at the meeting on
                                                                                                          g. Identify any cooperating agencies
                                               The ER may also be viewed on the                                                                              the scope of the NEPA review by
                                                                                                       and, as appropriate, allocate
                                               internet at https://www.nrc.gov/                        assignments for preparation and                       contacting the NRC Project Manager,
                                               reactors/operating/licensing/renewal/                   schedules for completing the                          Mr. David Drucker, by telephone at 301–
                                               applications/peach-bottom-                              supplement to the GEIS to the NRC and                 415–6223, or by email at
                                               subsequent.html. In addition, a paper                   any cooperating agencies; and                         david.drucker@nrc.gov no later than
                                               copy of the SLR application including                      h. Describe how the supplement to                  September 18, 2018. Members of the
                                               the ER are available for public review                  the GEIS will be prepared, including                  public may also register to speak during
                                               near the site at the Harford County                     any contractor assistance to be used.                 the registration period prior to the start
                                               Public Library: Whiteford Branch, 2407                     The NRC invites the following entities             of the meeting. Individual oral
                                               Whiteford Road, Whiteford, MD 21160.                    to participate in scoping:                            comments may be limited by the time
                                                  The NRC intends to gather the                           a. The applicant, Exelon;                          available, depending on the number of
                                               information necessary to prepare a                         b. Any Federal agency that has                     persons who register. Members of the
                                               plant-specific supplement to the NRC’s                  jurisdiction by law or special expertise              public who have not registered may also
                                               ‘‘Generic Environmental Impact                          with respect to any environmental                     have an opportunity to speak if time
                                               Statement (GEIS) for License Renewal of                 impact involved or that is authorized to              permits. Public comments will be
                                               Nuclear Plants’’ (NUREG–1437), related                  develop and enforce relevant                          considered in the scoping process for
                                               to the application for subsequent license               environmental standards;                              the Peach Bottom subsequent license
                                               renewal of the Peach Bottom operating                      c. Affected State and local                        renewal supplement to the GEIS. Please
                                               licenses for an additional 20 years                     government agencies, including those                  contact Mr. David Drucker no later than
                                               beyond the period specified in each of                  authorized to develop and enforce                     September 18, 2018, if accommodations
                                               the current renewed licenses.                           relevant environmental standards;                     or special equipment is needed to attend
                                                  Possible alternatives to the proposed                   d. Any affected Indian tribe;                      or present information at the public
                                               action include the no action alternative                   e. Any person who requests or has                  meeting, so that the NRC staff can
                                               and reasonable alternative energy                       requested an opportunity to participate               determine whether the request can be
                                               sources. The NRC is required by 10 CFR                  in the scoping process; and                           accommodated.
                                               51.95 to prepare a supplement to the                       f. Any person who has petitioned or                   Participation in the scoping process
                                               GEIS in connection with the renewal of                  intends to petition for leave to intervene            for the Peach Bottom subsequent license
                                               an operating license. This notice is                    under 10 CFR 2.309.                                   renewal supplement to the GEIS does
                                               being published in accordance with
                                               NEPA and the NRC’s regulations found                    IV. Public Scoping Meeting                            not entitle participants to become
daltland on DSKBBV9HB2PROD with NOTICES




                                               at 10 CFR part 51.                                        In accordance with 10 CFR 51.26, the                parties to the proceeding to which the
                                                  The NRC will first conduct scoping                   scoping process for an EIS may include                supplement to the GEIS relates. Matters
                                               for the supplement to the GEIS and, as                  a public scoping meeting to help                      related to participation in any hearing
                                               soon as practicable thereafter, will                    identify significant issues related to a              are outside the scope of matters to be
                                               prepare a draft supplement to the GEIS                  proposed activity and to determine the                discussed at this public meeting.
                                               for public comment. Participation in the                scope of issues to be addressed in an                   Dated at Rockville, Maryland, this 4th day
                                               scoping process by members of the                       EIS. The NRC will hold a public                       of September, 2018.



                                          VerDate Sep<11>2014   17:54 Sep 07, 2018   Jkt 244001   PO 00000   Frm 00100   Fmt 4703   Sfmt 4703   E:\FR\FM\10SEN1.SGM   10SEN1


                                               45694                     Federal Register / Vol. 83, No. 175 / Monday, September 10, 2018 / Notices

                                                 For the Nuclear Regulatory Commission.                   Detailed meeting agendas and meeting               Week of October 1, 2018—Tentative
                                               Eric R. Oesterle,                                       transcripts are available on the NRC
                                               Chief, License Renewal Projects Branch,                 website at http://www.nrc.gov/reading-                  There are no meetings scheduled for
                                               Division of Materials and License Renewal,              rm/doc-collections/#acrs. Information                 the week of October 1, 2018.
                                               Office of Nuclear Reactor Regulation.                   regarding topics to be discussed,                     Week of October 8, 2018—Tentative
                                               [FR Doc. 2018–19462 Filed 9–7–18; 8:45 am]              changes to the agenda, whether the
                                               BILLING CODE 7590–01–P                                  meeting has been canceled or                          Thursday, October 11, 2018
                                                                                                       rescheduled, and the time allotted to
                                                                                                       present oral statements can be obtained               9:00 a.m. Strategic Programmatic
                                               NUCLEAR REGULATORY                                      from the website cited above or by                        Overview of the Decommissioning
                                               COMMISSION                                              contacting the identified DFO.                            and Low-Level Waste and Spent
                                                                                                       Moreover, in view of the possibility that                 Fuel Storage and Transportation
                                               Meeting of the Advisory Committee on                    the schedule for ACRS meetings may be                     Business Lines (Public) (Contact:
                                               Reactor Safeguards Subcommittee on                      adjusted by the Chairman as necessary                     Matthew Meyer: 301–415–6198)
                                               Plant License Renewal                                   to facilitate the conduct of the meeting,               This meeting will be webcast live at
                                                 The ACRS Subcommittee on Plant                        persons planning to attend should check               the Web address—http://www.nrc.gov/.
                                               License Renewal will hold a meeting on                  with these references if such
                                               September 20, 2018 at U.S. Nuclear                      rescheduling would result in a major                  Week of October 15, 2018—Tentative
                                               Regulatory Commission, 11545                            inconvenience.
                                                                                                          If attending this meeting, please enter              There are no meetings scheduled for
                                               Rockville Pike, Room T–2B1, Rockville,                                                                        the week of October 15, 2018.
                                               Maryland 20852.                                         through the One White Flint North
                                                 The entire meeting will be open to                    Building, 11555 Rockville Pike,                       CONTACT PERSON FOR MORE INFORMATION:
                                               public attendance. The agenda for the                   Rockville, Maryland 20852. After                      For more information or to verify the
                                               subject meeting shall be as follows:                    registering with Security, please contact             status of meetings, contact Denise
                                                                                                       Mr. Theron Brown (Telephone 301–
                                               Thursday September 20, 2018—8:30                                                                              McGovern at 301–415–0681 or via email
                                                                                                       415–6702) to be escorted to the
                                               a.m. Until 12 p.m.                                                                                            at Denise.McGovern@nrc.gov. The
                                                                                                       conference room.
                                                                                                                                                             schedule for Commission meetings is
                                                 The Subcommittee will conduct a                         Dated: August 30, 2018.                             subject to change on short notice.
                                               briefing on the Waterford Steam Electric                Mark L. Banks,
                                               Station, Unit 3 License Renewal                                                                                  The NRC Commission Meeting
                                                                                                       Chief, Technical Support Branch, Advisory
                                               Application. The Subcommittee will                      Committee on Reactor Safeguards.
                                                                                                                                                             Schedule can be found on the internet
                                               hear presentations by and hold                                                                                at: http://www.nrc.gov/public-involve/
                                                                                                       [FR Doc. 2018–19591 Filed 9–7–18; 8:45 am]
                                               discussions with NRC staff and other                                                                          public-meetings/schedule.html.
                                                                                                       BILLING CODE 7590–01–P
                                               interested persons regarding this matter.                                                                        The NRC provides reasonable
                                               The Subcommittee will gather                                                                                  accommodation to individuals with
                                               information, analyze relevant issues and                NUCLEAR REGULATORY                                    disabilities where appropriate. If you
                                               facts, and formulate proposed positions                 COMMISSION                                            need a reasonable accommodation to
                                               and actions, as appropriate, for                                                                              participate in these public meetings, or
                                                                                                       [NRC–2018–0001]
                                               deliberation by the Full Committee.                                                                           need this meeting notice or the
                                                 Members of the public desiring to                     Sunshine Act Meetings                                 transcript or other information from the
                                               provide oral statements and/or written                                                                        public meetings in another format (e.g.,
                                               comments should notify the Designated                   TIME AND DATE: Weeks of September 10,                 Braille, large print), please notify
                                               Federal Official (DFO), Kent Howard                     17, 24, October 1, 8, 15, 2018.                       Kimberly Meyer-Chambers, NRC
                                               (Telephone 301–415–2989 or Email:                       PLACE: Commissioners’ Conference                      Disability Program Manager, at 301–
                                               Kent.Howard@nrc.gov) five days prior to                 Room, 11555 Rockville Pike, Rockville,                287–0739, by videophone at 240–428–
                                               the meeting, if possible, so that                       Maryland.
                                               appropriate arrangements can be made.                                                                         3217, or by email at Kimberly.Meyer-
                                                                                                       STATUS: Public and Closed.                            Chambers@nrc.gov. Determinations on
                                               Thirty-five hard copies of each                         MATTERS TO BE CONSIDERED:
                                               presentation or handout should be                                                                             requests for reasonable accommodation
                                               provided to the DFO thirty minutes                      Week of September 10, 2018                            will be made on a case-by-case basis.
                                               before the meeting. In addition, one                    Monday, September 10, 2018                               Members of the public may request to
                                               electronic copy of each presentation                                                                          receive this information electronically.
                                               should be emailed to the DFO one day                    10:00 a.m. Briefing on NRC                            If you would like to be added to the
                                               before the meeting. If an electronic copy                   International Activities (Closed—                 distribution, please contact the Nuclear
                                               cannot be provided within this                              Ex. 1 & 9)                                        Regulatory Commission, Office of the
                                               timeframe, presenters should provide                    Week of September 17, 2018—Tentative                  Secretary, Washington, DC 20555 (301–
                                               the DFO with a CD containing each                                                                             415–1969), or you may email
                                               presentation at least thirty minutes                      There are no meetings scheduled for
                                                                                                       the week of September 17, 2018.                       Patricia.Jimenez@nrc.gov or
                                               before the meeting. Electronic                                                                                Wendy.Moore@nrc.gov.
                                               recordings will be permitted only                       Week of September 24, 2018—Tentative
                                               during those portions of the meeting                                                                            Dated: September 5, 2018.
daltland on DSKBBV9HB2PROD with NOTICES




                                               that are open to the public. The public                 Thursday, September 27, 2018                          Denise L. McGovern,
                                               bridgeline number for the meeting is                    10:00 a.m. Strategic Programmatic                     Policy Coordinator, Office of the Secretary.
                                               866–822–3032, passcode 8272423.                             Overview of the Operating Reactors                [FR Doc. 2018–19652 Filed 9–6–18; 8:45 am]
                                               Detailed procedures for the conduct of                      Business Line (Public) (Contact:                  BILLING CODE 7590–01–P
                                               and participation in ACRS meetings                          Trent Wertz: 301–415–1568)
                                               were published in the Federal Register                    This meeting will be webcast live at
                                               on October 4, 2017 (82 FR 46312).                       the Web address—http://www.nrc.gov/.


                                          VerDate Sep<11>2014   17:54 Sep 07, 2018   Jkt 244001   PO 00000   Frm 00101   Fmt 4703   Sfmt 9990   E:\FR\FM\10SEN1.SGM   10SEN1



Document Created: 2018-09-08 00:43:29
Document Modified: 2018-09-08 00:43:29
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionIntent to conduct scoping process and prepare environmental impact statement; public meeting and request for comment.
DatesSubmit comments by October 10, 2018. Comments received after this date will be considered if it is practical to do so, but assurance of consideration cannot be given to comments received after this date.
ContactDavid Drucker, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001; telephone: 301-415-6223, email: [email protected]
FR Citation83 FR 45692 