83_FR_46168 83 FR 45992 - Proposed Revisions to Standard Review Plan Section 13.6, Physical Security

83 FR 45992 - Proposed Revisions to Standard Review Plan Section 13.6, Physical Security

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 83, Issue 176 (September 11, 2018)

Page Range45992-45993
FR Document2018-19684

The U.S. Nuclear Regulatory Commission (NRC) is soliciting public comment on draft NUREG-0800, ``Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition,'' Section 13.6, ``Physical Security.'' This section has been updated to reflect the latest NRC guidance concerning physical security.

Federal Register, Volume 83 Issue 176 (Tuesday, September 11, 2018)
[Federal Register Volume 83, Number 176 (Tuesday, September 11, 2018)]
[Notices]
[Pages 45992-45993]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-19684]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2018-0197]


Proposed Revisions to Standard Review Plan Section 13.6, Physical 
Security

AGENCY: Nuclear Regulatory Commission.

ACTION: Standard review plan-draft section revision; request for 
comment.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is soliciting 
public comment on draft NUREG-0800, ``Standard Review Plan for the 
Review of Safety Analysis Reports for Nuclear Power Plants: LWR 
Edition,'' Section 13.6, ``Physical Security.'' This section has been 
updated to reflect the latest NRC guidance concerning physical 
security.

DATES: Comments must be filed no later than November 13, 2018. Comments 
received after this date will be considered, if it is practical to do 
so, but the Commission is able to ensure consideration only for 
comments received on or before this date.

ADDRESSES: You may submit comments by any of the following methods:
     Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0197. Address 
questions about NRC dockets to Jennifer Borges; telephone: 301-287-
9127; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     Mail comments to: May Ma, Office of Administration, Mail 
Stop: TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Mark D. Notich, Office of New 
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001; telephone: 301-415-3053, email: [email protected].

SUPPLEMENTARY INFORMATION: 

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2018-0197 when contacting the NRC 
about the availability of information for this

[[Page 45993]]

action. You may obtain publicly-available information related to this 
action by any of the following methods:
     Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0197.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to [email protected].
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments

    Please include Docket ID NRC-2018-0197 in your comment submission.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC will post all comment submissions at http://www.regulations.gov as well as enter the comment submissions into 
ADAMS. The NRC does not routinely edit comment submissions to remove 
identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment into ADAMS.

II. Further Information

    The NRC seeks public comment on the proposed Standard Review Plan 
(SRP)-draft section revision of Section 13.6, ``Physical Security.'' 
The changes made in this revision to this section reflect the latest 
NRC guidance concerning physical security.
    Following NRC staff evaluation of public comments, the NRC intends 
to finalize SRP Section 13.6, ``Physical Security,'' Revision 4 in 
ADAMS and post it on the NRC's public website at http://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr0800/. The SRP is guidance 
for the NRC staff. The SRP is not a substitute for the NRC regulations, 
and compliance with the SRP is not required.

III. Backfitting and Issue Finality

    Issuance of this draft SRP, if finalized, would not constitute 
backfitting as defined in section 50.109 of title 10 of the Code of 
Federal Regulations (10 CFR) (the Backfit Rule) or otherwise be 
inconsistent with the issue finality provisions in 10 CFR part 52. The 
NRC's position is based upon the following considerations:
    1. The draft SRP positions do not constitute backfitting, inasmuch 
as the SRP is guidance directed to the NRC staff with respect to its 
regulatory responsibilities.
    The SRP provides internal guidance to the NRC staff on how to 
review an application for NRC regulatory approval in the form of 
licensing. Changes in guidance intended for use by only the staff are 
not matters that constitute backfitting as that term is defined in 10 
CFR 50.109(a)(1) or involve the issue finality provisions of 10 CFR 
part 52.
    2. Backfitting and issue finality--with certain exceptions 
discussed below--do not apply to current or future applicants.
    Applicants and potential applicants are not, with certain 
exceptions, the subject of either the Backfit Rule or any issue 
finality provisions under 10 CFR part 52. This is because neither the 
Backfit Rule nor the issue finality provisions under 10 CFR part 52 
were intended to apply to every NRC action that substantially changes 
the expectations of current and future applicants.
    The exceptions to the general principle are applicable whenever a 
10 CFR part 50 operating license applicant references a construction 
permit or a 10 CFR part 52 combined license applicant references a 
license (e.g., an early site permit) and/or NRC regulatory approval 
(e.g., a design certification rule) for which specified issue finality 
provisions apply.
    The NRC staff does not, at this time, intend to impose the 
positions represented in this draft SRP section in a manner that 
constitutes backfitting or is inconsistent with any issue finality 
provision of 10 CFR part 52. If, in the future, the staff seeks to 
impose a position in this draft SRP section in a manner that would 
constitute backfitting or be inconsistent with these issue finality 
provisions, the NRC staff must make the showing as set forth in the 
Backfit rule or address the regulatory criteria set forth in the 
applicable issue finality provision, as applicable, that would allow 
the staff to impose the position.
    3. The NRC staff has no intention to impose the SRP positions on 
existing nuclear power plant licensees either now or in the future 
(absent a voluntary request for a change from the licensee, holder of a 
regulatory approval or a design certification applicant).
    The NRC staff does not intend to impose or apply the positions 
described in the draft SRP to existing (already issued) licenses (e.g., 
operating licenses and combined licenses) and regulatory approvals. 
Hence, the issuance of this SRP guidance--even if considered guidance 
subject to the Backfit Rule or the issue finality provisions in 10 CFR 
part 52--would not need to be evaluated as if it were a backfit or as 
being inconsistent with these issue finality provisions. If, in the 
future, the NRC staff seeks to impose a position in the SRP on holders 
of already issued licenses in a manner that would constitute 
backfitting or does not provide issue finality as described in the 
applicable issue finality provision, then the staff must make a showing 
as set forth in the Backfit Rule or address the criteria set forth in 
the applicable issue finality provision, as applicable, that would 
allow the staff to impose the position.

    Dated at Rockville, Maryland, this 6th day of September 2018.

    For the Nuclear Regulatory Commission.
Jennivine K. Rankin,
Acting Chief, Division of Licensing, Siting, and Environmental 
Analysis, Licensing Branch 3, Office of New Reactors.
[FR Doc. 2018-19684 Filed 9-10-18; 8:45 am]
 BILLING CODE 7590-01-P



                                               45992                     Federal Register / Vol. 83, No. 176 / Tuesday, September 11, 2018 / Notices

                                               No. ML18191B091; documents related                        The Commission’s related evaluation                 NUCLEAR REGULATORY
                                               to this amendment are listed in the                     of the amendment is contained in the                  COMMISSION
                                               Safety Evaluation enclosed with the                     Safety Evaluation dated July 12, 2018.
                                                                                                                                                             [NRC–2018–0197]
                                               amendment.                                                No significant hazards consideration
                                                 Facility Combined Licenses No. NPF–                   comments received: No.                                Proposed Revisions to Standard
                                               91 and NPF–92: Amendment revised the                                                                          Review Plan Section 13.6, Physical
                                               Facility Combined Licenses.                             Tennessee Valley Authority, Docket No.                Security
                                                 Date of initial notice in Federal                     50–390, Watts Bar Nuclear Plant (WBN),
                                               Register: May 22, 2018 (83 FR 23728).                   Unit 1, Rhea County, Tennessee                        AGENCY:  Nuclear Regulatory
                                                 The Commission’s related evaluation                                                                         Commission.
                                               of the amendment is contained in the                       Date of amendment request: July 8,                 ACTION: Standard review plan-draft
                                               Safety Evaluation dated August 7, 2018.                 2018, as supplemented by letters dated                section revision; request for comment.
                                                 No significant hazards consideration                  July 24 and July 30, 2018.
                                               comments received: No.                                     Brief description of amendment: The                SUMMARY:   The U.S. Nuclear Regulatory
                                                                                                                                                             Commission (NRC) is soliciting public
                                               Southern Nuclear Operating Company,                     amendment extended Technical
                                                                                                                                                             comment on draft NUREG–0800,
                                               Docket Nos. 52–025 and 52–026, Vogtle                   Specification (TS) Surveillance
                                                                                                                                                             ‘‘Standard Review Plan for the Review
                                               Electric Generating Plant (VEGP), Units                 Requirements (SRs) 3.3.1.5, 3.3.2.2, and              of Safety Analysis Reports for Nuclear
                                               3 and 4, Burke County, Georgia                          3.3.6.2 by revising the WBN, Unit 1, TS               Power Plants: LWR Edition,’’ Section
                                                                                                       SR 3.0.2 and certain SRs in Table SR                  13.6, ‘‘Physical Security.’’ This section
                                                  Date of amendment request: January                   3.0.2–1.
                                               31, 2018, as supplemented by letter                                                                           has been updated to reflect the latest
                                               dated May 2, 2018.                                         Date of issuance: August 16, 2018.                 NRC guidance concerning physical
                                                  Description of amendment: The                           Effective date: As of the date of                  security.
                                               amendment revises the VEGP Units 3                      issuance and shall be implemented                     DATES:  Comments must be filed no later
                                               and 4 combined license (COL)                            immediately.                                          than November 13, 2018. Comments
                                               Appendix A, Technical Specification                        Amendment No.: 121. A publicly-                    received after this date will be
                                               (TS) related to Pressurizer Safety Valve                                                                      considered, if it is practical to do so, but
                                                                                                       available version is in ADAMS under
                                               (PSV) operability. The amendment                                                                              the Commission is able to ensure
                                                                                                       Accession No. ML18204A252;
                                               changes TS 3.4.6, ‘‘PSV Applicability’’                                                                       consideration only for comments
                                                                                                       documents related to this amendment
                                               to require the PSV to be operable when                                                                        received on or before this date.
                                               the TS 3.4.14, ‘‘Low Temperature                        are listed in the Safety Evaluation
                                                                                                                                                             ADDRESSES: You may submit comments
                                               Overpressure Protection,’’ is not                       enclosed with the amendment.
                                                                                                                                                             by any of the following methods:
                                               required to be operable. A conforming                      Facility Operating License No. NPF–                  • Federal Rulemaking Website: Go to
                                               change is made to the TS 3.4.6 Actions.                 90: The amendment revised the Facility                http://www.regulations.gov and search
                                               Additional TS changes necessary to                      Operating License and TSs.                            for Docket ID NRC–2018–0197. Address
                                               support PSV operability are made for                       Date of initial notice in Federal                  questions about NRC dockets to Jennifer
                                               consistency with the TS 3.4.6. The                      Register: July 16, 2018 (83 FR 32912).                Borges; telephone: 301–287–9127;
                                               amendment also approves moving TS                       The supplemental letters dated July 24                email: Jennifer.Borges@nrc.gov. For
                                               Limiting Condition for Operation Notes                                                                        technical questions, contact the
                                                                                                       and July 30, 2018, provided additional
                                               regarding reactor coolant pump starts                                                                         individual listed in the FOR FURTHER
                                                                                                       information that clarified the
                                               from TS 3.4.4, ‘‘Reactor Coolant System                                                                       INFORMATION CONTACT section of this
                                                                                                       application, did not expand the scope of
                                               (RCS) Loops, 3.4.8, ‘‘Minimum RCS                                                                             document.
                                                                                                       the application as originally notified,
                                               Flow,’’ and 3.4.14 to TS 3.4.3, ‘‘RCS
                                                                                                       and did not change the NRC staff’s                      • Mail comments to: May Ma, Office
                                               Pressure/Temperature Limits.’’                                                                                of Administration, Mail Stop: TWFN–7–
                                                  Date of issuance: July 12, 2018.                     proposed no significant hazards
                                                                                                                                                             A60M, U.S. Nuclear Regulatory
                                                  Effective date: As of the date of                    consideration determination as
                                                                                                                                                             Commission, Washington, DC 20555–
                                               issuance and shall be implemented                       published in the Federal Register.
                                                                                                                                                             0001.
                                               within 30 days of issuance.                                The Commission’s related evaluation                  For additional direction on obtaining
                                                  Amendment Nos.: 133 (Unit 3) and                     of the amendment and final                            information and submitting comments,
                                               132 (Unit 4). A publicly-available                      determination of no significant hazards               see ‘‘Obtaining Information and
                                               version is in ADAMS under Accession                     consideration is contained in a Safety                Submitting Comments’’ in the
                                               No. ML18159A437; documents related                      Evaluation dated August 16, 2018.                     SUPPLEMENTARY INFORMATION section of
                                               to this amendment are listed in the                                                                           this document.
                                                                                                          No significant hazards consideration
                                               Safety Evaluation enclosed with the                                                                           FOR FURTHER INFORMATION CONTACT:
                                                                                                       comments received: No.
                                               amendment.                                                                                                    Mark D. Notich, Office of New Reactors,
                                                  Facility Combined Licenses Nos. NPF–                   Dated at Rockville, Maryland, this 31st day         U.S. Nuclear Regulatory Commission,
                                               91 and NPF–92: Amendment revised the                    of August 2018.
                                                                                                                                                             Washington, DC 20555–0001; telephone:
                                               Facility COL.                                             For the Nuclear Regulatory Commission.              301–415–3053, email: Mark.Notich@
                                                  Date of Initial Notice in Federal                    Kathryn M. Brock,                                     nrc.gov.
                                               Register: March 13, 2018 (83 FR                         Deputy Director, Division of Operating
                                               10922). The supplement dated May 2,                                                                           SUPPLEMENTARY INFORMATION:
                                                                                                       Reactor Licensing, Office of Nuclear Reactor
daltland on DSKBBV9HB2PROD with NOTICES




                                               2018, provided additional information                   Regulation.                                           I. Obtaining Information and
                                               that clarified the application, did not                 [FR Doc. 2018–19419 Filed 9–10–18; 8:45 am]           Submitting Comments
                                               expand the scope of the application as
                                               originally noticed, and did not change
                                                                                                       BILLING CODE 7590–01–P                                A. Obtaining Information
                                               the NRC staff’s original proposed no                                                                            Please refer to Docket ID NRC–2018–
                                               significant hazards consideration                                                                             0197 when contacting the NRC about
                                               determination.                                                                                                the availability of information for this


                                          VerDate Sep<11>2014   18:49 Sep 10, 2018   Jkt 244001   PO 00000   Frm 00118   Fmt 4703   Sfmt 4703   E:\FR\FM\11SEN1.SGM   11SEN1


                                                                         Federal Register / Vol. 83, No. 176 / Tuesday, September 11, 2018 / Notices                                                 45993

                                               action. You may obtain publicly-                        SRP is not a substitute for the NRC                   applicable, that would allow the staff to
                                               available information related to this                   regulations, and compliance with the                  impose the position.
                                               action by any of the following methods:                 SRP is not required.                                     3. The NRC staff has no intention to
                                                  • Federal Rulemaking Website: Go to                                                                        impose the SRP positions on existing
                                               http://www.regulations.gov and search                   III. Backfitting and Issue Finality                   nuclear power plant licensees either
                                               for Docket ID NRC–2018–0197.                               Issuance of this draft SRP, if finalized,          now or in the future (absent a voluntary
                                                  • NRC’s Agencywide Documents                         would not constitute backfitting as                   request for a change from the licensee,
                                               Access and Management System                            defined in section 50.109 of title 10 of              holder of a regulatory approval or a
                                               (ADAMS): You may obtain publicly-                       the Code of Federal Regulations (10                   design certification applicant).
                                               available documents online in the                       CFR) (the Backfit Rule) or otherwise be                  The NRC staff does not intend to
                                               ADAMS Public Documents collection at                    inconsistent with the issue finality                  impose or apply the positions described
                                               http://www.nrc.gov/reading-rm/                          provisions in 10 CFR part 52. The NRC’s               in the draft SRP to existing (already
                                               adams.html. To begin the search, select                 position is based upon the following                  issued) licenses (e.g., operating licenses
                                               ‘‘Begin Web-based ADAMS Search.’’ For                   considerations:                                       and combined licenses) and regulatory
                                               problems with ADAMS, please contact                        1. The draft SRP positions do not                  approvals. Hence, the issuance of this
                                               the NRC’s Public Document Room (PDR)                    constitute backfitting, inasmuch as the               SRP guidance—even if considered
                                               reference staff at 1–800–397–4209, 301–                 SRP is guidance directed to the NRC                   guidance subject to the Backfit Rule or
                                               415–4737, or by email to pdr.resource@                  staff with respect to its regulatory                  the issue finality provisions in 10 CFR
                                               nrc.gov.                                                responsibilities.                                     part 52—would not need to be evaluated
                                                  • NRC’s PDR: You may examine and                        The SRP provides internal guidance                 as if it were a backfit or as being
                                               purchase copies of public documents at                  to the NRC staff on how to review an                  inconsistent with these issue finality
                                               the NRC’s PDR, Room O1–F21, One                         application for NRC regulatory approval               provisions. If, in the future, the NRC
                                               White Flint North, 11555 Rockville                      in the form of licensing. Changes in                  staff seeks to impose a position in the
                                               Pike, Rockville, Maryland 20852.                        guidance intended for use by only the                 SRP on holders of already issued
                                               B. Submitting Comments                                  staff are not matters that constitute                 licenses in a manner that would
                                                                                                       backfitting as that term is defined in 10             constitute backfitting or does not
                                                 Please include Docket ID NRC–2018–                                                                          provide issue finality as described in the
                                                                                                       CFR 50.109(a)(1) or involve the issue
                                               0197 in your comment submission.                                                                              applicable issue finality provision, then
                                                                                                       finality provisions of 10 CFR part 52.
                                                 The NRC cautions you not to include                                                                         the staff must make a showing as set
                                               identifying or contact information that                    2. Backfitting and issue finality—with
                                                                                                       certain exceptions discussed below—do                 forth in the Backfit Rule or address the
                                               you do not want to be publicly                                                                                criteria set forth in the applicable issue
                                               disclosed in your comment submission.                   not apply to current or future
                                                                                                       applicants.                                           finality provision, as applicable, that
                                               The NRC will post all comment                                                                                 would allow the staff to impose the
                                               submissions at http://                                     Applicants and potential applicants
                                                                                                       are not, with certain exceptions, the                 position.
                                               www.regulations.gov as well as enter the
                                               comment submissions into ADAMS.                         subject of either the Backfit Rule or any               Dated at Rockville, Maryland, this 6th day
                                                                                                       issue finality provisions under 10 CFR                of September 2018.
                                               The NRC does not routinely edit
                                               comment submissions to remove                           part 52. This is because neither the                    For the Nuclear Regulatory Commission.
                                               identifying or contact information.                     Backfit Rule nor the issue finality                   Jennivine K. Rankin,
                                                 If you are requesting or aggregating                  provisions under 10 CFR part 52 were                  Acting Chief, Division of Licensing, Siting,
                                               comments from other persons for                         intended to apply to every NRC action                 and Environmental Analysis, Licensing
                                               submission to the NRC, then you should                  that substantially changes the                        Branch 3, Office of New Reactors.
                                               inform those persons not to include                     expectations of current and future                    [FR Doc. 2018–19684 Filed 9–10–18; 8:45 am]
                                               identifying or contact information that                 applicants.                                           BILLING CODE 7590–01–P
                                               they do not want to be publicly                            The exceptions to the general
                                               disclosed in their comment submission.                  principle are applicable whenever a 10
                                               Your request should state that the NRC                  CFR part 50 operating license applicant               NUCLEAR REGULATORY
                                               does not routinely edit comment                         references a construction permit or a 10              COMMISSION
                                               submissions to remove such information                  CFR part 52 combined license applicant
                                                                                                       references a license (e.g., an early site             Meeting of the Advisory Committee on
                                               before making the comment
                                                                                                       permit) and/or NRC regulatory approval                Reactor Safeguards Subcommittee on
                                               submissions available to the public or
                                                                                                       (e.g., a design certification rule) for               Plant License Renewal
                                               entering the comment into ADAMS.
                                                                                                       which specified issue finality provisions               The ACRS Subcommittee on Plant
                                               II. Further Information                                 apply.                                                License Renewal will hold a meeting on
                                                  The NRC seeks public comment on                         The NRC staff does not, at this time,              September 20, 2018 at U.S. Nuclear
                                               the proposed Standard Review Plan                       intend to impose the positions                        Regulatory Commission, 11545
                                               (SRP)-draft section revision of Section                 represented in this draft SRP section in              Rockville Pike, Room T–2B1, Rockville,
                                               13.6, ‘‘Physical Security.’’ The changes                a manner that constitutes backfitting or              Maryland 20852.
                                               made in this revision to this section                   is inconsistent with any issue finality                 The entire meeting will be open to
                                               reflect the latest NRC guidance                         provision of 10 CFR part 52. If, in the               public attendance. The agenda for the
                                               concerning physical security.                           future, the staff seeks to impose a                   subject meeting shall be as follows:
                                                  Following NRC staff evaluation of                    position in this draft SRP section in a
daltland on DSKBBV9HB2PROD with NOTICES




                                               public comments, the NRC intends to                     manner that would constitute                          Thursday, September 20, 2018, 1 p.m.
                                               finalize SRP Section 13.6, ‘‘Physical                   backfitting or be inconsistent with these             Until 5 p.m.
                                               Security,’’ Revision 4 in ADAMS and                     issue finality provisions, the NRC staff                The Subcommittee will conduct a
                                               post it on the NRC’s public website at                  must make the showing as set forth in                 briefing on the River Bend Nuclear
                                               http://www.nrc.gov/reading-rm/doc-                      the Backfit rule or address the                       Generating Station Unit 1 License
                                               collections/nuregs/staff/sr0800/. The                   regulatory criteria set forth in the                  Renewal Application. The
                                               SRP is guidance for the NRC staff. The                  applicable issue finality provision, as               Subcommittee will hear presentations


                                          VerDate Sep<11>2014   18:49 Sep 10, 2018   Jkt 244001   PO 00000   Frm 00119   Fmt 4703   Sfmt 4703   E:\FR\FM\11SEN1.SGM   11SEN1



Document Created: 2018-09-11 01:03:16
Document Modified: 2018-09-11 01:03:16
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionStandard review plan-draft section revision; request for comment.
DatesComments must be filed no later than November 13, 2018. Comments received after this date will be considered, if it is practical to do so, but the Commission is able to ensure consideration only for comments received on or before this date.
ContactMark D. Notich, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555- 0001; telephone: 301-415-3053, email: [email protected]
FR Citation83 FR 45992 