In accordance with the National Environmental Policy Act of 1969 (NEPA), as amended, the Bureau of Land Management (BLM) and the U.S. Department of Agriculture, Forest Service (USFS) Caribou-Targhee National Forest (CTNF), have prepared a Draft Environmental Impact Statement (EIS) for the proposed East Smoky Panel Mine Project (Project), and by this Notice announce the opening of the public comment period.

Federal Register, Volume 83 Issue 189 (Friday, September 28, 2018)
[Federal Register Volume 83, Number 189 (Friday, September 28, 2018)]
[Notices]
[Pages 49123-49124]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-21204]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Land Management

DEPARTMENT OF AGRICULTURE

Forest Service

[17XL LLIDI00000.L71220000.EO0000.LVTFD1700100 241A 4500116174]


Notice of Availability of Draft Environmental Impact Statement 
for the Proposed East Smoky Panel Mine Project at Smoky Canyon Mine, 
Caribou County, ID

AGENCY: Bureau of Land Management, Interior; Forest Service, USDA.

ACTION: Notice of availability.

-----------------------------------------------------------------------

SUMMARY: In accordance with the National Environmental Policy Act of 
1969 (NEPA), as amended, the Bureau of Land Management (BLM) and the 
U.S. Department of Agriculture, Forest Service (USFS) Caribou-Targhee 
National Forest (CTNF), have prepared a Draft Environmental Impact 
Statement (EIS) for the proposed East Smoky Panel Mine Project 
(Project), and by this Notice announce the opening of the public 
comment period.

DATES: To ensure consideration, the Agencies must receive written 
comments on the East Smoky Panel Mine Project Draft EIS no later than 
90 days after the Environmental Protection Agency publishes its notice 
of availability of the Draft EIS in the Federal Register. The BLM will 
announce any future public meetings and any other public involvement 
activities at least 15 days in advance through public notices, media 
news releases, and/or mailings.

ADDRESSES: You may submit comments related to the Project Draft EIS by 
any of the following methods:
     Website: https://go.usa.gov/xnYTG.
     Email: [email protected].
     Mail: East Smoky Panel Mine Draft EIS, c/o Stantec 
Consulting Services Inc., 3995 South 700 East, Suite 300, Salt Lake 
City, Utah 84107.
    Please reference ``East Smoky Panel Mine Draft EIS'' on all 
correspondence. CD-ROM and print copies of the East Smoky Panel Mine 
Draft EIS are available in the BLM Pocatello Field Office at the 
following address: 4350 Cliffs Drive, Pocatello, ID 83204. In addition, 
an electronic copy of the Draft EIS is available online at:

 BLM Land Use Planning and NEPA Register: https://go.usa.gov/xnYTG
 Caribou-Targhee National Forest Current and Recent Projects: 
http://www.fs.usda.gov/projects/ctnf/landmanagement/projects.


FOR FURTHER INFORMATION CONTACT: Kyle Free, BLM Pocatello Field Office, 
4350 Cliffs Drive, Pocatello, ID 83204; phone 208-478-6352; email: 
[email protected]; fax 208-478-6376. Persons who use a telecommunications 
device for the deaf (TDD) may call the Federal Relay Service (FRS) at 
1-800-877-8339 to contact Mr. Free. The FRS is available 24 hours a 
day, 7 days a week, to leave a message or question for Mr. Free. You 
will receive a reply during normal business hours.

SUPPLEMENTARY INFORMATION: The BLM, as the Federal lease administrator, 
is the lead agency, and the USFS is the co-lead agency. The Idaho 
Department of Environmental Quality, Idaho Department of Lands, and 
Idaho Governor's Office of Energy and Mineral Resources are cooperating 
agencies. J.R. Simplot Company has submitted a proposed lease 
modification and Mine and Reclamation Plan (M&RP) for agency review for 
the East Smoky Panel leases (IDI-015259, IDI-26843, and IDI-012890) at 
the Smoky Canyon Phosphate Mine in Caribou County, Idaho. Existing 
Smoky Canyon mining and milling operations were authorized in 1982 by a 
mine plan approval issued by the BLM and Special Use Authorizations 
(SUAs) issued by the USFS for off-lease activities, supported by the 
Smoky Canyon Mine Final EIS and Record of Decision (ROD). Mining 
operations began in Panel A in 1984 and have continued ever since, with 
the mining of Panels A through G. The

[[Page 49124]]

proposed East Smoky Panel Project Area is located approximately one-
half mile directly east of Panel A and, in the northern portion, 
adjacent to Panel B. The BLM prepared a supplemental EIS for mining of 
Panels B and C, addressing selenium and endangered species issues, in 
2002; a subsequent ROD approved the mining of Panels B and C. The BLM 
and USFS approved the mining of Panels F and G in 2008 and a subsequent 
Mine Plan modification in 2015.
    The Proposed Action would consist of mining the East Smoky Panel as 
outlined in the Draft EIS. The Draft EIS fully evaluates Alternatives 
to the Proposed Action, including a No Action Alternative, and 
addresses issues identified during scoping.
    The BLM and USFS will make separate but coordinated decisions 
related to the proposed Project. The BLM will either approve, approve 
with modifications, or deny the M&RP; and recommend whether to modify 
lease IDI-015259. In addition, the BLM will decide whether to approve a 
modification to the existing B-Panel Mine Plan. The BLM will base its 
decisions on public and agency input on the Draft EIS, the Final EIS, 
and any recommendations the USFS may have regarding surface management 
of leased National Forest System lands. The USFS will make 
recommendations to the BLM concerning surface management and mitigation 
on leased lands within the CTNF and will issue decisions on SUAs for 
off-lease activities. SUAs from the USFS would be necessary for any 
off-lease disturbances/structures located within the CTNF and 
associated with the Project. A Forest Plan amendment by the USFS would 
also be necessary as outlined in the Draft EIS.
    On April 3, 2015, the Federal Register published a Notice of Intent 
to prepare this EIS (80 FR 18250), initiating a 30-day public scoping 
period for the Proposed Action during which the BLM accepted written 
comments. The scoping process identified concerns involving impacts to 
water resources and watersheds from potentially elevated levels of 
selenium; potential effects and/or cumulative effects of the Project 
regarding air quality, human health and safety, socioeconomics, 
wildlife, reclamation and financial assurance; and mitigation and 
monitoring of mine operations.
    To facilitate understanding and comments on the Draft EIS, the BLM 
has planned public meetings for Afton, Wyoming, and Pocatello, Idaho. 
Meetings will be open-house style, with displays explaining the Project 
and a forum for commenting on the Project. The BLM will announce dates, 
times, and locations of the public scoping meetings in mailings and 
local media at least 15 days in advance.
    Stakeholders, interested parties and members of the public should 
submit written and electronic comments regarding the Draft EIS no later 
than 90 days after the Environmental Protection Agency publishes its 
notice of availability of the Draft EIS in the Federal Register. To 
assist the BLM and the USFS in identifying issues and concerns related 
to this project, comments should be as specific as possible. The 
portion of the proposed project related to special use authorizations 
for off-lease activities are subject to the USFS objection process. Due 
to the need for a Forest Plan amendment, this proposed project is 
subject to the predecisional administrative review process pursuant to 
36 CFR part 218 subparts A and B and 36 CFR part 219 subpart B. Only 
those who provide comment during this comment period or who have 
previously submitted specific written comments on the Proposed Action, 
either during scoping or other designated opportunity for public 
comment, will be eligible as objectors (36 CFR 218.5(a) and 219.53(a)). 
BLM appeal procedures found in 43 CFR part 4, subpart E apply to the 
portion of the Project related to the Federal mineral lease(s).
    Before including your phone number, email address, or other 
personal identifying information in your comment, you should be aware 
that your entire comment--including your personal identifying 
information--may be made publicly available at any time. While you can 
ask us in your comment to withhold your personal identifying 
information from public review, we cannot guarantee that we will be 
able to do so.

    Authority: 42 U.S.C. 4321 et seq.; 43 U.S.C. 1701; 40 CFR parts 
1500 through 1508; 43 CFR part 4; 43 CFR part 3590.

    Dated: July 16, 2018.
Peter J. Ditton,
Acting State Director, Bureau of Land Management, Idaho State Office.
Mel Bolling,
Forest Supervisor, Caribou-Targhee National Forest.
[FR Doc. 2018-21204 Filed 9-27-18; 8:45 am]
 BILLING CODE 4310-GG-P



                                                                                   Federal Register / Vol. 83, No. 189 / Friday, September 28, 2018 / Notices                                                                               49123

                                                                                                                                                                   Number of          Number of        Completion time                 Total annual
                                                                                           Form/activity                                                             annual             annual          per response                  burden hours *
                                                                                                                                                                  respondents         responses

                                              3–2321 Membership Application .............................................................                                       76              76    2 hours ................                  152
                                              3–2322 Applicant Interview ......................................................................                                 76              76    30 minutes ..........                      38
                                              3–2323 Reference/Contact Interview ......................................................                                        189             189    15 minutes ..........                      47
                                              3–XXXX Incumbent Application ...............................................................                                      22              22    5 minutes ............                      2
                                              3–2326 Hunt Application and Permit .......................................................                                    11,141          11,141    10 minutes ..........                   1,857
                                              3–2326 Hunt Report ................................................................................                           11,141          11,141    5 minutes ............                    928
                                              3–2327 Designated Hunter Application and Permit ................................                                                 701             701    10 minutes ..........                     117
                                              3–2327 Designated Hunter—Hunt Report ...............................................                                             701             701    5 minutes ............                     58
                                              3–2328 Fishing Application and Permit ...................................................                                      2,136           2,136    10 minutes ..........                     356
                                              3–2328 Fishing Report ............................................................................                             2,136           2,136    5 minutes ............                    178
                                              3–2378 Designated Fishing Application and Permit ...............................                                                  58              58    10 minutes ..........                      10
                                              3–2378 Designated Fishing Report .........................................................                                        58              58    5 minutes ............                      5
                                              3–2379 Customary Trade Recordkeeping Application and Permit .........                                                             18              18    10 minutes ..........                       3
                                              3–2379 Customary Trade Recordkeeping—Report ................................                                                      18              18    5 minutes ............                      2
                                              Petition to Repeal .......................................................................................                         1               1    2 hours ................                    2
                                              Proposed Changes ....................................................................................                             70              70    30 minutes ..........                      35
                                              Special Actions Request ............................................................................                              17              17    30 minutes ..........                       9
                                              Request for Reconsideration (Appeal) .......................................................                                     741             741    4 hours ................                2,964
                                              Traditional/Cultural/Educational Permits and Reports ...............................                                               5               5    30 minutes ..........                       3
                                              Fishwheel, Fyke Net, and Under-Ice Permits and Reports .......................                                                     7               7    15 minutes ..........                       2

                                                    Totals ..................................................................................................               29,290          29,290    .............................           6,766
                                                 * Rounded.


                                                An agency may not conduct or                                            National Forest (CTNF), have prepared                                www.fs.usda.gov/projects/ctnf/
                                              sponsor and a person is not required to                                   a Draft Environmental Impact Statement                               landmanagement/projects.
                                              respond to a collection of information                                    (EIS) for the proposed East Smoky Panel                           FOR FURTHER INFORMATION CONTACT:     Kyle
                                              unless it displays a currently valid OMB                                  Mine Project (Project), and by this                               Free, BLM Pocatello Field Office, 4350
                                              control number.                                                           Notice announce the opening of the                                Cliffs Drive, Pocatello, ID 83204; phone
                                                The authority for this action is the                                    public comment period.                                            208–478–6352; email: kfree@blm.gov;
                                              Paperwork Reduction Act of 1995 (44                                       DATES: To ensure consideration, the                               fax 208–478–6376. Persons who use a
                                              U.S.C. 3501 et seq.).                                                     Agencies must receive written                                     telecommunications device for the deaf
                                                Dated: September 25, 2018.                                              comments on the East Smoky Panel                                  (TDD) may call the Federal Relay
                                              Madonna Baucum,                                                           Mine Project Draft EIS no later than 90                           Service (FRS) at 1–800–877–8339 to
                                              Information Collection Clearance Officer, U.S.                            days after the Environmental Protection                           contact Mr. Free. The FRS is available
                                              Fish and Wildlife Service.                                                Agency publishes its notice of                                    24 hours a day, 7 days a week, to leave
                                              [FR Doc. 2018–21160 Filed 9–27–18; 8:45 am]                               availability of the Draft EIS in the                              a message or question for Mr. Free. You
                                              BILLING CODE 4333–15–P
                                                                                                                        Federal Register. The BLM will                                    will receive a reply during normal
                                                                                                                        announce any future public meetings                               business hours.
                                                                                                                        and any other public involvement                                  SUPPLEMENTARY INFORMATION: The BLM,
                                              DEPARTMENT OF THE INTERIOR                                                activities at least 15 days in advance                            as the Federal lease administrator, is the
                                                                                                                        through public notices, media news                                lead agency, and the USFS is the co-lead
                                              Bureau of Land Management                                                 releases, and/or mailings.                                        agency. The Idaho Department of
                                                                                                                        ADDRESSES: You may submit comments                                Environmental Quality, Idaho
                                              DEPARTMENT OF AGRICULTURE                                                 related to the Project Draft EIS by any                           Department of Lands, and Idaho
                                                                                                                        of the following methods:                                         Governor’s Office of Energy and Mineral
                                              Forest Service                                                              • Website: https://go.usa.gov/xnYTG.                            Resources are cooperating agencies. J.R.
                                              [17XL LLIDI00000.L71220000.                                                 • Email: blm_id_espm_eis@blm.gov.                               Simplot Company has submitted a
                                              EO0000.LVTFD1700100 241A 4500116174]                                        • Mail: East Smoky Panel Mine Draft                             proposed lease modification and Mine
                                                                                                                        EIS, c/o Stantec Consulting Services                              and Reclamation Plan (M&RP) for
                                              Notice of Availability of Draft                                           Inc., 3995 South 700 East, Suite 300,                             agency review for the East Smoky Panel
                                              Environmental Impact Statement for                                        Salt Lake City, Utah 84107.                                       leases (IDI–015259, IDI–26843, and IDI–
                                              the Proposed East Smoky Panel Mine                                          Please reference ‘‘East Smoky Panel                             012890) at the Smoky Canyon
                                              Project at Smoky Canyon Mine,                                             Mine Draft EIS’’ on all correspondence.                           Phosphate Mine in Caribou County,
                                              Caribou County, ID                                                        CD–ROM and print copies of the East                               Idaho. Existing Smoky Canyon mining
                                              AGENCY:   Bureau of Land Management,                                      Smoky Panel Mine Draft EIS are                                    and milling operations were authorized
                                              Interior; Forest Service, USDA.                                           available in the BLM Pocatello Field                              in 1982 by a mine plan approval issued
                                                                                                                        Office at the following address: 4350                             by the BLM and Special Use
                                              ACTION: Notice of availability.
amozie on DSK3GDR082PROD with NOTICES1




                                                                                                                        Cliffs Drive, Pocatello, ID 83204. In                             Authorizations (SUAs) issued by the
                                              SUMMARY:  In accordance with the                                          addition, an electronic copy of the Draft                         USFS for off-lease activities, supported
                                              National Environmental Policy Act of                                      EIS is available online at:                                       by the Smoky Canyon Mine Final EIS
                                              1969 (NEPA), as amended, the Bureau of                                    • BLM Land Use Planning and NEPA                                  and Record of Decision (ROD). Mining
                                              Land Management (BLM) and the U.S.                                          Register: https://go.usa.gov/xnYTG                              operations began in Panel A in 1984 and
                                              Department of Agriculture, Forest                                         • Caribou-Targhee National Forest                                 have continued ever since, with the
                                              Service (USFS) Caribou-Targhee                                              Current and Recent Projects: http://                            mining of Panels A through G. The


                                         VerDate Sep<11>2014        19:22 Sep 27, 2018          Jkt 244001      PO 00000        Frm 00076       Fmt 4703        Sfmt 4703    E:\FR\FM\28SEN1.SGM   28SEN1


                                              49124                       Federal Register / Vol. 83, No. 189 / Friday, September 28, 2018 / Notices

                                              proposed East Smoky Panel Project Area                  The BLM will announce dates, times,                   INTERNATIONAL TRADE
                                              is located approximately one-half mile                  and locations of the public scoping                   COMMISSION
                                              directly east of Panel A and, in the                    meetings in mailings and local media at
                                                                                                                                                            [Investigation Nos. 701–TA–609 and 731–
                                              northern portion, adjacent to Panel B.                  least 15 days in advance.                             TA–1421 (Preliminary)]
                                              The BLM prepared a supplemental EIS
                                                                                                        Stakeholders, interested parties and
                                              for mining of Panels B and C, addressing                                                                      Steel Trailer Wheels From China
                                                                                                      members of the public should submit
                                              selenium and endangered species
                                              issues, in 2002; a subsequent ROD                       written and electronic comments                       Determinations
                                              approved the mining of Panels B and C.                  regarding the Draft EIS no later than 90
                                                                                                                                                               On the basis of the record 1 developed
                                              The BLM and USFS approved the                           days after the Environmental Protection
                                                                                                                                                            in the subject investigations, the United
                                              mining of Panels F and G in 2008 and                    Agency publishes its notice of                        States International Trade Commission
                                              a subsequent Mine Plan modification in                  availability of the Draft EIS in the                  (‘‘Commission’’) determines, pursuant
                                              2015.                                                   Federal Register. To assist the BLM and               to the Tariff Act of 1930 (‘‘the Act’’),
                                                 The Proposed Action would consist of                 the USFS in identifying issues and                    that there is a reasonable indication that
                                              mining the East Smoky Panel as                          concerns related to this project,                     an industry in the United States is
                                              outlined in the Draft EIS. The Draft EIS                comments should be as specific as                     materially injured by reason of imports
                                              fully evaluates Alternatives to the                     possible. The portion of the proposed                 of steel trailer wheels from China that
                                              Proposed Action, including a No Action                  project related to special use                        are alleged to be sold in the United
                                              Alternative, and addresses issues                       authorizations for off-lease activities are           States at less than fair value (‘‘LTFV’’)
                                              identified during scoping.                              subject to the USFS objection process.                and to be subsidized by the government
                                                 The BLM and USFS will make                           Due to the need for a Forest Plan                     of China.2 3
                                              separate but coordinated decisions                      amendment, this proposed project is
                                              related to the proposed Project. The                                                                          Commencement of Final Phase
                                                                                                      subject to the predecisional                          Investigations
                                              BLM will either approve, approve with
                                                                                                      administrative review process pursuant
                                              modifications, or deny the M&RP; and                                                                             Pursuant to section 207.18 of the
                                              recommend whether to modify lease                       to 36 CFR part 218 subparts A and B
                                                                                                                                                            Commission’s rules, the Commission
                                              IDI–015259. In addition, the BLM will                   and 36 CFR part 219 subpart B. Only
                                                                                                                                                            also gives notice of the commencement
                                              decide whether to approve a                             those who provide comment during this
                                                                                                                                                            of the final phase of its investigations.
                                              modification to the existing B-Panel                    comment period or who have previously                 The Commission will issue a final phase
                                              Mine Plan. The BLM will base its                        submitted specific written comments on                notice of scheduling, which will be
                                              decisions on public and agency input on                 the Proposed Action, either during                    published in the Federal Register as
                                              the Draft EIS, the Final EIS, and any                   scoping or other designated opportunity               provided in section 207.21 of the
                                              recommendations the USFS may have                       for public comment, will be eligible as               Commission’s rules, upon notice from
                                              regarding surface management of leased                  objectors (36 CFR 218.5(a) and                        the U.S. Department of Commerce
                                              National Forest System lands. The USFS                  219.53(a)). BLM appeal procedures                     (‘‘Commerce’’) of affirmative
                                              will make recommendations to the BLM                    found in 43 CFR part 4, subpart E apply               preliminary determinations in the
                                              concerning surface management and                       to the portion of the Project related to              investigations under sections 703(b) or
                                              mitigation on leased lands within the                   the Federal mineral lease(s).                         733(b) of the Act, or, if the preliminary
                                              CTNF and will issue decisions on SUAs                                                                         determinations are negative, upon
                                                                                                        Before including your phone number,
                                              for off-lease activities. SUAs from the                                                                       notice of affirmative final
                                              USFS would be necessary for any off-                    email address, or other personal
                                                                                                                                                            determinations in those investigations
                                              lease disturbances/structures located                   identifying information in your
                                                                                                                                                            under sections 705(a) or 735(a) of the
                                              within the CTNF and associated with                     comment, you should be aware that
                                                                                                                                                            Act. Parties that filed entries of
                                              the Project. A Forest Plan amendment                    your entire comment—including your                    appearance in the preliminary phase of
                                              by the USFS would also be necessary as                  personal identifying information—may                  the investigations need not enter a
                                              outlined in the Draft EIS.                              be made publicly available at any time.               separate appearance for the final phase
                                                 On April 3, 2015, the Federal Register               While you can ask us in your comment                  of the investigations. Industrial users,
                                              published a Notice of Intent to prepare                 to withhold your personal identifying                 and, if the merchandise under
                                              this EIS (80 FR 18250), initiating a 30-                information from public review, we                    investigation is sold at the retail level,
                                              day public scoping period for the                       cannot guarantee that we will be able to              representative consumer organizations
                                              Proposed Action during which the BLM                    do so.                                                have the right to appear as parties in
                                              accepted written comments. The                                                                                Commission antidumping and
                                                                                                        Authority: 42 U.S.C. 4321 et seq.; 43 U.S.C.
                                              scoping process identified concerns                                                                           countervailing duty investigations. The
                                                                                                      1701; 40 CFR parts 1500 through 1508; 43
                                              involving impacts to water resources                                                                          Secretary will prepare a public service
                                                                                                      CFR part 4; 43 CFR part 3590.
                                              and watersheds from potentially                                                                               list containing the names and addresses
                                              elevated levels of selenium; potential                    Dated: July 16, 2018.                               of all persons, or their representatives,
                                              effects and/or cumulative effects of the                Peter J. Ditton,                                      who are parties to the investigations.
                                              Project regarding air quality, human                    Acting State Director, Bureau of Land
                                              health and safety, socioeconomics,                      Management, Idaho State Office.                         1 The record is defined in sec. 207.2(f) of the

                                              wildlife, reclamation and financial                     Mel Bolling,
                                                                                                                                                            Commission’s Rules of Practice and Procedure (19
                                              assurance; and mitigation and                                                                                 CFR 207.2(f)).
                                                                                                      Forest Supervisor, Caribou-Targhee National             2 Certain Steel Wheels 12 to 16.5 Inches in
                                              monitoring of mine operations.
amozie on DSK3GDR082PROD with NOTICES1




                                                                                                      Forest.                                               Diameter From the People’s Republic of China:
                                                 To facilitate understanding and                                                                            Initiation of Countervailing Duty Investigation, 83
                                              comments on the Draft EIS, the BLM has                  [FR Doc. 2018–21204 Filed 9–27–18; 8:45 am]
                                                                                                                                                            FR 45100, September 5, 2018; Certain Steel Wheels
                                              planned public meetings for Afton,                      BILLING CODE 4310–GG–P                                12 to 16.5 Inches in Diameter From the People’s
                                              Wyoming, and Pocatello, Idaho.                                                                                Republic of China: Initiation of Less-Than-Fair-
                                                                                                                                                            Value Investigation, 83 FR 45095, September 5,
                                              Meetings will be open-house style, with                                                                       2018.
                                              displays explaining the Project and a                                                                           3 Commissioner Meredith M. Broadbent did not

                                              forum for commenting on the Project.                                                                          participate in the determinations.



                                         VerDate Sep<11>2014   19:22 Sep 27, 2018   Jkt 244001   PO 00000   Frm 00077   Fmt 4703   Sfmt 4703   E:\FR\FM\28SEN1.SGM   28SEN1



Document Created: 2018-09-28 01:22:22
Document Modified: 2018-09-28 01:22:22
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of availability.
DatesTo ensure consideration, the Agencies must receive written comments on the East Smoky Panel Mine Project Draft EIS no later than 90 days after the Environmental Protection Agency publishes its notice of availability of the Draft EIS in the Federal Register. The BLM will announce any future public meetings and any other public involvement activities at least 15 days in advance through public notices, media news releases, and/or mailings.
ContactKyle Free, BLM Pocatello Field Office, 4350 Cliffs Drive, Pocatello, ID 83204; phone 208-478-6352; email: [email protected]; fax 208-478-6376. Persons who use a telecommunications device for the deaf (TDD) may call the Federal Relay Service (FRS) at 1-800-877-8339 to contact Mr. Free. The FRS is available 24 hours a day, 7 days a week, to leave a message or question for Mr. Free. You will receive a reply during normal business hours.