The U.S. Army Corps of Engineers (USACE) Fort Worth District has prepared a Draft Environmental Impact Statement (EIS) to analyze the direct, indirect and cumulative effects of the construction of the Lake Ralph Hall Regional Water Supply Reservoir Project in Fannin County, TX, proposed by the Upper Trinity Regional Water District (UTRWD). This action requires authorization from USACE under Section 404 of the Clean Water Act for construction and operation of the proposed project. The proposed project is a regional water supply project intended to provide approximately 34,050 acre-feet (AF) per year of new water for 20 water providers, special districts, and municipalities in Denton County and small portions of Dallas, Collin, Grayson, Wise and Cooke counties to the extent that Denton County Customers' service areas extend outside the County. Construction of the reservoir and support facilities would result in permanent direct impacts to waters of the U.S. of approximately 8 acres of wetlands and 384 acres of other waters including streams, impoundments, and ponds. The proposed project pipeline will cross 59 streams with 11,893 lineal feet of temporary impact as well as 0.4 acres of stock tanks.

Federal Register, Volume 83 Issue 194 (Friday, October 5, 2018)
[Federal Register Volume 83, Number 194 (Friday, October 5, 2018)]
[Notices]
[Pages 50353-50354]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-21538]


-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Department of the Army; Corps of Engineers


Notice of Availability of the Draft Environmental Impact 
Statement for the Lake Ralph Hall Regional Water Supply Reservoir 
Project, Fannin County, TX

AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD.

ACTION: Notice of availability.

-----------------------------------------------------------------------

SUMMARY: The U.S. Army Corps of Engineers (USACE) Fort Worth District 
has prepared a Draft Environmental Impact Statement (EIS) to analyze 
the direct, indirect and cumulative effects of the construction of the 
Lake Ralph Hall Regional Water Supply Reservoir Project in Fannin 
County, TX, proposed by the Upper Trinity Regional Water District 
(UTRWD). This action requires authorization from USACE under Section 
404 of the Clean Water Act for construction and operation of the 
proposed project. The proposed project is a regional water supply 
project intended to provide approximately 34,050 acre-feet (AF) per 
year of new water for 20 water providers, special districts, and 
municipalities in Denton County and small portions of Dallas, Collin, 
Grayson, Wise and Cooke counties to the extent that Denton County 
Customers' service areas extend outside the County. Construction of the 
reservoir and support facilities would result in permanent direct 
impacts to waters of the U.S. of approximately 8 acres of wetlands and 
384 acres of other waters including streams, impoundments, and ponds. 
The proposed project pipeline will cross 59

[[Page 50354]]

streams with 11,893 lineal feet of temporary impact as well as 0.4 
acres of stock tanks.

DATES: Written comments on the Draft EIS will be accepted until 
November 21, 2018. Oral and/or written comments may also be presented 
at the Public Hearing.

ADDRESSES: A Public Hearing will be held Thursday, October 25, 2018 
starting at 5:30 p.m. at the H.L. Milton Sports Complex, 601 W Mill 
Street, Ladonia, TX 75449.

FOR FURTHER INFORMATION CONTACT: Chandler J. Peter, EIS Project 
Manager, at 817-886-1731 or [email protected].

SUPPLEMENTARY INFORMATION: The Draft EIS was prepared in accordance 
with the National Environmental Policy Act (NEPA) of 1969, as amended, 
and the Corps' regulations for NEPA implementation (33 Code of Federal 
Regulations [CFR] parts 230 and 325, Appendices B and C). The Corps, 
Fort Worth, Regulatory Branch is the lead federal agency responsible 
for the Draft EIS and information contained in the EIS serves as the 
basis for a decision regarding issuance of a Section 404 permit. It 
also provides information for federal, state and local agencies having 
jurisdictional responsibility for affected resources.
    The purpose of the Draft EIS is to provide decision-makers and the 
public with information pertaining to the Proposed Action and 
alternatives, and to disclose environmental impacts and identify 
mitigation measures to reduce impacts. UTRWD proposes to construct Lake 
Ralph Hall (including principal and emergency spillways, dam, and 
reservoir) with a conservation pool storage capacity of approximately 
160,235 AF. Construction of a new raw water pipeline from the proposed 
Lake Ralph Hall to the Tom Harpool Water Treatment Plant is also 
proposed, as well as a new balancing reservoir and pump station.
    The purpose for the project is to provide additional firm annual 
yield to the 20 water providers and communities to address anticipated 
water demands associated with projected growth.
    In addition to the Proposed Action, the Draft EIS analyzes the No 
Action Alternative. Other alternatives were evaluated but not carried 
forward for detailed consideration, including water supplied from five 
new (undeveloped) reservoirs; securing supplies from other existing 
sources, Oklahoma, additional Dallas Water Utilities Supply, the Gulf 
of Mexico, Cypress Creek Basin, groundwater imports and precipitation 
enhancement. In addition, alternative dam alignments and conservation 
pool sizes were considered.
    The U.S. Environmental Protection Agency Region VI, U.S. Fish and 
Wildlife Service, U.S. Forest Service, Texas Commission on 
Environmental Quality, Texas Parks and Wildlife Department and the 
Texas Historical Commission have participated as cooperating agencies 
in the formulation of the Draft EIS.
    Copies of the Draft EIS will also be available for review at:
    1. Ladonia City Hall, 100 Center Plaza, Ladonia, TX 75449.
    2. Wolfe City Public Library, 102 TX-11, Wolfe City, TX 75496.
    3. Commerce Public Library, 1210 Park Street, Commerce, TX 75428.
    4. Honey Grove Library, 500 N 6th Street, Honey Grove, TX 75446.
    5. Bonham Public Library, 305 E 5th Street, Bonham, TX 75418.
    6. Greenville Public Library, 1 Lou Finney Lane, Greenville, TX 
75401
    7. Upper Trinity Regional Water District, 900 North Kealy Street, 
Lewisville, TX 75067.
    8. U.S. Army Corps of Engineers, Fort Worth Regulatory Office, 819 
Taylor Street, Fort Worth, TX 76102.
    Send written comments regarding the Proposed Action and Draft EIS 
to Chandler J. Peter, EIS Project Manager, U.S. Army Corps of 
Engineers, Fort Worth District--Regulatory Division, 819 Taylor Street, 
Room 3A37, P.O. Box 17300, Fort Worth, Texas 76102 or via email: 
[email protected]. Requests to be placed on or removed 
from a mailing list for the Final EIS should also be sent to this 
address.
    Electronic copies of the Draft EIS may be obtained from the Fort 
Worth Regulatory Division or its website at: https://www.swf.usace.army.mil/Missions/Regulatory/Permitting/Proposed-Lake-Ralph-Hall/.

Stephen L. Brooks,
Chief, Regulatory Division, Fort Worth District.
[FR Doc. 2018-21538 Filed 10-4-18; 8:45 am]
 BILLING CODE 3720-58-P



                                                                              Federal Register / Vol. 83, No. 194 / Friday, October 5, 2018 / Notices                                                50353

                                               public meeting held by the DAC–IPAD.                          Proceedings Panel                               operates under the provisions of the
                                               For its first session, the Committee will                     Recommendations Related to                      Federal Advisory Committee Act, as
                                               receive testimony from a retired Service                      Articles 32, 33, and 34 of the                  amended, all written comments will be
                                               member who was accused of sexual                              Uniform Code of Military Justice                treated as public documents and will be
                                               assault and from a Marine Corps defense                       Referred to the DAC–IPAD for                    made available for public inspection.
                                               highly qualified expert (HQE) on the                          Examination;                                    Oral statements from the public will be
                                               effect of sexual assault investigations on              2:30 p.m.–3:50 p.m. Committee                         permitted, though the number and
                                               accused Service members. Next, the                            Deliberations on Expedited                      length of such oral statements may be
                                               Committee will receive testimony from                         Transfer—Final Assessment;                      limited based on the time available and
                                               three civilian sexual assault                           3:50 p.m.–4:00 p.m. Break;                            the number of such requests. Oral
                                               investigators regarding their                           4:00 p.m.–4:15 p.m. Data Working                      presentations by members of the public
                                               perspectives on making probable cause                         Group Update;                                   will be permitted from 4:45 p.m. to 5:00
                                               determinations and opening and closing                  4:15 p.m.–4:45 p.m. Briefing and                      p.m. on October 19, 2018, in front of the
                                               sexual assault investigations. The                            Committee Deliberations on Fiscal               Committee members.
                                               Committee will receive a presentation                         Year 2019 NDAA Required                           Dated: October 1, 2018.
                                               from the chair of the DAC–IPAD Case                           Collateral Misconduct Study;                    Aaron T. Siegel,
                                               Review Working Group on the working                     4:45 p.m.–5:00 p.m. Public Comment;
                                               group’s initial findings and                                                                                  Alternate OSD Federal Register Liaison
                                                                                                       5:00 p.m. Public Meeting Adjourned.                   Officer, Department of Defense.
                                               recommendations stemming from its                          Meeting Accessibility: Pursuant to 5               [FR Doc. 2018–21655 Filed 10–4–18; 8:45 am]
                                               review of fiscal year 2017 sexual assault               U.S.C. 552b and 41 CFR 102–3.140
                                               investigative case files. The Committee                                                                       BILLING CODE 5001–06–P
                                                                                                       through 102–3.165, and the availability
                                               will then receive a briefing from DAC–                  of space, this meeting is open to the
                                               IPAD staff regarding three                              public. Seating is limited and is on a
                                               recommendations made by its                                                                                   DEPARTMENT OF DEFENSE
                                                                                                       first-come basis. Visitors are required to
                                               predecessor sexual assault advisory                     sign in at the One Liberty Center                     Department of the Army; Corps of
                                               committee, the Judicial Proceedings                     security desk and must leave                          Engineers
                                               Panel (JPP) that the Department of                      government-issued photo identification
                                               Defense General Counsel has requested                   on file and wear a visitor badge while                Notice of Availability of the Draft
                                               the DAC–IPAD examine. Next, the                         in the building. Department of Defense                Environmental Impact Statement for
                                               Committee will conduct final                            Common Access Card (CAC) holders                      the Lake Ralph Hall Regional Water
                                               deliberations for its assessment of the                 who do not have authorized access to                  Supply Reservoir Project, Fannin
                                               military’s expedited transfer policy. For               One Liberty Center must provide an                    County, TX
                                               its final sessions, the Committee will                  alternate form of government-issued
                                               receive a briefing from its Data Working                photo identification to leave on file with            AGENCY:Department of the Army, U.S.
                                               Group staff on the status of its sexual                 security while in the building. All                   Army Corps of Engineers, DoD.
                                               assault case adjudication data collection               visitors must pass through a metal                    ACTION:   Notice of availability.
                                               project for fiscal years 2012 through                   detection security screening.
                                               2017, and a briefing on section 547 of                  Individuals requiring special                         SUMMARY:    The U.S. Army Corps of
                                               the National Defense Authorization Act                  accommodations to access the public                   Engineers (USACE) Fort Worth District
                                               for Fiscal Year 2019, which requires the                meeting should contact the DAC–IPAD                   has prepared a Draft Environmental
                                               Secretary of Defense, through the DAC–                  at whs.pentagon.em.mbx.dacipad@                       Impact Statement (EIS) to analyze the
                                               IPAD, to conduct a study every two                      mail.mil at least five (5) business days              direct, indirect and cumulative effects of
                                               years reporting on the number of                        prior to the meeting so that appropriate              the construction of the Lake Ralph Hall
                                               instances in which a sexual assault                     arrangements can be made. In the event                Regional Water Supply Reservoir Project
                                               victim was accused or received                          the Office of Personnel Management                    in Fannin County, TX, proposed by the
                                               disciplinary action for collateral                      closes the government due to inclement                Upper Trinity Regional Water District
                                               misconduct related to allegations of                    weather or for any other reason, please               (UTRWD). This action requires
                                               sexual assault committed against that                   consult the website for any changes to                authorization from USACE under
                                               victim.                                                 the public meeting date or time.                      Section 404 of the Clean Water Act for
                                               Agenda                                                     Written Statements: Pursuant to 41                 construction and operation of the
                                                                                                       CFR 102–3.140 and section 10(a)(3) of                 proposed project. The proposed project
                                               9:00 a.m.–9:10 a.m. Public Meeting
                                                                                                       the Federal Advisory Committee Act of                 is a regional water supply project
                                                   Begins—Welcome and Introduction;
                                               9:10 a.m.–10:30 a.m. Effects of Sexual                  1972, the public or interested                        intended to provide approximately
                                                   Assault Investigations on Accused                   organizations may submit written                      34,050 acre-feet (AF) per year of new
                                                   Service Members;                                    comments to the Committee about its                   water for 20 water providers, special
                                               10:30 a.m.–10:40 a.m. Break;                            mission and topics pertaining to this                 districts, and municipalities in Denton
                                               10:40 a.m.–12:00 p.m. Perspectives of                   public session. Written comments must                 County and small portions of Dallas,
                                                   Civilian Sexual Assault                             be received by the DAC–IPAD at least                  Collin, Grayson, Wise and Cooke
                                                   Investigators;                                      five (5) business days prior to the                   counties to the extent that Denton
                                               12:00 p.m.–1:00 p.m. Lunch;                             meeting date so that they may be made                 County Customers’ service areas extend
                                               1:10 p.m.–1:50 p.m. Case Review                         available to the Committee members for                outside the County. Construction of the
daltland on DSKBBV9HB2PROD with NOTICES




                                                   Working Group Presentation and                      their consideration prior to the meeting.             reservoir and support facilities would
                                                   Committee Deliberations on Initial                  Written comments should be submitted                  result in permanent direct impacts to
                                                   Findings and Recommendations                        via email to the DAC–IPAD at                          waters of the U.S. of approximately 8
                                                   Related to Sexual Assault                           whs.pentagon.em.mbx.dacipad@                          acres of wetlands and 384 acres of other
                                                   Investigative Case File Reviews;                    mail.mil in the following formats:                    waters including streams,
                                               1:50 p.m.–2:30 p.m. Briefing and                        Adobe Acrobat or Microsoft Word.                      impoundments, and ponds. The
                                                   Committee Deliberations on Judicial                 Please note that since the DAC–IPAD                   proposed project pipeline will cross 59


                                          VerDate Sep<11>2014   18:02 Oct 04, 2018   Jkt 247001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\05OCN1.SGM   05OCN1


                                               50354                          Federal Register / Vol. 83, No. 194 / Friday, October 5, 2018 / Notices

                                               streams with 11,893 lineal feet of                      enhancement. In addition, alternative                 SUMMARY:   Copies of the Bonneville
                                               temporary impact as well as 0.4 acres of                dam alignments and conservation pool                  Purchasing Instructions (BPI), which
                                               stock tanks.                                            sizes were considered.                                contain the policy and establish the
                                               DATES: Written comments on the Draft                       The U.S. Environmental Protection                  procedures that BPA uses in the
                                               EIS will be accepted until November 21,                 Agency Region VI, U.S. Fish and                       solicitation, award, and administration
                                               2018. Oral and/or written comments                      Wildlife Service, U.S. Forest Service,                of its purchases of goods and services,
                                               may also be presented at the Public                     Texas Commission on Environmental                     including construction, are available in
                                               Hearing.                                                Quality, Texas Parks and Wildlife                     printed form or at the following internet
                                                                                                       Department and the Texas Historical                   address: http://www.bpa.gov/corporate/
                                               ADDRESSES:    A Public Hearing will be                  Commission have participated as                       business/bpi.
                                               held Thursday, October 25, 2018                         cooperating agencies in the formulation                 Copies of the Bonneville Financial
                                               starting at 5:30 p.m. at the H.L. Milton                of the Draft EIS.                                     Assistance Instructions (BFAI), which
                                               Sports Complex, 601 W Mill Street,                         Copies of the Draft EIS will also be               contain the policy and establish the
                                               Ladonia, TX 75449.                                      available for review at:                              procedures that BPA uses in the
                                               FOR FURTHER INFORMATION CONTACT:                           1. Ladonia City Hall, 100 Center                   solicitation, award, and administration
                                               Chandler J. Peter, EIS Project Manager,                 Plaza, Ladonia, TX 75449.                             of financial assistance instruments
                                               at 817–886–1731 or chandler.j.peter@                       2. Wolfe City Public Library, 102 TX–              (principally grants and cooperative
                                               usace.army.mil.                                         11, Wolfe City, TX 75496.                             agreements), are available in printed
                                                                                                          3. Commerce Public Library, 1210
                                               SUPPLEMENTARY INFORMATION:      The Draft                                                                     form or available at the following
                                                                                                       Park Street, Commerce, TX 75428.
                                               EIS was prepared in accordance with                        4. Honey Grove Library, 500 N 6th                  internet address: http://www.bpa.gov/
                                               the National Environmental Policy Act                   Street, Honey Grove, TX 75446.                        corporate/business/bfai.
                                               (NEPA) of 1969, as amended, and the                        5. Bonham Public Library, 305 E 5th                ADDRESSES: Unbound copies of the BPI
                                               Corps’ regulations for NEPA                             Street, Bonham, TX 75418.                             or BFAI may be obtained by sending a
                                               implementation (33 Code of Federal                         6. Greenville Public Library, 1 Lou                request to the Head of the Contracting
                                               Regulations [CFR] parts 230 and 325,                    Finney Lane, Greenville, TX 75401                     Activity, Routing CGP–7, Bonneville
                                               Appendices B and C). The Corps, Fort                       7. Upper Trinity Regional Water                    Power Administration, P.O. Box 3621,
                                               Worth, Regulatory Branch is the lead                    District, 900 North Kealy Street,                     Portland, Oregon 97208–3621.
                                               federal agency responsible for the Draft                Lewisville, TX 75067.                                 FOR FURTHER INFORMATION CONTACT:
                                               EIS and information contained in the                       8. U.S. Army Corps of Engineers, Fort              Nicholas M. Jenkins, Head of the
                                               EIS serves as the basis for a decision                  Worth Regulatory Office, 819 Taylor                   Contracting Activity; direct telephone
                                               regarding issuance of a Section 404                     Street, Fort Worth, TX 76102.                         (503) 230–5498; or email nmjenkins@
                                               permit. It also provides information for                   Send written comments regarding the                bpa.gov.
                                               federal, state and local agencies having                Proposed Action and Draft EIS to
                                                                                                       Chandler J. Peter, EIS Project Manager,               SUPPLEMENTARY INFORMATION:      BPA was
                                               jurisdictional responsibility for affected                                                                    established in 1937 as a Federal Power
                                               resources.                                              U.S. Army Corps of Engineers, Fort
                                                                                                       Worth District—Regulatory Division,                   Marketing Agency in the Pacific
                                                 The purpose of the Draft EIS is to                                                                          Northwest. BPA operations are financed
                                               provide decision-makers and the public                  819 Taylor Street, Room 3A37, P.O. Box
                                                                                                       17300, Fort Worth, Texas 76102 or via                 from rate payer revenues rather than
                                               with information pertaining to the                                                                            annual appropriations. BPA’s
                                               Proposed Action and alternatives, and                   email: chandler.j.peter@usace.army.mil.
                                                                                                       Requests to be placed on or removed                   purchasing operations are conducted
                                               to disclose environmental impacts and                                                                         under 16 U.S.C. 832 et seq. and related
                                               identify mitigation measures to reduce                  from a mailing list for the Final EIS
                                                                                                       should also be sent to this address.                  statutes. Pursuant to these special
                                               impacts. UTRWD proposes to construct                                                                          authorities, the BPI is promulgated as a
                                               Lake Ralph Hall (including principal                      Electronic copies of the Draft EIS may
                                                                                                       be obtained from the Fort Worth                       statement of purchasing policy and as a
                                               and emergency spillways, dam, and                                                                             body of interpretative regulations
                                               reservoir) with a conservation pool                     Regulatory Division or its website at:
                                                                                                       https://www.swf.usace.army.mil/                       governing the conduct of BPA
                                               storage capacity of approximately                                                                             purchasing activities, and reflects BPA’s
                                               160,235 AF. Construction of a new raw                   Missions/Regulatory/Permitting/
                                                                                                       Proposed-Lake-Ralph-Hall/.                            private sector approach to purchasing
                                               water pipeline from the proposed Lake                                                                         the goods and services that it requires.
                                               Ralph Hall to the Tom Harpool Water                     Stephen L. Brooks,                                    BPA’s financial assistance operations
                                               Treatment Plant is also proposed, as                    Chief, Regulatory Division, Fort Worth                are conducted under 16 U.S.C. 832 et
                                               well as a new balancing reservoir and                   District.                                             seq. and 16 U.S.C. 839 et seq. The BFAI
                                               pump station.                                           [FR Doc. 2018–21538 Filed 10–4–18; 8:45 am]           express BPA’s financial assistance
                                                 The purpose for the project is to                     BILLING CODE 3720–58–P                                policy. The BFAI also comprise BPA’s
                                               provide additional firm annual yield to                                                                       rules governing implementation of the
                                               the 20 water providers and communities                                                                        principles set forth in 2 CFR part 200.
                                               to address anticipated water demands                    DEPARTMENT OF ENERGY                                     BPA’s solicitations and contracts
                                               associated with projected growth.                                                                             include notice of applicability and
                                                 In addition to the Proposed Action,                   Bonneville Power Administration                       availability of the BPI and the BFAI, as
                                               the Draft EIS analyzes the No Action                                                                          appropriate, for offerors to obtain
                                               Alternative. Other alternatives were                    Availability of the Bonneville
                                                                                                                                                             information on particular purchases or
                                               evaluated but not carried forward for                   Purchasing Instructions (BPI) and
                                                                                                                                                             financial assistance transactions.
daltland on DSKBBV9HB2PROD with NOTICES




                                               detailed consideration, including water                 Bonneville Financial Assistance
                                               supplied from five new (undeveloped)                    Instructions (BFAI)                                      Signed in Portland, Oregon, on September
                                               reservoirs; securing supplies from other                                                                      6, 2018
                                                                                                       AGENCY: Bonneville Power                              Nicholas M. Jenkins,
                                               existing sources, Oklahoma, additional                  Administration (BPA), Department of
                                               Dallas Water Utilities Supply, the Gulf                                                                       Manager, Purchasing/Property Governance.
                                                                                                       Energy (DOE).
                                               of Mexico, Cypress Creek Basin,                                                                               [FR Doc. 2018–21725 Filed 10–4–18; 8:45 am]
                                                                                                       ACTION: Notice of document availability.
                                               groundwater imports and precipitation                                                                         BILLING CODE 6450–01–P




                                          VerDate Sep<11>2014   17:11 Oct 04, 2018   Jkt 247001   PO 00000   Frm 00024   Fmt 4703   Sfmt 9990   E:\FR\FM\05OCN1.SGM   05OCN1



Document Created: 2018-10-05 01:53:00
Document Modified: 2018-10-05 01:53:00
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of availability.
DatesWritten comments on the Draft EIS will be accepted until November 21, 2018. Oral and/or written comments may also be presented at the Public Hearing.
ContactChandler J. Peter, EIS Project Manager, at 817-886-1731 or [email protected]