83_FR_5118 83 FR 5094 - Watterra Energy, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

83 FR 5094 - Watterra Energy, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 24 (February 5, 2018)

Page Range5094-5095
FR Document2018-02242

Federal Register, Volume 83 Issue 24 (Monday, February 5, 2018)
[Federal Register Volume 83, Number 24 (Monday, February 5, 2018)]
[Notices]
[Pages 5094-5095]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-02242]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14865-000]


Watterra Energy, LLC; Notice of Preliminary Permit Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Competing Applications

    On November 29, 2017, Watterra Energy, LLC, filed an application 
for a preliminary permit, pursuant to section 4(f) of the Federal Power 
Act (FPA), proposing to study the feasibility of the Sutton Dam 
Hydroelectric Project to be located at the U.S. Army Corps of 
Engineers' (Corps) Sutton Dam, on the Elk River, in Sutton, Braxton 
County, West Virginia. The sole purpose of a preliminary permit, if 
issued, is to grant the permit holder priority to file a license 
application during the permit term. A preliminary permit does not 
authorize the permit holder to perform any land-disturbing activities 
or otherwise enter upon lands or waters owned by others without the 
owners' express permission.
    The proposed project would consist of the following: (1) A new 70-
foot-long, 55-foot-wide powerhouse containing three turbine-generator 
units with a total rated capacity of 14 megawatts; (2) a new multiple-
port intake structure to be located at the upstream face of the Sutton 
dam; (3) a new 300-foot-long, 15-foot-diameter steel penstock; (4) a 
new 50-foot-long, 50-foot-wide switchyard; (5) a new 13.8-kilovolt, 
500-foot-long transmission line; and (6) appurtenant facilities. The 
proposed project would have an annual generation of 47,200 megawatt-
hours.
    Applicant Contact: Craig Dalton, Watterra Energy, LLC, 220 West 
Main

[[Page 5095]]

Street, Hamilton, MT 59840; phone: 406-384-0080.
    FERC Contact: Monir Chowdhury; phone: (202) 502-6736.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-14865-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of the 
Commission's website at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14865) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: January 30, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-02242 Filed 2-2-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                5094                         Federal Register / Vol. 83, No. 24 / Monday, February 5, 2018 / Notices

                                                   Filed Date: 1/30/18.                                   Dated: January 30, 2018.                            review in the Commission’s Public
                                                   Accession Number: 20180130–5147.                     Nathaniel J. Davis, Sr.,                              Reference Room in Washington, DC.
                                                   Comments Due: 5 p.m. ET 2/20/18.                     Deputy Secretary.                                     There is an ‘‘eSubscription’’ link on the
                                                   Docket Numbers: ER18–745–000.                        [FR Doc. 2018–02226 Filed 2–2–18; 8:45 am]            website that enables subscribers to
                                                   Applicants: ISO New England Inc.,                    BILLING CODE 6717–01–P                                receive email notification when a
                                                Eversource Energy Service Company.                                                                            document is added to a subscribed
                                                   Description: § 205(d) Rate Filing: ISO–                                                                    docket(s). For assistance with any FERC
                                                NE and Eversource—Original Service                      DEPARTMENT OF ENERGY                                  Online service, please email
                                                Agreement .0Under Schedule 21–ES to                                                                           FERCOnlineSupport@ferc.gov, or call
                                                                                                        Federal Energy Regulatory                             (866) 208–3676 (toll free). For TTY, call
                                                be effective 1/1/2018.                                  Commission
                                                   Filed Date: 1/30/18.                                                                                       (202) 502–8659.
                                                                                                        [Docket No. EL18–58–000]                                Comment Date: 5:00 p.m. Eastern
                                                   Accession Number: 20180130–5165.
                                                                                                                                                              Time on February 15, 2018.
                                                   Comments Due: 5 p.m. ET 2/20/18.
                                                                                                        Oklahoma Municipal Power Authority                      Dated: January 29, 2018.
                                                   Docket Numbers: ER18–746–000.                        v. Oklahoma Gas and Electric                          Nathaniel J. Davis, Sr.,
                                                   Applicants: Northern Indiana Public                  Company; Notice of Complaint
                                                Service Company.                                                                                              Deputy Secretary.
                                                   Description: § 205(d) Rate Filing:                      Take notice that on January 26, 2018,              [FR Doc. 2018–02228 Filed 2–2–18; 8:45 am]
                                                WVPA IA, Recloser Replacements CIAC                     pursuant to section 206 and 306 of the                BILLING CODE 6717–01–P
                                                (2018) to be effective 1/31/2018.                       Federal Power Act, 16 U.S.C. 824e,
                                                   Filed Date: 1/30/18.                                 825e, and Rule 206 of the Federal
                                                   Accession Number: 20180130–5178.                     Energy Regulatory Commission’s                        DEPARTMENT OF ENERGY
                                                   Comments Due: 5 p.m. ET 2/20/18.                     (Commission) Rules of Practice and
                                                                                                        Procedure, 18 CFR 385.206, .212, the                  Federal Energy Regulatory
                                                   Docket Numbers: ER18–747–000.                        Oklahoma Municipal Power Authority                    Commission
                                                   Applicants: Imperial Valley Solar 3,                 (Complainant) filed a formal complaint
                                                LLC.                                                                                                          [Project No. 14865–000]
                                                                                                        against Oklahoma Gas and Electric
                                                   Description: Baseline eTariff Filing:                Company (Respondent) alleging that the                Watterra Energy, LLC; Notice of
                                                Imperial Valley Solar 3, LLC Co                         formula rate used by Respondent to                    Preliminary Permit Application
                                                Tenancy Agreement to be effective 1/31/                 determine the charges for transmission                Accepted for Filing and Soliciting
                                                2018.                                                   service in Zone 7 of the Southwest                    Comments, Motions To Intervene, and
                                                   Filed Date: 1/30/18.                                 Power Pool is unjust and unreasonable,                Competing Applications
                                                   Accession Number: 20180130–5181.                     all as more fully explained in the
                                                   Comments Due: 5 p.m. ET 2/20/18.                     complaint.                                               On November 29, 2017, Watterra
                                                   Take notice that the Commission                         Complainant certifies that copies of               Energy, LLC, filed an application for a
                                                received the following electric securities              the complaint were served on the                      preliminary permit, pursuant to section
                                                filings:                                                contacts for Respondent as listed on the              4(f) of the Federal Power Act (FPA),
                                                                                                        Commission’s list of Corporate Officials.             proposing to study the feasibility of the
                                                   Docket Numbers: ES18–22–000.                                                                               Sutton Dam Hydroelectric Project to be
                                                   Applicants: AEP Texas Inc.                              Any person desiring to intervene or to
                                                                                                        protest this filing must file in                      located at the U.S. Army Corps of
                                                   Description: Application Under                                                                             Engineers’ (Corps) Sutton Dam, on the
                                                                                                        accordance with Rules 211 and 214 of
                                                Section 204 of the Federal Power Act for                                                                      Elk River, in Sutton, Braxton County,
                                                                                                        the Commission’s Rules of Practice and
                                                Authorization to Issue Securities of AEP                                                                      West Virginia. The sole purpose of a
                                                                                                        Procedure (18 CFR 385.211 and
                                                Texas Inc.                                                                                                    preliminary permit, if issued, is to grant
                                                                                                        385.214). Protests will be considered by
                                                   Filed Date: 1/30/18.                                                                                       the permit holder priority to file a
                                                                                                        the Commission in determining the
                                                   Accession Number: 20180130–5253.                                                                           license application during the permit
                                                                                                        appropriate action to be taken, but will
                                                   Comments Due: 5 p.m. ET 2/20/18.                                                                           term. A preliminary permit does not
                                                                                                        not serve to make protestants parties to
                                                   The filings are accessible in the                    the proceeding. Any person wishing to                 authorize the permit holder to perform
                                                Commission’s eLibrary system by                         become a party must file a notice of                  any land-disturbing activities or
                                                clicking on the links or querying the                   intervention or motion to intervene, as               otherwise enter upon lands or waters
                                                docket number.                                          appropriate. The Respondent’s answer                  owned by others without the owners’
                                                   Any person desiring to intervene or                  and all interventions, or protests must               express permission.
                                                protest in any of the above proceedings                 be filed on or before the comment date.                  The proposed project would consist of
                                                must file in accordance with Rules 211                  The Respondent’s answer, motions to                   the following: (1) A new 70-foot-long,
                                                and 214 of the Commission’s                             intervene, and protests must be served                55-foot-wide powerhouse containing
                                                Regulations (18 CFR 385.211 and                         on the Complainant.                                   three turbine-generator units with a total
                                                385.214) on or before 5:00 p.m. Eastern                    The Commission encourages                          rated capacity of 14 megawatts; (2) a
                                                time on the specified comment date.                     electronic submission of protests and                 new multiple-port intake structure to be
                                                Protests may be considered, but                         interventions in lieu of paper using the              located at the upstream face of the
                                                intervention is necessary to become a                   ‘‘eFiling’’ link at http://www.ferc.gov.              Sutton dam; (3) a new 300-foot-long, 15-
                                                party to the proceeding.                                Persons unable to file electronically                 foot-diameter steel penstock; (4) a new
                                                   eFiling is encouraged. More detailed                                                                       50-foot-long, 50-foot-wide switchyard;
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                        should submit an original and 5 copies
                                                information relating to filing                          of the protest or intervention to the                 (5) a new 13.8-kilovolt, 500-foot-long
                                                requirements, interventions, protests,                  Federal Energy Regulatory Commission,                 transmission line; and (6) appurtenant
                                                service, and qualifying facilities filings              888 First Street NE, Washington, DC                   facilities. The proposed project would
                                                can be found at: http://www.ferc.gov/                   20426.                                                have an annual generation of 47,200
                                                docs-filing/efiling/filing-req.pdf. For                    This filing is accessible on-line at               megawatt-hours.
                                                other information, call (866) 208–3676                  http://www.ferc.gov, using the                           Applicant Contact: Craig Dalton,
                                                (toll free). For TTY, call (202) 502–8659.              ‘‘eLibrary’’ link and is available for                Watterra Energy, LLC, 220 West Main


                                           VerDate Sep<11>2014   18:08 Feb 02, 2018   Jkt 244001   PO 00000   Frm 00037   Fmt 4703   Sfmt 4703   E:\FR\FM\05FEN1.SGM   05FEN1


                                                                             Federal Register / Vol. 83, No. 24 / Monday, February 5, 2018 / Notices                                             5095

                                                Street, Hamilton, MT 59840; phone:                         b. Project No.: 10532–006.                         Enter the docket number (P–10532–006)
                                                406–384–0080.                                              c. Date Filed: January 18, 2018.                   excluding the last three digits in the
                                                   FERC Contact: Monir Chowdhury;                          d. Licensee: Water Facilities Authority            docket number field to access the
                                                phone: (202) 502–6736.                                  a Joint Power Agency (WFA–JPA).                       document. You may also register online
                                                   Deadline for filing comments, motions                   e. Name of Project: WFA–JPA                        at http://www.ferc.gov/docs-filing/
                                                to intervene, competing applications                    Regional Water Supply Energy Recovery                 esubscription.asp to be notified via
                                                (without notices of intent), or notices of              Facilities Project.                                   email of new filings and issuances
                                                intent to file competing applications: 60                  f. Location: The project is located on             related to this or other pending projects.
                                                days from the issuance of this notice.                  a water transmission pipeline near the                For assistance, call 1–866–208–3676 or
                                                Competing applications and notices of                   City of Ontario, San Bernardino,                      email FERCOnlineSupport@ferc.gov, for
                                                intent must meet the requirements of 18                 California.                                           TTY, call (202) 502–8659. A copy is also
                                                CFR 4.36.                                                  g. Filed Pursuant to: Federal Power                available for inspection and
                                                   The Commission strongly encourages                   Act, 16 U.S.C. 791a–825r.                             reproduction in the Commission’s
                                                                                                           h. Licensee Contact: Ms. Chelsea                   Public Reference Room located at 888
                                                electronic filing. Please file comments,
                                                                                                        Murphy, Natural Resources Project                     First Street NE, Room 2A, Washington,
                                                motions to intervene, notices of intent,
                                                                                                        Manager, SWCA Environmental                           DC 20426, or by calling (202) 502–8371.
                                                and competing applications using the
                                                                                                        Consultants, 150 South Arroyo Parkway,                   m. Individuals desiring to be included
                                                Commission’s eFiling system at http://
                                                                                                        Second Floor, Pasadena, California,                   on the Commission’s mailing list should
                                                www.ferc.gov/docs-filing/efiling.asp.
                                                                                                        Telephone: (626) 240–0587 ext. 6609,                  so indicate by writing to the Secretary
                                                Commenters can submit brief comments
                                                                                                        cmurphy@swca.com.                                     of the Commission.
                                                up to 6,000 characters, without prior                      i. FERC Contact: Ms. Rebecca Martin,
                                                registration, using the eComment system                                                                          n. Comments, Protests, or Motions to
                                                                                                        (202) 502–6012, Rebecca.Martin@                       Intervene: Anyone may submit
                                                at http://www.ferc.gov/docs-filing/                     ferc.gov.
                                                ecomment.asp. You must include your                                                                           comments, a protest, or a motion to
                                                                                                           j. Deadline for filing comments,                   intervene in accordance with the
                                                name and contact information at the end                 interventions, and protests is February
                                                of your comments. For assistance,                                                                             requirements of Rules of Practice and
                                                                                                        28, 2018. The Commission strongly                     Procedure, 18 CFR 385.210, .211, .212
                                                please contact FERC Online Support at                   encourages electronic filing. Please file
                                                FERCOnlineSupport@ferc.gov, (866)                                                                             and .214. In determining the appropriate
                                                                                                        motions to intervene, protests and                    action to take, the Commission will
                                                208–3676 (toll free), or (202) 502–8659                 comments using the Commission’s
                                                (TTY). In lieu of electronic filing, please                                                                   consider all protests or other comments
                                                                                                        eFiling system at http://www.ferc.gov/                filed, but only those who file a motion
                                                send a paper copy to: Secretary, Federal                docs-filing/efiling.asp. Commenters can
                                                Energy Regulatory Commission, 888                                                                             to intervene in accordance with the
                                                                                                        submit brief comments up to 6,000                     Commission’s Rules may become a
                                                First Street NE, Washington, DC 20426.                  characters, without prior registration,               party to the proceeding. Any comments,
                                                The first page of any filing should                     using the eComment system at http://                  protests, or motions to intervene must
                                                include docket number P–14865–000.                      www.ferc.gov/docs-filing/                             be received on or before the specified
                                                   More information about this project,                 ecomment.asp. You must include your                   comment date for the particular
                                                including a copy of the application, can                name and contact information at the end               application.
                                                be viewed or printed on the ‘‘eLibrary’’                of your comments. For assistance,                        o. Filing and Service of Responsive
                                                link of the Commission’s website at                     please contact FERC Online Support at                 Documents: Any filing must (1) bear in
                                                http://www.ferc.gov/docs-filing/                        FERCOnlineSupport@ferc.gov, (866)                     all capital letters the title
                                                elibrary.asp. Enter the docket number                   208–3676 (toll free), or (202) 502–8659               ‘‘COMMENTS’’, ‘‘PROTEST’’, or
                                                (P–14865) in the docket number field to                 (TTY). In lieu of electronic filing, please           ‘‘MOTION TO INTERVENE’’ as
                                                access the document. For assistance,                    send a paper copy to: Secretary, Federal              applicable; (2) set forth in the heading
                                                contact FERC Online Support.                            Energy Regulatory Commission, 888                     the name of the applicant and the
                                                  Dated: January 30, 2018.                              First Street NE, Washington, DC 20426.                project number of the application to
                                                Kimberly D. Bose,                                       The first page of any filing should                   which the filing responds; (3) furnish
                                                Secretary.                                              include docket number P–10532–006.                    the name, address, and telephone
                                                [FR Doc. 2018–02242 Filed 2–2–18; 8:45 am]                 k. Description of Request: The project             number of the person protesting or
                                                BILLING CODE 6717–01–P
                                                                                                        consists of the existing water supply                 intervening; and (4) otherwise comply
                                                                                                        transmission system and one                           with the requirements of 18 CFR
                                                                                                        powerhouse containing one turbine                     385.2001 through 385.2005. All
                                                DEPARTMENT OF ENERGY                                    generating unit with a total rated                    comments, motions to intervene, or
                                                                                                        capacity of 225 kilowatts (kW). The                   protests must set forth their evidentiary
                                                Federal Energy Regulatory                               project has not operated since October                basis and otherwise comply with the
                                                Commission                                              7, 2005. The demand for water at the                  requirements of 18 CFR 4.34(b). All
                                                                                                        project has been around 0.5 million                   comments, motions to intervene, or
                                                [Project No. 10532–006]
                                                                                                        gallons per day (MGD). The minimum                    protests should relate to the surrender
                                                Water Facilities Authority a Joint                      required flow required to operate the                 application that is the subject of this
                                                Power Agency; Notice of Application                     hydrogenerator is 6.1 MGD. As a result,               notice. Agencies may obtain copies of
                                                for Surrender of Exemption, Soliciting                  the exemptee, has determined it would                 the application directly from the
                                                Comments, Motions To Intervene, and                     like to surrender the exemption.                      applicant. A copy of any protest or
                                                                                                                                                              motion to intervene must be served
sradovich on DSK3GMQ082PROD with NOTICES




                                                Protests                                                Electricity to the hydrogenerator has
                                                                                                        been permanently disconnected. No                     upon each representative of the
                                                  Take notice that the following                        ground disturbance is associated with                 applicant specified in the particular
                                                hydroelectric application has been filed                the proposed surrender and project                    application. If an intervener files
                                                with the Commission and is available                    features will remain in place.                        comments or documents with the
                                                for public inspection:                                     l. This filing may be viewed on the                Commission relating to the merits of an
                                                  a. Type of Proceeding: Application for                Commission’s website at http://                       issue that may affect the responsibilities
                                                surrender of conduit exemption.                         www.ferc.gov/docs-filing/elibrary.asp.                of a particular resource agency, they


                                           VerDate Sep<11>2014   18:08 Feb 02, 2018   Jkt 244001   PO 00000   Frm 00038   Fmt 4703   Sfmt 4703   E:\FR\FM\05FEN1.SGM   05FEN1



Document Created: 2018-02-03 01:25:09
Document Modified: 2018-02-03 01:25:09
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 5094 