83_FR_53521 83 FR 53317 - Exelon Generation Company, LLC; Oyster Creek Nuclear Generating Station Request for Exemptions Regarding Emergency Planning Requirements

83 FR 53317 - Exelon Generation Company, LLC; Oyster Creek Nuclear Generating Station Request for Exemptions Regarding Emergency Planning Requirements

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 83, Issue 204 (October 22, 2018)

Page Range53317-53321
FR Document2018-22986

The U.S. Nuclear Regulatory Commission (NRC) has issued exemptions in response to a request from Exelon Generation Company, LLC (Exelon or the licensee) regarding certain emergency planning (EP) requirements. The exemptions eliminate the requirements to maintain an offsite radiological emergency preparedness plan and reduce the scope of onsite EP activities at the Oyster Creek Nuclear Generating Station (Oyster Creek), based on the reduced risks of accidents that could result in an offsite radiological release at a decommissioning nuclear power reactor.

Federal Register, Volume 83 Issue 204 (Monday, October 22, 2018)
[Federal Register Volume 83, Number 204 (Monday, October 22, 2018)]
[Notices]
[Pages 53317-53321]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-22986]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-219; NRC-2018-0167]


Exelon Generation Company, LLC; Oyster Creek Nuclear Generating 
Station Request for Exemptions Regarding Emergency Planning 
Requirements

AGENCY: Nuclear Regulatory Commission.

ACTION: Exemption; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued 
exemptions in response to a request from Exelon Generation Company, LLC 
(Exelon or the licensee) regarding certain emergency planning (EP) 
requirements. The exemptions eliminate the requirements to maintain an 
offsite radiological emergency preparedness plan and reduce the scope 
of onsite EP activities at the Oyster Creek Nuclear Generating Station 
(Oyster Creek), based on the reduced risks of accidents that could 
result in an offsite radiological release at a decommissioning nuclear 
power reactor.

DATES: The exemption was issued on October 16, 2018.

ADDRESSES: Please refer to Docket ID NRC-2018-0167 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0167. Address 
questions about NRC dockets to Jennifer Borges; telephone: 301-287-
9127; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to [email protected]. The ADAMS accession number for each 
document referenced (if it is available in ADAMS) is provided the first 
time that it is mentioned in this document. In addition, for the 
convenience of the reader, the ADAMS accession numbers are provided in 
a table in the ``Availability of Documents'' section of this document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: John G. Lamb, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-3100; email: [email protected].

SUPPLEMENTARY INFORMATION: The text of the exemption is attached.

I. Availability of Documents

    The documents identified in the following table are available for 
public inspection through ADAMS, a public web page, or by using one of 
the methods discussed in the ADDRESSES section of this document.

----------------------------------------------------------------------------------------------------------------
                                                                              ADAMS accession no. or public web
               Title                                  Date                                  page
----------------------------------------------------------------------------------------------------------------
Exelon Generation Company, LLC,      February 14, 2018....................  ML18045A084.
 letter to U.S. Nuclear Regulatory
 Commission, ``Certification of
 Permanent Cessation of Power
 Operations for Oyster Creek
 Nuclear Generating Station''.
Exelon Generation Company, LLC,      August 22, 2017......................  ML17234A082.
 letter to U.S. Nuclear Regulatory
 Commission, ``Request for
 Exemptions from Portions of 10 CFR
 50.47 and 10 CFR Part 50, Appendix
 E''.
Exelon Generation Company, LLC,      December 6, 2017.....................  ML17340A708.
 letter to U.S. Nuclear Regulatory
 Commission, ``Response to Request
 for Additional Information (RAI)
 Regarding Request for Exemption
 from Portions of 10 CFR 50.47 and
 10 CFR Part 50, Appendix E''.
Exelon Generation Company, LLC,      January 23, 2018.....................  ML18023A138.
 letter to U.S. Nuclear Regulatory
 Commission, ``Supplement to
 Request for Exemption from
 Portions of 10 CFR 50.47 and 10
 CFR Part 50, Appendix E''.
Exelon Generation Company, LLC,      March 8, 2018........................  ML18067A087.
 letter to U.S. Nuclear Regulatory
 Commission, ``Supplement to
 Request for Exemption from
 Portions of 10 CFR 50.47 and 10
 CFR Part 50, Appendix E''.
Exelon Generation Company, LLC,      March 19, 2018.......................  ML18078A146.
 letter to U.S. Nuclear Regulatory
 Commission, ``Response to Request
 for Additional Information (RAI)
 Related to Exemption Request from
 Portions of 10 CFR 50.47 and 10
 CFR Part 50, Appendix E''.
U.S. Nuclear Regulatory Commission,  August 1997..........................  ML082260098.
 NUREG/CR-6451, ``A Safety and
 Regulatory Assessment of Generic
 BWR and PWR Permanently Shutdown
 Nuclear Power Plants''.
U.S. Nuclear Regulatory Commission,  February 2001........................  ML010430066.
 NUREG-1738, ``Technical Study of
 Spent Fuel Pool Accident Risk at
 Decommissioning Nuclear Power
 Plants''.
Federal Emergency Management Agency  November 2010........................  http://www.fema.gov/pdf/about/
 Comprehensive Preparedness Guide                                            divisions/npd/CPG_101_V2.pdf.
 101, ``Developing and Maintaining
 Emergency Operations Plans,''
 Version 2.0.
U.S. Nuclear Regulatory Commission,  September 2014.......................  ML14255A365.
 NUREG-2161, ``Consequence Study of
 a Beyond-Design-Basis Earthquake
 Affecting the Spent Fuel Pool for
 a U.S. Mark I Boiling Water
 Reactor''.
U.S. Nuclear Regulatory Commission,  November 12, 2013....................  ML13329A918.
 COMSECY-13-0030, ``Staff
 Evaluation and Recommendation for
 Japan Lessons-Learned Tier 3 Issue
 on Expedited Transfer of Spent
 Fuel''.

[[Page 53318]]

 
U.S. Nuclear Regulatory Commission,  May 31, 2018.........................  ML18030B359.
 SECY-18-0062, ``Request by the
 Exelon Generation Company, LLC for
 Exemptions from Certain Emergency
 Planning Requirements for the
 Oyster Creek Nuclear Generating
 Station''.
U.S. Nuclear Regulatory Commission,  July 17, 2018........................  ML18198A449.
 ``Staff Requirements--SECY-18-
 0062, Request by the Exelon
 Generation Company, LLC for
 Exemptions from Certain Emergency
 Planning Requirements for the
 Oyster Creek Nuclear Generating
 Station''.
U.S. Nuclear Regulatory Commission,  October 16, 2018.....................  ML18220A980.
 letter to Exelon Generation
 Company, LLC ``Oyster Creek
 Nuclear Generating Station--
 Exemptions from Certain Emergency
 Planning Requirements and Related
 Safety Evaluation''.
----------------------------------------------------------------------------------------------------------------


    Dated at Rockville, Maryland, on October 17, 2018.

    For the Nuclear Regulatory Commission.
John G. Lamb,
Senior Project Manager, Special Projects and Process Branch, Division 
of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.

Attachment--Exemption

NUCLEAR REGULATORY COMMISSION

Docket No. 50-219

Exelon Generation Company, LLC

Oyster Creek Nuclear Generating Station

Exemption

I. Background.

    Exelon Generation Company, LLC (Exelon or the licensee) is the 
holder of Renewed Facility Operating License No. DPR[dash]16 for 
Oyster Creek Nuclear Generating Station (Oyster Creek). The license 
provides, among other things, that the facility is subject to all 
rules, regulations, and orders of the U.S. Nuclear Regulatory 
Commission (NRC) now or hereafter in effect. The facility consists 
of a boiling[dash]water reactor (BWR) located in Ocean County, New 
Jersey.
    By letter dated February 14, 2018 (Agencywide Documents Access 
and Management System (ADAMS) Accession No. ML18045A084), Exelon 
submitted a certification to the NRC that it would permanently cease 
power operations at Oyster Creek no later than October 31, 2018. On 
September 17, 2018, Exelon permanently ceased power operations at 
Oyster Creek. By letter dated September 25, 2018 (ADAMS Accession 
No. ML18268A258), Exelon certified the permanent removal of fuel 
from the Oyster Creek reactor vessel.
    In accordance with Sec.  50.82(a)(2) of Title 10 of the Code of 
Federal Regulations (10 CFR), the license for a power reactor 
facility no longer authorizes operation of the reactor or 
emplacement or retention of fuel into the reactor vessel upon the 
docketing of the certifications for permanent cessation of 
operations and permanent removal of fuel from the reactor vessel. 
The facility is still authorized to possess and store irradiated 
(i.e., spent) nuclear fuel. Spent fuel is currently stored onsite in 
the Oyster Creek spent fuel pool (SFP) and a dry cask independent 
spent fuel storage installation (ISFSI) at the Oyster Creek 
facility.
    During normal power reactor operations, the forced flow of water 
through the reactor coolant system removes heat generated by the 
reactor. The reactor coolant system, operating at high temperatures 
and pressures, transfers this heat through the steam generator tubes 
converting non[dash]radioactive feedwater to steam, which then flows 
to the main turbine generator to produce electricity. Many of the 
accident scenarios postulated in the updated safety analysis reports 
(USARs) for operating power reactors involve failures or 
malfunctions of systems, which could affect the fuel in the reactor 
core and, in the most severe postulated accidents, would involve the 
release of large quantities of fission products. With the permanent 
cessation of operations at Oyster Creek and the permanent removal of 
the fuel from the reactor vessel, such accidents are no longer 
possible. The reactor, reactor coolant system, and supporting 
systems are no longer in operation and have no function related to 
the storage of the spent fuel. Therefore, emergency planning (EP) 
provisions for postulated accidents involving failure or malfunction 
of the reactor, reactor coolant system, or supporting systems are no 
longer applicable.
    The EP requirements of 10 CFR 50.47, ``Emergency plans,'' and 
Appendix E to 10 CFR part 50, ``Emergency Planning and Preparedness 
for Production and Utilization Facilities,'' continue to apply to 
nuclear power reactors that have permanently ceased operation and 
have permanently removed all fuel from the reactor vessel. There are 
no explicit regulatory provisions distinguishing EP requirements for 
a power reactor that is permanently shut down and defueled from 
those for a reactor that is authorized to operate. To reduce or 
eliminate EP requirements that are no longer necessary due to the 
decommissioning status of the facility, Exelon must obtain 
exemptions from those EP regulations. Only then can Exelon modify 
the Oyster Creek emergency plan to reflect the reduced risk 
associated with the permanently shutdown and defueled condition of 
Oyster Creek.

II. Request/Action.

    By letter dated August 22, 2017 (ADAMS Accession No. 
ML17234A082), Exelon requested exemptions from certain EP 
requirements of 10 CFR part 50 for Oyster Creek. Specifically, 
Exelon requested exemptions from certain planning standards in 10 
CFR 50.47(b) regarding onsite and offsite radiological emergency 
preparedness plans for nuclear power reactors, from certain 
requirements in 10 CFR 50.47(c)(2) for establishment of plume 
exposure and ingestion pathway emergency planning zones for nuclear 
power reactors; and from certain requirements in 10 CFR part 50, 
Appendix E, Section IV, which establishes the elements that make up 
the content of emergency plans. In letters dated December 6, 2017, 
and January 23, March 8, and March 19, 2018 (ADAMS Accession Nos. 
ML17340A708, ML18023A138, ML18067A087, and ML18078A146, 
respectively), Exelon provided supplemental information and 
responses to the NRC staff's requests for additional information 
concerning the proposed exemptions.
    The information provided by Exelon included justifications for 
each exemption requested. The exemptions requested by Exelon would 
eliminate the requirements to maintain formal offsite radiological 
emergency preparedness plans reviewed by the Federal Emergency 
Management Agency (FEMA) under the requirements of 44 CFR part 350 
and would reduce the scope of onsite EP activities at Oyster Creek. 
The licensee stated that the application of all of the standards and 
requirements in 10 CFR 50.47(b), 10 CFR 50.47(c), and 10 CFR part 
50, Appendix E is not needed for adequate emergency response 
capability, based on the substantially lower onsite and offsite 
radiological consequences of accidents still possible at the 
permanently shutdown and defueled facility, as compared to an 
operating facility. If offsite protective actions were needed for a 
highly unlikely beyond-design-basis accident that could challenge 
the safe storage of spent fuel at Oyster Creek, provisions exist for 
offsite agencies to take protective actions using a comprehensive 
emergency management plan (CEMP) under the National Preparedness 
System to protect the health and safety of the public. A CEMP in 
this context, also referred to as an emergency operations plan, is 
addressed in FEMA's Comprehensive Preparedness Guide 101, 
``Developing and Maintaining Emergency Operations Plans,'' which is 
publicly available at http://www.fema.gov/pdf/about/divisions/npd/CPG_101_V2.pdf. Comprehensive Preparedness Guide 101 is the 
foundation for State, territorial, Tribal, and local EP in the 
United States. It promotes a common understanding of the 
fundamentals of risk[dash]informed planning and decision[dash]making 
and helps planners at all levels of government in their efforts to 
develop and maintain viable, all[dash]hazards, all[dash]threats 
emergency plans. An emergency operations plan is flexible enough for 
use in all emergencies. It describes how people and property will be 
protected; details who is responsible for carrying out specific 
actions; identifies the personnel, equipment, facilities, supplies 
and other resources

[[Page 53319]]

available; and outlines how all actions will be coordinated. A CEMP 
is often referred to as a synonym for ``all[dash]hazards planning.''

III. Discussion.

    In accordance with 10 CFR 50.12, ``Specific exemptions,'' the 
Commission may, upon application by any interested person or upon 
its own initiative, grant exemptions from the requirements of 10 CFR 
part 50 when: (1) the exemptions are authorized by law, will not 
present an undue risk to public health and safety, and are 
consistent with the common defense and security; and (2) any of the 
special circumstances listed in 10 CFR 50.12(a)(2) are present. 
These special circumstances include, among other things, that the 
application of the regulation in the particular circumstances would 
not serve the underlying purpose of the rule or is not necessary to 
achieve the underlying purpose of the rule.
    As noted previously, the EP regulations contained in 10 CFR 
50.47(b) and Appendix E to 10 CFR part 50 apply to both operating 
and shutdown power reactors. The NRC has consistently acknowledged 
that the risk of an offsite radiological release at a power reactor 
that has permanently ceased operations and permanently removed fuel 
from the reactor vessel is significantly lower, and the types of 
possible accidents are significantly fewer, than at an operating 
power reactor. However, the EP regulations do not recognize that 
once a power reactor permanently ceases operation, the risk of a 
large radiological release from credible emergency accident 
scenarios is significantly reduced. The reduced risk for any 
significant offsite radiological release is based on two factors. 
One factor is the elimination of accidents applicable only to an 
operating power reactor, resulting in fewer credible accident 
scenarios. The second factor is the reduced short[dash]lived 
radionuclide inventory and decay heat production due to radioactive 
decay. Due to the permanently defueled status of the reactor, no new 
spent fuel will be added to the SFP and the radionuclides in the 
current spent fuel will continue to decay as the spent fuel ages. 
The irradiated fuel will produce less heat due to radioactive decay, 
increasing the available time to mitigate a loss of water inventory 
from the SFP. The NRC's NUREG/CR-6451, ``A Safety and Regulatory 
Assessment of Generic BWR [Boiling Water Reactor] and PWR 
[Pressurized Water Reactor] Permanently Shutdown Nuclear Power 
Plants,'' dated August 1997 (ADAMS Accession No. ML082260098), and 
the NRC's NUREG[dash]1738, ``Technical Study of Spent Fuel Pool 
Accident Risk at Decommissioning Nuclear Power Plants,'' dated 
February 2001 (ADAMS Accession No. ML010430066), confirmed that for 
permanently shutdown and defueled power reactors that are bounded by 
the assumptions and conditions in the report, the risk of offsite 
radiological release is significantly less than for an operating 
power reactor.
    In the past, EP exemptions similar to those requested for Oyster 
Creek, have been granted to permanently shutdown and defueled power 
reactor licensees. However, the exemptions did not relieve the 
licensees of all EP requirements. Rather, the exemptions allowed the 
licensees to modify their emergency plans commensurate with the 
credible site-specific risks that were consistent with a permanently 
shutdown and defueled status. Specifically, the NRC's approval of 
these prior exemptions was based on the licensee's demonstration 
that: (1) the radiological consequences of design-basis accidents 
would not exceed the limits of the U.S. Environmental Protection 
Agency's (EPA) early phase Protective Action Guides (PAGs) of one 
roentgen equivalent man (rem) at the exclusion area boundary; and 
(2) in the highly unlikely event of a beyond-design-basis accident 
resulting in a loss of all modes of heat transfer from the fuel 
stored in the SFP, there is sufficient time to initiate appropriate 
mitigating actions, and if needed, for offsite authorities to 
implement offsite protective actions using a CEMP approach to 
protect the health and safety of the public.
    With respect to design[dash]basis accidents at Oyster Creek, the 
licensee provided an analysis demonstrating that 12 months (365 
days) following permanent cessation of power operations, the 
radiological consequences of the only remaining design[dash]basis 
accident with potential for offsite radiological release (the fuel 
handling accident in the Auxiliary Building, where the SFP is 
located) will not exceed the limits of the EPA PAGs at the exclusion 
area boundary.
    With respect to beyond-design-basis accidents at Oyster Creek, 
the licensee analyzed a drain down of the SFP water that would 
effectively impede any decay heat removal. The analysis demonstrates 
that at 12 months (365 days) after permanent cessation of power 
operations, there would be 10 hours after the assemblies have been 
uncovered until the limiting fuel assembly (for decay heat and 
adiabatic heatup analysis) reaches 900 degrees Celsius ([deg]C), the 
temperature used to assess the potential onset of fission product 
release. The analysis conservatively assumed that the heat up time 
starts when the SFP has been completely drained, although it is 
likely that site personnel will start to respond to an incident when 
drain down starts. The analysis also does not consider the period of 
time from the initiating event causing loss of SFP water inventory 
until cooling is lost.
    The NRC reviewed the licensee's justification for the requested 
exemptions against the criteria in 10 CFR 50.12(a) and determined, 
as described below, that the criteria in 10 CFR 50.12(a) will be 
met, and that the exemptions should be granted 365 days after Oyster 
Creek has permanently defueled. An assessment of the Exelon EP 
exemptions is described in SECY-18-0062, ``Request by the Exelon 
Generation Company, LLC for Exemptions from Certain Emergency 
Planning Requirements for the Oyster Creek Nuclear Generating 
Station,'' dated May 31, 2018 (ADAMS Accession No. ML18030B340). The 
Commission approved the NRC staff's recommendation to grant the 
exemptions in the staff requirements memorandum to SECY-18-0062, 
dated July 17, 2018 (ADAMS Accession No. ML18198A449). Descriptions 
of the specific exemptions requested by Exelon and the NRC staff's 
basis for granting each exemption are provided in SECY-18-0062. The 
NRC staff's detailed review and technical basis for the approval of 
the specific EP exemptions requested by Exelon, are provided in the 
NRC staff's safety evaluation associated with this exemption (ADAMS 
Accession No. ML18220A980).

A. The Exemption is Authorized by Law.

    The licensee has proposed exemptions from certain EP 
requirements in 10 CFR 50.47(b), 10 CFR 50.47(c)(2), and 10 CFR 50, 
Appendix E, Section IV, that would allow Exelon to revise the Oyster 
Creek Emergency Plan to reflect the permanently shutdown and 
defueled condition of the facility. As stated above, in accordance 
with 10 CFR 50.12, the Commission may, upon application by any 
interested person or upon its own initiative, grant exemptions from 
the requirements of 10 CFR part 50. The NRC staff has determined 
that granting of the licensee's proposed exemptions will not result 
in a violation of the Atomic Energy Act of 1954, as amended, or the 
NRC's regulations. Therefore, the exemptions are authorized by law.

B. The Exemption Presents No Undue Risk to Public Health and Safety.

    As stated previously, Exelon provided an analysis that show that 
the radiological consequences of design-basis accidents will not 
exceed the limits of the EPA early phase PAGs at the exclusion area 
boundary. Therefore, formal offsite radiological emergency 
preparedness plans required under 10 CFR part 50 will no longer be 
needed for protection of the public beyond the exclusion area 
boundary, based on the radiological consequences of design-basis 
accidents still possible at Oyster Creek 365 days after the plant 
has permanently ceased power operations.
    Although highly unlikely, there is one postulated beyond-design-
basis accident that might result in significant offsite radiological 
releases. However, NUREG-1738 confirms that the risk of beyond-
design-basis accidents is greatly reduced at permanently shutdown 
and defueled reactors. The NRC staff's analyses in NUREG-1738 
conclude that the event sequences important to risk at permanently 
shutdown and defueled power reactors are limited to large 
earthquakes and cask drop events. For EP assessments, this is an 
important difference relative to operating power reactors, where 
typically a large number of different sequences make significant 
contributions to risk. As described in NUREG-1738, relaxation of 
offsite EP requirements in 10 CFR part 50 beyond a few months after 
shutdown resulted in only a small change in risk. The report further 
concludes that the change in risk due to relaxation of offsite EP 
requirements is small because the overall risk is low, and because 
even under current EP requirements for operating power reactors, EP 
was judged to have marginal impact on evacuation effectiveness for 
the severe earthquakes that dominate SFP risk. All other sequences 
including cask drops (for which offsite radiological emergency 
preparedness plans are expected to be more effective) are too low in 
likelihood to have a significant impact on risk.

[[Page 53320]]

    Therefore, granting exemptions to eliminate the requirements of 
10 CFR part 50 to maintain offsite radiological emergency 
preparedness plans and to reduce the scope of onsite EP activities 
will not present an undue risk to the public health and safety.

C. The Exemption Is Consistent With the Common Defense and Security.

    The requested exemptions only involve EP requirements under 10 
CFR part 50 and will allow Exelon to revise the Oyster Creek 
Emergency Plan to reflect the permanently shutdown and defueled 
condition of the facility. Physical security measures at Oyster 
Creek are not affected by the requested EP exemptions. The 
discontinuation of formal offsite radiological emergency 
preparedness plans and the reduction in scope of the onsite EP 
activities at Oyster Creek will not adversely affect Exelon's 
ability to physically secure the site or protect special nuclear 
material. Therefore, the proposed exemptions are consistent with 
common defense and security.

D. Special Circumstances.

    Special circumstances, in accordance with 10 CFR 
50.12(a)(2)(ii), are present whenever application of the regulation 
in the particular circumstances is not necessary to achieve the 
underlying purpose of the rule. The underlying purpose of 10 CFR 
50.47(b), 10 CFR 50.47(c)(2), and 10 CFR part 50, Appendix E, 
Section IV, is to provide reasonable assurance that adequate 
protective measures can and will be taken in the event of a 
radiological emergency, to establish plume exposure and ingestion 
pathway emergency planning zones for nuclear power plants, and to 
ensure that licensees maintain effective offsite and onsite 
radiological emergency preparedness plans. The standards and 
requirements in these regulations were developed by considering the 
risks associated with operation of a power reactor at its licensed 
full-power level. These risks include the potential for a reactor 
accident with offsite radiological dose consequences.
    As discussed previously in Section III, because Oyster Creek 
will be permanently shut down and defueled, there will no longer be 
a risk of a significant offsite radiological release from a design-
basis accident exceeding EPA early phase PAG at the exclusion area 
boundary and the risk of a significant offsite radiological release 
from a beyond-design-basis accident is greatly reduced when compared 
to an operating power reactor. The NRC staff has confirmed the 
reduced risks at Oyster Creek by comparing the generic risk 
assumptions in the analyses in NUREG-1738 to site-specific 
conditions at Oyster Creek and determined that the risk values in 
NUREG-1738 bound the risks presented at Oyster Creek. As indicated 
by the results of the research conducted for NUREG-1738, and more 
recently for NUREG-2161, ``Consequence Study of a Beyond-Design-
Basis Earthquake Affecting the Spent Fuel Pool for a U.S. Mark I 
Boiling Water Reactor,'' dated September 2014 (ADAMS Accession No. 
ML14255A365), while other consequences can be extensive, accidents 
from SFPs with significant decay time have little potential to cause 
offsite early fatalities, even if the formal offsite radiological EP 
requirements were relaxed. The licensee's analysis of a beyond-
design-basis accident involving a complete loss of SFP water 
inventory, based on an adiabatic heatup analysis of the limiting 
fuel assembly for decay heat, shows that within 12 months (365 days) 
after permanent cessation of power operations, the time for the 
limiting fuel assembly to reach 900 [deg]C is at least 10 hours 
after the assemblies have been uncovered assuming a loss of all 
cooling means.
    The only analyzed beyond-design-basis accident scenario that 
progresses to a condition where a significant offsite release might 
occur, involves the highly unlikely event where the SFP drains in 
such a way that all modes of cooling or heat transfer are assumed to 
be unavailable, which is referred to as an adiabatic heatup of the 
spent fuel. The licensee's analysis of this beyond-design-basis 
accident shows that within 12 months (365 days) after permanent 
cessation of power operations, at least 10 hours would be available 
between the time that all cooling means are lost to the fuel (at 
which time adiabatic heatup is conservatively assumed to begin), 
until the fuel cladding reaches a temperature of 1652 degrees 
Fahrenheit (900 [deg]C), which is the temperature associated with 
rapid cladding oxidation and the potential for a significant 
radiological release. This analysis conservatively does not include 
the period of time from the initiating event causing a loss of SFP 
water inventory until all cooling means are lost.
    The NRC staff has verified Exelon's analyses and its 
calculations. The analyses provide reasonable assurance that in 
granting the requested exemptions to Exelon, there is no design-
basis accident that will result in an offsite radiological release 
exceeding the EPA early phase PAGs at the exclusion area boundary. 
In the highly unlikely event of a beyond-design-basis accident 
affecting the SFP that results in a complete loss of heat removal 
via all modes of heat transfer, there will be over 10 hours 
available before an offsite release might occur and, therefore, at 
least 10 hours to initiate appropriate mitigating actions to restore 
a means of heat removal to the spent fuel. If a radiological release 
were projected to occur under this highly unlikely scenario, a 
minimum of 10 hours is considered sufficient time for offsite 
authorities to implement protective actions using a CEMP approach to 
protect the health and safety of the public.
    Exemptions from the offsite EP requirements in 10 CFR Part 50 
have previously been approved by the NRC when the site-specific 
analyses show that at least 10 hours is available following a loss 
of SFP coolant inventory accident with no air cooling (or other 
methods of removing decay heat) until cladding of the hottest fuel 
assembly reaches the rapid oxidation temperature. The NRC staff 
concluded in its previously granted exemptions, as it does with 
Exelon's requested EP exemptions, that if a minimum of 10 hours is 
available to initiate mitigative actions consistent with plant 
conditions, or if needed, for offsite authorities to implement 
protective actions using a CEMP approach, then formal offsite 
radiological emergency preparedness plans, required under 10 CFR 
Part 50, are not necessary at permanently shutdown and defueled 
facilities.
    Additionally, Oyster Creek committed to maintaining SFP makeup 
strategies in its letters to the NRC dated March 8 and 19, 2018. The 
multiple strategies for providing makeup to the SFP include: using 
existing plant systems for inventory makeup; an internal strategy 
that relies on the fire protection system with redundant pumps (one 
diesel-driven and electric motor-driven); and onsite diesel fire 
truck that can take suction from the Barnegat Bay. These strategies 
will continue to be required as condition 2.C.(8), ``Mitigation 
Strategy License Condition,'' of renewed facility operating license 
DPR-16 for Oyster Creek. Considering the very low probability of 
beyond-design-basis accidents affecting the SFP, these diverse 
strategies provide multiple methods to obtain additional makeup or 
spray to the SFP before the onset of any postulated offsite 
radiological release.
    For all of the reasons stated above, the NRC staff finds that 
the licensee's requested exemptions meet the underlying purpose of 
all of the standards in 10 CFR 50.47(b), and requirements in 10 CFR 
50.47(c)(2) and 10 CFR Part 50, Appendix E, and satisfy the special 
circumstances provision in 10 CFR 50.12(a)(2)(ii) in view of the 
greatly reduced risk of offsite radiological consequences associated 
with the permanently shutdown and defueled state of the Oyster Creek 
facility 12 months (365 days) after permanent cessation of power 
operations.
    The NRC staff has concluded that the exemptions being granted by 
this action will maintain an acceptable level of emergency 
preparedness at Oyster Creek and, if needed, that there is 
reasonable assurance that adequate offsite protective measures can 
and will be taken by State and local government agencies using a 
CEMP approach in the unlikely event of a radiological emergency at 
Oyster Creek. Since the underlying purposes of the rules, as 
exempted, would continue to be achieved, even with the elimination 
of the requirements under 10 CFR Part 50 to maintain formal offsite 
radiological emergency preparedness plans and the reduction in the 
scope of the onsite emergency planning activities at Oyster Creek, 
the special circumstances required by 10 CFR 50.12(a)(2)(ii) exist.

E. Environmental Considerations.

    In accordance with 10 CFR 51.31(a), the Commission has 
determined that the granting of this exemption will not have a 
significant effect on the quality of the human environment as 
discussed in the NRC staff's Finding of No Significant Impact and 
associated Environmental Assessment published in the Federal 
Register on August 13, 2018 (83 FR 40092).

IV. Conclusions.

    Accordingly, the Commission has determined that, pursuant to 10 
CFR 50.12, Exelon's request for exemptions from certain EP 
requirements in 10 CFR 50.47(b), 10 CFR 50.47(c)(2), and 10 CFR Part 
50, Appendix E,

[[Page 53321]]

Section IV, and as summarized in Enclosure 2 to SECY-18-0062, are 
authorized by law, will not present an undue risk to the public 
health and safety, and are consistent with the common defense and 
security. Also, special circumstances are present. Therefore, the 
Commission hereby grants Exelon's exemptions from certain EP 
requirements in 10 CFR 50.47(b), 10 CFR 50.47(c)(2), and 10 CFR Part 
50, Appendix E, Section IV, as discussed and evaluated in detail in 
the NRC staff's safety evaluation associated with this exemption. 
The exemptions are effective as of 12 months (365 days) after 
permanent cessation of power operations.

    Dated at Rockville, Maryland, this 16th day of October 2018.

    For the Nuclear Regulatory Commission.

/RA/

Kathryn M. Brock,

Deputy Director, Division of Operating Reactor Licensing, Office of 
Nuclear Reactor Regulation.

[FR Doc. 2018-22986 Filed 10-19-18; 8:45 am]
 BILLING CODE 7590-01-P



                                                                            Federal Register / Vol. 83, No. 204 / Monday, October 22, 2018 / Notices                                                      53317

                                               granted the exemptions and issued the                      certain emergency planning (EP)                      adams.html. To begin the search, select
                                               amendments that SNC requested on                           requirements. The exemptions eliminate               ‘‘Begin Web-based ADAMS Search.’’ For
                                               April 26, 2018. The exemption and                          the requirements to maintain an offsite              problems with ADAMS, please contact
                                               amendment were issued on August 24,                        radiological emergency preparedness                  the NRC’s Public Document Room (PDR)
                                               2018, as part of a combined package to                     plan and reduce the scope of onsite EP               reference staff at 1–800–397–4209, 301–
                                               SNC (ADAMS Accession No.                                   activities at the Oyster Creek Nuclear               415–4737, or by email to pdr.resource@
                                               ML18220B095).                                              Generating Station (Oyster Creek), based             nrc.gov. The ADAMS accession number
                                                 Dated at Rockville, Maryland, this 17th day              on the reduced risks of accidents that               for each document referenced (if it is
                                               of October 2018.                                           could result in an offsite radiological              available in ADAMS) is provided the
                                                 For the Nuclear Regulatory Commission.                   release at a decommissioning nuclear                 first time that it is mentioned in this
                                               Jennifer L. Dixon-Herrity,                                 power reactor.                                       document. In addition, for the
                                               Chief, Licensing Branch 4, Division of                     DATES: The exemption was issued on                   convenience of the reader, the ADAMS
                                               Licensing, Siting, and Environmental                       October 16, 2018.                                    accession numbers are provided in a
                                               Analysis, Office of New Reactors.                                                                               table in the ‘‘Availability of Documents’’
                                                                                                          ADDRESSES: Please refer to Docket ID
                                               [FR Doc. 2018–22983 Filed 10–19–18; 8:45 am]                                                                    section of this document.
                                                                                                          NRC–2018–0167 when contacting the
                                               BILLING CODE 7590–01–P                                     NRC about the availability of                           • NRC’s PDR: You may examine and
                                                                                                          information regarding this document.                 purchase copies of public documents at
                                                                                                          You may obtain publicly-available                    the NRC’s PDR, Room O1–F21, One
                                               NUCLEAR REGULATORY                                         information related to this document                 White Flint North, 11555 Rockville
                                               COMMISSION                                                 using any of the following methods:                  Pike, Rockville, Maryland 20852.
                                               [Docket No. 50–219; NRC–2018–0167]                           • Federal Rulemaking Website: Go to                FOR FURTHER INFORMATION CONTACT: John
                                                                                                          http://www.regulations.gov and search                G. Lamb, Office of Nuclear Reactor
                                               Exelon Generation Company, LLC;                            for Docket ID NRC–2018–0167. Address                 Regulation, U.S. Nuclear Regulatory
                                               Oyster Creek Nuclear Generating                            questions about NRC dockets to Jennifer              Commission, Washington, DC 20555–
                                               Station Request for Exemptions                             Borges; telephone: 301–287–9127;                     0001; telephone: 301–415–3100; email:
                                               Regarding Emergency Planning                               email: Jennifer.Borges@nrc.gov. For                  John.Lamb@nrc.gov.
                                               Requirements                                               technical questions, contact the                     SUPPLEMENTARY INFORMATION: The text of
                                               AGENCY:  Nuclear Regulatory                                individual listed in the FOR FURTHER                 the exemption is attached.
                                               Commission.                                                INFORMATION CONTACT section of this
                                                                                                          document.                                            I. Availability of Documents
                                               ACTION: Exemption; issuance.
                                                                                                            • NRC’s Agencywide Documents                         The documents identified in the
                                               SUMMARY:  The U.S. Nuclear Regulatory                      Access and Management System                         following table are available for public
                                               Commission (NRC) has issued                                (ADAMS): You may obtain publicly-                    inspection through ADAMS, a public
                                               exemptions in response to a request                        available documents online in the                    web page, or by using one of the
                                               from Exelon Generation Company, LLC                        ADAMS Public Documents collection at                 methods discussed in the ADDRESSES
                                               (Exelon or the licensee) regarding                         http://www.nrc.gov/reading-rm/                       section of this document.

                                                                                                                                                                                           ADAMS accession no.
                                                                                                  Title                                                             Date                    or public web page

                                               Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, ‘‘Cer-                     February 14, 2018 .........       ML18045A084.
                                                 tification of Permanent Cessation of Power Operations for Oyster Creek Nuclear Gener-
                                                 ating Station’’.
                                               Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, ‘‘Re-                      August 22, 2017 ............      ML17234A082.
                                                 quest for Exemptions from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E’’.
                                               Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, ‘‘Re-                      December 6, 2017 .........        ML17340A708.
                                                 sponse to Request for Additional Information (RAI) Regarding Request for Exemption
                                                 from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E’’.
                                               Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, ‘‘Sup-                     January 23, 2018 ...........      ML18023A138.
                                                 plement to Request for Exemption from Portions of 10 CFR 50.47 and 10 CFR Part 50,
                                                 Appendix E’’.
                                               Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, ‘‘Sup-                     March 8, 2018 ................    ML18067A087.
                                                 plement to Request for Exemption from Portions of 10 CFR 50.47 and 10 CFR Part 50,
                                                 Appendix E’’.
                                               Exelon Generation Company, LLC, letter to U.S. Nuclear Regulatory Commission, ‘‘Re-                      March 19, 2018 ..............     ML18078A146.
                                                 sponse to Request for Additional Information (RAI) Related to Exemption Request from
                                                 Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E’’.
                                               U.S. Nuclear Regulatory Commission, NUREG/CR–6451, ‘‘A Safety and Regulatory As-                         August 1997 ...................   ML082260098.
                                                 sessment of Generic BWR and PWR Permanently Shutdown Nuclear Power Plants’’.
                                               U.S. Nuclear Regulatory Commission, NUREG–1738, ‘‘Technical Study of Spent Fuel                          February 2001 ...............     ML010430066.
                                                 Pool Accident Risk at Decommissioning Nuclear Power Plants’’.
                                               Federal Emergency Management Agency Comprehensive Preparedness Guide 101, ‘‘De-                          November 2010 .............       http://www.fema.gov/pdf/
daltland on DSKBBV9HB2PROD with NOTICES




                                                 veloping and Maintaining Emergency Operations Plans,’’ Version 2.0.                                                                         about/divisions/npd/
                                                                                                                                                                                             CPG_101_V2.pdf.
                                               U.S. Nuclear Regulatory Commission, NUREG–2161, ‘‘Consequence Study of a Beyond-                         September 2014 ............       ML14255A365.
                                                 Design-Basis Earthquake Affecting the Spent Fuel Pool for a U.S. Mark I Boiling Water
                                                 Reactor’’.
                                               U.S. Nuclear Regulatory Commission, COMSECY–13–0030, ‘‘Staff Evaluation and Rec-                         November 12, 2013 .......         ML13329A918.
                                                 ommendation for Japan Lessons-Learned Tier 3 Issue on Expedited Transfer of Spent
                                                 Fuel’’.



                                          VerDate Sep<11>2014   18:12 Oct 19, 2018   Jkt 247001   PO 00000   Frm 00112   Fmt 4703   Sfmt 4703   E:\FR\FM\22OCN1.SGM     22OCN1


                                               53318                        Federal Register / Vol. 83, No. 204 / Monday, October 22, 2018 / Notices

                                                                                                                                                                                            ADAMS accession no.
                                                                                                  Title                                                              Date                    or public web page

                                               U.S. Nuclear Regulatory Commission, SECY–18–0062, ‘‘Request by the Exelon Genera-                         May 31, 2018 .................    ML18030B359.
                                                 tion Company, LLC for Exemptions from Certain Emergency Planning Requirements for
                                                 the Oyster Creek Nuclear Generating Station’’.
                                               U.S. Nuclear Regulatory Commission, ‘‘Staff Requirements—SECY–18–0062, Request by                         July 17, 2018 .................   ML18198A449.
                                                 the Exelon Generation Company, LLC for Exemptions from Certain Emergency Plan-
                                                 ning Requirements for the Oyster Creek Nuclear Generating Station’’.
                                               U.S. Nuclear Regulatory Commission, letter to Exelon Generation Company, LLC ‘‘Oyster                     October 16, 2018 ...........      ML18220A980.
                                                 Creek Nuclear Generating Station—Exemptions from Certain Emergency Planning Re-
                                                 quirements and Related Safety Evaluation’’.



                                                 Dated at Rockville, Maryland, on October                 reactor. The reactor coolant system, operating        requirements in 10 CFR part 50, Appendix E,
                                               17, 2018.                                                  at high temperatures and pressures, transfers         Section IV, which establishes the elements
                                                 For the Nuclear Regulatory Commission.                   this heat through the steam generator tubes           that make up the content of emergency plans.
                                                                                                          converting non-radioactive feedwater to               In letters dated December 6, 2017, and
                                               John G. Lamb,
                                                                                                          steam, which then flows to the main turbine           January 23, March 8, and March 19, 2018
                                               Senior Project Manager, Special Projects and               generator to produce electricity. Many of the         (ADAMS Accession Nos. ML17340A708,
                                               Process Branch, Division of Operating Reactor              accident scenarios postulated in the updated          ML18023A138, ML18067A087, and
                                               Licensing, Office of Nuclear Reactor                       safety analysis reports (USARs) for operating         ML18078A146, respectively), Exelon
                                               Regulation.                                                power reactors involve failures or                    provided supplemental information and
                                               Attachment—Exemption                                       malfunctions of systems, which could affect           responses to the NRC staff’s requests for
                                                                                                          the fuel in the reactor core and, in the most         additional information concerning the
                                               NUCLEAR REGULATORY COMMISSION                              severe postulated accidents, would involve            proposed exemptions.
                                                                                                          the release of large quantities of fission               The information provided by Exelon
                                               Docket No. 50–219
                                                                                                          products. With the permanent cessation of             included justifications for each exemption
                                               Exelon Generation Company, LLC                             operations at Oyster Creek and the                    requested. The exemptions requested by
                                                                                                          permanent removal of the fuel from the                Exelon would eliminate the requirements to
                                               Oyster Creek Nuclear Generating Station                    reactor vessel, such accidents are no longer          maintain formal offsite radiological
                                               Exemption                                                  possible. The reactor, reactor coolant system,        emergency preparedness plans reviewed by
                                                                                                          and supporting systems are no longer in               the Federal Emergency Management Agency
                                               I. Background.                                             operation and have no function related to the         (FEMA) under the requirements of 44 CFR
                                                  Exelon Generation Company, LLC (Exelon                  storage of the spent fuel. Therefore,                 part 350 and would reduce the scope of
                                               or the licensee) is the holder of Renewed                  emergency planning (EP) provisions for                onsite EP activities at Oyster Creek. The
                                               Facility Operating License No. DPR-16 for                  postulated accidents involving failure or             licensee stated that the application of all of
                                               Oyster Creek Nuclear Generating Station                    malfunction of the reactor, reactor coolant           the standards and requirements in 10 CFR
                                               (Oyster Creek). The license provides, among                system, or supporting systems are no longer           50.47(b), 10 CFR 50.47(c), and 10 CFR part
                                               other things, that the facility is subject to all          applicable.                                           50, Appendix E is not needed for adequate
                                               rules, regulations, and orders of the U.S.                    The EP requirements of 10 CFR 50.47,               emergency response capability, based on the
                                               Nuclear Regulatory Commission (NRC) now                    ‘‘Emergency plans,’’ and Appendix E to 10             substantially lower onsite and offsite
                                               or hereafter in effect. The facility consists of           CFR part 50, ‘‘Emergency Planning and                 radiological consequences of accidents still
                                               a boiling-water reactor (BWR) located in                   Preparedness for Production and Utilization           possible at the permanently shutdown and
                                               Ocean County, New Jersey.                                  Facilities,’’ continue to apply to nuclear            defueled facility, as compared to an operating
                                                  By letter dated February 14, 2018                       power reactors that have permanently ceased           facility. If offsite protective actions were
                                               (Agencywide Documents Access and                           operation and have permanently removed all            needed for a highly unlikely beyond-design-
                                               Management System (ADAMS) Accession                        fuel from the reactor vessel. There are no            basis accident that could challenge the safe
                                               No. ML18045A084), Exelon submitted a                       explicit regulatory provisions distinguishing         storage of spent fuel at Oyster Creek,
                                               certification to the NRC that it would                     EP requirements for a power reactor that is           provisions exist for offsite agencies to take
                                               permanently cease power operations at                      permanently shut down and defueled from               protective actions using a comprehensive
                                               Oyster Creek no later than October 31, 2018.               those for a reactor that is authorized to             emergency management plan (CEMP) under
                                               On September 17, 2018, Exelon permanently                  operate. To reduce or eliminate EP                    the National Preparedness System to protect
                                               ceased power operations at Oyster Creek. By                requirements that are no longer necessary             the health and safety of the public. A CEMP
                                               letter dated September 25, 2018 (ADAMS                     due to the decommissioning status of the              in this context, also referred to as an
                                               Accession No. ML18268A258), Exelon                         facility, Exelon must obtain exemptions from          emergency operations plan, is addressed in
                                               certified the permanent removal of fuel from               those EP regulations. Only then can Exelon            FEMA’s Comprehensive Preparedness Guide
                                               the Oyster Creek reactor vessel.                           modify the Oyster Creek emergency plan to             101, ‘‘Developing and Maintaining
                                                  In accordance with § 50.82(a)(2) of Title 10            reflect the reduced risk associated with the          Emergency Operations Plans,’’ which is
                                               of the Code of Federal Regulations (10 CFR),               permanently shutdown and defueled                     publicly available at http://www.fema.gov/
                                               the license for a power reactor facility no                condition of Oyster Creek.                            pdf/about/divisions/npd/CPG_101_V2.pdf.
                                               longer authorizes operation of the reactor or                                                                    Comprehensive Preparedness Guide 101 is
                                               emplacement or retention of fuel into the                  II. Request/Action.                                   the foundation for State, territorial, Tribal,
                                               reactor vessel upon the docketing of the                      By letter dated August 22, 2017 (ADAMS             and local EP in the United States. It promotes
                                               certifications for permanent cessation of                  Accession No. ML17234A082), Exelon                    a common understanding of the
                                               operations and permanent removal of fuel                   requested exemptions from certain EP                  fundamentals of risk-informed planning and
                                               from the reactor vessel. The facility is still             requirements of 10 CFR part 50 for Oyster             decision-making and helps planners at all
                                               authorized to possess and store irradiated                 Creek. Specifically, Exelon requested                 levels of government in their efforts to
daltland on DSKBBV9HB2PROD with NOTICES




                                               (i.e., spent) nuclear fuel. Spent fuel is                  exemptions from certain planning standards            develop and maintain viable, all-hazards,
                                               currently stored onsite in the Oyster Creek                in 10 CFR 50.47(b) regarding onsite and               all-threats emergency plans. An emergency
                                               spent fuel pool (SFP) and a dry cask                       offsite radiological emergency preparedness           operations plan is flexible enough for use in
                                               independent spent fuel storage installation                plans for nuclear power reactors, from certain        all emergencies. It describes how people and
                                               (ISFSI) at the Oyster Creek facility.                      requirements in 10 CFR 50.47(c)(2) for                property will be protected; details who is
                                                  During normal power reactor operations,                 establishment of plume exposure and                   responsible for carrying out specific actions;
                                               the forced flow of water through the reactor               ingestion pathway emergency planning zones            identifies the personnel, equipment,
                                               coolant system removes heat generated by the               for nuclear power reactors; and from certain          facilities, supplies and other resources



                                          VerDate Sep<11>2014   18:12 Oct 19, 2018   Jkt 247001   PO 00000    Frm 00113   Fmt 4703   Sfmt 4703   E:\FR\FM\22OCN1.SGM     22OCN1


                                                                            Federal Register / Vol. 83, No. 204 / Monday, October 22, 2018 / Notices                                                53319

                                               available; and outlines how all actions will            exemptions allowed the licensees to modify            provided in SECY–18–0062. The NRC staff’s
                                               be coordinated. A CEMP is often referred to             their emergency plans commensurate with               detailed review and technical basis for the
                                               as a synonym for ‘‘all-hazards planning.’’              the credible site-specific risks that were            approval of the specific EP exemptions
                                                                                                       consistent with a permanently shutdown and            requested by Exelon, are provided in the NRC
                                               III. Discussion.                                        defueled status. Specifically, the NRC’s              staff’s safety evaluation associated with this
                                                  In accordance with 10 CFR 50.12, ‘‘Specific          approval of these prior exemptions was based          exemption (ADAMS Accession No.
                                               exemptions,’’ the Commission may, upon                  on the licensee’s demonstration that: (1) the         ML18220A980).
                                               application by any interested person or upon            radiological consequences of design-basis
                                               its own initiative, grant exemptions from the                                                                 A. The Exemption is Authorized by Law.
                                                                                                       accidents would not exceed the limits of the
                                               requirements of 10 CFR part 50 when: (1) the            U.S. Environmental Protection Agency’s                   The licensee has proposed exemptions
                                               exemptions are authorized by law, will not              (EPA) early phase Protective Action Guides            from certain EP requirements in 10 CFR
                                               present an undue risk to public health and              (PAGs) of one roentgen equivalent man (rem)           50.47(b), 10 CFR 50.47(c)(2), and 10 CFR 50,
                                               safety, and are consistent with the common              at the exclusion area boundary; and (2) in the        Appendix E, Section IV, that would allow
                                               defense and security; and (2) any of the                highly unlikely event of a beyond-design-             Exelon to revise the Oyster Creek Emergency
                                               special circumstances listed in 10 CFR                  basis accident resulting in a loss of all modes       Plan to reflect the permanently shutdown
                                               50.12(a)(2) are present. These special                  of heat transfer from the fuel stored in the          and defueled condition of the facility. As
                                               circumstances include, among other things,              SFP, there is sufficient time to initiate             stated above, in accordance with 10 CFR
                                               that the application of the regulation in the           appropriate mitigating actions, and if needed,        50.12, the Commission may, upon
                                               particular circumstances would not serve the            for offsite authorities to implement offsite          application by any interested person or upon
                                               underlying purpose of the rule or is not                protective actions using a CEMP approach to           its own initiative, grant exemptions from the
                                               necessary to achieve the underlying purpose             protect the health and safety of the public.          requirements of 10 CFR part 50. The NRC
                                               of the rule.                                               With respect to design-basis accidents at          staff has determined that granting of the
                                                  As noted previously, the EP regulations              Oyster Creek, the licensee provided an                licensee’s proposed exemptions will not
                                               contained in 10 CFR 50.47(b) and Appendix               analysis demonstrating that 12 months (365            result in a violation of the Atomic Energy Act
                                               E to 10 CFR part 50 apply to both operating             days) following permanent cessation of                of 1954, as amended, or the NRC’s
                                               and shutdown power reactors. The NRC has                power operations, the radiological                    regulations. Therefore, the exemptions are
                                               consistently acknowledged that the risk of an           consequences of the only remaining                    authorized by law.
                                               offsite radiological release at a power reactor         design-basis accident with potential for              B. The Exemption Presents No Undue Risk
                                               that has permanently ceased operations and              offsite radiological release (the fuel handling       to Public Health and Safety.
                                               permanently removed fuel from the reactor               accident in the Auxiliary Building, where the
                                                                                                                                                                As stated previously, Exelon provided an
                                               vessel is significantly lower, and the types of         SFP is located) will not exceed the limits of
                                                                                                                                                             analysis that show that the radiological
                                               possible accidents are significantly fewer,             the EPA PAGs at the exclusion area
                                                                                                                                                             consequences of design-basis accidents will
                                               than at an operating power reactor. However,            boundary.
                                                                                                                                                             not exceed the limits of the EPA early phase
                                               the EP regulations do not recognize that once              With respect to beyond-design-basis
                                                                                                                                                             PAGs at the exclusion area boundary.
                                               a power reactor permanently ceases                      accidents at Oyster Creek, the licensee
                                                                                                                                                             Therefore, formal offsite radiological
                                               operation, the risk of a large radiological             analyzed a drain down of the SFP water that           emergency preparedness plans required
                                               release from credible emergency accident                would effectively impede any decay heat               under 10 CFR part 50 will no longer be
                                               scenarios is significantly reduced. The                 removal. The analysis demonstrates that at 12         needed for protection of the public beyond
                                               reduced risk for any significant offsite                months (365 days) after permanent cessation           the exclusion area boundary, based on the
                                               radiological release is based on two factors.           of power operations, there would be 10 hours          radiological consequences of design-basis
                                               One factor is the elimination of accidents              after the assemblies have been uncovered              accidents still possible at Oyster Creek 365
                                               applicable only to an operating power                   until the limiting fuel assembly (for decay           days after the plant has permanently ceased
                                               reactor, resulting in fewer credible accident           heat and adiabatic heatup analysis) reaches           power operations.
                                               scenarios. The second factor is the reduced             900 degrees Celsius (°C), the temperature                Although highly unlikely, there is one
                                               short-lived radionuclide inventory and decay            used to assess the potential onset of fission         postulated beyond-design-basis accident that
                                               heat production due to radioactive decay.               product release. The analysis conservatively          might result in significant offsite radiological
                                               Due to the permanently defueled status of the           assumed that the heat up time starts when             releases. However, NUREG-1738 confirms
                                               reactor, no new spent fuel will be added to             the SFP has been completely drained,                  that the risk of beyond-design-basis accidents
                                               the SFP and the radionuclides in the current            although it is likely that site personnel will        is greatly reduced at permanently shutdown
                                               spent fuel will continue to decay as the spent          start to respond to an incident when drain            and defueled reactors. The NRC staff’s
                                               fuel ages. The irradiated fuel will produce             down starts. The analysis also does not               analyses in NUREG-1738 conclude that the
                                               less heat due to radioactive decay, increasing          consider the period of time from the                  event sequences important to risk at
                                               the available time to mitigate a loss of water          initiating event causing loss of SFP water            permanently shutdown and defueled power
                                               inventory from the SFP. The NRC’s NUREG/                inventory until cooling is lost.                      reactors are limited to large earthquakes and
                                               CR–6451, ‘‘A Safety and Regulatory                         The NRC reviewed the licensee’s                    cask drop events. For EP assessments, this is
                                               Assessment of Generic BWR [Boiling Water                justification for the requested exemptions            an important difference relative to operating
                                               Reactor] and PWR [Pressurized Water                     against the criteria in 10 CFR 50.12(a) and           power reactors, where typically a large
                                               Reactor] Permanently Shutdown Nuclear                   determined, as described below, that the              number of different sequences make
                                               Power Plants,’’ dated August 1997 (ADAMS                criteria in 10 CFR 50.12(a) will be met, and          significant contributions to risk. As described
                                               Accession No. ML082260098), and the NRC’s               that the exemptions should be granted 365             in NUREG-1738, relaxation of offsite EP
                                               NUREG-1738, ‘‘Technical Study of Spent                  days after Oyster Creek has permanently               requirements in 10 CFR part 50 beyond a few
                                               Fuel Pool Accident Risk at Decommissioning              defueled. An assessment of the Exelon EP              months after shutdown resulted in only a
                                               Nuclear Power Plants,’’ dated February 2001             exemptions is described in SECY–18–0062,              small change in risk. The report further
                                               (ADAMS Accession No. ML010430066),                      ‘‘Request by the Exelon Generation Company,           concludes that the change in risk due to
                                               confirmed that for permanently shutdown                 LLC for Exemptions from Certain Emergency             relaxation of offsite EP requirements is small
                                               and defueled power reactors that are                    Planning Requirements for the Oyster Creek            because the overall risk is low, and because
                                               bounded by the assumptions and conditions               Nuclear Generating Station,’’ dated May 31,           even under current EP requirements for
                                               in the report, the risk of offsite radiological         2018 (ADAMS Accession No.                             operating power reactors, EP was judged to
daltland on DSKBBV9HB2PROD with NOTICES




                                               release is significantly less than for an               ML18030B340). The Commission approved                 have marginal impact on evacuation
                                               operating power reactor.                                the NRC staff’s recommendation to grant the           effectiveness for the severe earthquakes that
                                                  In the past, EP exemptions similar to those          exemptions in the staff requirements                  dominate SFP risk. All other sequences
                                               requested for Oyster Creek, have been                   memorandum to SECY–18–0062, dated July                including cask drops (for which offsite
                                               granted to permanently shutdown and                     17, 2018 (ADAMS Accession No.                         radiological emergency preparedness plans
                                               defueled power reactor licensees. However,              ML18198A449). Descriptions of the specific            are expected to be more effective) are too low
                                               the exemptions did not relieve the licensees            exemptions requested by Exelon and the NRC            in likelihood to have a significant impact on
                                               of all EP requirements. Rather, the                     staff’s basis for granting each exemption are         risk.



                                          VerDate Sep<11>2014   18:12 Oct 19, 2018   Jkt 247001   PO 00000   Frm 00114   Fmt 4703   Sfmt 4703   E:\FR\FM\22OCN1.SGM   22OCN1


                                               53320                        Federal Register / Vol. 83, No. 204 / Monday, October 22, 2018 / Notices

                                                  Therefore, granting exemptions to                    significant decay time have little potential to       using a CEMP approach, then formal offsite
                                               eliminate the requirements of 10 CFR part 50            cause offsite early fatalities, even if the           radiological emergency preparedness plans,
                                               to maintain offsite radiological emergency              formal offsite radiological EP requirements           required under 10 CFR Part 50, are not
                                               preparedness plans and to reduce the scope              were relaxed. The licensee’s analysis of a            necessary at permanently shutdown and
                                               of onsite EP activities will not present an             beyond-design-basis accident involving a              defueled facilities.
                                               undue risk to the public health and safety.             complete loss of SFP water inventory, based              Additionally, Oyster Creek committed to
                                                                                                       on an adiabatic heatup analysis of the                maintaining SFP makeup strategies in its
                                               C. The Exemption Is Consistent With the                 limiting fuel assembly for decay heat, shows          letters to the NRC dated March 8 and 19,
                                               Common Defense and Security.                            that within 12 months (365 days) after                2018. The multiple strategies for providing
                                                  The requested exemptions only involve EP             permanent cessation of power operations, the          makeup to the SFP include: using existing
                                               requirements under 10 CFR part 50 and will              time for the limiting fuel assembly to reach          plant systems for inventory makeup; an
                                               allow Exelon to revise the Oyster Creek                 900 °C is at least 10 hours after the                 internal strategy that relies on the fire
                                               Emergency Plan to reflect the permanently               assemblies have been uncovered assuming a             protection system with redundant pumps
                                               shutdown and defueled condition of the                  loss of all cooling means.                            (one diesel-driven and electric motor-driven);
                                               facility. Physical security measures at Oyster             The only analyzed beyond-design-basis              and onsite diesel fire truck that can take
                                               Creek are not affected by the requested EP              accident scenario that progresses to a                suction from the Barnegat Bay. These
                                               exemptions. The discontinuation of formal               condition where a significant offsite release         strategies will continue to be required as
                                               offsite radiological emergency preparedness             might occur, involves the highly unlikely             condition 2.C.(8), ‘‘Mitigation Strategy
                                               plans and the reduction in scope of the onsite          event where the SFP drains in such a way              License Condition,’’ of renewed facility
                                               EP activities at Oyster Creek will not                  that all modes of cooling or heat transfer are        operating license DPR–16 for Oyster Creek.
                                               adversely affect Exelon’s ability to physically         assumed to be unavailable, which is referred          Considering the very low probability of
                                               secure the site or protect special nuclear              to as an adiabatic heatup of the spent fuel.          beyond-design-basis accidents affecting the
                                               material. Therefore, the proposed exemptions            The licensee’s analysis of this beyond-design-        SFP, these diverse strategies provide multiple
                                               are consistent with common defense and                  basis accident shows that within 12 months            methods to obtain additional makeup or
                                               security.                                               (365 days) after permanent cessation of               spray to the SFP before the onset of any
                                                                                                       power operations, at least 10 hours would be          postulated offsite radiological release.
                                               D. Special Circumstances.                               available between the time that all cooling              For all of the reasons stated above, the NRC
                                                  Special circumstances, in accordance with            means are lost to the fuel (at which time             staff finds that the licensee’s requested
                                               10 CFR 50.12(a)(2)(ii), are present whenever            adiabatic heatup is conservatively assumed            exemptions meet the underlying purpose of
                                               application of the regulation in the particular         to begin), until the fuel cladding reaches a          all of the standards in 10 CFR 50.47(b), and
                                               circumstances is not necessary to achieve the           temperature of 1652 degrees Fahrenheit (900           requirements in 10 CFR 50.47(c)(2) and 10
                                               underlying purpose of the rule. The                     °C), which is the temperature associated with         CFR Part 50, Appendix E, and satisfy the
                                               underlying purpose of 10 CFR 50.47(b), 10               rapid cladding oxidation and the potential            special circumstances provision in 10 CFR
                                               CFR 50.47(c)(2), and 10 CFR part 50,                    for a significant radiological release. This          50.12(a)(2)(ii) in view of the greatly reduced
                                               Appendix E, Section IV, is to provide                   analysis conservatively does not include the          risk of offsite radiological consequences
                                               reasonable assurance that adequate protective           period of time from the initiating event              associated with the permanently shutdown
                                               measures can and will be taken in the event             causing a loss of SFP water inventory until           and defueled state of the Oyster Creek facility
                                               of a radiological emergency, to establish               all cooling means are lost.                           12 months (365 days) after permanent
                                               plume exposure and ingestion pathway                       The NRC staff has verified Exelon’s                cessation of power operations.
                                               emergency planning zones for nuclear power              analyses and its calculations. The analyses              The NRC staff has concluded that the
                                               plants, and to ensure that licensees maintain           provide reasonable assurance that in granting         exemptions being granted by this action will
                                               effective offsite and onsite radiological               the requested exemptions to Exelon, there is          maintain an acceptable level of emergency
                                               emergency preparedness plans. The                       no design-basis accident that will result in an       preparedness at Oyster Creek and, if needed,
                                               standards and requirements in these                     offsite radiological release exceeding the EPA        that there is reasonable assurance that
                                               regulations were developed by considering               early phase PAGs at the exclusion area                adequate offsite protective measures can and
                                               the risks associated with operation of a                boundary. In the highly unlikely event of a           will be taken by State and local government
                                               power reactor at its licensed full-power level.         beyond-design-basis accident affecting the            agencies using a CEMP approach in the
                                               These risks include the potential for a reactor         SFP that results in a complete loss of heat           unlikely event of a radiological emergency at
                                               accident with offsite radiological dose                 removal via all modes of heat transfer, there         Oyster Creek. Since the underlying purposes
                                               consequences.                                           will be over 10 hours available before an             of the rules, as exempted, would continue to
                                                  As discussed previously in Section III,              offsite release might occur and, therefore, at        be achieved, even with the elimination of the
                                               because Oyster Creek will be permanently                least 10 hours to initiate appropriate                requirements under 10 CFR Part 50 to
                                               shut down and defueled, there will no longer            mitigating actions to restore a means of heat         maintain formal offsite radiological
                                               be a risk of a significant offsite radiological         removal to the spent fuel. If a radiological          emergency preparedness plans and the
                                               release from a design-basis accident                    release were projected to occur under this            reduction in the scope of the onsite
                                               exceeding EPA early phase PAG at the                    highly unlikely scenario, a minimum of 10             emergency planning activities at Oyster
                                               exclusion area boundary and the risk of a               hours is considered sufficient time for offsite       Creek, the special circumstances required by
                                               significant offsite radiological release from a         authorities to implement protective actions           10 CFR 50.12(a)(2)(ii) exist.
                                               beyond-design-basis accident is greatly                 using a CEMP approach to protect the health
                                               reduced when compared to an operating                   and safety of the public.                             E. Environmental Considerations.
                                               power reactor. The NRC staff has confirmed                 Exemptions from the offsite EP                        In accordance with 10 CFR 51.31(a), the
                                               the reduced risks at Oyster Creek by                    requirements in 10 CFR Part 50 have                   Commission has determined that the granting
                                               comparing the generic risk assumptions in               previously been approved by the NRC when              of this exemption will not have a significant
                                               the analyses in NUREG-1738 to site-specific             the site-specific analyses show that at least         effect on the quality of the human
                                               conditions at Oyster Creek and determined               10 hours is available following a loss of SFP         environment as discussed in the NRC staff’s
                                               that the risk values in NUREG-1738 bound                coolant inventory accident with no air                Finding of No Significant Impact and
                                               the risks presented at Oyster Creek. As                 cooling (or other methods of removing decay           associated Environmental Assessment
                                               indicated by the results of the research                heat) until cladding of the hottest fuel              published in the Federal Register on August
daltland on DSKBBV9HB2PROD with NOTICES




                                               conducted for NUREG-1738, and more                      assembly reaches the rapid oxidation                  13, 2018 (83 FR 40092).
                                               recently for NUREG-2161, ‘‘Consequence                  temperature. The NRC staff concluded in its
                                               Study of a Beyond-Design-Basis Earthquake               previously granted exemptions, as it does             IV. Conclusions.
                                               Affecting the Spent Fuel Pool for a U.S. Mark           with Exelon’s requested EP exemptions, that             Accordingly, the Commission has
                                               I Boiling Water Reactor,’’ dated September              if a minimum of 10 hours is available to              determined that, pursuant to 10 CFR 50.12,
                                               2014 (ADAMS Accession No.                               initiate mitigative actions consistent with           Exelon’s request for exemptions from certain
                                               ML14255A365), while other consequences                  plant conditions, or if needed, for offsite           EP requirements in 10 CFR 50.47(b), 10 CFR
                                               can be extensive, accidents from SFPs with              authorities to implement protective actions           50.47(c)(2), and 10 CFR Part 50, Appendix E,



                                          VerDate Sep<11>2014   18:12 Oct 19, 2018   Jkt 247001   PO 00000   Frm 00115   Fmt 4703   Sfmt 4703   E:\FR\FM\22OCN1.SGM   22OCN1


                                                                            Federal Register / Vol. 83, No. 204 / Monday, October 22, 2018 / Notices                                          53321

                                               Section IV, and as summarized in Enclosure              in the FOR FURTHER INFORMATION                        II. NRC Staff Determination of
                                               2 to SECY–18–0062, are authorized by law,               CONTACT section of this document.                     Completion of ITAAC
                                               will not present an undue risk to the public
                                               health and safety, and are consistent with the             • NRC’s Agencywide Documents                          The NRC staff has determined that the
                                               common defense and security. Also, special              Access and Management System                          specified inspections, tests, and
                                               circumstances are present. Therefore, the               (ADAMS): You may obtain publicly                      analyses have been successfully
                                               Commission hereby grants Exelon’s                       available documents online in the                     completed, and that the specified
                                               exemptions from certain EP requirements in              ADAMS Public Documents collection at                  acceptance criteria are met. The
                                               10 CFR 50.47(b), 10 CFR 50.47(c)(2), and 10             http://www.nrc.gov/reading-rm/                        documentation of the NRC staff’s
                                               CFR Part 50, Appendix E, Section IV, as                 adams.html. To begin the search, select               determination is in the ITAAC Closure
                                               discussed and evaluated in detail in the NRC            ‘‘Begin Web-based ADAMS Search.’’ For
                                               staff’s safety evaluation associated with this
                                                                                                                                                             Verification Evaluation Form (VEF) for
                                                                                                       problems with ADAMS, please contact                   each ITAAC. The VEF is a form that
                                               exemption. The exemptions are effective as
                                               of 12 months (365 days) after permanent                 the NRC’s Public Document Room (PDR)                  represents the NRC staff’s structured
                                               cessation of power operations.                          reference staff at 1–800–397–4209, 301–               process for reviewing ICNs. Each ICN
                                                                                                       415–4737, or by email to pdr.resource@                presents a narrative description of how
                                                 Dated at Rockville, Maryland, this 16th day
                                                                                                       nrc.gov. The ADAMS accession number                   the ITAAC was completed. The NRC’s
                                               of October 2018.
                                                                                                       for each document referenced in this                  ICN review process involves a
                                                 For the Nuclear Regulatory Commission.
                                                                                                       document (if that document is available               determination on whether, among other
                                               /RA/                                                    in ADAMS) is provided the first time                  things: (1) Each ICN provides sufficient
                                               Kathryn M. Brock,                                       that a document is referenced.                        information, including a summary of the
                                               Deputy Director, Division of Operating                     • NRC’s PDR: You may examine and                   methodology used to perform the
                                               Reactor Licensing, Office of Nuclear Reactor                                                                  ITAAC, to demonstrate that the
                                                                                                       purchase copies of public documents at
                                               Regulation.
                                                                                                       the NRC’s PDR, Room O1–F21, One                       inspections, tests, and analyses have
                                               [FR Doc. 2018–22986 Filed 10–19–18; 8:45 am]            White Flint North, 11555 Rockville                    been successfully completed; (2) each
                                               BILLING CODE 7590–01–P                                  Pike, Rockville, Maryland 20852.                      ICN provides sufficient information to
                                                                                                                                                             demonstrate that the acceptance criteria
                                                                                                       FOR FURTHER INFORMATION CONTACT:
                                                                                                                                                             of the ITAAC are met; and (3) any NRC
                                               NUCLEAR REGULATORY                                      Chandu Patel, Office of New Reactors,
                                                                                                                                                             inspections for the ITAAC have been
                                               COMMISSION                                              U.S. Nuclear Regulatory Commission,
                                                                                                                                                             completed and any ITAAC findings
                                                                                                       Washington, DC 20555–0001; telephone:
                                               [Docket Nos. 52–025 and 52–026; NRC–                                                                          associated with that ITAAC have been
                                                                                                       301–415–3025; email: Chandu.Patel@
                                               2008–0252]                                                                                                    closed.
                                                                                                       nrc.gov.
                                                                                                                                                                The NRC staff’s determination of the
                                               Southern Nuclear Operating Company,                     SUPPLEMENTARY INFORMATION:                            successful completion of these ITAAC is
                                               Inc.; Vogtle Electric Generating Plant,                                                                       based on information available at this
                                               Units 3 and 4; Inspections, Tests,                      I. Licensee Notification of Completion                time and is subject to the licensee’s
                                               Analyses, and Acceptance Criteria                       of ITAAC                                              ability to maintain the condition that
                                                                                                          Southern Nuclear Operating                         the acceptance criteria are met. If the
                                               AGENCY:  Nuclear Regulatory
                                                                                                       Company, Inc. (SNC), Georgia Power                    staff receives new information that
                                               Commission.
                                                                                                       Company, Oglethorpe Power                             suggests the staff’s determination on any
                                               ACTION: Determination of the successful                                                                       of these ITAAC is incorrect, then the
                                                                                                       Corporation, MEAG Power SPVM, LLC.,
                                               completion of inspections, tests, and                                                                         staff will determine whether to reopen
                                                                                                       MEAG Power SPVJ, LLC., MEAG Power
                                               analyses.                                                                                                     that ITAAC (including withdrawing the
                                                                                                       SPVP, LLC., and the City of Dalton,
                                                                                                       Georgia, (hereafter called the licensee)              staff’s determination on that ITAAC).
                                               SUMMARY:    The U.S. Nuclear Regulatory
                                                                                                       have submitted Inspections, Tests,                    The NRC staff’s determination will be
                                               Commission (NRC) staff has determined
                                                                                                       Analyses, and Acceptance Criteria                     used to support a subsequent finding,
                                               that the inspections, tests, and analyses
                                                                                                       (ITAAC) closure notifications (ICNs)                  pursuant to 10 CFR 52.103(g), at the end
                                               have been successfully completed, and
                                                                                                       under paragraph 52.99(c)(1) of title 10 of            of construction that all acceptance
                                               that the specified acceptance criteria are
                                                                                                       the Code of Federal Regulations (10                   criteria in the combined license are met.
                                               met for the Vogtle Electric Generating
                                                                                                       CFR), informing the NRC that the                      The ITAAC closure process is not
                                               Plant (VEGP), Units 3 and 4.
                                                                                                       licensee has successfully performed the               finalized for these ITAAC until the NRC
                                               DATES: The determination of the                                                                               makes an affirmative finding under 10
                                               successful completion of inspections,                   required inspections, tests, and
                                                                                                       analyses, and that the acceptance                     CFR 52.103(g). Any future updates to
                                               tests, and analyses for VEGP Units 3 and                                                                      the status of these ITAAC will be
                                               4 is effective October 22, 2018.                        criteria are met for:
                                                                                                          VEGP Unit 3 ITAAC: 2.2.03.08b.02                   reflected on the NRC’s website at http://
                                               ADDRESSES: Please refer to Docket ID                                                                          www.nrc.gov/reactors/new-reactors/
                                               NRC–2008–0252 when contacting the                       (176), 2.2.03.08c.iv.04 (186),
                                                                                                       2.2.05.07a.ii (266), 2.3.05.03a.i (343),              oversight/itaac.html.
                                               NRC about the availability of                                                                                    This notice fulfills the staff’s
                                               information regarding this document.                    2.3.09.03.iii (425), 3.2.00.01c.ii (742),
                                                                                                                                                             obligations under 10 CFR 52.99(e)(1) to
                                               You may obtain publicly-available                       and 3.2.00.01d (743).
                                                                                                                                                             publish a notice in the Federal Register
                                               information related to this document                       VEGP Unit 4 ITAAC: 2.2.05.07a.ii                   of the NRC staff’s determination of the
                                               using any of the following methods:                     (266), 3.2.00.01c.ii (742), and 3.2.00.01d            successful completion of inspections,
                                                  • Federal Rulemaking website: Go to                  (743).                                                tests, and analyses.
daltland on DSKBBV9HB2PROD with NOTICES




                                               http://www.regulations.gov and search                      The ITAAC for VEGP Unit 3 are in
                                               for Docket ID NRC–2008–0252. Address                    Appendix C of the VEGP Unit 3                         Vogtle Electric Generating Plant Unit 3,
                                               questions regarding Docket IDs in                       combined license (ADAMS Accession                     Docket No. 5200025
                                               Regulations.gov to Jennifer Borges;                     No. ML14100A106). The ITAAC for                         A complete list of the review status
                                               telephone: 301–287–9127; email:                         VEGP Unit 4 are in Appendix C of VEGP                 for VEGP Unit 3 ITAAC, including the
                                               Jennifer.Borges@nrc.gov. For technical                  Unit 4 combined license (ADAMS                        submission date and ADAMS Accession
                                               questions, contact the individual listed                Accession No. ML14100A135).                           Number for each ICN received, the


                                          VerDate Sep<11>2014   18:12 Oct 19, 2018   Jkt 247001   PO 00000   Frm 00116   Fmt 4703   Sfmt 4703   E:\FR\FM\22OCN1.SGM   22OCN1



Document Created: 2018-10-20 01:50:24
Document Modified: 2018-10-20 01:50:24
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionExemption; issuance.
DatesThe exemption was issued on October 16, 2018.
ContactJohn G. Lamb, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-3100; email: [email protected]
FR Citation83 FR 53317 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR