83_FR_54951 83 FR 54740 - Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene; Haights Creek Irrigation Company

83 FR 54740 - Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene; Haights Creek Irrigation Company

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 211 (October 31, 2018)

Page Range54740-54741
FR Document2018-23769

Federal Register, Volume 83 Issue 211 (Wednesday, October 31, 2018)
[Federal Register Volume 83, Number 211 (Wednesday, October 31, 2018)]
[Notices]
[Pages 54740-54741]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-23769]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD19-1-000]


Notice of Preliminary Determination of a Qualifying Conduit 
Hydropower Facility and Soliciting Comments and Motions To Intervene; 
Haights Creek Irrigation Company

    On October 12, 2018, the Haights Creek Irrigation Company, filed a 
notice of intent to construct a qualifying conduit hydropower facility, 
pursuant to section 30 of the Federal Power Act (FPA), as amended by 
section 4 of the Hydropower Regulatory Efficiency Act of 2013 (HREA). 
The proposed Haights Creek Micro-Hydropower Project would have a total 
installed capacity up to 24 kilowatts (kW), and would be located on the 
existing Haights Creek Irrigation Pipeline. The project would be 
located near the City of Kaysville in Davis County, Utah.
    Applicant Contact: Dan Robinson, Haights Creek Irrigation Company, 
820 East 200 North, Kaysville, UT 84037,

[[Page 54741]]

Phone No. (801) 546-4242, email: dan@haightscreek.comcastbiz.
    FERC Contact: Robert Bell, Phone No. (202) 502-6062; Email: 
robert.bell@ferc.gov.
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) Up to six 4-kW turbine-generators 
connected to an existing irrigation pipeline with a total generating 
capacity of up to 24 kW, and (2) appurtenant facilities. The proposed 
project would have an estimated annual generation of up to 105.42 
megawatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

                          Table 1--Criteria for Qualifying Conduit Hydropower Facility
----------------------------------------------------------------------------------------------------------------
                                                                                                      Satisfies
              Statutory provision                                   Description                         (Y/N)
----------------------------------------------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by HREA............  The conduit the facility uses is a tunnel, canal,            Y
                                                  pipeline, aqueduct, flume, ditch, or similar
                                                  manmade water conveyance that is operated for
                                                  the distribution of water for agricultural,
                                                  municipal, or industrial consumption and not
                                                  primarily for the generation of electricity.
FPA 30(a)(3)(C)(i), as amended by HREA.........  The facility is constructed, operated, or                    Y
                                                  maintained for the generation of electric power
                                                  and uses for such generation only the
                                                  hydroelectric potential of a non-federally owned
                                                  conduit.
FPA 30(a)(3)(C)(ii), as amended by HREA........  The facility has an installed capacity that does             Y
                                                  not exceed 5 megawatts.
FPA 30(a)(3)(C)(iii), as amended by HREA.......  On or before August 9, 2013, the facility is not             Y
                                                  licensed, or exempted from the licensing
                                                  requirements of Part I of the FPA.
----------------------------------------------------------------------------------------------------------------

    Preliminary Determination: The proposed Haights Creek Micro-
Hydropower Project will not interfere with the primary purpose of the 
conduit, which is to transport water for irrigation by filling an 
equalizing reservoir, which in turn provides pressure for an irrigation 
zone in their service area. Therefore, based upon the above criteria, 
Commission staff preliminarily determines that the proposal satisfies 
the requirements for a qualifying conduit hydropower facility, which is 
not required to be licensed or exempted from licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the COMMENTS CONTESTING QUALIFICATION FOR A 
CONDUIT HYDROPOWER FACILITY or MOTION TO INTERVENE, as applicable; (2) 
state in the heading the name of the applicant and the project number 
of the application to which the filing responds; (3) state the name, 
address, and telephone number of the person filing; and (4) otherwise 
comply with the requirements of sections 385.2001 through 385.2005 of 
the Commission's regulations.\1\ All comments contesting Commission 
staff's preliminary determination that the facility meets the 
qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2018).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE, Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE, Washington, DC 20426. The filing may also be 
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp using 
the eLibrary link. Enter the docket number (i.e., CD19-1) in the docket 
number field to access the document. For assistance, call toll-free 1-
866-208-3676 or email FERCOnlineSupport@ferc.gov. For TTY, call (202) 
502-8659.

    Dated: October 25, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-23769 Filed 10-30-18; 8:45 am]
BILLING CODE 6717-01-P



                                              54740                      Federal Register / Vol. 83, No. 211 / Wednesday, October 31, 2018 / Notices

                                                                FERC–549C: STANDARDS FOR BUSINESS PRACTICES OF INTERSTATE NATURAL GAS PIPELINES
                                                                                                                                            Average
                                                                                                     Average           Total                 burden
                                                                                                                                                                     Total annual burden              Cost per
                                                                              Number of             number of       number of              hrs. & cost
                                                                                                                                                                        hours & total               respondent
                                                                             respondents         responses per      responses                  ($)
                                                                                                                                                                         annual cost                 (rounded)
                                                                                                  respondent 10                          per response 11
                                                                                                                                                                             ($)                         ($)

                                                                                    (1)          (2) = (3) ÷ (1)         (3)                     (4)                     (3) * (4) = (5)             (5) ÷ (1)

                                              Standards for Business                      165                2.97              490    96 hrs.; $8,928 ........   47,040 hrs.; $4,374,720 .......         $26,513
                                                Practices of Interstate
                                                Natural Gas Pipelines.



                                                 Comments: Comments are invited on:                    DEPARTMENT OF ENERGY                                      888 First Street NE, Washington, DC
                                              (1) Whether either collection of                                                                                   20426.
                                              information is necessary for the proper                  Federal Energy Regulatory                                    The filings in the above-referenced
                                              performance of the functions of the                      Commission                                                proceeding are accessible in the
                                              Commission, including whether the                                                                                  Commission’s eLibrary system by
                                                                                                       [Docket No. ER19–170–000]
                                              information will have practical utility;                                                                           clicking on the appropriate link in the
                                              (2) the accuracy of the agency’s                         Supplemental Notice That Initial                          above list. They are also available for
                                              estimates of the burden and costs of the                 Market-Based Rate Filing Includes                         electronic review in the Commission’s
                                                                                                       Request for Blanket Section 204                           Public Reference Room in Washington,
                                              collection of information, including the
                                                                                                       Authorization: Gateway Energy                             DC. There is an eSubscription link on
                                              validity of the methodology and
                                                                                                       Storage, LLC                                              the website that enables subscribers to
                                              assumptions used on each collection; (3)                                                                           receive email notification when a
                                              ways to enhance the quality, utility and                    This is a supplemental notice in the                   document is added to a subscribed
                                              clarity of either information collection;                above-referenced proceeding of Gateway                    docket(s). For assistance with any FERC
                                              and (4) ways to minimize the burden of                   Energy Storage, LLC’s application for                     Online service, please email
                                              either collection of information on those                market-based rate authority, with an                      FERCOnlineSupport@ferc.gov or call
                                              who are to respond, including the use                    accompanying rate tariff, noting that                     (866) 208–3676 (toll free). For TTY, call
                                              of automated collection techniques or                    such application includes a request for                   (202) 502–8659.
                                              other forms of information technology.                   blanket authorization, under 18 CFR                         Dated: October 25, 2018.
                                                Dated: October 25, 2018.                               part 34, of future issuances of securities                Nathaniel J. Davis, Sr.,
                                                                                                       and assumptions of liability.
                                              Kimberly D. Bose,                                                                                                  Deputy Secretary.
                                                                                                          Any person desiring to intervene or to
                                              Secretary.                                                                                                         [FR Doc. 2018–23749 Filed 10–30–18; 8:45 am]
                                                                                                       protest should file with the Federal
                                              [FR Doc. 2018–23770 Filed 10–30–18; 8:45 am]             Energy Regulatory Commission, 888                         BILLING CODE 6717–01–P

                                              BILLING CODE 6717–01–P                                   First Street NE, Washington, DC 20426,
                                                                                                       in accordance with Rules 211 and 214
                                                                                                                                                                 DEPARTMENT OF ENERGY
                                                                                                       of the Commission’s Rules of Practice
                                                                                                       and Procedure (18 CFR 385.211 and                         Federal Energy Regulatory
                                                                                                       385.214). Anyone filing a motion to                       Commission
                                                                                                       intervene or protest must serve a copy
                                                                                                       of that document on the Applicant.                        [Docket No. CD19–1–000]
                                                                                                          Notice is hereby given that the
                                                                                                                                                                 Notice of Preliminary Determination of
                                                                                                       deadline for filing protests with regard
                                                                                                                                                                 a Qualifying Conduit Hydropower
                                                                                                       to the applicant’s request for blanket
                                                                                                                                                                 Facility and Soliciting Comments and
                                                 10 The average number of responses per                authorization, under 18 CFR part 34, of
                                                                                                                                                                 Motions To Intervene; Haights Creek
                                              respondent were calculated by dividing the total         future issuances of securities and
                                              number of responses (Column 3) in each category                                                                    Irrigation Company
                                                                                                       assumptions of liability, is November
                                              by the number of responses (Column 1).
                                                 11 The estimated hourly cost (salary plus benefits)
                                                                                                       14, 2018.                                                   On October 12, 2018, the Haights
                                                                                                          The Commission encourages                              Creek Irrigation Company, filed a notice
                                              provided in this section is based on the salary
                                              figures (http://www.bls.gov/oes/current/naics2_
                                                                                                       electronic submission of protests and                     of intent to construct a qualifying
                                              22.htm) and benefits (http://www.bls.gov/                interventions in lieu of paper, using the                 conduit hydropower facility, pursuant
                                              news.release/ecec.nr0.htm) for May 2017 posted by        FERC Online links at http://                              to section 30 of the Federal Power Act
                                              the Bureau of Labor Statistics for the Utilities         www.ferc.gov. To facilitate electronic                    (FPA), as amended by section 4 of the
                                              sector. The hourly estimates for salary plus benefits    service, persons with internet access                     Hydropower Regulatory Efficiency Act
                                              are:                                                     who will eFile a document and/or be                       of 2013 (HREA). The proposed Haights
                                                 Petroleum Engineer (Occupation Code: 17–2171),        listed as a contact for an intervenor                     Creek Micro-Hydropower Project would
                                              $71.62
                                                                                                       must create and validate an                               have a total installed capacity up to 24
                                                 Computer Systems Analyst (Occupation Code:
                                                                                                       eRegistration account using the                           kilowatts (kW), and would be located on
amozie on DSK3GDR082PROD with NOTICES1




                                              15–1121), $67.82
                                                                                                       eRegistration link. Select the eFiling                    the existing Haights Creek Irrigation
                                                 Legal (Occupation Code: 23–0000), $143.68
                                                                                                       link to log on and submit the                             Pipeline. The project would be located
                                                 Economist (Occupation Code: 19–3011), $71.98
                                                 The average hourly cost (salary plus benefits) is
                                                                                                       intervention or protests.                                 near the City of Kaysville in Davis
                                              calculated weighting each of the aforementioned
                                                                                                          Persons unable to file electronically                  County, Utah.
                                              wage categories as follows: $71.62 (0.3) + $143.68       should submit an original and 5 copies                      Applicant Contact: Dan Robinson,
                                              (0.3) + $67.82 (0.15) + $71.98 (0.25) = $92.76. The      of the intervention or protest to the                     Haights Creek Irrigation Company, 820
                                              Commission rounds it to $93/hour.                        Federal Energy Regulatory Commission,                     East 200 North, Kaysville, UT 84037,


                                         VerDate Sep<11>2014   18:06 Oct 30, 2018   Jkt 247001   PO 00000   Frm 00040   Fmt 4703     Sfmt 4703   E:\FR\FM\31OCN1.SGM    31OCN1


                                                                        Federal Register / Vol. 83, No. 211 / Wednesday, October 31, 2018 / Notices                                                     54741

                                              Phone No. (801) 546–4242, email: dan@                   project would consist of: (1) Up to six                 generation of up to 105.42 megawatt-
                                              haightscreek.comcastbiz.                                4-kW turbine-generators connected to an                 hours.
                                                FERC Contact: Robert Bell, Phone No.                  existing irrigation pipeline with a total                 A qualifying conduit hydropower
                                              (202) 502–6062; Email: robert.bell@                     generating capacity of up to 24 kW, and                 facility is one that is determined or
                                              ferc.gov.                                               (2) appurtenant facilities. The proposed
                                                Qualifying Conduit Hydropower                                                                                 deemed to meet all of the criteria shown
                                                                                                      project would have an estimated annual                  in the table below.
                                              Facility Description: The proposed

                                                                               TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                                                                                                                                                      Satisfies
                                                      Statutory provision                                                             Description                                                      (Y/N)

                                              FPA 30(a)(3)(A), as amended             The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar man-                Y
                                                by HREA.                                made water conveyance that is operated for the distribution of water for agricultural, munic-
                                                                                        ipal, or industrial consumption and not primarily for the generation of electricity.
                                              FPA 30(a)(3)(C)(i), as amended          The facility is constructed, operated, or maintained for the generation of electric power and                      Y
                                                by HREA.                                uses for such generation only the hydroelectric potential of a non-federally owned conduit.
                                              FPA 30(a)(3)(C)(ii), as amended         The facility has an installed capacity that does not exceed 5 megawatts .....................................      Y
                                                by HREA.
                                              FPA 30(a)(3)(C)(iii), as amend-         On or before August 9, 2013, the facility is not licensed, or exempted from the licensing re-                      Y
                                                ed by HREA.                            quirements of Part I of the FPA.



                                                 Preliminary Determination: The                       Commission’s regulations.1 All                          3676 or email FERCOnlineSupport@
                                              proposed Haights Creek Micro-                           comments contesting Commission staff’s                  ferc.gov. For TTY, call (202) 502–8659.
                                              Hydropower Project will not interfere                   preliminary determination that the                        Dated: October 25, 2018.
                                              with the primary purpose of the                         facility meets the qualifying criteria                  Kimberly D. Bose,
                                              conduit, which is to transport water for                must set forth their evidentiary basis.
                                                                                                         The Commission strongly encourages                   Secretary.
                                              irrigation by filling an equalizing
                                                                                                      electronic filing. Please file motions to               [FR Doc. 2018–23769 Filed 10–30–18; 8:45 am]
                                              reservoir, which in turn provides
                                              pressure for an irrigation zone in their                intervene and comments using the                        BILLING CODE 6717–01–P

                                              service area. Therefore, based upon the                 Commission’s eFiling system at http://
                                              above criteria, Commission staff                        www.ferc.gov/docs-filing/efiling.asp.
                                              preliminarily determines that the                       Commenters can submit brief comments                    ENVIRONMENTAL PROTECTION
                                              proposal satisfies the requirements for a               up to 6,000 characters, without prior                   AGENCY
                                              qualifying conduit hydropower facility,                 registration, using the eComment system
                                                                                                      at http://www.ferc.gov/docs-filing/                     [EPA–HQ–OECA–2014–0096; FRL–9984–
                                              which is not required to be licensed or                                                                         04–OEI]
                                              exempted from licensing.                                ecomment.asp. You must include your
                                                 Comments and Motions to Intervene:                   name and contact information at the end                 Information Collection Request
                                              Deadline for filing comments contesting                 of your comments. For assistance,                       Submitted to OMB for Review and
                                              whether the facility meets the qualifying               please contact FERC Online Support at                   Approval; Comment Request; NESHAP
                                              criteria is 45 days from the issuance                   FERCOnlineSupport@ferc.gov, (866)                       for Iron and Steel Foundries Area
                                              date of this notice.                                    208–3676 (toll free), or (202) 502–8659                 Sources (Renewal)
                                                 Deadline for filing motions to                       (TTY). In lieu of electronic filing, please
                                                                                                      send a paper copy to: Secretary, Federal                AGENCY: Environmental Protection
                                              intervene is 30 days from the issuance
                                                                                                      Energy Regulatory Commission, 888                       Agency (EPA).
                                              date of this notice.
                                                                                                      First Street NE, Washington, DC 20426.                  ACTION: Notice.
                                                 Anyone may submit comments or a
                                                                                                      A copy of all other filings in reference
                                              motion to intervene in accordance with                                                                          SUMMARY:   The Environmental Protection
                                                                                                      to this application must be accompanied
                                              the requirements of Rules of Practice                                                                           Agency (EPA) has submitted an
                                                                                                      by proof of service on all persons listed
                                              and Procedure, 18 CFR 385.210 and                                                                               information collection request (ICR),
                                                                                                      in the service list prepared by the
                                              385.214. Any motions to intervene must                                                                          NESHAP for Iron and Steel Foundries
                                                                                                      Commission in this proceeding, in
                                              be received on or before the specified                                                                          Area Sources (EPA ICR Number
                                                                                                      accordance with 18 CFR 4.34(b) and
                                              deadline date for the particular                                                                                2267.05, OMB Control number 2060–
                                                                                                      385.2010.
                                              proceeding.                                                Locations of Notice of Intent: Copies                0605), to the Office of Management and
                                                 Filing and Service of Responsive                     of the notice of intent can be obtained                 Budget (OMB) for review and approval
                                              Documents: All filings must (1) bear in                 directly from the applicant or such                     in accordance with the Paperwork
                                              all capital letters the COMMENTS                        copies can be viewed and reproduced at                  Reduction Act. This is a proposed
                                              CONTESTING QUALIFICATION FOR A                          the Commission in its Public Reference                  extension of the ICR, which is currently
                                              CONDUIT HYDROPOWER FACILITY or                          Room, Room 2A, 888 First Street NE,                     approved through November 30, 2018.
                                              MOTION TO INTERVENE, as                                 Washington, DC 20426. The filing may                    Public comments were previously
                                              applicable; (2) state in the heading the                also be viewed on the web at http://                    requested via the Federal Register on
amozie on DSK3GDR082PROD with NOTICES1




                                              name of the applicant and the project                   www.ferc.gov/docs-filing/elibrary.asp                   June 29, 2017 during a 60-day comment
                                              number of the application to which the                  using the eLibrary link. Enter the docket               period. This notice allows for an
                                              filing responds; (3) state the name,                    number (i.e., CD19–1) in the docket                     additional 30 days for public comments.
                                              address, and telephone number of the                    number field to access the document.                    A fuller description of the ICR is given
                                              person filing; and (4) otherwise comply                 For assistance, call toll-free 1–866–208–               below, including its estimated burden
                                              with the requirements of sections                                                                               and cost to the public. An agency may
                                              385.2001 through 385.2005 of the                          1 18   CFR 385.2001–2005 (2018).                      neither conduct nor sponsor, and a


                                         VerDate Sep<11>2014   18:06 Oct 30, 2018   Jkt 247001   PO 00000   Frm 00041   Fmt 4703   Sfmt 4703   E:\FR\FM\31OCN1.SGM    31OCN1



Document Created: 2018-10-31 00:32:40
Document Modified: 2018-10-31 00:32:40
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 54740 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR