83_FR_60574 83 FR 60347 - Geomagnetic Disturbance Reliability Standard; Reliability Standard for Transmission System Planned Performance for Geomagnetic Disturbance Events

83 FR 60347 - Geomagnetic Disturbance Reliability Standard; Reliability Standard for Transmission System Planned Performance for Geomagnetic Disturbance Events

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 227 (November 26, 2018)

Page Range60347-60360
FR Document2018-25678

The Federal Energy Regulatory Commission (Commission) approves Reliability Standard TPL-007-2 (Transmission System Planned Performance for Geomagnetic Disturbance Events). The North American Electric Reliability Corporation (NERC), the Commission-certified Electric Reliability Organization, submitted Reliability Standard TPL- 007-2 for Commission approval. The Commission also directs NERC to develop and submit modifications to Reliability Standard TPL-007-2: To require the development and implementation of corrective action plans to mitigate assessed supplemental GMD event vulnerabilities; and to authorize extensions of time to implement corrective action plans on a case-by-case basis. In addition, the Commission accepts the revised GMD research work plan submitted by NERC.

Federal Register, Volume 83 Issue 227 (Monday, November 26, 2018)
[Federal Register Volume 83, Number 227 (Monday, November 26, 2018)]
[Rules and Regulations]
[Pages 60347-60360]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-25678]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

18 CFR Part 40

[Docket Nos. RM18-8-000 and RM15-11-003; Order No. 851]


Geomagnetic Disturbance Reliability Standard; Reliability 
Standard for Transmission System Planned Performance for Geomagnetic 
Disturbance Events

AGENCY:  Federal Energy Regulatory Commission.

ACTION:  Final rule.

-----------------------------------------------------------------------

SUMMARY:  The Federal Energy Regulatory Commission (Commission) 
approves Reliability Standard TPL-007-2 (Transmission System Planned 
Performance for Geomagnetic Disturbance Events). The North American 
Electric Reliability Corporation (NERC), the Commission-certified 
Electric Reliability Organization, submitted Reliability Standard TPL-
007-2 for Commission approval. The Commission also directs NERC to 
develop and submit modifications to Reliability Standard TPL-007-2: To 
require the development and implementation of corrective action plans 
to mitigate assessed supplemental GMD event vulnerabilities; and to 
authorize extensions of time to implement corrective action plans on a

[[Page 60348]]

case-by-case basis. In addition, the Commission accepts the revised GMD 
research work plan submitted by NERC.

DATES:  This rule will become effective January 25, 2019.

FOR FURTHER INFORMATION CONTACT:.
Michael Gandolfo (Technical Information), Office of Electric 
Reliability, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426, (202) 502-6817, Michael.Gandolfo@ferc.gov.
Matthew Vlissides (Legal Information), Office of the General Counsel, 
Federal Energy Regulatory Commission, 888 First Street NE, Washington, 
DC 20426, (202) 502-8408, Matthew.Vlissides@ferc.gov.

SUPPLEMENTARY INFORMATION: 
    1. Pursuant to section 215 of the Federal Power Act (FPA), the 
Commission approves Reliability Standard TPL-007-2 (Transmission System 
Planned Performance for Geomagnetic Disturbance Events).\1\ The North 
American Electric Reliability Corporation (NERC), the Commission-
certified Electric Reliability Organization (ERO), submitted 
Reliability Standard TPL-007-2 for Commission approval in response to 
directives in Order No. 830.\2\ As discussed in this final rule, we 
determine that Reliability Standard TPL-007-2 better addresses the 
risks posed by geomagnetic disturbances (GMDs) to the Bulk-Power 
System, particularly with respect to the potential impacts of locally-
enhanced GMD events, than currently-effective Reliability Standard TPL-
007-1 and complies with the Commission's directives in Order No. 830.
---------------------------------------------------------------------------

    \1\ 16 U.S.C. 824o.
    \2\ Reliability Standard for Transmission System Planned 
Performance for Geomagnetic Disturbance Events, Order No. 830, 156 
FERC ] 61,215, (2016) reh'g denied, Order No. 830-A, 158 FERC ] 
61,041 (2017).
---------------------------------------------------------------------------

    2. GMD events occur when the sun ejects charged particles that 
interact with and cause changes in the earth's magnetic fields. GMD 
events have the potential to cause severe, wide-spread impacts on the 
Bulk-Power System.\3\ Currently-effective Reliability Standard TPL-007-
1 requires applicable entities to assess the vulnerability of their 
transmission systems to a ``benchmark GMD event.'' An applicable entity 
that does not meet certain performance requirements, based on the 
results of the benchmark GMD vulnerability assessment, must develop and 
implement a corrective action plan to achieve the performance 
requirements.
---------------------------------------------------------------------------

    \3\ Reliability Standards for Geomagnetic Disturbances, Order 
No. 779, 143 FERC ] 61,147, at P 3, reh'g denied, 144 FERC ] 61,113 
(2013); see also Reliability Standard TPL-007-2, Background.
---------------------------------------------------------------------------

    3. The improvements in Reliability Standard TPL-007-2 are 
responsive to the directives in Order No. 830: (1) To revise the 
benchmark GMD event definition, as it pertains to the required GMD 
vulnerability assessments and transformer thermal impact assessments, 
so that the definition is not based solely on spatially-averaged data; 
(2) to require the collection of necessary geomagnetically induced 
current (GIC) monitoring and magnetometer data; and (3) to include a 
one-year deadline for the completion of corrective action plans and 
two- and four-year deadlines to complete mitigation actions involving 
non-hardware and hardware mitigation.\4\ As discussed below, 
Reliability Standard TPL-007-2 complies with these directives and 
improves upon the currently-effective version of the Reliability 
Standard by requiring applicable entities to: (1) In addition to the 
benchmark GMD event requirements, conduct supplemental GMD 
vulnerability assessments and thermal impact assessments, which apply a 
new supplemental GMD event definition that does not rely solely on 
spatially-averaged data; (2) obtain GIC and magnetometer data; and (3) 
meet the Commission-directed deadlines for the development and 
completion of tasks in corrective action plans. Accordingly, pursuant 
to section 215(d)(2) of the FPA, we approve Reliability Standard TPL-
007-2.\5\
---------------------------------------------------------------------------

    \4\ ``Spatial averaging'' refers to the averaging of 
magnetometer readings over a geographic area. In developing the 
benchmark GMD event definition, the standard drafting team averaged 
several (but not all) geomagnetic field readings taken by 
magnetometers located within square geographical areas of 500 km per 
side.
    \5\ 16 U.S.C. 824o(d)(2).
---------------------------------------------------------------------------

    4. In addition, as discussed in the Notice of Proposed Rulemaking, 
we determine that it is appropriate, pursuant to section 215(d)(5) of 
the FPA,\6\ to direct NERC to develop and submit modifications to 
Reliability Standard TPL-007-2 to require the development and 
completion of corrective action plans to mitigate assessed supplemental 
GMD event vulnerabilities.\7\ As discussed below, requiring corrective 
action plans for supplemental GMD event vulnerabilities is appropriate 
to ensure the reliability of the Bulk-Power System when confronted with 
locally-enhanced GMD events, just as corrective action plans are 
necessary to mitigate the effects of benchmark GMD events. Based on the 
record in this proceeding, we discern no technical barriers to either 
developing or complying with such a requirement. Moreover, the record 
supports issuance of a directive at this time notwithstanding comments 
in response to the NOPR advocating postponement of any directive until 
after the completion of additional GMD research. As discussed below, 
the relevant GMD research tasks are scheduled to be completed before 
the modified Reliability Standard must be submitted. The Commission 
directs NERC to submit the modified Reliability Standard for approval 
within 12 months from the effective date of Reliability Standard TPL-
007-2.
---------------------------------------------------------------------------

    \6\ Id. 824o(d)(5).
    \7\ Geomagnetic Disturbance Reliability Standard, Notice of 
Proposed Rulemaking, 83 FR 23854 (May 23, 2018), 163 FERC ] 61,126 
(2018) (NOPR).
---------------------------------------------------------------------------

    5. We also determine that it is appropriate, pursuant to section 
215(d)(5) of the FPA, to direct that NERC modify the provision in 
Reliability Standard TPL-007-2, Requirement R7.4 that allows applicable 
entities to exceed deadlines for completing corrective action plan 
tasks when ``situations beyond the control of the responsible entity 
[arise].'' The NOPR raised concerns regarding the appropriateness of a 
self-executing deadline extension and observed that it was inconsistent 
with guidance in Order No. 830 that extension requests be considered on 
a case-by-case basis.\8\ We recognize the point made in NERC's comments 
in response to the NOPR that, under NERC's proposal, ``NERC and 
Regional Entity staff would exercise their authority to review the 
reasonableness of any Corrective Action Plan delay, including reviewing 
the `situations beyond the control of the responsible entity' that are 
cited as causing the delay'' and that Requirement R7.4 is ``not so 
flexible . . . as to allow entities to extend Corrective Action Plan 
deadlines indefinitely or for any reason whatsoever.'' \9\ While we 
generally agree with the standard of review that NERC states it will 
use to assess the merits of extension requests, we conclude that such 
assessments should be made before any time extensions are permitted. By 
requiring prior approval of extension requests, the modified 
Reliability Standard will limit the potential for unwarranted delays in 
implementing corrective action plans while also providing NERC with an 
advance and more holistic understanding of where, to whom, and for how 
long, extensions are granted. We expect that the extension process 
developed by NERC in response to our directive will be timely and 
efficient such that applicable

[[Page 60349]]

entities will receive prompt responses after submitting to NERC or a 
Regional Entity, as appropriate, the extension request and associated 
information described in Requirement R7.4.\10\ We also direct NERC, as 
proposed in the NOPR, to prepare and submit a report addressing how 
often and why applicable entities are exceeding corrective action plan 
deadlines as well as the disposition of extension requests, which is 
due within 12 months from the date on which applicable entities must 
comply with the last requirement of Reliability Standard TPL-007-2. 
Following receipt of the report, the Commission will determine whether 
further action is necessary.
---------------------------------------------------------------------------

    \8\ Order No. 830, 156 FERC ] 61,215 at P 102.
    \9\ NERC Comments at 20-21.
    \10\ NOPR, 163 FERC ] 61,126 at P 50.
---------------------------------------------------------------------------

    6. The Commission, as discussed below, also accepts the revised GMD 
research work plan submitted by NERC on April 19, 2018.\11\
---------------------------------------------------------------------------

    \11\ North American Electric Reliability Corporation, Filing, 
Docket No. RM15-11-003 (filed Apr. 19, 2018) (Revised GMD Research 
Work Plan).
---------------------------------------------------------------------------

I. Background

A. Section 215 and Mandatory Reliability Standards

    7. Section 215 of the FPA requires the Commission to certify an ERO 
to develop mandatory and enforceable Reliability Standards, subject to 
Commission review and approval. Once approved, the Reliability 
Standards may be enforced in the United States by the ERO, subject to 
Commission oversight, or by the Commission independently.\12\
---------------------------------------------------------------------------

    \12\ 16 U.S.C. 824o(e).
---------------------------------------------------------------------------

B. GMD Primer

    8. GMD events occur when the sun ejects charged particles that 
interact and cause changes in the earth's magnetic fields.\13\ Once a 
solar particle is ejected, it can take between 17 to 96 hours 
(depending on its energy level) to reach earth.\14\ A geoelectric field 
is the electric potential (measured in volts per kilometer (V/km)) on 
the earth's surface and is directly related to the rate of change of 
the magnetic fields.\15\ The geoelectric field has an amplitude and 
direction and acts as a voltage source that can cause GICs to flow on 
long conductors, such as transmission lines.\16\ The magnitude of the 
geoelectric field amplitude is impacted by local factors such as 
geomagnetic latitude and local earth conductivity.\17\ Geomagnetic 
latitude is the proximity to earth's magnetic north and south poles, as 
opposed to earth's geographic poles.\18\ Local earth conductivity is 
the ability of the earth's crust to conduct electricity at a certain 
location to depths of hundreds of kilometers down to the earth's 
mantle. Local earth conductivity impacts the magnitude (i.e., severity) 
of the geoelectric fields that are formed during a GMD event by, all 
else being equal, a lower earth conductivity resulting in higher 
geoelectric fields.\19\
---------------------------------------------------------------------------

    \13\ See NERC, 2012 Special Reliability Assessment Interim 
Report: Effects of Geomagnetic Disturbances on the Bulk Power System 
at i-ii (February 2012).
    \14\ Id. at ii.
    \15\ Id.
    \16\ Id.
    \17\ NERC, Benchmark Geomagnetic Disturbance Event Description, 
Docket No. 15-11-000, at 4 (filed June 28, 2016) (2016 NERC White 
Paper).
    \18\ Id.
    \19\ Id.
---------------------------------------------------------------------------

    9. GICs can flow in an electric power system with varying intensity 
depending on the various factors discussed above. As explained in the 
Background section of Reliability Standard TPL-007-2, ``[d]uring a GMD 
event, geomagnetically[hyphen]induced currents (GIC) may cause 
transformer hot[hyphen]spot heating or damage, loss of Reactive Power 
sources, increased Reactive Power demand, and Misoperation(s), the 
combination of which may result in voltage collapse and blackout.''

C. Currently-Effective Reliability Standard TPL-007-1 and Order No. 830

1. Currently-Effective Reliability Standard TPL-007-1
    10. Reliability Standard TPL-007-1 consists of seven requirements 
and applies to planning coordinators, transmission planners, 
transmission owners and generation owners who own or whose planning 
coordinator area or transmission planning area includes a power 
transformer with a high side, wye-grounded winding connected at 200 kV 
or higher.
    11. Requirement R1 requires planning coordinators and transmission 
planners (i.e., ``responsible entities'') to determine the individual 
and joint responsibilities in the planning coordinator's planning area 
for maintaining models and performing studies needed to complete the 
GMD vulnerability assessment required in Requirement R4. Requirement R2 
requires responsible entities to maintain system models and GIC system 
models needed to complete the GMD vulnerability assessment required in 
Requirement R4. Requirement R3 requires each responsible entity to have 
criteria for acceptable system steady state voltage performance for its 
system during the GMD conditions described in Attachment 1 of 
Reliability Standard TPL-007-1. Requirement R4 requires responsible 
entities to conduct a GMD vulnerability assessment every 60 months 
using the benchmark GMD event described in Attachment 1. Requirement R5 
requires responsible entities to provide GIC flow information, based on 
the benchmark GMD event definition, to be used in the transformer 
thermal impact assessments required in Requirement R6, to each 
transmission owner and generator owner that owns an applicable 
transformer within the applicable planning area. Requirement R6 
requires transmission owners and generator owners to conduct thermal 
impact assessments on solely and jointly owned applicable transformers 
where the maximum effective GIC value provided in Requirement R5 is 75 
Amperes per phase (A/phase) or greater. Requirement R7 requires 
responsible entities to develop corrective action plans if the GMD 
vulnerability assessment concludes that the system does not meet the 
performance requirements in Table 1 of Reliability Standard TPL-007-1.
    12. Calculation of the benchmark GMD event, against which 
applicable entities must assess their facilities, is fundamental to 
compliance with Reliability Standard TPL-007-1. Reliability Standard 
TPL-007-1, Requirement R3 states that ``[e]ach responsible entity, as 
determined in Requirement R1, shall have criteria for acceptable System 
steady state voltage performance for its System during the benchmark 
GMD event described in Attachment 1.''
    13. Reliability Standard TPL-007-1, Attachment 1 states that the 
benchmark GMD event is composed of four elements: (1) A reference peak 
geoelectric field amplitude of 8 V/km derived from statistical analysis 
of historical magnetometer data; (2) a scaling factor to account for 
local geomagnetic latitude; (3) a scaling factor to account for local 
earth conductivity; and (4) a reference geomagnetic field time series 
or wave shape to facilitate time-domain analysis of GMD impact on 
equipment. The product of the first three elements is referred to as 
the regional peak geoelectric field amplitude. The benchmark GMD event 
defines the geoelectric field values used to compute GIC flows for a 
GMD vulnerability assessment, which is required in Reliability Standard 
TPL-007-1.\20\
---------------------------------------------------------------------------

    \20\ See Reliability Standard TPL-007-1, Requirements R4 and R5. 
Reliability Standard TPL-007-1 does not set a threshold amount of 
GIC flow that would constitute a vulnerable transformer. However, if 
a transformer is calculated to experience a maximum effective GIC 
flow during a benchmark GMD event of a least 75 A/phase, a thermal 
impact assessment of that transformer is required. See Reliability 
Standard TPL-007-1, Requirement R6.

---------------------------------------------------------------------------

[[Page 60350]]

    14. For the purpose of determining a benchmark event that specifies 
what severity GMD events a responsible entity must assess for potential 
impacts on the Bulk-Power System, NERC determined that a 1-in-100 year 
GMD event would cause an 8 V/km reference peak geoelectric field 
amplitude at 60 degree north geomagnetic latitude using Qu[eacute]bec's 
earth conductivity.\21\ Scaling factors (i.e., multiplying values) are 
applied to this reference peak geoelectric field amplitude to adjust 
the 8 V/km value for different geomagnetic latitudes (scaling factors 
between 0.1 and 1.0) and earth conductivities (scaling factors between 
0.21 and 1.17). NERC identified a reference geomagnetic field time 
series from an Ottawa, Ontario magnetic observatory during a 1989 GMD 
storm affecting Qu[eacute]bec. NERC used this to estimate a time series 
(i.e., 10-second values over a period of days) of the geoelectric field 
that is representative of what is expected to occur at 60 degree 
geomagnetic latitude during a 1-in-100 year GMD event. Such a time 
series is used in some methods of calculating the vulnerability of a 
transformer to damage from heating caused by GIC.
---------------------------------------------------------------------------

    \21\ NERC used Qu[eacute]bec as the location for the reference 
peak 1-in-100 year GMD event because of its proximity to 60 degree 
geomagnetic latitude and its well understood earth model. By 
creating scaling factors, each entity can scale this reference peak 
geoelectric field and geoelectric field time series values to match 
its own expected field conditions.
---------------------------------------------------------------------------

    15. NERC used field measurements taken from the International 
Monitor for Auroral Geomagnetic Effects (IMAGE) magnetometer chain, 
which consists of 39 magnetometer stations in Northern Europe, for the 
period 1993-2013 to calculate the reference peak geoelectric field 
amplitude. As described in the 2016 NERC White Paper, to arrive at a 
reference peak geoelectric field amplitude of 8 V/km, NERC ``spatially 
averaged'' four different station groups each spanning a square area of 
approximately 500 km (roughly 310 miles) in width.
2. Order No. 830
    16. On January 21, 2015, NERC submitted for Commission approval 
Reliability Standard TPL-007-1 in response to the directive in Order 
No. 779 that NERC develop one or more Reliability Standards to address 
the effects of GMD events on the electric grid.\22\ In Order No. 830, 
the Commission approved Reliability Standard TPL-007-1, concluding that 
Reliability Standard TPL-007-1 addressed the Commission's directive by 
requiring applicable Bulk-Power System owners and operators to conduct, 
on a recurring five-year cycle, initial and ongoing vulnerability 
assessments regarding the potential impact of a benchmark GMD event on 
the Bulk-Power System as a whole and on Bulk-Power System components. 
In addition, the Commission determined that Reliability Standard TPL-
007-1 requires applicable entities to develop and implement corrective 
action plans to mitigate vulnerabilities identified through those 
recurring vulnerability assessments and that potential mitigation 
strategies identified in Reliability Standard TPL-007-1 include, but 
are not limited to, the installation, modification or removal of 
transmission and generation facilities and associated equipment.
---------------------------------------------------------------------------

    \22\ Order No. 779, 144 FERC ] 61,113 at P 54.
---------------------------------------------------------------------------

    17. In Order No. 830, the Commission also determined that 
Reliability Standard TPL-007-1 should be modified. Specifically, Order 
No. 830 directed NERC to develop and submit modifications to 
Reliability Standard TPL-007-1 concerning: (1) The calculation of the 
reference peak geoelectric field amplitude component of the benchmark 
GMD event definition; (2) the collection and public availability of 
necessary GIC monitoring and magnetometer data; and (3) deadlines for 
completing corrective action plans and the mitigation measures called 
for in corrective action plans. Order No. 830 directed NERC to develop 
and submit these revisions for Commission approval within 18 months of 
the effective date of Order No. 830.
    18. With respect to the calculation of the reference peak 
geoelectric field amplitude component of the benchmark GMD event 
definition, Order No. 830 expressed concern with relying solely on 
spatial averaging in Reliability Standard TPL-007-1 because ``the use 
of spatial averaging in this context is new, and thus there is a dearth 
of information or research regarding its application or appropriate 
scale.'' \23\ While Order No. 830 directed that the peak geoelectric 
field amplitude should not be based solely on spatially-averaged data, 
the Commission indicated that this ``directive should not be construed 
to prohibit the use of spatial averaging in some capacity, particularly 
if more research results in a better understanding of how spatial 
averaging can be used to reflect actual GMD events.'' \24\
---------------------------------------------------------------------------

    \23\ Order No. 830, 156 FERC ] 61,215 at P 45.
    \24\ Id. P 46.
---------------------------------------------------------------------------

D. NERC Petition and Reliability Standard TPL-007-2

    19. NERC states that Reliability Standard TPL-007-2 enhances 
currently-effective Reliability Standard TPL-007-1 by addressing 
reliability risks posed by GMDs more effectively and implementing the 
directives in Order No. 830.\25\ NERC asserts that Reliability Standard 
TPL-007-2 reflects the latest in GMD understanding and provides a 
technically sound and flexible approach to addressing the concerns 
discussed in Order No. 830. NERC contends that the proposed 
modifications enhance reliability by expanding GMD vulnerability 
assessments to include severe, localized impacts and by implementing 
deadlines and processes to maintain accountability in the development, 
completion, and revision of corrective action plans developed to 
address identified vulnerabilities. Further, NERC states that the 
proposed modifications improve the availability of GMD monitoring data 
that may be used to inform GMD vulnerability assessments.
---------------------------------------------------------------------------

    \25\ Reliability Standard TPL-007-2 is not attached to this 
final rule. Reliability Standard TPL-007-2 is available on the 
Commission's eLibrary document retrieval system in Docket No. RM18-
8-000 and on the NERC website, www.nerc.com.
---------------------------------------------------------------------------

    20. Reliability Standard TPL-007-2 modifies currently-effective 
Reliability Standard TPL-007-1 by requiring applicable entities to: (1) 
Conduct supplemental GMD vulnerability and transformer thermal impact 
assessments in addition to the existing benchmark GMD vulnerability and 
transformer thermal impact assessments required in Reliability Standard 
TPL-007-1; (2) collect data from GIC monitors and magnetometers as 
necessary to enable model validation and situational awareness; and (3) 
develop necessary corrective action plans within one year from the 
completion of the benchmark GMD vulnerability assessment, include a 
two-year deadline for the implementation of non-hardware mitigation, 
and include a four-year deadline to complete hardware mitigation.\26\
---------------------------------------------------------------------------

    \26\ Unless otherwise indicated, the requirements of Reliability 
Standard TPL-007-2 are substantively the same as the requirements in 
currently-effective Reliability Standard TPL-007-1.
---------------------------------------------------------------------------

    21. In particular, Reliability Standard TPL-007-2 modifies 
Requirements R1 (identification of responsibilities), R2 (system and 
GIC system models) and R3 (criteria for acceptable System steady state) 
to extend the existing requirements pertaining to benchmark GMD 
assessments to the new supplemental GMD assessments.

[[Page 60351]]

Reliability Standard TPL-007-2 adds the newly mandated supplemental GMD 
vulnerability and transformer thermal impact assessments in new 
Requirements R8 (supplemental GMD vulnerability assessment), R9 (GIC 
flow information needed for supplemental GMD thermal impact 
assessments) and R10 (supplemental GMD thermal impact assessments). The 
supplemental GMD event definition contains a higher, non-spatially-
averaged reference peak geoelectric field amplitude component than the 
benchmark GMD event definition (12 V/km versus 8 V/km). These three new 
requirements largely mirror existing Requirements R4, R5, and R6 that 
currently apply, and continue to apply, only to benchmark GMD 
vulnerability and transformer thermal impact assessments.\27\
---------------------------------------------------------------------------

    \27\ An exception is the qualifying threshold for transformers 
required to undergo thermal impact assessments: For the supplemental 
GMD assessment the qualifying threshold for transformers is a 
maximum effective GIC value of 85 A/phase while the threshold for 
benchmark GMD event assessments is 75 A/phase.
---------------------------------------------------------------------------

    22. In addition, Reliability Standard TPL-007-2 includes two other 
new requirements, Requirements R11 and R12, that require applicable 
entities to gather GIC monitoring data (Requirement R11) and 
magnetometer data (Requirement R12).
    23. Reliability Standard TPL-007-2 modifies existing Requirement R7 
(corrective action plans) to create a one-year deadline for the 
development of corrective action plans and two and four-year deadlines 
to complete actions involving non-hardware and hardware mitigation, 
respectively, for vulnerabilities identified in the benchmark GMD 
assessment. The modifications to Requirement R7 include a provision 
allowing for extension of deadlines if ``situations beyond the control 
of the responsible entity determined in Requirement R1 prevent 
implementation of the [corrective action plan] within the timetable for 
implementation.''

E. NOPR

    24. On May 17, 2018, the Commission issued a NOPR that proposed to 
approve Reliability Standard TPL-007-2 as the Reliability Standard 
largely addresses the directives in Order No. 830. However, the NOPR 
identified two aspects of Reliability Standard TPL-007-2 that are 
inconsistent with Order No. 830: (1) The lack of any requirement to 
develop and implement corrective action plans in response to assessed 
supplemental GMD event vulnerabilities; and (2) a general allowance, 
per proposed Requirement R7.4, of extensions of time to complete 
corrective action plans as opposed to permitting extensions of time on 
a case-by-case basis.
    25. Having identified these issues, the NOPR proposed to direct 
NERC, pursuant to section 215(d)(5) of the FPA, to develop and submit 
modifications to Reliability Standard TPL-007-2 to require applicable 
entities to develop and implement corrective action plans to mitigate 
vulnerabilities discovered through supplemental GMD vulnerability 
assessments. The NOPR proposed to direct NERC to submit the modified 
Reliability Standard for approval within 12 months from the effective 
date of Reliability Standard TPL-007-2. The NOPR also sought comment on 
two options for addressing the Commission's concerns regarding the 
potential for undue delay of mitigation because of the proposed time-
extension process in Requirement R7.4: (1) Direct NERC to bring 
Reliability Standard TPL-007-2 into alignment with Order No. 830 
through a process whereby NERC or Regional Entities consider extensions 
on a case-by-case basis using the information that must be submitted 
under Requirement R7.4; or (2) approve the proposed provision without 
directing modifications. Under either option, NERC would prepare and 
submit a report regarding how often and why applicable entities are 
exceeding corrective action plan deadlines following implementation of 
Reliability Standard TPL-007-2.\28\
---------------------------------------------------------------------------

    \28\ The NOPR proposed that the report, under the first option, 
would also include statistics describing how often extension 
requests were granted.
---------------------------------------------------------------------------

    26. The Commission received NOPR comments from nine entities. We 
address below the issues raised in the NOPR and comments as well as 
NERC's revised GMD research work plan and the comments submitted in 
response. The Appendix to this final rule lists the entities that filed 
comments in both matters.

II. Discussion

    27. Pursuant to section 215(d)(2) of the FPA, the Commission 
approves Reliability Standard TPL-007-2 as just, reasonable, not unduly 
discriminatory or preferential, and in the public interest. We conclude 
that Reliability Standard TPL-007-2 is an improvement over currently-
effective Reliability Standard TPL-007-1 and responds to the directives 
in Order No. 830: (1) To revise the benchmark GMD event definition, as 
it pertains to the required GMD Vulnerability Assessments and 
transformer thermal impact assessments, so that the definition is not 
based solely on spatially-averaged data; (2) to require the collection 
of necessary GIC monitoring and magnetometer data; and (3) to include a 
one-year deadline for the completion of corrective action plans and two 
and four-year deadlines to complete mitigation actions involving non-
hardware and hardware mitigation, respectively.\29\
---------------------------------------------------------------------------

    \29\ In its petition, NERC stated that it would address the 
directive in Order No. 830 on the collection of GIC monitoring and 
magnetometer data through a forthcoming NERC data request to 
applicable entities pursuant to Section 1600 of the NERC Rules of 
Procedure rather than through a Reliability Standard requirement. 
NERC Petition at 27. On February 7, 2018, NERC released a draft data 
request for a 45-day comment period. The NERC Board of Trustees 
(BOT) subsequently approved the GMD data request at the August 2018 
BOT meeting.
---------------------------------------------------------------------------

    28. Reliability Standard TPL-007-2 complies with the directives in 
Order No. 830 by requiring, in addition to the benchmark GMD event 
vulnerability and thermal impact assessments, supplemental GMD 
vulnerability and thermal impact assessments. The supplemental GMD 
event definition in Reliability Standard TPL-007-2 contains a non-
spatially-averaged reference peak geoelectric field amplitude component 
of 12 V/km, in contrast to the 8 V/km figure in the spatially-averaged 
benchmark GMD event definition. As NERC explains in its petition, the 
supplemental GMD event will be used to ``represent conditions 
associated with localized enhancement of the geomagnetic field during a 
severe GMD event for use in assessing GMD impacts.'' \30\ Reliability 
Standard TPL-007-2 therefore addresses the Commission's directive to 
modify currently-effective Reliability Standard TPL-007-1 so that the 
benchmark GMD event does not rely solely on spatially-averaged data to 
calculate the reference peak geoelectric field amplitude.
---------------------------------------------------------------------------

    \30\ NERC Petition at 12.
---------------------------------------------------------------------------

    29. As proposed in the NOPR, pursuant to section 215(d)(5) of the 
FPA, we also determine that it is appropriate to direct NERC to develop 
and submit modifications to Reliability Standard TPL-007-2 to require 
the development and completion of corrective action plans to mitigate 
assessed supplemental GMD event vulnerabilities. Given that NERC has 
acknowledged the potential for ``severe, localized impacts'' associated 
with supplemental GMD event vulnerabilities, we see no basis for 
requiring corrective action plans for benchmark GMD events but not for

[[Page 60352]]

supplemental GMD events.\31\ Based on the record in this proceeding, 
there appear to be no technical barriers to developing or complying 
with such a requirement. Moreover, as discussed below, the record 
supports issuance of a directive at this time, notwithstanding NOPR 
comments advocating postponement of any directive until after the 
completion of additional GMD research, because relevant GMD research is 
scheduled to be completed before the due date for submitting a modified 
Reliability Standard. The Commission therefore adopts the NOPR proposal 
and directs NERC to submit the modified Reliability Standard for 
approval within 12 months from the effective date of Reliability 
Standard TPL-007-2.
---------------------------------------------------------------------------

    \31\ NERC Petition at 4 (``these revisions would enhance 
reliability by expanding GMD Vulnerability Assessments to include 
severe, localized impacts and by implementing new deadlines and 
processes to maintain accountability in the development, completion, 
and revision of entity Corrective Action Plans developed to address 
identified vulnerabilities'').
---------------------------------------------------------------------------

    30. We also determine, pursuant to section 215(d)(5) of the FPA, 
that it is appropriate to direct that NERC develop further 
modifications to Reliability Standard TPL-007-2, Requirement R7.4. 
Under NERC's proposal, applicable entities are allowed, without prior 
approval, to exceed deadlines for completing corrective action plan 
tasks when ``situations beyond the control of the responsible entity 
[arise].'' \32\ Instead, as discussed below, we direct NERC to develop 
a timely and efficient process, consistent with the Commission's 
guidance in Order No. 830, to consider time extension requests on a 
case-by-case basis. Our directive balances the availability of time 
extensions when applicable entities are presented with the types of 
uncontrollable delays identified in NERC's petition and NOPR comments 
with the need to ensure that the mitigation of known GMD 
vulnerabilities is not being improperly delayed through such requests. 
Further, as proposed in the NOPR, we direct NERC to prepare and submit 
a report addressing how often and why applicable entities are exceeding 
corrective action plan deadlines as well as the disposition of time 
extension requests. The report is due within 12 months from the date on 
which applicable entities must comply with the last requirement of 
Reliability Standard TPL-007-2. Following receipt of the report, the 
Commission will determine whether further action is necessary.
---------------------------------------------------------------------------

    \32\ In the Supplemental Material section of Reliability 
Standard TPL-007-2, examples of situations beyond the control of the 
of the responsible entity include, but are not limited to, delays 
resulting from regulatory/legal processes, such as permitting; 
delays resulting from stakeholder processes required by tariff; 
delays resulting from equipment lead times; or delays resulting from 
the inability to acquire necessary Right-of-Way.
---------------------------------------------------------------------------

    31. The Commission, as discussed below, also accepts the revised 
GMD research work plan submitted by NERC on April 19, 2018.

A. Corrective Action Plan for Supplemental GMD Event Vulnerabilities 
NOPR

    32. The NOPR proposed to determine that the absence of a 
requirement to mitigate assessed supplemental GMD event vulnerabilities 
is inconsistent with Order No. 830, and Order No. 779, because the 
proposal does not require ``owners and operators [to] develop and 
implement a plan to protect against instability, uncontrolled 
separation, or cascading failures of the Bulk-Power System.'' \33\
---------------------------------------------------------------------------

    \33\ NOPR, 163 FERC ] 61,126 at P 32.
---------------------------------------------------------------------------

    33. The NOPR explained that the Commission was not persuaded by 
NERC's justification that technical limitations--specifically the small 
number of observations used to define the supplemental GMD event and 
the availability of modeling tools to assist entities in assessing 
vulnerabilities--make requiring mitigation premature at this time.\34\ 
The NOPR, instead, accepted NERC's statement that the supplemental GMD 
event definition ``provides a technically justified method of assessing 
vulnerabilities to the localized peak effects of severe GMD events.'' 
\35\ The NOPR also observed that mitigation of supplemental GMD event 
vulnerabilities is appropriate because Reliability Standard TPL-007-2: 
(1) Does not prescribe how applicable entities must perform such 
studies, and thus may incorporate any uncertainties regarding the 
geographic size of such events into their studies; (2) there are 
commercially-available tools that could allow for modeling of 
supplemental GMD events; and (3) other methods could be used within the 
framework of the Reliability Standard to study planning areas (e.g., 
superposition or sensitivity studies) in conjunction with other power 
system modeling tools. The NOPR further recognized that research tasks 
under way pursuant to the GMD research work plan that are relevant to 
the supplemental GMD event definition are scheduled to be completed in 
2019 and the results of such research should inform the work of the 
standard drafting team.
---------------------------------------------------------------------------

    \34\ The Commission also rejected the assertion in NERC's 
petition that an evaluation of possible actions for supplemental GMD 
events that result in Cascading is similar to the treatment of 
extreme events in Reliability Standard TPL-001-4 (Transmission 
System Planning Performance Requirements).
    \35\ NOPR, 163 FERC ] 61,126 at P 35 (quoting NERC Petition at 
13).
---------------------------------------------------------------------------

Comments
    34. NERC does not support the proposed directive. NERC maintains 
that the provision in Requirement R8.3 that requires applicable 
entities to evaluate possible actions designed to reduce the likelihood 
or mitigate the adverse impacts of a supplemental GMD event ``is not 
merely advisory, but rather supports a range of potential mitigating 
actions, such as additional hardware mitigation, operating procedures, 
or other resilience actions to enhance recovery and restoration.'' \36\ 
NERC expounds on this by noting that the requirement to consider 
mitigation in Reliability Standard TPL-007-2 ``would directly support 
mitigation that is required by [Reliability Standard EOP-010-1].'' \37\ 
NERC also contends that it ``anticipates that the Corrective Action 
Plans, when needed to address performance requirements for the 
benchmark GMD event, will also provide a large degree of protection to 
the Bulk-Power System for events with locally-enhanced geomagnetic 
fields.'' \38\
---------------------------------------------------------------------------

    \36\ NERC Comments at 9.
    \37\ Id. at 10.
    \38\ Id. at 11.
---------------------------------------------------------------------------

    35. NERC's comments reiterate the rationale in its petition that 
requiring mitigation ``would result in the de facto replacement of the 
benchmark GMD event with the proposed supplemental GMD event.'' \39\ 
NERC maintains that ``while the supplemental GMD event is strongly 
supported by data and analysis in ways that mirror the benchmark GMD 
event, there are aspects of it that are less definitive than the 
benchmark GMD event and less appropriate as the basis of requiring 
Corrective Action Plans.'' \40\ NERC also claims that the uncertainty 
of geographic size of the supplemental GMD event could not be addressed 
adequately by sensitivity analysis or through other methods because 
there are ``inherent sources of modeling uncertainty (e.g., earth 
conductivity model, substation grounding grid resistance values, 
transformer thermal and magnetic response models) . . . [and] 
introducing additional variables

[[Page 60353]]

for sensitivity analysis, such as the size of the localized 
enhancement, may not improve the accuracy of GMD Vulnerability 
Assessments.'' \41\ NERC further states that ``commercially-available 
modeling tools now advertise capabilities that could be used to model 
localized GMD enhancements, [but] to NERC's knowledge these 
capabilities have not been used extensively by planners, nor have the 
different software tools been benchmarked for consistency in results.'' 
\42\
---------------------------------------------------------------------------

    \39\ Id. at 11-12; see also id. at 14 (``many entities would 
likely employ the most conservative approach for conducting 
supplemental GMD Vulnerability Assessments, which would be to apply 
extreme peak values uniformly over an entire planning area'').
    \40\ Id. at 13.
    \41\ Id. at 15.
    \42\ Id.
---------------------------------------------------------------------------

    36. NERC contends that completing the GMD work plan is a better 
alternative to the NOPR directive. Moreover, NERC states that it 
``commits to initiate a review of TPL-007-2 following the completion of 
the GMD Research Work Plan to evaluate whether the standard continues 
to be supported by the available knowledge or whether additional 
refinements are necessary . . . [which] could result in modifications 
to, or additional support for, the proposed supplemental GMD event, and 
thereby inform what the TPL-007 standard should require in terms of 
mitigation based on supplemental GMD Vulnerability Assessments.'' \43\ 
In response to the NOPR's statement that the results of the GMD 
research work plan may inform the work of the standard drafting team 
tasked with carrying out the Commission's proposed directive, NERC 
comments state that ``it expects that the last of the project's 
deliverables will be ready by early 2020 . . . [but] [a]ny scientific 
research project schedule, however, must account for the possibility 
that additional time may be needed to explore potential findings or 
amend project approaches to provide more useful results.'' \44\ NERC 
states that while the technical report for Task 1 is scheduled to be 
completed by the fourth quarter of 2019 according to the revised GMD 
research work plan, NERC estimates that it will file a report with the 
Commission, after allowing a period of public comment, six months later 
(i.e., mid-2020).\45\
---------------------------------------------------------------------------

    \43\ Id. at 18.
    \44\ Id. at 17.
    \45\ Revised GMD Research Work Plan at 5 (``NERC expects to 
submit [informational filings with the Commission] approximately six 
months following EPRI's completion of the associated technical 
report(s)''); id., Attachment 1 (Order No. 830 GMD Research Work 
Plan (April 2018)) at 7 (identifying ``Q4 2019'' as the estimated 
completion date of ``Final technical report to provide additional 
technical support for the existing supplementary (localized) 
benchmark; or, propose update to the benchmark, as appropriate'').
---------------------------------------------------------------------------

    37. Trade Associations, Idaho Power, NE ISO, TVA and BPA do not 
support the proposed directive. They contend that requiring corrective 
action plans for supplemental GMD event vulnerabilities: (1) May be 
premature given the limited data regarding localized GMD events; (2) 
would address low-probability events that are unlikely to affect a wide 
area; and (3) could impose costs on applicable entities that outweigh 
the potential benefits of such a directive. Like NERC, these commenters 
support completing the GMD research work plan before considering 
mandating corrective action plans for supplemental GMD event 
vulnerabilities. Idaho Power, moreover, contends that it would be 
better for registered entities to gain experience with corrective 
action plans for benchmark GMD events before mandating corrective 
action plans for supplemental GMD events. Trade Associations state that 
instead of the NOPR directive, any Commission directive should be 
limited to requiring NERC to develop ``a study of the mitigation 
measures deployed and the effectiveness of these measures to mitigate 
benchmark GMD events before mandating mitigation measures on more 
localized events.'' \46\ Similarly, BPA maintains that instead of the 
NOPR directive, in order to assess the costs and benefits of requiring 
corrective action plans for supplemental GMD events, the Commission 
should require NERC to file periodic reports on supplemental GMD events 
and the possible actions to mitigate them.
---------------------------------------------------------------------------

    \46\ Trade Associations Comments at 12.
---------------------------------------------------------------------------

    38. Resilient Societies and Reclamation support the NOPR directive. 
Reclamation states, and Resilient Societies concurs, that ``[a]n 
exercise to only identify vulnerabilities arising from localized GMD 
events is not a cost-effective use of resources unless accompanied by 
activities to mitigate the identified vulnerabilities.'' \47\
---------------------------------------------------------------------------

    \47\ Reclamation Comments at 1; Resilient Societies Comments at 
3.
---------------------------------------------------------------------------

Commission Determination
    39. Pursuant to section 215(d)(5) of the FPA, the Commission adopts 
the NOPR proposal and directs NERC to develop and submit modifications 
to Reliability Standard TPL-007-2 to require corrective action plans 
for assessed supplemental GMD event vulnerabilities. While Reliability 
Standard TPL-007-2 requires applicable entities to assess supplemental 
GMD event vulnerabilities, it does not require corrective action plans 
to address assessed vulnerabilities. Instead, Reliability Standard TPL-
007-2, Requirement R8.3 only requires applicable entities to make ``an 
evaluation of possible actions to reduce the likelihood or mitigate the 
consequences and adverse impacts of the events if a supplemental GMD 
event is assessed to result in Cascading.'' As the Commission observed 
in the NOPR, NERC's proposal differs significantly from Order No. 830 
because the intent of the directive was not only to identify 
vulnerabilities arising from localized GMD events but also to mitigate 
such vulnerabilities.
    40. The comments opposing the NOPR directive offer two rationales 
for approving Reliability Standard TPL-007-2 without directing 
modifications at this time: (1) Reliability Standard TPL-007-2 provides 
sufficient protection against supplemental GMD event vulnerabilities; 
and (2) requiring mitigation of supplemental GMD events is premature at 
this time.
    41. With respect to the first rationale, NERC observes that the 
provision requiring applicable entities to consider supplemental GMD 
event mitigation is not ``merely advisory.'' However, there is no 
dispute that an applicable entity must ``consider'' mitigation under 
Reliability Standard TPL-007-2. What is significant is that after 
having done so, an applicable entity has no obligation under 
Reliability Standard TPL-007-2 to implement mitigation even if the 
applicable entity ``considered'' mitigation necessary to address an 
assessed supplemental GMD event vulnerability.
    42. NERC also maintains that Reliability Standard EOP-010-1 
requires transmission operators to ``develop, maintain, and implement a 
GMD Operating Procedure or Operating Process to mitigate the effects of 
GMD events on the reliable operation of its respective system.'' And in 
Order No. 779, the Commission determined that ``while the development 
of the required mitigation plan [for benchmark GMD event 
vulnerabilities] cannot be limited to considering operational 
procedures or enhanced training alone, operational procedures and 
enhanced training may be sufficient if that is verified by the 
vulnerability assessments.'' \48\ Again, NERC's point does not resolve 
the Commission's concern because Reliability Standard EOP-010-1 does 
not ensure mitigation of all supplemental GMD event vulnerabilities 
assessed under Reliability Standard TPL-007-2. That is because: (1) 
Reliability Standard EOP-010-1 applies, in relevant part, only to

[[Page 60354]]

transmission operators (viz., it does not apply to other applicable 
entity types, such as planning coordinators, transmission planners and 
generator owners, subject to Reliability Standard TPL-007-2); and (2) 
Reliability Standard EOP-010-1 does not require mitigation if the 
supplemental GMD event vulnerability cannot be addressed through 
operational procedures or enhanced training alone. Thus, Reliability 
Standard EOP-010-1 does not ensure satisfactory mitigation or provide 
an adequate substitute for mitigation as contemplated in Order No. 830.
---------------------------------------------------------------------------

    \48\ Order No. 779, 143 FERC ] 61,147 at P 83.
---------------------------------------------------------------------------

    43. In addition, NERC asserts that the required mitigation of 
benchmark GMD event vulnerabilities could also address supplemental GMD 
event vulnerabilities. Of course that may occur in some circumstances, 
but that is not a substitute for requiring mitigation to the extent 
that benchmark GMD event mitigation does not completely address a 
supplemental GMD event vulnerability. Under Reliability Standard TPL-
007-2 there is currently no requirement to mitigate the remaining 
vulnerability to the Bulk-Power System.
    44. Regarding the second rationale in the NOPR comments, NERC and 
other commenters reiterate the assertion in NERC's petition that it 
would be premature, from a technical standpoint, to require corrective 
action plans to address supplemental GMD event vulnerabilities. As 
reflected in the comment summary, these commenters instead request that 
NERC complete the GMD research work plan and then produce a report that 
assesses the possible need for modifications to Reliability Standard 
TPL-007-2.
    45. The NOPR discussed how a standard drafting team could use new 
information gathered through the GMD research work plan to develop a 
modified Reliability Standard. The Commission noted that Task 1 of the 
GMD research work plan (Further Analyze Spatial Averaging Used in the 
Benchmark GMD Event), which encompasses localized GMD event research, 
would be delivered in 2019 according to the most recent version of the 
GMD research work plan (i.e., the revised GMD research work plan). The 
NOPR stated that ``[s]uch GMD research on localized events should 
inform the standard development process and aid applicable entities 
when implementing a modified Reliability Standard.'' \49\ While we 
appreciate that the informational filing for Task 1 may not be 
submitted to the Commission prior to the deadline for submitting a 
modified Reliability Standard, the underlying research in Task 1 is 
scheduled to be completed before then. As such, the standard drafting 
team and personnel working on the GMD research work plan could operate 
in parallel and share information to ensure that research relevant to 
the Commission's directive is incorporated into the modified 
Reliability Standard. Thus we are not persuaded by the comments seeking 
a delay of our directive.
---------------------------------------------------------------------------

    \49\ NOPR, 163 FERC ] 61,126 at P 39.
---------------------------------------------------------------------------

    46. We are not persuaded by the other points raised by commenters 
to support their assertion that requiring corrective action plans is 
premature. First, NERC assumes that under such a requirement ``many'' 
applicable entities will adopt a ``conservative approach'' and use the 
supplemental GMD event definition in all GMD vulnerability assessments, 
thus effectively supplanting the benchmark GMD event definition. NERC 
bases this assumption on the standard drafting team's ``extensive 
experience in system planning and the relative immaturity of tools and 
methods for modeling localized enhancements.'' \50\ NERC acknowledges 
the discussion in the NOPR on how uncertainties regarding the 
supplemental GMD event definition--in particular the geographic size of 
localized events--are ameliorated by the flexibility afforded by 
Reliability Standard TPL-007-2. Specifically, Reliability Standard TPL-
007-2 permits applicable entities to apply the supplemental GMD event 
definition to an entire planning area or any subset of a planning area. 
However, NERC asserts that even with this flexibility, at least some 
applicable entities would default to using the supplemental GMD event 
definition in an overly-broad manner. Notwithstanding NERC's assertion, 
nothing in Reliability Standard TPL-007-2 requires applicable entities 
to apply the supplemental GMD event definition to an entire planning 
area or otherwise supplant the benchmark GMD event definition.
---------------------------------------------------------------------------

    \50\ NERC Comments at 14.
---------------------------------------------------------------------------

    47. With respect to the statement in the NOPR that modeling tools 
are currently available to support corrective action plans, NERC admits 
that ``some commercially-available modeling tools now advertise 
capabilities that could be used to model localized GMD enhancements.'' 
\51\ However, NERC contends that to its ``knowledge these capabilities 
have not been used extensively by planners, nor have the different 
software tools been benchmarked for consistency in result.'' \52\ Given 
that GMDs have only recently been addressed in the Reliability 
Standards and there is currently no requirement to model and assess, 
let alone mitigate, localized GMD events, it is not unexpected that 
these modeling tools have not been used extensively for that purpose. 
Moreover, NERC does not assert that existing tools are incapable of 
performing the desired modeling function.\53\ Thus, NERC's objections 
on this point are not persuasive.
---------------------------------------------------------------------------

    \51\ Id. at 15.
    \52\ Id. at 15-16.
    \53\ See also Trade Associations Comments at 8 (``Although 
current tools are available to model localized events, we understand 
that such modeling will require significant time as the processes 
involved are still largely manual, making it difficult to develop 
accurate, system-wide models that appropriately consider the 
localized impacts of the supplemental GMD event.'').
---------------------------------------------------------------------------

    48. NERC does not offer support for its comment in response to the 
NOPR's observation that sensitivity analysis can serve, among other 
methods, as a method to refine the geographic scope of localized GMD 
impacts on planning areas. NERC responds that it ``does not believe 
that concerns regarding the uncertainty of the geographic size of the 
supplemental GMD event could be addressed adequately by sensitivity 
analysis or though other methods in planning studies.'' \54\ NERC 
claims there are already inherent sources of modeling uncertainty and 
that introducing another variable, such as the size of the localized 
enhancement, ``may not improve the accuracy of the GMD Vulnerability 
Analysis.'' \55\ And yet NERC's concern implies that the benchmark GMD 
event contains a geographic domain that does not itself inject 
uncertainties. However, as the Commission stated in Order No. 830, the 
geographic area for spatial averaging in the benchmark GMD event 
definition is itself a ``subjective'' figure.\56\ Indeed, in Order No. 
830, as part of the GMD research work plan directive, to address the 
uncertainties surrounding the geographic scale of spatial averaging, 
the Commission directed that NERC should ``further analyze the area 
over which spatial averaging should be calculated for stability 
studies, including performing sensitivity analyses on squares less than 
500 km per side (e.g., 100 km, 200 km),'' which NERC is addressing in 
Task 1.\57\ As

[[Page 60355]]

such, we see no basis, technical or otherwise, for not requiring 
corrective action plans for assessed supplemental GMD event 
vulnerabilities while requiring corrective action plans for assessed 
benchmark GMD event vulnerabilities consistent with the Commission's 
directions in Order Nos. 779 and 830. Accordingly, the Commission is 
not persuaded by the arguments of NERC and other commenters for the 
reasons discussed above, and directs that NERC develop modifications to 
Reliability Standard TPL-007-2 to require corrective action plans for 
assessed supplemental GMD event vulnerabilities.
---------------------------------------------------------------------------

    \54\ NERC Comments at 15.
    \55\ Id.
    \56\ Order No. 830, 156 FERC ] 61,215 at P 45 (quoting 
Pulkkinen, A., Bernabeu, E., Eichner, J., Viljanen, A., Ngwira, C., 
``Regional-Scale High-Latitude Extreme Geoelectric Fields Pertaining 
to Geomagnetically Induced Currents,'' Earth, Planets and Space at 2 
(June 19, 2015)).
    \57\ Id. P 26; see also revised GMD Research Work Plan (Task 1) 
at 6 (``further analyze the area over which spatial averaging should 
be used in stability studies and transformer thermal assessments by 
performing GIC analysis on squares less than 500 km per side (e.g., 
100 km, 200 km) and using the results to perform power flow and 
transformer thermal assessments'').
---------------------------------------------------------------------------

B. Corrective Action Plan Deadline Extensions

NOPR
    49. The NOPR stated that Requirement R7.4 of Reliability Standard 
TPL-007-2 differs from Order No. 830 by allowing applicable entities to 
``revise'' or ``update'' corrective action plans to extend deadlines. 
This provision contrasts with the guidance in Order No. 830 that ``NERC 
should consider extensions of time on a case-by-case basis.'' While 
agreeing that there should be a mechanism for allowing extensions of 
corrective action plan implementation deadlines, the NOPR expressed 
concern with unnecessary delays in implementing protection against GMD 
threats.
    50. The NOPR identified two options for addressing Requirement 
R7.4. Under the first option, the Commission would, pursuant to section 
215(d)(5) of the FPA, direct NERC to modify Reliability Standard TPL-
007-2 to comport with Order No. 830, by requiring that NERC and the 
Regional Entities, as appropriate, consider requests for extension of 
time on a case-by-case basis. Under this option, responsible entities 
seeking an extension would submit the information required by 
Requirement R7.4 to NERC and the Regional Entities for their 
consideration of the request. The Commission would also direct NERC to 
prepare and submit a report addressing the disposition of any such 
requests, as well as information regarding how often and why applicable 
entities are exceeding corrective action plan deadlines following 
implementation of Reliability Standard TPL-007-2. Under such a 
directive, NERC would submit the report within 12 months from the date 
on which applicable entities must comply with the last requirement of 
Reliability Standard TPL-007-2. Following receipt of the report, the 
Commission would determine whether further action is necessary. Under 
the second option, the Commission would approve proposed Requirement 
R7.4 but also direct NERC to prepare and submit the report described in 
the first option (without the statistics on disposition). Following 
receipt of the report, the Commission would determine whether further 
action is necessary.
Comments
    51. NERC supports the second option in the NOPR. NERC contends that 
Reliability Standard TPL-007-2 ``provides clarity and certainty 
regarding when an entity may extend a Corrective Action Plan mitigation 
deadline and what steps must be followed to maintain accountability and 
thus compliance with the standard.'' \58\ NERC also maintains that the 
proposal ``avoids the administrative burden, uncertainty, and further 
delay that could be associated with implementing a new ERO adjudication 
process, such as one that would be dedicated to evaluating GMD 
Corrective Action Plan deadline extensions on a case-by-case basis. '' 
\59\ To address concerns regarding the possible abuse of deadline 
extensions, NERC states that as ``part of the compliance monitoring and 
enforcement activities for the proposed standard, NERC and Regional 
Entity staff would exercise their authority to review the 
reasonableness of any Corrective Action Plan delay, including reviewing 
the `situations beyond the control of the responsible entity' that are 
cited as causing the delay.'' \60\ As noted in the Supplemental 
Material section of Reliability Standard TPL-007-2, NERC explains that 
examples of such situations include ``lengthy legal or regulatory 
processes, stakeholder processes required by tariff, or long equipment 
lead times.'' \61\ NERC, moreover, ``agrees that a report describing 
the results of NERC's monitoring of this provision could provide useful 
information . . . [and] therefore commits to prepare and submit to the 
Commission a report that describes how often and the reasons why 
entities in the United States are exceeding Corrective Action Plan 
deadlines.'' \62\
---------------------------------------------------------------------------

    \58\ NERC Comments at 20.
    \59\ Id.
    \60\ Id. at 20-21.
    \61\ Id. at 20.
    \62\ Id. at 22.
---------------------------------------------------------------------------

    52. Trade Associations, BPA, ISO NE, Idaho Power, and TVA support 
the second option and echo the rationale for adopting the second option 
in NERC's comments. Trade Associations explain that while they 
previously supported a case-by-case exception process, they now believe 
NERC's proposal to be more efficient and effective. Trade Associations 
contend that a case-by-case approach would ``only increase 
administrative tasks for NERC and applicable entities . . . [and] would 
further delay any actions to mitigate rather than expedite the approval 
process.'' \63\ Trade Associations also maintain that Reliability 
Standard TPL-007-2 ``will not delay mitigation because this requirement 
is only applicable if circumstances are beyond the entity's control.'' 
\64\
---------------------------------------------------------------------------

    \63\ Trade Associations Comments at 13.
    \64\ Id.
---------------------------------------------------------------------------

    53. Reclamation does not appear to support modifying Requirement R7 
to institute a case-by-case time extension process. However, 
Reclamation comments that the sub-requirement in Requirement R7.4.1 
requiring documentation of reasons for delaying corrective action plans 
should be eliminated because it ``is merely a compliance exercise and 
does not improve Bulk Electric System reliability.'' Reclamation makes 
the same contention regarding the sub-requirement in Requirement R7.4.2 
that a revised corrective action plan describe the original corrective 
action plan.
Commission Determination
    54. Reliability Standard TPL-007-2, Requirement R7.4 differs from 
Order No. 830 by allowing applicable entities, under certain 
conditions, to extend corrective action plan implementation deadlines 
without prior approval. This conflicts with the Commission's guidance 
in Order No. 830 that, using its compliance discretion, ``NERC should 
consider extensions of time on a case-by-case basis.'' \65\ Based on 
our consideration of the record, we believe that the case-by-case 
review process contemplated by Order No. 830 is the appropriate means 
for considering extension requests. Accordingly, pursuant to section 
215(d)(5) of the FPA, we direct that NERC develop modifications to 
Reliability Standard TPL-007-2 to replace the time-extension provision 
in Requirement R7.4 with a process through which extensions of time are 
considered on a case-by-case basis.
---------------------------------------------------------------------------

    \65\ Order No. 830, 156 FERC ] 61,215 at P 102.
---------------------------------------------------------------------------

    55. At the outset, we note that the extension process in 
Requirement R7.4

[[Page 60356]]

applies only to the implementation of corrective action plans and not 
to the development of corrective action plans.\66\ NERC and other 
commenters supportive of the second option in the NOPR urge approval of 
Requirement R7.4 without modification largely because of the perceived 
uncertainty and burden associated with treating extension requests on a 
case-by-case basis. While it is true that granting extensions on a 
case-by-case basis involves more uncertainty and potential burdens 
versus the automatic extension of time afforded by Requirement R7.4, we 
must weigh this against the potential for abuse of Requirement R7.4 to 
unduly delay mitigation, as well as the delayed visibility that NERC 
would have into the deployment of needed GMD protections. Presented 
with these competing concerns, we conclude that the imperative to 
address known GMD vulnerabilities in a timely manner, and without 
unwarranted delays, is more compelling. We recognize that applicable 
entities that have a legitimate need for extensions require timely 
responses from NERC and Regional Entities, as appropriate. Accordingly, 
we expect that the extension process developed by NERC in response to 
our directive will be timely and efficient such that applicable 
entities will receive prompt responses after submitting to NERC or a 
Regional Entity, as appropriate, the extension request and associated 
information described in Requirement R7.4.\67\
---------------------------------------------------------------------------

    \66\ Reliability Standard TPL-007-2, Requirement R7.4 (``[t]he 
[corrective action plan] shall . . . [b]e revised if situations 
beyond the control of the responsible entity . . . prevent 
implementation of the [corrective action plan] within the timetable 
for implementation'').
    \67\ NOPR, 163 FERC ] 61,126 at P 50.
---------------------------------------------------------------------------

    56. In reaching our determination on this issue, we considered 
NERC's NOPR comments, which attempted to address the concerns with 
Requirement R7.4 expressed in the NOPR, stating that NERC and Regional 
Entity compliance and enforcement staff will review the reasonableness 
of any delay in implementing corrective action plans, including 
reviewing the asserted ``situations beyond the control of the 
responsible entity'' cited by the applicable entity, and by citing 
specific examples of the types of delays that might justify the 
invocation of Requirement R7.4. NERC's comments also characterized 
Requirement R7.4 as being ``not so flexible . . . as to allow entities 
to extend Corrective Action Plan deadlines indefinitely or for any 
reason whatsoever.'' \68\ We generally agree with the standard of 
review that NERC indicates it will use to determine whether an 
extension of time to implement a corrective action plan is appropriate. 
However, the assessment of whether an extension of time is warranted is 
more appropriately made before an applicable entity is permitted to 
delay mitigation of a known GMD vulnerability. While NERC indicates 
that under proposed Requirement R7.4 there are compliance consequences 
for improperly delaying mitigation, mitigation of a known GMD 
vulnerability will nonetheless have been delayed, and we conclude it is 
important that any proposed delay be reviewed ahead of time. Therefore, 
we direct NERC to modify Reliability Standard TPL-007-2, Requirement 
R7.4 to develop a timely and efficient process, consistent with the 
Commission's guidance in Order No. 830, to consider time extension 
requests on a case-by-case basis.
---------------------------------------------------------------------------

    \68\ NERC Comments at 20.
---------------------------------------------------------------------------

    57. We disagree with Reclamation's comment regarding Requirement 
R7.4.1, which requires a description of the circumstances necessitating 
mitigation delays, because it is at odds with NERC's NOPR comments, 
discussed above, in which NERC states that NERC and Regional Entities 
will review the reasons for delaying mitigation. Contrary to 
Reclamation's assertion that this requirement is ``merely a 
documentation exercise and does not improve [bulk electric system] 
reliability,'' unreasonable delays of mitigation could harm bulk 
electric system reliability by leaving it vulnerable to GMDs. Moreover, 
Requirement R7.4.2, also opposed by Reclamation, requiring that revised 
corrective action plans describe the original and previous revisions, 
provides compliance enforcement authorities with a revision history of 
the corrective action plan in a single document, thus facilitating 
compliance review.

C. Other Issues Raised in NOPR Comments

    58. Resilient Societies' comments raise three issues not addressed 
in the NOPR. First, Resilient Societies maintains that transformers 
that experience an estimated GIC above 15 A/phase should be subject to 
mandatory corrective action plans and the Commission should ``encourage 
owner-operators and their research partners to develop `Corrective 
Action Plans' for both [extra high voltage] transformers and for 
associated generation stations, even if these long replacement-time 
systems experience overstress at levels significantly below 75 amps per 
phase.'' Second, Resilient Societies states that the Commission should 
encourage best practices by industry beyond the mandatory requirements 
of the Reliability Standards, including allowing cost recovery for such 
practices. Third, Resilient Societies states that the Commission should 
address combined GMD and electromagnetic pulse (EMP) protection.
    59. In Order No. 830, the Commission approved the 75 A/phase 
threshold in Reliability Standard TPL-007-1 based on the record and 
despite objections from certain commenters. The Commission, however, 
directed further study of this issue as part of the GMD research work 
plan. Resilient Societies' comments provide no new basis for revisiting 
this issue at this time. Moreover, as reflected in the NOPR proposal, 
NERC has adequately supported the 85 A/phase threshold proposed in 
Reliability Standard TPL-007-2 for the supplemental GMD event analysis. 
However, new information resulting from the GMD research work plan will 
also be relevant to this higher threshold. We will consider such 
research at the appropriate time.
    60. In Order No. 830, the Commission stated that ``cost recovery 
for prudent costs associated with or incurred to comply with 
Reliability Standard TPL-007-1 and future revisions to the Reliability 
Standard will be available to registered entities.'' \69\ It is 
therefore beyond the scope of this proceeding to determine, as a 
general matter, whether voluntary measures beyond those required to 
comply with the governing Reliability Standards are eligible for cost 
recovery. That said, jurisdictional entities may of course pursue such 
voluntary measures, and the Commission would consider appropriate cost 
recovery for those investments through a formula rate or other rate 
proceeding.
---------------------------------------------------------------------------

    \69\ Order No. 830, 156 FERC ] 61,215 at P 24.
---------------------------------------------------------------------------

    61. The Commission in previous orders has indicated that the 
Commission's GMD proceedings are not directed to EMPs and thus 
Resilient Societies' comments on EMP are out-of-scope.\70\
---------------------------------------------------------------------------

    \70\ See, e.g., Order No. 830, 156 FERC ] 61,215 at P 119.
---------------------------------------------------------------------------

D. Revised GMD Research Work Plan

    62. On April 19, 2018, NERC submitted a revised GMD research work 
plan in response to a Commission order issued on October 19, 2017.\71\ 
In the October 19 Order, the Commission accepted the initial GMD 
research work

[[Page 60357]]

plan filed by NERC on May 30, 2017. The Commission also directed NERC 
to file a final GMD research work plan within six months and ensure 
that the final GMD research work plan included a reevaluation of 
reliance on single station readings when adjusting for latitude as part 
of the benchmark GMD event definition. At NERC's request, the October 
19 Order also provided guidance on how NERC should prioritize the tasks 
in the GMD research work plan.
---------------------------------------------------------------------------

    \71\ Reliability Standard for Transmission System Planned 
Performance for Geomagnetic Disturbance Events, 161 FERC ] 61,048 
(2017) (October 19 Order).
---------------------------------------------------------------------------

    63. Bardin and Resilient Societies submitted comments in response 
to the revised GMD research work plan, which largely focused on a 
request for combined research on GMDs and EMPs. As discussed above, 
however, EMPs are outside the scope of the Commission's directive 
regarding GMD research. Resilient Societies also submitted comments 
criticizing aspects of five tasks in the revised GMD research work 
plan. With respect to Tasks 1, 2, 8 and 9, Resilient Societies' 
criticism is based on the contention that the ``real-world data'' will 
not be used to verify models. For example, Resilient Societies contends 
that NERC will not use ``real-world'' GIC data to validate spatial 
averaging (Task 1) or latitude scaling (Task 2). These assertions, 
however, are refuted by the revised GMD research work plan. The revised 
GMD research work plan indicates that the research on spatial averaging 
includes an analysis of ``a large number (10-20) of localized extreme 
events and collection of both ground-based and space-based data around 
the times of these events.'' \72\ For latitude scaling, the revised GMD 
research work plan states that NERC will evaluate the scaling factor 
``using existing models and developing new models to extrapolate, from 
historical data, the potential scaling of a 1-in-100 year GMD event on 
lower geomagnetic latitudes.'' \73\ In addition, NERC indicates that 
the data gathered through the Section 1600 data request ``will help 
validate various models used in calculating GIC's and assessing their 
impacts in data systems.'' \74\
---------------------------------------------------------------------------

    \72\ Revised GMD Research Work Plan, Attachment 1 (Order No. 830 
GMD Research Work Plan (April 2018)) at 2.
    \73\ Id. at 8.
    \74\ Id. at 19.
---------------------------------------------------------------------------

    64. Resilient Societies other comments are directed to an alleged 
lack of specificity, granularity or ``scientific assurance'' in the 
testing described in Tasks 5, 8 and 9 of the revised GMD research work 
plan. These criticisms are misplaced as they demand an unreasonable 
degree of detail in the revised GMD research work plan. For example, 
regarding Task 5, NERC states that it will ``validate[e] existing 
transformer tools with all data that is presently available and with 
upcoming field/laboratory test results.'' \75\ Resilient Societies, 
however, contends unpersuasively that ``NERC neglects to specify `all 
data that is presently available' . . . and the number of transformers 
to be employed in `upcoming field laboratory test results' and also 
neglects to disclose details of the test protocols to be used.'' \76\ 
Regarding harmonics (Tasks 8 and 9), Task 9 specifically includes 
``tank vibration measurements,'' not just simulations.\77\ Moreover, 
Task 8 (Improving Harmonic Analysis Capabilities) is intended to 
develop more basic information than some of the other tasks in the 
revised GMD research work plan where industry has more knowledge. As 
with all of the revised GMD research work plan tasks (with the 
exception of Task 6, which deals with the Section 1600 data request), 
NERC will submit a report to the Commission on its findings.
---------------------------------------------------------------------------

    \75\ Id. at 17.
    \76\ Resilient Societies Comments on Revised GMD Research Work 
Plan at 11.
    \77\ Id. at 25.
---------------------------------------------------------------------------

    65. As the revised GMD research work plan complies with Order No. 
830 and the Commission's October 19 Order, we accept the revised GMD 
research work plan.

III. Information Collection Statement

    66. The collection of information contained in this final rule is 
subject to review by the Office of Management and Budget (OMB) under 
section 3507(d) of the Paperwork Reduction Act of 1995.\78\ OMB's 
regulations require review and approval of certain information 
collection requirements imposed by agency rules.\79\ Upon approval of a 
collection of information, OMB will assign an OMB control number and an 
expiration date. Respondents subject to the information collection 
requirements of a rule will not be penalized for failing to respond to 
the collection of information unless the collection of information 
displays a valid OMB control number.
---------------------------------------------------------------------------

    \78\ 44 U.S.C. 3507(d).
    \79\ 5 CFR part 1320 (2018).
---------------------------------------------------------------------------

    67. In the NOPR, the Commission solicited comments on the need for 
this information, whether the information will have practical utility, 
the accuracy of the burden estimates, ways to enhance the quality, 
utility, and clarity of the information to be collected or retained, 
and any suggested methods for minimizing respondents' burden, including 
the use of automated information techniques. Specifically, the 
Commission asked that any revised burden or cost estimates submitted by 
commenters be supported by sufficient detail to understand how the 
estimates were generated. The Commission did not receive any comments 
regarding the Commission's burden estimates.
    68. The Commission approves Reliability Standard TPL-007-2, which 
replaces currently-effective Reliability Standard TPL-007-1. When 
compared to Reliability Standard TPL-007-1, Reliability Standard TPL-
007-2 maintains the current information collection requirements, 
modifies existing Requirements R1 through R7 and adds new requirements 
in Requirements R8 through R12.
    69. Reliability Standard TPL-007-2 includes new corrective action 
plan development and implementation deadlines in Requirement R7, new 
supplemental GMD vulnerability and transformer thermal impact 
assessments in Requirements R8 through R10, and requirements for 
applicable entities to gather magnetometer and GIC monitored data in 
Requirements R11 and R12. Deadlines in Requirement R7 for the 
development and implementation of corrective action plans would only 
change the timeline of such documentation and are not expected to 
revise the burden to applicable entities. The burden estimates for new 
Requirements R8 through R10 are expected to be similar to the burden 
estimates for Requirements R4 through R6 in currently-effective 
Reliability Standard TPL-007-1 due to the closely-mirrored 
requirements.\80\ The Commission expects that only 25 percent or fewer 
of transmission owners and generator owners would have to complete a 
supplemental transformer thermal impact assessment per Requirement R10. 
Requirements R11 and R12 require applicable entities to have a process 
to collect GIC and magnetometer data from meters in planning 
coordinator planning areas.
---------------------------------------------------------------------------

    \80\ NERC Petition at 14-17.
---------------------------------------------------------------------------

    Public Reporting Burden: The burden and cost estimates below are 
based on the changes to the reporting and recordkeeping burden imposed 
by Reliability Standard TPL-007-2. Our estimates for the number of 
respondents are based on the NERC Compliance Registry as of March 3, 
2018, which indicates there are 183 entities registered as transmission 
planner (TP), 65 planning coordinators (PC), 330 transmission owners 
(TO), 944 generator owners (GO) within the United States. However, due 
to significant overlap, the

[[Page 60358]]

total number of unique affected entities (i.e., entities registered as 
a transmission planner, planning coordinator, transmission owner or 
generator owner, or some combination of these functional entities) is 
1,130 entities. This includes 188 entities that are registered as a 
transmission planner or planning coordinator (applicability for 
Requirements R7 to R9 and R11 to R12), and 1,119 entities registered as 
a transmission or generation owner (applicability for Requirement R10). 
Given the assumption above, there is an expectation that at most only 
25 percent of the 1,119 entities (or 280 entities) will have to 
complete compliance activities for Requirement R10. The estimated 
burden and cost are as follow.\81\
---------------------------------------------------------------------------

    \81\ Hourly costs are based on the Bureau of Labor Statistics 
(BLS) figures for May 2017 (Sector 22, Utilities) for wages (https://www.bls.gov/oes/current/naics2_22.htm) and benefits for December 
2017 (https://www.bls.gov/news.release/ecec.nr0.htm). We estimate 
that an Electrical Engineer (NAICS code 17-2071) would perform the 
functions associated with reporting requirements, at an average 
hourly cost (for wages and benefits) of $66.90 The functions 
associated with recordkeeping requirements, we estimate, would be 
performed by a File Clerk (NAICS code 43-4071) at an average hourly 
cost of $32.04 for wages and benefits.
    The estimated burden and cost are in addition to the burden and 
cost that are associated with the existing requirements in 
Reliability Standard TPL-007-1 (and in the current OMB-approved 
inventory), which would continue under Reliability Standard TPL-007-
2.
    The requirements for NERC to provide reports to the Commission 
and to develop and submit modifications to Reliability Standard TPL-
007-2 are already covered under FERC-725 (OMB Control No. 1902-
0225).

                                             FERC-725N, Changes Due to Final Rule in Docket No. RM18-8 82 83
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                                                     Total annual
                                                      Annual number of     Total number of      Average burden       burden hrs. &         Cost per
        Requirement (R)          Number and type of     responses per      responses  (1) x     hrs. & cost per   total  annual cost    respondent ($)
                                  respondents  (1)     respondent  (2)        (2) = (3)          response  (4)      (rounded)  (3) x       (5) / (1)
                                                                                                                       (4) = (5)
--------------------------------------------------------------------------------------------------------------------------------------------------------
R1 through R6 \84\.............  No change.........  No change.........  No change..........  No change.........  No change.........  No change
R7.............................  188 (PC and TP)...  1/5 (once for       37.6...............  Rep. 5 hrs.,        Rep. 188 hrs.,      Rep. 1 hr.,
                                                      every five year                          $334.50; RK 5       $12,577; RK 188     $66.90; RK 1 hr.,
                                                      study).                                  hrs., $160.20.      hrs., $6,023.       $32.04
R8.............................  188 (PC and TP)...  1/5 (once for       37.6...............  Rep., 27 hrs.,      Rep. 1,015 hrs.,    Rep., 5.4 hrs.,
                                                      every five year                          $1,806.30; RK, 21   $67,917; RK 790     $361.26; RK 4.2
                                                      study).                                  hrs., $672.84.      hrs., $25,299.      hrs., $134.57
R9.............................  188 (PC and TP)...  1/5 (once for       37.6...............  Rep. 9 hrs.,        Rep. 338 hrs.,      Rep. 1.8 hrs.,
                                                      every five year                          $602.10; RK 7       $22,639; RK 263     $120.42; RK 1.4
                                                      study).                                  hrs., $224.28.      hrs., $8,432.       hrs., $44.85
R10............................  280 (25% of 1,119)  1/5 (once for       56.................  Rep. 22 hrs.,       Rep. 1,232 hrs.,    Rep. 4.4 hrs.,
                                  (GO and TO).        every five year                          $1,471.80; RK 18    $82,421; RK 1,008   $294.36; RK 3.6
                                                      study).                                  hrs., $576.72.      hrs., $32,296.      hrs., $115.34
R11............................  188 (PC and TP)...  1 (on-going         188................  Rep. 10 hrs.,       Rep. 1,880 hrs.,    Rep. 10 hrs.,
                                                      reporting).                              $669; RK. 10        $125,772; RK        $669; RK 10 hrs.,
                                                                                               hrs., $320.40.      1,880 hrs.,         $320.40
                                                                                                                   $60,235.
R12............................  188 (PC and TP)...  1 (on-going         188................  Rep. 10 hrs.,       Rep. 1,880 hrs.     Rep. 10 hrs.,
                                                      reporting).                              $669; RK. 10        $125,772; RK        $669; RK 10 hrs.,
                                                                                               hrs., 320.40.       1,880 hrs.,         $320.40
                                                                                                                   $60,235.
Total Additional Hrs. and Cost   ..................  ..................  ...................  ..................  Rep., 6,533 hrs.,   ..................
 (rounded), due to Final Rule                                                                                      $437,057; RK
 in RM18-8.                                                                                                        6,009 hrs.,
                                                                                                                   $192,528.
--------------------------------------------------------------------------------------------------------------------------------------------------------

    Title: FERC-725N, Mandatory Reliability Standards: TPL Reliability 
Standards
---------------------------------------------------------------------------

    \82\ Rep.=reporting requirements; RK-recordkeeping requirements 
(Evidence Retention).
    \83\ For each Reliability Standard, the Measure shows the 
acceptable evidence (Reporting Requirement) for the associated 
Requirement (R numbers), and the Compliance section details the 
related Recordkeeping Requirement.
    \84\ While Reliability Standard TPL-007-2 extends the 
requirements in existing Reliability Standard TPL-007-1, 
Requirements R1 through R3 to the newly required supplemental GMD 
event analyses, the obligation to conduct the supplemental GMD event 
analyses is found in Reliability Standard TPL-007-2, Requirements R8 
through R10.
---------------------------------------------------------------------------

    Action: Revisions to an existing collection of information
    OMB Control No: 1902-0264
    Respondents: Business or other for profit, and not for profit 
institutions.
    Frequency of Responses: \85\ Every five years (for Requirement R7-
R10), annually (for Requirement R11 and R12), and ongoing.
---------------------------------------------------------------------------

    \85\ The frequency of Requirements R1 through R6 in Reliability 
Standard TPL-007-2 is unchanged from the existing requirements in 
Reliability Standard TPL-007-1.
---------------------------------------------------------------------------

    Necessity of the Information: Reliability Standard TPL-007-2 
implements the Congressional mandate of the Energy Policy Act of 2005 
to develop mandatory and enforceable Reliability Standards to better 
ensure the reliability of the nation's Bulk-Power System. Specifically, 
these requirements address the threat posed by GMD events to the Bulk-
Power System and conform to the Commission's directives to modify 
Reliability Standard TPL-007-1 as directed in Order No. 830.
    Internal review: The Commission has reviewed Reliability Standard 
TPL-007-2, and made a determination that its action is necessary to 
implement section 215 of the FPA. The Commission has assured itself, by 
means of its internal review, that there is specific, objective support 
for the burden estimates associated with the information requirements.
    70. Interested persons may obtain information on the reporting 
requirements by contacting the Federal Energy Regulatory Commission, 
Office of the Executive Director, 888 First Street NE, Washington, DC 
20426

[[Page 60359]]

[Attention: Ellen Brown, email: DataClearance@ferc.gov, phone: (202) 
502-8663, fax: (202) 273-0873].
    71. Comments concerning the collection of information and the 
associated burden estimate should be sent to the Commission in this 
docket and may also be sent to the Office of Information and Regulatory 
Affairs, Office of Management and Budget, 725 17th Street NW, 
Washington, DC 20503 [Attention: Desk Officer for the Federal Energy 
Regulatory Commission]. Due to security concerns, comments should be 
sent electronically to the following email address: 
oira_submission@omb.eop.gov. Comments submitted to OMB should refer to 
FERC-725N and OMB Control No. 1902-0264.

IV. Environmental Analysis

    72. The Commission is required to prepare an Environmental 
Assessment or an Environmental Impact Statement for any action that may 
have a significant adverse effect on the human environment.\86\ The 
Commission has categorically excluded certain actions from this 
requirement as not having a significant effect on the human 
environment. Included in the exclusion are rules that are clarifying, 
corrective, or procedural or that do not substantially change the 
effect of the regulations being amended.\87\ The actions here fall 
within this categorical exclusion in the Commission's regulations.
---------------------------------------------------------------------------

    \86\ Regulations Implementing the National Environmental Policy 
Act of 1969, Order No. 486, FERC Stats. & Regs. ] 30,783 (1987) 
(cross-referenced at 41 FERC ] 61,284).
    \87\ 18 CFR 380.4(a)(2)(ii) (2018).
---------------------------------------------------------------------------

V. Regulatory Flexibility Act

    73. The Regulatory Flexibility Act of 1980 (RFA) \88\ generally 
requires a description and analysis of proposed rules that will have 
significant economic impact on a substantial number of small entities. 
The definition of small business is provided by the Small Business 
Administration (SBA) at 13 CFR 121.201. The threshold for a small 
utility (using SBA's sub-sector 221) is based on the number of 
employees for a concern and its affiliates. As discussed above, 
Reliability Standard TPL-007-2 applies to a total of 1,130 unique 
planning coordinators, transmission planners, transmission owners, and 
generation owners.\89\ A small utility (and its affiliates) is defined 
as having no more than the following number of employees:
---------------------------------------------------------------------------

    \88\ 5 U.S.C. 601-12.
    \89\ In the NERC Registry, there are approximately 65 PCs, 188 
TPs, 944 GOs, and 330 TOs (in the United States), which will be 
affected by this final rule. Because some entities serve in more 
than one role, these figures involve some double counting.
---------------------------------------------------------------------------

     For planning coordinators, transmission planners, and 
transmission owners (NAICS code 221121, Electric Bulk Power 
Transmission and Control), a maximum of 500 employees
     for generator owners, a maximum of 750 employees.\90\
---------------------------------------------------------------------------

    \90\ The maximum number of employees for a generator owner (and 
its affiliates) to be ``small'' varies from 250 to 750 employees, 
depending on the type of generation (e.g., hydroelectric, nuclear, 
fossil fuel, wind). For this analysis, we use the most conservative 
threshold of 750 employees.
---------------------------------------------------------------------------

    74. As estimated in the NOPR, the total cost to all entities (large 
and small) is $629,585 annually (or an average of $1,345.27 for each of 
the estimated 468 entities affected annually). For the estimated 280 
generator owners and transmission owners affected annually, the average 
cost would be $409.70 per year. For the estimated 188 planning 
coordinators and transmission planners, the estimated average annual 
cost would be $2,738.84. The estimated annual cost to each affected 
entity varies from $409.70 to $2,738.84 and is not considered 
significant. The Commission did not receive any comments regarding 
these burden and cost estimates.
    75. Accordingly, the Commission certifies that this final rule will 
not have a significant economic impact on a substantial number of small 
entities.

VI. Document Availability

    76. In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through FERC's Home Page (http://www.ferc.gov) and in FERC's 
Public Reference Room during normal business hours (8:30 a.m. to 5:00 
p.m. Eastern time) at 888 First Street NE, Room 2A, Washington DC 
20426.
    77. From FERC's Home Page on the internet, this information is 
available on eLibrary. The full text of this document is available on 
eLibrary in PDF and Microsoft Word format for viewing, printing, and/or 
downloading. To access this document in eLibrary, type the docket 
number excluding the last three digits of this document in the docket 
number field.
    78. User assistance is available for eLibrary and the FERC's 
website during normal business hours from FERC Online Support at (202) 
502-6652 (toll free at 1-866-208-3676) or email at 
ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502-
8371, TTY (202)502-8659. Email the Public Reference Room at 
public.referenceroom@ferc.gov.

VII. Effective Date and Congressional Notification

    These regulations are effective January 25, 2019. The Commission 
has determined, with the concurrence of the Administrator of the Office 
of Information and Regulatory Affairs of OMB that this rule is not a 
``major rule'' as defined in section 351 of the Small Business 
Regulatory Enforcement Fairness Act of 1996. The rule will be provided 
to the Senate, House, Government Accountability Office, and the SBA.

    By the Commission. Commissioner McIntyre is not voting on this 
order.
    Issued: November 15, 2018.
Kimberly D. Bose,
Secretary.

    Note:  The following appendix will not appear in the Code of 
Federal Regulations.


                      APPENDIX--List of Commenters
------------------------------------------------------------------------
           Abbreviation                           Commenter
------------------------------------------------------------------------
Bardin............................  David Bardin.
BPA...............................  Bonneville Power Administration.
Idaho Power.......................  Idaho Power Company.
ISO NE............................  ISO New England Inc.
NERC..............................  North American Electric Reliability
                                     Corporation.
Reclamation.......................  Bureau of Reclamation.
Resilient Societies...............  Foundation for Resilient Societies.
Trade Associations................  American Public Power Association,
                                     Edison Electric Institute,
                                     Electricity Consumers Resource
                                     Council, Large Public Power
                                     Council, National Rural Electric
                                     Cooperative Association.
TVA...............................  Tennessee Valley Authority.
------------------------------------------------------------------------


[[Page 60360]]

[FR Doc. 2018-25678 Filed 11-23-18; 8:45 am]
BILLING CODE 6717-01-P



                      Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations                                              60347

     and is committed to considering other                   published in the Federal Register on                   Operators must cap cost-based
     meritorious requests for relief.                        March 6, 2018. Order No. 841 amended                   incremental energy offers at $2,000/
     [FR Doc. 2018–25602 Filed 11–23–18; 8:45 am]            18 CFR 35.28(g) by adding a further new                MWh. The actual or expected costs
     BILLING CODE 6351–01–P                                  paragraph, which was also numbered                     underlying a resource’s cost-based
                                                             (g)(9).4 As a result, the regulatory text              incremental energy offer above $1,000/
                                                             adopted in Order No. 841 incorrectly                   MWh must be verified before that offer
     DEPARTMENT OF ENERGY                                    replaced—rather than added to—the                      can be used for purposes of calculating
                                                             regulatory text adopted in Order Nos.                  Locational Marginal Prices. If a resource
     Federal Energy Regulatory                               831 and 831–A.                                         submits an incremental energy offer
     Commission                                                 4. In this Correcting Amendment, 18                 above $1,000/MWh and the actual or
                                                             CFR 35.28(g) is corrected by restoring                 expected costs underlying that offer
     18 CFR Part 35                                          the regulatory text from Order Nos. 831                cannot be verified before the market
     [Docket Nos. RM16–5–000; RM16–5–001;                    and 831–A as new paragraph 18 CFR                      clearing process begins, that offer may
     RM16–23–000; AD16–20–000]                               35.28(g)(11). Nothing in this Correcting               not be used to calculate Locational
                                                             Amendment is intended to alter any                     Marginal Prices and the resource would
     Non-Discriminatory Open Access                          previous compliance requirements or                    be eligible for a make-whole payment if
     Transmission Tariff; Corrections                        effective dates established under Order                that resource is dispatched and the
                                                             Nos. 831, 831–A, or 841, nor does this                 resource’s actual costs are verified after-
     AGENCY:  Federal Energy Regulatory
                                                             Correcting Amendment affect any tariff                 the-fact. A resource would also be
     Commission, Department of Energy.
                                                             changes previously accepted by the                     eligible for a make-whole payment if it
     ACTION: Correcting amendment.                           Commission in compliance with these                    is dispatched and its verified cost-based
     SUMMARY:   This document corrects one                   orders.                                                incremental energy offer exceeds
     section of the regulations of the Federal                                                                      $2,000/MWh. All resources, regardless
                                                             List of Subjects in 18 CFR Part 35
     Energy Regulatory Commission, as                                                                               of type, are eligible to submit cost-based
     published in the Federal Register on                       Electric power rates, Electric utilities,           incremental energy offers in excess of
     March 6, 2018. This correction restores                 Non-discriminatory open access                         $1,000/MWh.
     regulatory text that was inadvertently                  transmission tariffs.                                  [FR Doc. 2018–25584 Filed 11–23–18; 8:45 am]
     replaced with other regulatory text                       By the Commission. Commissioner                      BILLING CODE 6717–01–P
     adopted in another, later final rule.                   McIntyre is not voting on this order.
     DATES: Effective November 26, 2018.                       Issued: November 16, 2018.
     FOR FURTHER INFORMATION CONTACT:                        Kimberly D. Bose,                                      DEPARTMENT OF ENERGY
     Anne Marie Hirschberger, Office of the                  Secretary.
                                                                                                                    Federal Energy Regulatory
     General Counsel, Federal Energy                           In consideration of the foregoing, 18                Commission
     Regulatory Commission, 888 First Street                 CFR part 35 is corrected by making the
     NE, Washington, DC 20426, (202) 502–                    following correcting amendments:                       18 CFR Part 40
     8387, annemarie.hirschberger@ferc.gov.
     SUPPLEMENTARY INFORMATION:                              PART 35—FILING OF RATE                                 [Docket Nos. RM18–8–000 and RM15–11–
                                                             SCHEDULES AND TARIFFS                                  003; Order No. 851]
     I. Background
        1. On November 17, 2016, the Federal                 ■ 1. The authority citation for part 35                Geomagnetic Disturbance Reliability
     Energy Regulatory Commission                            continues to read as follows:                          Standard; Reliability Standard for
     (Commission) issued Order No. 831                                                                              Transmission System Planned
                                                               Authority: 16 U.S.C. 791a–825r, 2601–
     concerning offer caps in Regional                                                                              Performance for Geomagnetic
                                                             2645; 31 U.S.C. 9701; 42 U.S.C. 7101–7352.
     Transmission Organization (RTO) and                                                                            Disturbance Events
                                                             ■ 2. Amend § 35.28 by adding a new
     Independent System Operator (ISO)                                                                              AGENCY:  Federal Energy Regulatory
                                                             paragraph (g)(11) to read as follows:
     markets,1 which was published in the                                                                           Commission.
     Federal Register on December 5, 2016.                   § 35.28 Non-discriminatory open access                 ACTION: Final rule.
     Order No. 831 amended 18 CFR 35.28                      transmission tariff.
     by adding new paragraph (g)(9).                         *     *    *     *    *                                SUMMARY:   The Federal Energy
        2. On November 9, 2017, the                            (g) * * *                                            Regulatory Commission (Commission)
     Commission issued Order No. 831–A,2                       (11) A resource’s incremental energy                 approves Reliability Standard TPL–007–
     which was published in the Federal                      offer must be capped at the higher of                  2 (Transmission System Planned
     Register on November 16, 2017. Order                    $1,000/MWh or that resource’s cost-                    Performance for Geomagnetic
     No. 831–A further revised 18 CFR                        based incremental energy offer. For the                Disturbance Events). The North
     35.28(g)(9) regarding offer caps.                       purpose of calculating Locational                      American Electric Reliability
        3. On February 15, 2018, the                         Marginal Prices, Regional Transmission                 Corporation (NERC), the Commission-
     Commission issued Order No. 841                         Organizations and Independent System                   certified Electric Reliability
     concerning electric storage participation                                                                      Organization, submitted Reliability
     in RTO/ISO markets,3 which was                          and Independent System Operators, Order No. 841,       Standard TPL–007–2 for Commission
                                                             83 FR 9580 (Mar. 6, 2018), FERC Stats. & Regs. ¶       approval. The Commission also directs
       1 Offer Caps in Markets Operated by Regional          31,398 (2018) (cross-referenced at 162 FERC ¶          NERC to develop and submit
     Transmission Organizations and Independent              61,127).
     System Operators, Order No. 831, FERC Stats. &            4 On February 28, 2018, the Commission issued        modifications to Reliability Standard
     Regs. ¶ 31,387 (2016) (cross-referenced at 157 FERC     an Errata Notice for Order No. 841. Electric Storage   TPL–007–2: To require the development
     ¶ 61,115), order on reh’g and clarification, Order      Participation in Markets Operated by Regional          and implementation of corrective action
     No. 831–A, 82 FR 53403 (Nov. 16, 2017), FERC            Transmission Organizations and Independent
     Stats. & Regs. ¶ 31,394 (2017).
                                                                                                                    plans to mitigate assessed supplemental
                                                             System Operators, Errata Notice, Docket Nos.
       2 Order No. 831–A, FERC Stats. & Regs. ¶ 31,394.
                                                             RM16–23–000, AD16–20–000 (Feb. 28, 2018).
                                                                                                                    GMD event vulnerabilities; and to
       3 Electric Storage Participation in Markets           Among other things, the Errata Notice revised 18       authorize extensions of time to
     Operated by Regional Transmission Organizations         CFR 35.28(g)(9).                                       implement corrective action plans on a


VerDate Sep<11>2014   16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00015   Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM   26NOR1


     60348             Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations

     case-by-case basis. In addition, the                     implement a corrective action plan to                   record in this proceeding, we discern no
     Commission accepts the revised GMD                       achieve the performance requirements.                   technical barriers to either developing
     research work plan submitted by NERC.                       3. The improvements in Reliability                   or complying with such a requirement.
     DATES: This rule will become effective                   Standard TPL–007–2 are responsive to                    Moreover, the record supports issuance
     January 25, 2019.                                        the directives in Order No. 830: (1) To                 of a directive at this time
                                                              revise the benchmark GMD event                          notwithstanding comments in response
     FOR FURTHER INFORMATION CONTACT:.
                                                              definition, as it pertains to the required              to the NOPR advocating postponement
     Michael Gandolfo (Technical                              GMD vulnerability assessments and                       of any directive until after the
        Information), Office of Electric                      transformer thermal impact                              completion of additional GMD research.
        Reliability, Federal Energy Regulatory                assessments, so that the definition is not              As discussed below, the relevant GMD
        Commission, 888 First Street NE,                      based solely on spatially-averaged data;                research tasks are scheduled to be
        Washington, DC 20426, (202) 502–                      (2) to require the collection of necessary              completed before the modified
        6817, Michael.Gandolfo@ferc.gov.                      geomagnetically induced current (GIC)                   Reliability Standard must be submitted.
     Matthew Vlissides (Legal Information),                   monitoring and magnetometer data; and                   The Commission directs NERC to
        Office of the General Counsel, Federal                (3) to include a one-year deadline for                  submit the modified Reliability
        Energy Regulatory Commission, 888                     the completion of corrective action                     Standard for approval within 12 months
        First Street NE, Washington, DC                       plans and two- and four-year deadlines                  from the effective date of Reliability
        20426, (202) 502–8408,                                to complete mitigation actions involving                Standard TPL–007–2.
        Matthew.Vlissides@ferc.gov.                           non-hardware and hardware                                  5. We also determine that it is
     SUPPLEMENTARY INFORMATION:                               mitigation.4 As discussed below,                        appropriate, pursuant to section
        1. Pursuant to section 215 of the                     Reliability Standard TPL–007–2                          215(d)(5) of the FPA, to direct that
     Federal Power Act (FPA), the                             complies with these directives and                      NERC modify the provision in
     Commission approves Reliability                          improves upon the currently-effective                   Reliability Standard TPL–007–2,
     Standard TPL–007–2 (Transmission                         version of the Reliability Standard by                  Requirement R7.4 that allows applicable
     System Planned Performance for                           requiring applicable entities to: (1) In                entities to exceed deadlines for
     Geomagnetic Disturbance Events).1 The                    addition to the benchmark GMD event                     completing corrective action plan tasks
     North American Electric Reliability                      requirements, conduct supplemental                      when ‘‘situations beyond the control of
     Corporation (NERC), the Commission-                      GMD vulnerability assessments and                       the responsible entity [arise].’’ The
     certified Electric Reliability                           thermal impact assessments, which                       NOPR raised concerns regarding the
     Organization (ERO), submitted                            apply a new supplemental GMD event                      appropriateness of a self-executing
     Reliability Standard TPL–007–2 for                       definition that does not rely solely on                 deadline extension and observed that it
     Commission approval in response to                       spatially-averaged data; (2) obtain GIC                 was inconsistent with guidance in Order
     directives in Order No. 830.2 As                         and magnetometer data; and (3) meet                     No. 830 that extension requests be
     discussed in this final rule, we                         the Commission-directed deadlines for                   considered on a case-by-case basis.8 We
     determine that Reliability Standard                      the development and completion of                       recognize the point made in NERC’s
     TPL–007–2 better addresses the risks                     tasks in corrective action plans.                       comments in response to the NOPR that,
     posed by geomagnetic disturbances                        Accordingly, pursuant to section                        under NERC’s proposal, ‘‘NERC and
     (GMDs) to the Bulk-Power System,                         215(d)(2) of the FPA, we approve                        Regional Entity staff would exercise
     particularly with respect to the potential               Reliability Standard TPL–007–2.5                        their authority to review the
     impacts of locally-enhanced GMD                             4. In addition, as discussed in the                  reasonableness of any Corrective Action
     events, than currently-effective                         Notice of Proposed Rulemaking, we                       Plan delay, including reviewing the
     Reliability Standard TPL–007–1 and                       determine that it is appropriate,                       ‘situations beyond the control of the
     complies with the Commission’s                           pursuant to section 215(d)(5) of the                    responsible entity’ that are cited as
     directives in Order No. 830.                             FPA,6 to direct NERC to develop and                     causing the delay’’ and that
        2. GMD events occur when the sun                      submit modifications to Reliability                     Requirement R7.4 is ‘‘not so flexible
     ejects charged particles that interact                   Standard TPL–007–2 to require the                       . . . as to allow entities to extend
     with and cause changes in the earth’s                    development and completion of                           Corrective Action Plan deadlines
     magnetic fields. GMD events have the                     corrective action plans to mitigate                     indefinitely or for any reason
     potential to cause severe, wide-spread                   assessed supplemental GMD event                         whatsoever.’’ 9 While we generally agree
     impacts on the Bulk-Power System.3                       vulnerabilities.7 As discussed below,                   with the standard of review that NERC
     Currently-effective Reliability Standard                 requiring corrective action plans for                   states it will use to assess the merits of
     TPL–007–1 requires applicable entities                   supplemental GMD event vulnerabilities                  extension requests, we conclude that
     to assess the vulnerability of their                     is appropriate to ensure the reliability of             such assessments should be made before
     transmission systems to a ‘‘benchmark                    the Bulk-Power System when                              any time extensions are permitted. By
     GMD event.’’ An applicable entity that                   confronted with locally-enhanced GMD                    requiring prior approval of extension
     does not meet certain performance                        events, just as corrective action plans                 requests, the modified Reliability
     requirements, based on the results of the                are necessary to mitigate the effects of                Standard will limit the potential for
     benchmark GMD vulnerability                              benchmark GMD events. Based on the                      unwarranted delays in implementing
     assessment, must develop and                                                                                     corrective action plans while also
                                                                 4 ‘‘Spatial averaging’’ refers to the averaging of
                                                                                                                      providing NERC with an advance and
                                                              magnetometer readings over a geographic area. In        more holistic understanding of where,
       1 16  U.S.C. 824o.                                     developing the benchmark GMD event definition,
       2 Reliability  Standard for Transmission System        the standard drafting team averaged several (but not    to whom, and for how long, extensions
     Planned Performance for Geomagnetic Disturbance          all) geomagnetic field readings taken by                are granted. We expect that the
     Events, Order No. 830, 156 FERC ¶ 61,215, (2016)         magnetometers located within square geographical        extension process developed by NERC
     reh’g denied, Order No. 830–A, 158 FERC ¶ 61,041         areas of 500 km per side.
                                                                 5 16 U.S.C. 824o(d)(2).
                                                                                                                      in response to our directive will be
     (2017).
        3 Reliability Standards for Geomagnetic                  6 Id. 824o(d)(5).                                    timely and efficient such that applicable
     Disturbances, Order No. 779, 143 FERC ¶ 61,147,             7 Geomagnetic Disturbance Reliability Standard,
                                                                                                                       8 Order   No. 830, 156 FERC ¶ 61,215 at P 102.
     at P 3, reh’g denied, 144 FERC ¶ 61,113 (2013); see      Notice of Proposed Rulemaking, 83 FR 23854 (May
     also Reliability Standard TPL–007–2, Background.         23, 2018), 163 FERC ¶ 61,126 (2018) (NOPR).              9 NERC    Comments at 20–21.



VerDate Sep<11>2014    16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00016   Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM   26NOR1


                      Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations                                              60349

     entities will receive prompt responses                  local earth conductivity.17 Geomagnetic               responsible entities to conduct a GMD
     after submitting to NERC or a Regional                  latitude is the proximity to earth’s                  vulnerability assessment every 60
     Entity, as appropriate, the extension                   magnetic north and south poles, as                    months using the benchmark GMD
     request and associated information                      opposed to earth’s geographic poles.18                event described in Attachment 1.
     described in Requirement R7.4.10 We                     Local earth conductivity is the ability of            Requirement R5 requires responsible
     also direct NERC, as proposed in the                    the earth’s crust to conduct electricity at           entities to provide GIC flow
     NOPR, to prepare and submit a report                    a certain location to depths of hundreds              information, based on the benchmark
     addressing how often and why                            of kilometers down to the earth’s                     GMD event definition, to be used in the
     applicable entities are exceeding                       mantle. Local earth conductivity                      transformer thermal impact assessments
     corrective action plan deadlines as well                impacts the magnitude (i.e., severity) of             required in Requirement R6, to each
     as the disposition of extension requests,               the geoelectric fields that are formed                transmission owner and generator
     which is due within 12 months from the                  during a GMD event by, all else being                 owner that owns an applicable
     date on which applicable entities must                  equal, a lower earth conductivity                     transformer within the applicable
                                                             resulting in higher geoelectric fields.19             planning area. Requirement R6 requires
     comply with the last requirement of
                                                                9. GICs can flow in an electric power              transmission owners and generator
     Reliability Standard TPL–007–2.                         system with varying intensity                         owners to conduct thermal impact
     Following receipt of the report, the                    depending on the various factors                      assessments on solely and jointly owned
     Commission will determine whether                       discussed above. As explained in the                  applicable transformers where the
     further action is necessary.                            Background section of Reliability                     maximum effective GIC value provided
        6. The Commission, as discussed                      Standard TPL–007–2, ‘‘[d]uring a GMD                  in Requirement R5 is 75 Amperes per
     below, also accepts the revised GMD                     event, geomagnetically-induced currents               phase (A/phase) or greater. Requirement
     research work plan submitted by NERC                    (GIC) may cause transformer hot-spot                  R7 requires responsible entities to
     on April 19, 2018.11                                    heating or damage, loss of Reactive                   develop corrective action plans if the
                                                             Power sources, increased Reactive                     GMD vulnerability assessment
     I. Background                                           Power demand, and Misoperation(s), the                concludes that the system does not meet
     A. Section 215 and Mandatory                            combination of which may result in                    the performance requirements in Table
     Reliability Standards                                   voltage collapse and blackout.’’                      1 of Reliability Standard TPL–007–1.
                                                                                                                      12. Calculation of the benchmark
                                                             C. Currently-Effective Reliability
       7. Section 215 of the FPA requires the                                                                      GMD event, against which applicable
                                                             Standard TPL–007–1 and Order No. 830
     Commission to certify an ERO to                                                                               entities must assess their facilities, is
     develop mandatory and enforceable                  1. Currently-Effective Reliability                         fundamental to compliance with
     Reliability Standards, subject to                  Standard TPL–007–1                                         Reliability Standard TPL–007–1.
     Commission review and approval. Once                  10. Reliability Standard TPL–007–1                      Reliability Standard TPL–007–1,
     approved, the Reliability Standards may            consists of seven requirements and                         Requirement R3 states that ‘‘[e]ach
     be enforced in the United States by the            applies to planning coordinators,                          responsible entity, as determined in
     ERO, subject to Commission oversight,              transmission planners, transmission                        Requirement R1, shall have criteria for
     or by the Commission independently.12              owners and generation owners who own                       acceptable System steady state voltage
                                                        or whose planning coordinator area or                      performance for its System during the
     B. GMD Primer                                                                                                 benchmark GMD event described in
                                                        transmission planning area includes a
                                                        power transformer with a high side,                        Attachment 1.’’
        8. GMD events occur when the sun                                                                              13. Reliability Standard TPL–007–1,
     ejects charged particles that interact and wye-grounded winding connected at                                  Attachment 1 states that the benchmark
     cause changes in the earth’s magnetic              200 kV or higher.
                                                           11. Requirement R1 requires planning                    GMD event is composed of four
     fields.13 Once a solar particle is ejected,                                                                   elements: (1) A reference peak
     it can take between 17 to 96 hours                 coordinators and transmission planners
                                                        (i.e., ‘‘responsible entities’’) to                        geoelectric field amplitude of 8 V/km
     (depending on its energy level) to reach                                                                      derived from statistical analysis of
     earth.14 A geoelectric field is the electric determine the individual and joint                               historical magnetometer data; (2) a
                                                        responsibilities in the planning
     potential (measured in volts per                                                                              scaling factor to account for local
                                                        coordinator’s planning area for
     kilometer (V/km)) on the earth’s surface                                                                      geomagnetic latitude; (3) a scaling factor
                                                        maintaining models and performing
     and is directly related to the rate of                                                                        to account for local earth conductivity;
                                                        studies needed to complete the GMD
     change of the magnetic fields. The    15
                                                                                                                   and (4) a reference geomagnetic field
                                                        vulnerability assessment required in
     geoelectric field has an amplitude and                                                                        time series or wave shape to facilitate
                                                        Requirement R4. Requirement R2
     direction and acts as a voltage source             requires responsible entities to maintain                  time-domain analysis of GMD impact on
     that can cause GICs to flow on long                system models and GIC system models                        equipment. The product of the first
     conductors, such as transmission                   needed to complete the GMD                                 three elements is referred to as the
     lines.16 The magnitude of the geoelectric vulnerability assessment required in                                regional peak geoelectric field
     field amplitude is impacted by local               Requirement R4. Requirement R3                             amplitude. The benchmark GMD event
     factors such as geomagnetic latitude and requires each responsible entity to have                             defines the geoelectric field values used
                                                        criteria for acceptable system steady                      to compute GIC flows for a GMD
       10 NOPR, 163 FERC ¶ 61,126 at P 50.
                                                        state voltage performance for its system                   vulnerability assessment, which is
       11 North American Electric Reliability
                                                        during the GMD conditions described in                     required in Reliability Standard TPL–
     Corporation, Filing, Docket No. RM15–11–003 (filed                                                            007–1.20
     Apr. 19, 2018) (Revised GMD Research Work Plan).   Attachment 1 of Reliability Standard
       12 16 U.S.C. 824o(e).                            TPL–007–1. Requirement R4 requires                           20 See Reliability Standard TPL–007–1,
       13 See NERC, 2012 Special Reliability Assessment
                                                                                                                   Requirements R4 and R5. Reliability Standard TPL–
     Interim Report: Effects of Geomagnetic Disturbances       17 NERC,  Benchmark Geomagnetic Disturbance         007–1 does not set a threshold amount of GIC flow
     on the Bulk Power System at i–ii (February 2012).       Event Description, Docket No. 15–11–000, at 4         that would constitute a vulnerable transformer.
       14 Id. at ii.                                         (filed June 28, 2016) (2016 NERC White Paper).        However, if a transformer is calculated to
       15 Id.                                                   18 Id.
                                                                                                                   experience a maximum effective GIC flow during a
       16 Id.                                                   19 Id.                                                                                     Continued




VerDate Sep<11>2014   16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00017   Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM   26NOR1


     60350            Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations

        14. For the purpose of determining a                 Reliability Standard TPL–007–1                          D. NERC Petition and Reliability
     benchmark event that specifies what                     addressed the Commission’s directive                    Standard TPL–007–2
     severity GMD events a responsible                       by requiring applicable Bulk-Power                         19. NERC states that Reliability
     entity must assess for potential impacts                System owners and operators to                          Standard TPL–007–2 enhances
     on the Bulk-Power System, NERC                          conduct, on a recurring five-year cycle,                currently-effective Reliability Standard
     determined that a 1-in-100 year GMD                     initial and ongoing vulnerability                       TPL–007–1 by addressing reliability
     event would cause an 8 V/km reference                   assessments regarding the potential                     risks posed by GMDs more effectively
     peak geoelectric field amplitude at 60                  impact of a benchmark GMD event on                      and implementing the directives in
     degree north geomagnetic latitude using                 the Bulk-Power System as a whole and                    Order No. 830.25 NERC asserts that
     Québec’s earth conductivity.21 Scaling                 on Bulk-Power System components. In                     Reliability Standard TPL–007–2 reflects
     factors (i.e., multiplying values) are                  addition, the Commission determined                     the latest in GMD understanding and
     applied to this reference peak                          that Reliability Standard TPL–007–1                     provides a technically sound and
     geoelectric field amplitude to adjust the               requires applicable entities to develop                 flexible approach to addressing the
     8 V/km value for different geomagnetic                  and implement corrective action plans                   concerns discussed in Order No. 830.
     latitudes (scaling factors between 0.1                  to mitigate vulnerabilities identified                  NERC contends that the proposed
     and 1.0) and earth conductivities                       through those recurring vulnerability                   modifications enhance reliability by
     (scaling factors between 0.21 and 1.17).                assessments and that potential                          expanding GMD vulnerability
     NERC identified a reference                             mitigation strategies identified in                     assessments to include severe, localized
     geomagnetic field time series from an                   Reliability Standard TPL–007–1                          impacts and by implementing deadlines
     Ottawa, Ontario magnetic observatory                    include, but are not limited to, the                    and processes to maintain
     during a 1989 GMD storm affecting                       installation, modification or removal of                accountability in the development,
     Québec. NERC used this to estimate a                   transmission and generation facilities                  completion, and revision of corrective
     time series (i.e., 10-second values over                and associated equipment.                               action plans developed to address
     a period of days) of the geoelectric field                 17. In Order No. 830, the Commission                 identified vulnerabilities. Further,
     that is representative of what is                       also determined that Reliability                        NERC states that the proposed
     expected to occur at 60 degree                          Standard TPL–007–1 should be                            modifications improve the availability
     geomagnetic latitude during a 1-in-100                  modified. Specifically, Order No. 830                   of GMD monitoring data that may be
     year GMD event. Such a time series is                   directed NERC to develop and submit                     used to inform GMD vulnerability
     used in some methods of calculating the                 modifications to Reliability Standard                   assessments.
     vulnerability of a transformer to damage                TPL–007–1 concerning: (1) The                              20. Reliability Standard TPL–007–2
     from heating caused by GIC.                             calculation of the reference peak                       modifies currently-effective Reliability
        15. NERC used field measurements                                                                             Standard TPL–007–1 by requiring
                                                             geoelectric field amplitude component
     taken from the International Monitor for                                                                        applicable entities to: (1) Conduct
                                                             of the benchmark GMD event definition;
     Auroral Geomagnetic Effects (IMAGE)                                                                             supplemental GMD vulnerability and
                                                             (2) the collection and public availability
     magnetometer chain, which consists of                                                                           transformer thermal impact assessments
                                                             of necessary GIC monitoring and
     39 magnetometer stations in Northern                                                                            in addition to the existing benchmark
                                                             magnetometer data; and (3) deadlines
     Europe, for the period 1993–2013 to                                                                             GMD vulnerability and transformer
                                                             for completing corrective action plans
     calculate the reference peak geoelectric                                                                        thermal impact assessments required in
                                                             and the mitigation measures called for
     field amplitude. As described in the                                                                            Reliability Standard TPL–007–1; (2)
     2016 NERC White Paper, to arrive at a                   in corrective action plans. Order No.
                                                             830 directed NERC to develop and                        collect data from GIC monitors and
     reference peak geoelectric field                                                                                magnetometers as necessary to enable
     amplitude of 8 V/km, NERC ‘‘spatially                   submit these revisions for Commission
                                                             approval within 18 months of the                        model validation and situational
     averaged’’ four different station groups                                                                        awareness; and (3) develop necessary
     each spanning a square area of                          effective date of Order No. 830.
                                                                18. With respect to the calculation of               corrective action plans within one year
     approximately 500 km (roughly 310                                                                               from the completion of the benchmark
     miles) in width.                                        the reference peak geoelectric field
                                                             amplitude component of the benchmark                    GMD vulnerability assessment, include
     2. Order No. 830                                        GMD event definition, Order No. 830                     a two-year deadline for the
                                                             expressed concern with relying solely                   implementation of non-hardware
        16. On January 21, 2015, NERC
     submitted for Commission approval                       on spatial averaging in Reliability                     mitigation, and include a four-year
     Reliability Standard TPL–007–1 in                       Standard TPL–007–1 because ‘‘the use                    deadline to complete hardware
     response to the directive in Order No.                  of spatial averaging in this context is                 mitigation.26
                                                             new, and thus there is a dearth of                         21. In particular, Reliability Standard
     779 that NERC develop one or more
                                                             information or research regarding its                   TPL–007–2 modifies Requirements R1
     Reliability Standards to address the
                                                             application or appropriate scale.’’ 23                  (identification of responsibilities), R2
     effects of GMD events on the electric
                                                                                                                     (system and GIC system models) and R3
     grid.22 In Order No. 830, the                           While Order No. 830 directed that the
                                                                                                                     (criteria for acceptable System steady
     Commission approved Reliability                         peak geoelectric field amplitude should
                                                                                                                     state) to extend the existing
     Standard TPL–007–1, concluding that                     not be based solely on spatially-
                                                                                                                     requirements pertaining to benchmark
                                                             averaged data, the Commission
                                                                                                                     GMD assessments to the new
     benchmark GMD event of a least 75 A/phase, a            indicated that this ‘‘directive should not
     thermal impact assessment of that transformer is                                                                supplemental GMD assessments.
                                                             be construed to prohibit the use of
     required. See Reliability Standard TPL–007–1,
     Requirement R6.
                                                             spatial averaging in some capacity,                       25 Reliability Standard TPL–007–2 is not attached
        21 NERC used Québec as the location for the         particularly if more research results in                to this final rule. Reliability Standard TPL–007–2 is
     reference peak 1-in-100 year GMD event because of       a better understanding of how spatial                   available on the Commission’s eLibrary document
     its proximity to 60 degree geomagnetic latitude and     averaging can be used to reflect actual                 retrieval system in Docket No. RM18–8–000 and on
     its well understood earth model. By creating scaling    GMD events.’’ 24                                        the NERC website, www.nerc.com.
     factors, each entity can scale this reference peak                                                                26 Unless otherwise indicated, the requirements
     geoelectric field and geoelectric field time series                                                             of Reliability Standard TPL–007–2 are substantively
     values to match its own expected field conditions.        23 Order    No. 830, 156 FERC ¶ 61,215 at P 45.       the same as the requirements in currently-effective
        22 Order No. 779, 144 FERC ¶ 61,113 at P 54.           24 Id.   P 46.                                        Reliability Standard TPL–007–1.



VerDate Sep<11>2014   16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00018     Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM   26NOR1


                      Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations                                                   60351

     Reliability Standard TPL–007–2 adds                     R7.4, of extensions of time to complete                  assessments, so that the definition is not
     the newly mandated supplemental GMD                     corrective action plans as opposed to                    based solely on spatially-averaged data;
     vulnerability and transformer thermal                   permitting extensions of time on a case-                 (2) to require the collection of necessary
     impact assessments in new                               by-case basis.                                           GIC monitoring and magnetometer data;
     Requirements R8 (supplemental GMD                          25. Having identified these issues, the               and (3) to include a one-year deadline
     vulnerability assessment), R9 (GIC flow                 NOPR proposed to direct NERC,                            for the completion of corrective action
     information needed for supplemental                     pursuant to section 215(d)(5) of the                     plans and two and four-year deadlines
     GMD thermal impact assessments) and                     FPA, to develop and submit                               to complete mitigation actions involving
     R10 (supplemental GMD thermal impact                    modifications to Reliability Standard                    non-hardware and hardware mitigation,
     assessments). The supplemental GMD                      TPL–007–2 to require applicable entities                 respectively.29
     event definition contains a higher, non-                to develop and implement corrective
     spatially-averaged reference peak                       action plans to mitigate vulnerabilities                    28. Reliability Standard TPL–007–2
     geoelectric field amplitude component                   discovered through supplemental GMD                      complies with the directives in Order
     than the benchmark GMD event                            vulnerability assessments. The NOPR                      No. 830 by requiring, in addition to the
     definition (12 V/km versus 8 V/km).                     proposed to direct NERC to submit the                    benchmark GMD event vulnerability
     These three new requirements largely                    modified Reliability Standard for                        and thermal impact assessments,
     mirror existing Requirements R4, R5,                    approval within 12 months from the                       supplemental GMD vulnerability and
     and R6 that currently apply, and                        effective date of Reliability Standard                   thermal impact assessments. The
     continue to apply, only to benchmark                    TPL–007–2. The NOPR also sought                          supplemental GMD event definition in
     GMD vulnerability and transformer                       comment on two options for addressing                    Reliability Standard TPL–007–2
     thermal impact assessments.27                           the Commission’s concerns regarding                      contains a non-spatially-averaged
       22. In addition, Reliability Standard                 the potential for undue delay of                         reference peak geoelectric field
     TPL–007–2 includes two other new                        mitigation because of the proposed                       amplitude component of 12 V/km, in
     requirements, Requirements R11 and                      time-extension process in Requirement                    contrast to the 8 V/km figure in the
     R12, that require applicable entities to                R7.4: (1) Direct NERC to bring                           spatially-averaged benchmark GMD
     gather GIC monitoring data                              Reliability Standard TPL–007–2 into                      event definition. As NERC explains in
     (Requirement R11) and magnetometer                      alignment with Order No. 830 through                     its petition, the supplemental GMD
     data (Requirement R12).                                 a process whereby NERC or Regional                       event will be used to ‘‘represent
       23. Reliability Standard TPL–007–2                    Entities consider extensions on a case-                  conditions associated with localized
     modifies existing Requirement R7                        by-case basis using the information that                 enhancement of the geomagnetic field
     (corrective action plans) to create a one-              must be submitted under Requirement                      during a severe GMD event for use in
     year deadline for the development of                    R7.4; or (2) approve the proposed                        assessing GMD impacts.’’ 30 Reliability
     corrective action plans and two and                     provision without directing
     four-year deadlines to complete actions                                                                          Standard TPL–007–2 therefore
                                                             modifications. Under either option,                      addresses the Commission’s directive to
     involving non-hardware and hardware                     NERC would prepare and submit a
     mitigation, respectively, for                                                                                    modify currently-effective Reliability
                                                             report regarding how often and why                       Standard TPL–007–1 so that the
     vulnerabilities identified in the                       applicable entities are exceeding
     benchmark GMD assessment. The                                                                                    benchmark GMD event does not rely
                                                             corrective action plan deadlines
     modifications to Requirement R7                                                                                  solely on spatially-averaged data to
                                                             following implementation of Reliability
     include a provision allowing for                                                                                 calculate the reference peak geoelectric
                                                             Standard TPL–007–2.28
     extension of deadlines if ‘‘situations                    26. The Commission received NOPR                       field amplitude.
     beyond the control of the responsible                   comments from nine entities. We                             29. As proposed in the NOPR,
     entity determined in Requirement R1                     address below the issues raised in the                   pursuant to section 215(d)(5) of the
     prevent implementation of the                           NOPR and comments as well as NERC’s                      FPA, we also determine that it is
     [corrective action plan] within the                     revised GMD research work plan and                       appropriate to direct NERC to develop
     timetable for implementation.’’                         the comments submitted in response.                      and submit modifications to Reliability
     E. NOPR                                                 The Appendix to this final rule lists the                Standard TPL–007–2 to require the
                                                             entities that filed comments in both                     development and completion of
        24. On May 17, 2018, the Commission                  matters.                                                 corrective action plans to mitigate
     issued a NOPR that proposed to approve
                                                             II. Discussion                                           assessed supplemental GMD event
     Reliability Standard TPL–007–2 as the
     Reliability Standard largely addresses                                                                           vulnerabilities. Given that NERC has
                                                                27. Pursuant to section 215(d)(2) of                  acknowledged the potential for ‘‘severe,
     the directives in Order No. 830.                        the FPA, the Commission approves
     However, the NOPR identified two                                                                                 localized impacts’’ associated with
                                                             Reliability Standard TPL–007–2 as just,
     aspects of Reliability Standard TPL–                                                                             supplemental GMD event
                                                             reasonable, not unduly discriminatory
     007–2 that are inconsistent with Order                                                                           vulnerabilities, we see no basis for
                                                             or preferential, and in the public
     No. 830: (1) The lack of any requirement                                                                         requiring corrective action plans for
                                                             interest. We conclude that Reliability
     to develop and implement corrective                                                                              benchmark GMD events but not for
                                                             Standard TPL–007–2 is an improvement
     action plans in response to assessed                    over currently-effective Reliability
                                                                                                                        29 In its petition, NERC stated that it would
     supplemental GMD event                                  Standard TPL–007–1 and responds to                       address the directive in Order No. 830 on the
     vulnerabilities; and (2) a general                      the directives in Order No. 830: (1) To                  collection of GIC monitoring and magnetometer
     allowance, per proposed Requirement                     revise the benchmark GMD event                           data through a forthcoming NERC data request to
                                                             definition, as it pertains to the required               applicable entities pursuant to Section 1600 of the
        27 An exception is the qualifying threshold for                                                               NERC Rules of Procedure rather than through a
                                                             GMD Vulnerability Assessments and                        Reliability Standard requirement. NERC Petition at
     transformers required to undergo thermal impact
     assessments: For the supplemental GMD assessment        transformer thermal impact                               27. On February 7, 2018, NERC released a draft data
     the qualifying threshold for transformers is a                                                                   request for a 45-day comment period. The NERC
     maximum effective GIC value of 85 A/phase while            28 The NOPR proposed that the report, under the       Board of Trustees (BOT) subsequently approved the
     the threshold for benchmark GMD event                   first option, would also include statistics describing   GMD data request at the August 2018 BOT meeting.
     assessments is 75 A/phase.                              how often extension requests were granted.                 30 NERC Petition at 12.




VerDate Sep<11>2014   16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00019   Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM     26NOR1


     60352            Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations

     supplemental GMD events.31 Based on                     months from the date on which                         tasks under way pursuant to the GMD
     the record in this proceeding, there                    applicable entities must comply with                  research work plan that are relevant to
     appear to be no technical barriers to                   the last requirement of Reliability                   the supplemental GMD event definition
     developing or complying with such a                     Standard TPL–007–2. Following receipt                 are scheduled to be completed in 2019
     requirement. Moreover, as discussed                     of the report, the Commission will                    and the results of such research should
     below, the record supports issuance of                  determine whether further action is                   inform the work of the standard drafting
     a directive at this time, notwithstanding               necessary.                                            team.
     NOPR comments advocating                                  31. The Commission, as discussed                    Comments
     postponement of any directive until                     below, also accepts the revised GMD
     after the completion of additional GMD                  research work plan submitted by NERC                     34. NERC does not support the
     research, because relevant GMD                          on April 19, 2018.                                    proposed directive. NERC maintains
     research is scheduled to be completed                                                                         that the provision in Requirement R8.3
     before the due date for submitting a                    A. Corrective Action Plan for                         that requires applicable entities to
     modified Reliability Standard. The                      Supplemental GMD Event                                evaluate possible actions designed to
     Commission therefore adopts the NOPR                    Vulnerabilities NOPR                                  reduce the likelihood or mitigate the
     proposal and directs NERC to submit                        32. The NOPR proposed to determine                 adverse impacts of a supplemental GMD
     the modified Reliability Standard for                   that the absence of a requirement to                  event ‘‘is not merely advisory, but rather
     approval within 12 months from the                      mitigate assessed supplemental GMD                    supports a range of potential mitigating
     effective date of Reliability Standard                  event vulnerabilities is inconsistent                 actions, such as additional hardware
     TPL–007–2.                                              with Order No. 830, and Order No. 779,                mitigation, operating procedures, or
        30. We also determine, pursuant to                   because the proposal does not require                 other resilience actions to enhance
     section 215(d)(5) of the FPA, that it is                ‘‘owners and operators [to] develop and               recovery and restoration.’’ 36 NERC
     appropriate to direct that NERC develop                 implement a plan to protect against                   expounds on this by noting that the
     further modifications to Reliability                    instability, uncontrolled separation, or              requirement to consider mitigation in
     Standard TPL–007–2, Requirement                         cascading failures of the Bulk-Power                  Reliability Standard TPL–007–2 ‘‘would
     R7.4. Under NERC’s proposal,                            System.’’ 33                                          directly support mitigation that is
     applicable entities are allowed, without                   33. The NOPR explained that the                    required by [Reliability Standard EOP–
     prior approval, to exceed deadlines for                 Commission was not persuaded by                       010–1].’’ 37 NERC also contends that it
     completing corrective action plan tasks                 NERC’s justification that technical                   ‘‘anticipates that the Corrective Action
     when ‘‘situations beyond the control of                 limitations—specifically the small                    Plans, when needed to address
     the responsible entity [arise].’’ 32                    number of observations used to define                 performance requirements for the
     Instead, as discussed below, we direct                  the supplemental GMD event and the                    benchmark GMD event, will also
     NERC to develop a timely and efficient                  availability of modeling tools to assist              provide a large degree of protection to
     process, consistent with the                            entities in assessing vulnerabilities—                the Bulk-Power System for events with
     Commission’s guidance in Order No.                      make requiring mitigation premature at                locally-enhanced geomagnetic fields.’’ 38
     830, to consider time extension requests                this time.34 The NOPR, instead,                          35. NERC’s comments reiterate the
     on a case-by-case basis. Our directive                  accepted NERC’s statement that the                    rationale in its petition that requiring
     balances the availability of time                       supplemental GMD event definition                     mitigation ‘‘would result in the de facto
     extensions when applicable entities are                 ‘‘provides a technically justified method             replacement of the benchmark GMD
     presented with the types of                             of assessing vulnerabilities to the                   event with the proposed supplemental
     uncontrollable delays identified in                     localized peak effects of severe GMD                  GMD event.’’ 39 NERC maintains that
     NERC’s petition and NOPR comments                       events.’’ 35 The NOPR also observed that              ‘‘while the supplemental GMD event is
     with the need to ensure that the                        mitigation of supplemental GMD event                  strongly supported by data and analysis
     mitigation of known GMD                                 vulnerabilities is appropriate because                in ways that mirror the benchmark GMD
     vulnerabilities is not being improperly                 Reliability Standard TPL–007–2: (1)                   event, there are aspects of it that are less
     delayed through such requests. Further,                 Does not prescribe how applicable                     definitive than the benchmark GMD
     as proposed in the NOPR, we direct                      entities must perform such studies, and               event and less appropriate as the basis
     NERC to prepare and submit a report                     thus may incorporate any uncertainties                of requiring Corrective Action Plans.’’ 40
     addressing how often and why                            regarding the geographic size of such                 NERC also claims that the uncertainty of
     applicable entities are exceeding                       events into their studies; (2) there are              geographic size of the supplemental
     corrective action plan deadlines as well                commercially-available tools that could               GMD event could not be addressed
     as the disposition of time extension                    allow for modeling of supplemental                    adequately by sensitivity analysis or
     requests. The report is due within 12                   GMD events; and (3) other methods                     through other methods because there are
                                                             could be used within the framework of                 ‘‘inherent sources of modeling
        31 NERC Petition at 4 (‘‘these revisions would
                                                             the Reliability Standard to study                     uncertainty (e.g., earth conductivity
     enhance reliability by expanding GMD
     Vulnerability Assessments to include severe,            planning areas (e.g., superposition or                model, substation grounding grid
     localized impacts and by implementing new               sensitivity studies) in conjunction with              resistance values, transformer thermal
     deadlines and processes to maintain accountability      other power system modeling tools. The                and magnetic response models) . . .
     in the development, completion, and revision of                                                               [and] introducing additional variables
     entity Corrective Action Plans developed to address
                                                             NOPR further recognized that research
     identified vulnerabilities’’).                                                                                  36 NERC
        32 In the Supplemental Material section of             33 NOPR,   163 FERC ¶ 61,126 at P 32.                            Comments at 9.
                                                               34 The                                                37 Id. at 10.
     Reliability Standard TPL–007–2, examples of                      Commission also rejected the assertion in
                                                                                                                     38 Id. at 11.
     situations beyond the control of the of the             NERC’s petition that an evaluation of possible
     responsible entity include, but are not limited to,     actions for supplemental GMD events that result in      39 Id. at 11–12; see also id. at 14 (‘‘many entities

     delays resulting from regulatory/legal processes,       Cascading is similar to the treatment of extreme      would likely employ the most conservative
     such as permitting; delays resulting from               events in Reliability Standard TPL–001–4              approach for conducting supplemental GMD
     stakeholder processes required by tariff; delays        (Transmission System Planning Performance             Vulnerability Assessments, which would be to
     resulting from equipment lead times; or delays          Requirements).                                        apply extreme peak values uniformly over an entire
     resulting from the inability to acquire necessary         35 NOPR, 163 FERC ¶ 61,126 at P 35 (quoting         planning area’’).
     Right-of-Way.                                           NERC Petition at 13).                                   40 Id. at 13.




VerDate Sep<11>2014   16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00020   Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM     26NOR1


                         Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations                                                   60353

     for sensitivity analysis, such as the size                 the proposed directive. They contend                   Reliability Standard TPL–007–2,
     of the localized enhancement, may not                      that requiring corrective action plans for             Requirement R8.3 only requires
     improve the accuracy of GMD                                supplemental GMD event                                 applicable entities to make ‘‘an
     Vulnerability Assessments.’’ 41 NERC                       vulnerabilities: (1) May be premature                  evaluation of possible actions to reduce
     further states that ‘‘commercially-                        given the limited data regarding                       the likelihood or mitigate the
     available modeling tools now advertise                     localized GMD events; (2) would                        consequences and adverse impacts of
     capabilities that could be used to model                   address low-probability events that are                the events if a supplemental GMD event
     localized GMD enhancements, [but] to                       unlikely to affect a wide area; and (3)                is assessed to result in Cascading.’’ As
     NERC’s knowledge these capabilities                        could impose costs on applicable                       the Commission observed in the NOPR,
     have not been used extensively by                          entities that outweigh the potential                   NERC’s proposal differs significantly
     planners, nor have the different software                  benefits of such a directive. Like NERC,               from Order No. 830 because the intent
     tools been benchmarked for consistency                     these commenters support completing                    of the directive was not only to identify
     in results.’’ 42                                           the GMD research work plan before                      vulnerabilities arising from localized
        36. NERC contends that completing                       considering mandating corrective action                GMD events but also to mitigate such
     the GMD work plan is a better                              plans for supplemental GMD event                       vulnerabilities.
     alternative to the NOPR directive.                         vulnerabilities. Idaho Power, moreover,                   40. The comments opposing the
     Moreover, NERC states that it ‘‘commits                    contends that it would be better for                   NOPR directive offer two rationales for
     to initiate a review of TPL–007–2                          registered entities to gain experience                 approving Reliability Standard TPL–
     following the completion of the GMD                        with corrective action plans for                       007–2 without directing modifications
     Research Work Plan to evaluate whether                     benchmark GMD events before                            at this time: (1) Reliability Standard
     the standard continues to be supported                     mandating corrective action plans for                  TPL–007–2 provides sufficient
     by the available knowledge or whether                      supplemental GMD events. Trade                         protection against supplemental GMD
     additional refinements are necessary                       Associations state that instead of the                 event vulnerabilities; and (2) requiring
     . . . [which] could result in                              NOPR directive, any Commission                         mitigation of supplemental GMD events
     modifications to, or additional support                    directive should be limited to requiring               is premature at this time.
     for, the proposed supplemental GMD                         NERC to develop ‘‘a study of the                          41. With respect to the first rationale,
     event, and thereby inform what the                         mitigation measures deployed and the                   NERC observes that the provision
     TPL–007 standard should require in                         effectiveness of these measures to                     requiring applicable entities to consider
     terms of mitigation based on                               mitigate benchmark GMD events before                   supplemental GMD event mitigation is
     supplemental GMD Vulnerability                             mandating mitigation measures on more                  not ‘‘merely advisory.’’ However, there
     Assessments.’’ 43 In response to the                       localized events.’’ 46 Similarly, BPA                  is no dispute that an applicable entity
     NOPR’s statement that the results of the                   maintains that instead of the NOPR                     must ‘‘consider’’ mitigation under
     GMD research work plan may inform                          directive, in order to assess the costs                Reliability Standard TPL–007–2. What
     the work of the standard drafting team                     and benefits of requiring corrective                   is significant is that after having done
     tasked with carrying out the                               action plans for supplemental GMD                      so, an applicable entity has no
     Commission’s proposed directive, NERC                      events, the Commission should require                  obligation under Reliability Standard
     comments state that ‘‘it expects that the                  NERC to file periodic reports on                       TPL–007–2 to implement mitigation
     last of the project’s deliverables will be                 supplemental GMD events and the                        even if the applicable entity
     ready by early 2020 . . . [but] [a]ny                      possible actions to mitigate them.                     ‘‘considered’’ mitigation necessary to
     scientific research project schedule,                         38. Resilient Societies and                         address an assessed supplemental GMD
     however, must account for the                              Reclamation support the NOPR                           event vulnerability.
     possibility that additional time may be                    directive. Reclamation states, and                        42. NERC also maintains that
     needed to explore potential findings or                    Resilient Societies concurs, that ‘‘[a]n               Reliability Standard EOP–010–1
     amend project approaches to provide                        exercise to only identify vulnerabilities              requires transmission operators to
     more useful results.’’ 44 NERC states that                 arising from localized GMD events is                   ‘‘develop, maintain, and implement a
     while the technical report for Task 1 is                   not a cost-effective use of resources                  GMD Operating Procedure or Operating
     scheduled to be completed by the fourth                    unless accompanied by activities to                    Process to mitigate the effects of GMD
     quarter of 2019 according to the revised                   mitigate the identified                                events on the reliable operation of its
     GMD research work plan, NERC                               vulnerabilities.’’ 47                                  respective system.’’ And in Order No.
     estimates that it will file a report with                                                                         779, the Commission determined that
                                                                Commission Determination                               ‘‘while the development of the required
     the Commission, after allowing a period
                                                                  39. Pursuant to section 215(d)(5) of                 mitigation plan [for benchmark GMD
     of public comment, six months later
                                                                the FPA, the Commission adopts the                     event vulnerabilities] cannot be limited
     (i.e., mid-2020).45
        37. Trade Associations, Idaho Power,                    NOPR proposal and directs NERC to                      to considering operational procedures or
     NE ISO, TVA and BPA do not support                         develop and submit modifications to                    enhanced training alone, operational
                                                                Reliability Standard TPL–007–2 to                      procedures and enhanced training may
       41 Id.   at 15.                                          require corrective action plans for                    be sufficient if that is verified by the
       42 Id.
                                                                assessed supplemental GMD event                        vulnerability assessments.’’ 48 Again,
       43 Id. at 18.                                            vulnerabilities. While Reliability                     NERC’s point does not resolve the
       44 Id. at 17.                                            Standard TPL–007–2 requires                            Commission’s concern because
        45 Revised GMD Research Work Plan at 5 (‘‘NERC
                                                                applicable entities to assess                          Reliability Standard EOP–010–1 does
     expects to submit [informational filings with the                                                                 not ensure mitigation of all
     Commission] approximately six months following             supplemental GMD event
     EPRI’s completion of the associated technical              vulnerabilities, it does not require                   supplemental GMD event vulnerabilities
     report(s)’’); id., Attachment 1 (Order No. 830 GMD         corrective action plans to address                     assessed under Reliability Standard
     Research Work Plan (April 2018)) at 7 (identifying
                                                                assessed vulnerabilities. Instead,                     TPL–007–2. That is because: (1)
     ‘‘Q4 2019’’ as the estimated completion date of                                                                   Reliability Standard EOP–010–1
     ‘‘Final technical report to provide additional
     technical support for the existing supplementary             46 Trade
                                                                        Associations Comments at 12.                   applies, in relevant part, only to
     (localized) benchmark; or, propose update to the             47 Reclamation
                                                                               Comments at 1; Resilient Societies
     benchmark, as appropriate’’).                              Comments at 3.                                           48 Order   No. 779, 143 FERC ¶ 61,147 at P 83.



VerDate Sep<11>2014      16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00021    Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM   26NOR1


     60354            Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations

     transmission operators (viz., it does not                the deadline for submitting a modified                    result.’’ 52 Given that GMDs have only
     apply to other applicable entity types,                  Reliability Standard, the underlying                      recently been addressed in the
     such as planning coordinators,                           research in Task 1 is scheduled to be                     Reliability Standards and there is
     transmission planners and generator                      completed before then. As such, the                       currently no requirement to model and
     owners, subject to Reliability Standard                  standard drafting team and personnel                      assess, let alone mitigate, localized GMD
     TPL–007–2); and (2) Reliability                          working on the GMD research work plan                     events, it is not unexpected that these
     Standard EOP–010–1 does not require                      could operate in parallel and share                       modeling tools have not been used
     mitigation if the supplemental GMD                       information to ensure that research                       extensively for that purpose. Moreover,
     event vulnerability cannot be addressed                  relevant to the Commission’s directive                    NERC does not assert that existing tools
     through operational procedures or                        is incorporated into the modified                         are incapable of performing the desired
     enhanced training alone. Thus,                           Reliability Standard. Thus we are not                     modeling function.53 Thus, NERC’s
     Reliability Standard EOP–010–1 does                      persuaded by the comments seeking a                       objections on this point are not
     not ensure satisfactory mitigation or                    delay of our directive.                                   persuasive.
     provide an adequate substitute for                          46. We are not persuaded by the other                     48. NERC does not offer support for
     mitigation as contemplated in Order No.                  points raised by commenters to support                    its comment in response to the NOPR’s
     830.                                                     their assertion that requiring corrective                 observation that sensitivity analysis can
        43. In addition, NERC asserts that the                action plans is premature. First, NERC                    serve, among other methods, as a
     required mitigation of benchmark GMD                     assumes that under such a requirement                     method to refine the geographic scope of
     event vulnerabilities could also address                 ‘‘many’’ applicable entities will adopt a                 localized GMD impacts on planning
     supplemental GMD event                                   ‘‘conservative approach’’ and use the                     areas. NERC responds that it ‘‘does not
     vulnerabilities. Of course that may                      supplemental GMD event definition in                      believe that concerns regarding the
     occur in some circumstances, but that is                 all GMD vulnerability assessments, thus                   uncertainty of the geographic size of the
     not a substitute for requiring mitigation                effectively supplanting the benchmark                     supplemental GMD event could be
     to the extent that benchmark GMD event                   GMD event definition. NERC bases this                     addressed adequately by sensitivity
     mitigation does not completely address                   assumption on the standard drafting                       analysis or though other methods in
     a supplemental GMD event                                 team’s ‘‘extensive experience in system                   planning studies.’’ 54 NERC claims there
     vulnerability. Under Reliability                         planning and the relative immaturity of                   are already inherent sources of
     Standard TPL–007–2 there is currently                    tools and methods for modeling                            modeling uncertainty and that
     no requirement to mitigate the                           localized enhancements.’’ 50 NERC                         introducing another variable, such as
     remaining vulnerability to the Bulk-                     acknowledges the discussion in the                        the size of the localized enhancement,
     Power System.                                            NOPR on how uncertainties regarding                       ‘‘may not improve the accuracy of the
        44. Regarding the second rationale in                 the supplemental GMD event                                GMD Vulnerability Analysis.’’ 55 And
     the NOPR comments, NERC and other                        definition—in particular the geographic                   yet NERC’s concern implies that the
     commenters reiterate the assertion in                    size of localized events—are                              benchmark GMD event contains a
     NERC’s petition that it would be                         ameliorated by the flexibility afforded                   geographic domain that does not itself
     premature, from a technical standpoint,                  by Reliability Standard TPL–007–2.                        inject uncertainties. However, as the
     to require corrective action plans to                    Specifically, Reliability Standard TPL–                   Commission stated in Order No. 830,
     address supplemental GMD event                           007–2 permits applicable entities to                      the geographic area for spatial averaging
     vulnerabilities. As reflected in the                     apply the supplemental GMD event                          in the benchmark GMD event definition
     comment summary, these commenters                        definition to an entire planning area or                  is itself a ‘‘subjective’’ figure.56 Indeed,
     instead request that NERC complete the                   any subset of a planning area. However,                   in Order No. 830, as part of the GMD
     GMD research work plan and then                          NERC asserts that even with this                          research work plan directive, to address
     produce a report that assesses the                       flexibility, at least some applicable                     the uncertainties surrounding the
     possible need for modifications to                       entities would default to using the                       geographic scale of spatial averaging,
     Reliability Standard TPL–007–2.                          supplemental GMD event definition in                      the Commission directed that NERC
        45. The NOPR discussed how a                          an overly-broad manner.                                   should ‘‘further analyze the area over
     standard drafting team could use new                     Notwithstanding NERC’s assertion,                         which spatial averaging should be
     information gathered through the GMD                     nothing in Reliability Standard TPL–                      calculated for stability studies,
     research work plan to develop a                          007–2 requires applicable entities to                     including performing sensitivity
     modified Reliability Standard. The                       apply the supplemental GMD event                          analyses on squares less than 500 km
     Commission noted that Task 1 of the                      definition to an entire planning area or                  per side (e.g., 100 km, 200 km),’’ which
     GMD research work plan (Further                          otherwise supplant the benchmark GMD                      NERC is addressing in Task 1.57 As
     Analyze Spatial Averaging Used in the                    event definition.
     Benchmark GMD Event), which                                 47. With respect to the statement in                     52 Id.  at 15–16.
     encompasses localized GMD event                          the NOPR that modeling tools are                            53 See   also Trade Associations Comments at 8
     research, would be delivered in 2019                     currently available to support corrective                 (‘‘Although current tools are available to model
                                                                                                                        localized events, we understand that such modeling
     according to the most recent version of                  action plans, NERC admits that ‘‘some                     will require significant time as the processes
     the GMD research work plan (i.e., the                    commercially-available modeling tools                     involved are still largely manual, making it difficult
     revised GMD research work plan). The                     now advertise capabilities that could be                  to develop accurate, system-wide models that
     NOPR stated that ‘‘[s]uch GMD research                                                                             appropriately consider the localized impacts of the
                                                              used to model localized GMD                               supplemental GMD event.’’).
     on localized events should inform the                    enhancements.’’ 51 However, NERC                             54 NERC Comments at 15.
     standard development process and aid                     contends that to its ‘‘knowledge these                       55 Id.
     applicable entities when implementing                    capabilities have not been used                              56 Order No. 830, 156 FERC ¶ 61,215 at P 45

     a modified Reliability Standard.’’ 49                    extensively by planners, nor have the                     (quoting Pulkkinen, A., Bernabeu, E., Eichner, J.,
     While we appreciate that the                             different software tools been                             Viljanen, A., Ngwira, C., ‘‘Regional-Scale High-
                                                                                                                        Latitude Extreme Geoelectric Fields Pertaining to
     informational filing for Task 1 may not                  benchmarked for consistency in                            Geomagnetically Induced Currents,’’ Earth, Planets
     be submitted to the Commission prior to                                                                            and Space at 2 (June 19, 2015)).
                                                                50 NERC      Comments at 14.                               57 Id. P 26; see also revised GMD Research Work
       49 NOPR,   163 FERC ¶ 61,126 at P 39.                    51 Id.   at 15.                                         Plan (Task 1) at 6 (‘‘further analyze the area over



VerDate Sep<11>2014    16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00022     Fmt 4700     Sfmt 4700   E:\FR\FM\26NOR1.SGM     26NOR1


                      Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations                                                     60355

     such, we see no basis, technical or                     report within 12 months from the date                       52. Trade Associations, BPA, ISO NE,
     otherwise, for not requiring corrective                 on which applicable entities must                        Idaho Power, and TVA support the
     action plans for assessed supplemental                  comply with the last requirement of                      second option and echo the rationale for
     GMD event vulnerabilities while                         Reliability Standard TPL–007–2.                          adopting the second option in NERC’s
     requiring corrective action plans for                   Following receipt of the report, the                     comments. Trade Associations explain
     assessed benchmark GMD event                            Commission would determine whether                       that while they previously supported a
     vulnerabilities consistent with the                     further action is necessary. Under the                   case-by-case exception process, they
     Commission’s directions in Order Nos.                   second option, the Commission would                      now believe NERC’s proposal to be more
     779 and 830. Accordingly, the                           approve proposed Requirement R7.4 but                    efficient and effective. Trade
     Commission is not persuaded by the                      also direct NERC to prepare and submit                   Associations contend that a case-by-case
     arguments of NERC and other                             the report described in the first option                 approach would ‘‘only increase
     commenters for the reasons discussed                    (without the statistics on disposition).                 administrative tasks for NERC and
     above, and directs that NERC develop                    Following receipt of the report, the                     applicable entities . . . [and] would
     modifications to Reliability Standard                   Commission would determine whether                       further delay any actions to mitigate
     TPL–007–2 to require corrective action                  further action is necessary.                             rather than expedite the approval
     plans for assessed supplemental GMD                                                                              process.’’ 63 Trade Associations also
                                                             Comments
     event vulnerabilities.                                                                                           maintain that Reliability Standard TPL–
                                                                51. NERC supports the second option                   007–2 ‘‘will not delay mitigation
     B. Corrective Action Plan Deadline                      in the NOPR. NERC contends that                          because this requirement is only
     Extensions                                              Reliability Standard TPL–007–2                           applicable if circumstances are beyond
     NOPR                                                    ‘‘provides clarity and certainty                         the entity’s control.’’ 64
                                                             regarding when an entity may extend a                       53. Reclamation does not appear to
        49. The NOPR stated that                             Corrective Action Plan mitigation                        support modifying Requirement R7 to
     Requirement R7.4 of Reliability                         deadline and what steps must be                          institute a case-by-case time extension
     Standard TPL–007–2 differs from Order                   followed to maintain accountability and                  process. However, Reclamation
     No. 830 by allowing applicable entities                 thus compliance with the standard.’’ 58                  comments that the sub-requirement in
     to ‘‘revise’’ or ‘‘update’’ corrective                  NERC also maintains that the proposal                    Requirement R7.4.1 requiring
     action plans to extend deadlines. This                  ‘‘avoids the administrative burden,                      documentation of reasons for delaying
     provision contrasts with the guidance in                uncertainty, and further delay that                      corrective action plans should be
     Order No. 830 that ‘‘NERC should                        could be associated with implementing                    eliminated because it ‘‘is merely a
     consider extensions of time on a case-                  a new ERO adjudication process, such                     compliance exercise and does not
     by-case basis.’’ While agreeing that there              as one that would be dedicated to                        improve Bulk Electric System
     should be a mechanism for allowing                      evaluating GMD Corrective Action Plan                    reliability.’’ Reclamation makes the
     extensions of corrective action plan                    deadline extensions on a case-by-case                    same contention regarding the sub-
     implementation deadlines, the NOPR                      basis. ’’ 59 To address concerns regarding               requirement in Requirement R7.4.2 that
     expressed concern with unnecessary                      the possible abuse of deadline                           a revised corrective action plan describe
     delays in implementing protection                       extensions, NERC states that as ‘‘part of                the original corrective action plan.
     against GMD threats.                                    the compliance monitoring and
        50. The NOPR identified two options                  enforcement activities for the proposed                  Commission Determination
     for addressing Requirement R7.4. Under                  standard, NERC and Regional Entity                         54. Reliability Standard TPL–007–2,
     the first option, the Commission would,                 staff would exercise their authority to                  Requirement R7.4 differs from Order
     pursuant to section 215(d)(5) of the                    review the reasonableness of any                         No. 830 by allowing applicable entities,
     FPA, direct NERC to modify Reliability                  Corrective Action Plan delay, including                  under certain conditions, to extend
     Standard TPL–007–2 to comport with                      reviewing the ‘situations beyond the                     corrective action plan implementation
     Order No. 830, by requiring that NERC                   control of the responsible entity’ that are              deadlines without prior approval. This
     and the Regional Entities, as                           cited as causing the delay.’’ 60 As noted                conflicts with the Commission’s
     appropriate, consider requests for                      in the Supplemental Material section of                  guidance in Order No. 830 that, using its
     extension of time on a case-by-case                     Reliability Standard TPL–007–2, NERC                     compliance discretion, ‘‘NERC should
     basis. Under this option, responsible                   explains that examples of such                           consider extensions of time on a case-
     entities seeking an extension would                     situations include ‘‘lengthy legal or                    by-case basis.’’ 65 Based on our
     submit the information required by                      regulatory processes, stakeholder                        consideration of the record, we believe
     Requirement R7.4 to NERC and the                        processes required by tariff, or long                    that the case-by-case review process
     Regional Entities for their consideration               equipment lead times.’’ 61 NERC,                         contemplated by Order No. 830 is the
     of the request. The Commission would                    moreover, ‘‘agrees that a report                         appropriate means for considering
     also direct NERC to prepare and submit                  describing the results of NERC’s                         extension requests. Accordingly,
     a report addressing the disposition of                  monitoring of this provision could                       pursuant to section 215(d)(5) of the
     any such requests, as well as                           provide useful information . . . [and]                   FPA, we direct that NERC develop
     information regarding how often and                     therefore commits to prepare and                         modifications to Reliability Standard
     why applicable entities are exceeding                   submit to the Commission a report that                   TPL–007–2 to replace the time-
     corrective action plan deadlines                        describes how often and the reasons                      extension provision in Requirement
     following implementation of Reliability                 why entities in the United States are                    R7.4 with a process through which
     Standard TPL–007–2. Under such a                        exceeding Corrective Action Plan                         extensions of time are considered on a
     directive, NERC would submit the                        deadlines.’’ 62                                          case-by-case basis.
                                                                                                                        55. At the outset, we note that the
     which spatial averaging should be used in stability       58 NERC                                                extension process in Requirement R7.4
                                                                         Comments at 20.
     studies and transformer thermal assessments by            59 Id.
     performing GIC analysis on squares less than 500
                                                               60 Id. at 20–21.                                         63 Trade   Associations Comments at 13.
     km per side (e.g., 100 km, 200 km) and using the
                                                               61 Id. at 20.                                            64 Id.
     results to perform power flow and transformer
     thermal assessments’’).                                   62 Id. at 22.                                            65 Order   No. 830, 156 FERC ¶ 61,215 at P 102.



VerDate Sep<11>2014   16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00023      Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM     26NOR1


     60356            Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations

     applies only to the implementation of                     indicates it will use to determine                   the Commission should encourage best
     corrective action plans and not to the                    whether an extension of time to                      practices by industry beyond the
     development of corrective action                          implement a corrective action plan is                mandatory requirements of the
     plans.66 NERC and other commenters                        appropriate. However, the assessment of              Reliability Standards, including
     supportive of the second option in the                    whether an extension of time is                      allowing cost recovery for such
     NOPR urge approval of Requirement                         warranted is more appropriately made                 practices. Third, Resilient Societies
     R7.4 without modification largely                         before an applicable entity is permitted             states that the Commission should
     because of the perceived uncertainty                      to delay mitigation of a known GMD                   address combined GMD and
     and burden associated with treating                       vulnerability. While NERC indicates                  electromagnetic pulse (EMP) protection.
     extension requests on a case-by-case                      that under proposed Requirement R7.4                    59. In Order No. 830, the Commission
     basis. While it is true that granting                     there are compliance consequences for                approved the 75 A/phase threshold in
     extensions on a case-by-case basis                        improperly delaying mitigation,                      Reliability Standard TPL–007–1 based
     involves more uncertainty and potential                   mitigation of a known GMD                            on the record and despite objections
     burdens versus the automatic extension                    vulnerability will nonetheless have been             from certain commenters. The
     of time afforded by Requirement R7.4,                     delayed, and we conclude it is                       Commission, however, directed further
     we must weigh this against the potential                  important that any proposed delay be                 study of this issue as part of the GMD
     for abuse of Requirement R7.4 to unduly                   reviewed ahead of time. Therefore, we                research work plan. Resilient Societies’
     delay mitigation, as well as the delayed                  direct NERC to modify Reliability                    comments provide no new basis for
     visibility that NERC would have into the                  Standard TPL–007–2, Requirement R7.4                 revisiting this issue at this time.
     deployment of needed GMD protections.                     to develop a timely and efficient                    Moreover, as reflected in the NOPR
     Presented with these competing                            process, consistent with the                         proposal, NERC has adequately
     concerns, we conclude that the                            Commission’s guidance in Order No.                   supported the 85 A/phase threshold
     imperative to address known GMD                           830, to consider time extension requests             proposed in Reliability Standard TPL–
     vulnerabilities in a timely manner, and                   on a case-by-case basis.                             007–2 for the supplemental GMD event
     without unwarranted delays, is more                         57. We disagree with Reclamation’s                 analysis. However, new information
     compelling. We recognize that                             comment regarding Requirement R7.4.1,                resulting from the GMD research work
     applicable entities that have a legitimate                which requires a description of the                  plan will also be relevant to this higher
     need for extensions require timely                        circumstances necessitating mitigation               threshold. We will consider such
     responses from NERC and Regional                          delays, because it is at odds with                   research at the appropriate time.
     Entities, as appropriate. Accordingly,                    NERC’s NOPR comments, discussed                         60. In Order No. 830, the Commission
     we expect that the extension process                      above, in which NERC states that NERC                stated that ‘‘cost recovery for prudent
     developed by NERC in response to our                      and Regional Entities will review the                costs associated with or incurred to
     directive will be timely and efficient                    reasons for delaying mitigation.                     comply with Reliability Standard TPL–
     such that applicable entities will receive                Contrary to Reclamation’s assertion that             007–1 and future revisions to the
     prompt responses after submitting to                      this requirement is ‘‘merely a                       Reliability Standard will be available to
     NERC or a Regional Entity, as                             documentation exercise and does not                  registered entities.’’ 69 It is therefore
     appropriate, the extension request and                    improve [bulk electric system]                       beyond the scope of this proceeding to
     associated information described in                       reliability,’’ unreasonable delays of                determine, as a general matter, whether
     Requirement R7.4.67                                       mitigation could harm bulk electric                  voluntary measures beyond those
        56. In reaching our determination on                   system reliability by leaving it                     required to comply with the governing
     this issue, we considered NERC’s NOPR                     vulnerable to GMDs. Moreover,                        Reliability Standards are eligible for cost
     comments, which attempted to address                      Requirement R7.4.2, also opposed by                  recovery. That said, jurisdictional
     the concerns with Requirement R7.4                        Reclamation, requiring that revised                  entities may of course pursue such
     expressed in the NOPR, stating that                       corrective action plans describe the                 voluntary measures, and the
     NERC and Regional Entity compliance                       original and previous revisions,                     Commission would consider
     and enforcement staff will review the                     provides compliance enforcement                      appropriate cost recovery for those
     reasonableness of any delay in                            authorities with a revision history of the           investments through a formula rate or
     implementing corrective action plans,                     corrective action plan in a single                   other rate proceeding.
     including reviewing the asserted                          document, thus facilitating compliance                 61. The Commission in previous
     ‘‘situations beyond the control of the                    review.                                              orders has indicated that the
     responsible entity’’ cited by the                                                                              Commission’s GMD proceedings are not
                                                               C. Other Issues Raised in NOPR
     applicable entity, and by citing specific                                                                      directed to EMPs and thus Resilient
                                                               Comments
     examples of the types of delays that                                                                           Societies’ comments on EMP are out-of-
     might justify the invocation of                             58. Resilient Societies’ comments                  scope.70
     Requirement R7.4. NERC’s comments                         raise three issues not addressed in the
                                                               NOPR. First, Resilient Societies                     D. Revised GMD Research Work Plan
     also characterized Requirement R7.4 as
     being ‘‘not so flexible . . . as to allow                 maintains that transformers that                        62. On April 19, 2018, NERC
     entities to extend Corrective Action Plan                 experience an estimated GIC above 15                 submitted a revised GMD research work
     deadlines indefinitely or for any reason                  A/phase should be subject to mandatory               plan in response to a Commission order
     whatsoever.’’ 68 We generally agree with                  corrective action plans and the                      issued on October 19, 2017.71 In the
     the standard of review that NERC                          Commission should ‘‘encourage owner-                 October 19 Order, the Commission
                                                               operators and their research partners to             accepted the initial GMD research work
       66 Reliability Standard TPL–007–2, Requirement          develop ‘Corrective Action Plans’ for
     R7.4 (‘‘[t]he [corrective action plan] shall . . . [b]e   both [extra high voltage] transformers                 69 Order    No. 830, 156 FERC ¶ 61,215 at P 24.
     revised if situations beyond the control of the           and for associated generation stations,                70 See,   e.g., Order No. 830, 156 FERC ¶ 61,215 at
     responsible entity . . . prevent implementation of                                                             P 119.
     the [corrective action plan] within the timetable for
                                                               even if these long replacement-time                    71 Reliability Standard for Transmission System
     implementation’’).                                        systems experience overstress at levels              Planned Performance for Geomagnetic Disturbance
       67 NOPR, 163 FERC ¶ 61,126 at P 50.                     significantly below 75 amps per phase.’’             Events, 161 FERC ¶ 61,048 (2017) (October 19
       68 NERC Comments at 20.                                 Second, Resilient Societies states that              Order).



VerDate Sep<11>2014    16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00024   Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM      26NOR1


                      Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations                                         60357

     plan filed by NERC on May 30, 2017.                     example, regarding Task 5, NERC states                  including the use of automated
     The Commission also directed NERC to                    that it will ‘‘validate[e] existing                     information techniques. Specifically,
     file a final GMD research work plan                     transformer tools with all data that is                 the Commission asked that any revised
     within six months and ensure that the                   presently available and with upcoming                   burden or cost estimates submitted by
     final GMD research work plan included                   field/laboratory test results.’’ 75 Resilient           commenters be supported by sufficient
     a reevaluation of reliance on single                    Societies, however, contends                            detail to understand how the estimates
     station readings when adjusting for                     unpersuasively that ‘‘NERC neglects to                  were generated. The Commission did
     latitude as part of the benchmark GMD                   specify ‘all data that is presently                     not receive any comments regarding the
     event definition. At NERC’s request, the                available’ . . . and the number of                      Commission’s burden estimates.
     October 19 Order also provided                          transformers to be employed in                             68. The Commission approves
     guidance on how NERC should                             ‘upcoming field laboratory test results’                Reliability Standard TPL–007–2, which
     prioritize the tasks in the GMD research                and also neglects to disclose details of                replaces currently-effective Reliability
     work plan.                                              the test protocols to be used.’’ 76                     Standard TPL–007–1. When compared
        63. Bardin and Resilient Societies                   Regarding harmonics (Tasks 8 and 9),                    to Reliability Standard TPL–007–1,
     submitted comments in response to the                   Task 9 specifically includes ‘‘tank                     Reliability Standard TPL–007–2
     revised GMD research work plan, which                   vibration measurements,’’ not just                      maintains the current information
     largely focused on a request for                        simulations.77 Moreover, Task 8                         collection requirements, modifies
     combined research on GMDs and EMPs.                     (Improving Harmonic Analysis                            existing Requirements R1 through R7
     As discussed above, however, EMPs are                   Capabilities) is intended to develop                    and adds new requirements in
     outside the scope of the Commission’s                   more basic information than some of the                 Requirements R8 through R12.
     directive regarding GMD research.                       other tasks in the revised GMD research                    69. Reliability Standard TPL–007–2
     Resilient Societies also submitted                      work plan where industry has more                       includes new corrective action plan
     comments criticizing aspects of five                    knowledge. As with all of the revised                   development and implementation
     tasks in the revised GMD research work                  GMD research work plan tasks (with the                  deadlines in Requirement R7, new
     plan. With respect to Tasks 1, 2, 8 and                 exception of Task 6, which deals with                   supplemental GMD vulnerability and
     9, Resilient Societies’ criticism is based              the Section 1600 data request), NERC                    transformer thermal impact assessments
     on the contention that the ‘‘real-world                 will submit a report to the Commission                  in Requirements R8 through R10, and
     data’’ will not be used to verify models.               on its findings.                                        requirements for applicable entities to
     For example, Resilient Societies                           65. As the revised GMD research work                 gather magnetometer and GIC monitored
     contends that NERC will not use ‘‘real-                 plan complies with Order No. 830 and                    data in Requirements R11 and R12.
     world’’ GIC data to validate spatial                    the Commission’s October 19 Order, we                   Deadlines in Requirement R7 for the
     averaging (Task 1) or latitude scaling                                                                          development and implementation of
                                                             accept the revised GMD research work
     (Task 2). These assertions, however, are                                                                        corrective action plans would only
                                                             plan.
     refuted by the revised GMD research                                                                             change the timeline of such
     work plan. The revised GMD research                     III. Information Collection Statement                   documentation and are not expected to
     work plan indicates that the research on                  66. The collection of information                     revise the burden to applicable entities.
     spatial averaging includes an analysis of               contained in this final rule is subject to              The burden estimates for new
     ‘‘a large number (10–20) of localized                   review by the Office of Management and                  Requirements R8 through R10 are
     extreme events and collection of both                   Budget (OMB) under section 3507(d) of                   expected to be similar to the burden
     ground-based and space-based data                       the Paperwork Reduction Act of 1995.78                  estimates for Requirements R4 through
                                                             OMB’s regulations require review and                    R6 in currently-effective Reliability
     around the times of these events.’’ 72 For
                                                                                                                     Standard TPL–007–1 due to the closely-
     latitude scaling, the revised GMD                       approval of certain information
                                                                                                                     mirrored requirements.80 The
     research work plan states that NERC                     collection requirements imposed by
                                                                                                                     Commission expects that only 25
     will evaluate the scaling factor ‘‘using                agency rules.79 Upon approval of a
                                                                                                                     percent or fewer of transmission owners
     existing models and developing new                      collection of information, OMB will
                                                                                                                     and generator owners would have to
     models to extrapolate, from historical                  assign an OMB control number and an
                                                                                                                     complete a supplemental transformer
     data, the potential scaling of a 1-in-100               expiration date. Respondents subject to
                                                                                                                     thermal impact assessment per
     year GMD event on lower geomagnetic                     the information collection requirements
                                                                                                                     Requirement R10. Requirements R11
     latitudes.’’ 73 In addition, NERC                       of a rule will not be penalized for failing
                                                                                                                     and R12 require applicable entities to
     indicates that the data gathered through                to respond to the collection of
                                                                                                                     have a process to collect GIC and
     the Section 1600 data request ‘‘will help               information unless the collection of
                                                                                                                     magnetometer data from meters in
     validate various models used in                         information displays a valid OMB                        planning coordinator planning areas.
     calculating GIC’s and assessing their                   control number.                                            Public Reporting Burden: The burden
     impacts in data systems.’’ 74                             67. In the NOPR, the Commission                       and cost estimates below are based on
        64. Resilient Societies other                        solicited comments on the need for this                 the changes to the reporting and
     comments are directed to an alleged                     information, whether the information                    recordkeeping burden imposed by
     lack of specificity, granularity or                     will have practical utility, the accuracy               Reliability Standard TPL–007–2. Our
     ‘‘scientific assurance’’ in the testing                 of the burden estimates, ways to                        estimates for the number of respondents
     described in Tasks 5, 8 and 9 of the                    enhance the quality, utility, and clarity               are based on the NERC Compliance
     revised GMD research work plan. These                   of the information to be collected or                   Registry as of March 3, 2018, which
     criticisms are misplaced as they demand                 retained, and any suggested methods for                 indicates there are 183 entities
     an unreasonable degree of detail in the                 minimizing respondents’ burden,                         registered as transmission planner (TP),
     revised GMD research work plan. For                                                                             65 planning coordinators (PC), 330
                                                               75 Id.   at 17.
       72 Revised                                              76 Resilient  Societies Comments on Revised GMD
                                                                                                                     transmission owners (TO), 944 generator
                     GMD Research Work Plan, Attachment
     1 (Order No. 830 GMD Research Work Plan (April          Research Work Plan at 11.                               owners (GO) within the United States.
     2018)) at 2.                                              77 Id. at 25.                                         However, due to significant overlap, the
        73 Id. at 8.                                           78 44 U.S.C. 3507(d).
        74 Id. at 19.                                          79 5 CFR part 1320 (2018).                              80 NERC   Petition at 14–17.



VerDate Sep<11>2014   16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00025     Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM   26NOR1


     60358                Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations

     total number of unique affected entities                                 transmission planner or planning                                              expectation that at most only 25 percent
     (i.e., entities registered as a transmission                             coordinator (applicability for                                                of the 1,119 entities (or 280 entities) will
     planner, planning coordinator,                                           Requirements R7 to R9 and R11 to R12),                                        have to complete compliance activities
     transmission owner or generator owner,                                   and 1,119 entities registered as a                                            for Requirement R10. The estimated
     or some combination of these functional                                  transmission or generation owner                                              burden and cost are as follow.81
     entities) is 1,130 entities. This includes                               (applicability for Requirement R10).
     188 entities that are registered as a                                    Given the assumption above, there is an

                                             FERC–725N, CHANGES DUE TO FINAL RULE IN DOCKET NO. RM18–8 82 83
                                                                                                                                                                       Total annual
                                                                        Annual number of                  Total number              Average burden
                                      Number and type                                                                                                               burden hrs. & total           Cost per
                                                                         responses per                    of responses              hrs. & cost per
       Requirement (R)                 of respondents                                                                                                                  annual cost             respondent ($)
                                                                           respondent                      (1) × (2) =                 response
                                             (1)                                                                                                                        (rounded)                 (5) ÷ (1)
                                                                               (2)                             (3)                        (4)                         (3) × (4) = (5)

     R1 through R6 84 ...            No change ............            No change ............             No change ..            No change ............            No change ............   No change
     R7 ..........................   188 (PC and TP) ..                1/5 (once for every                37.6 .............      Rep. 5 hrs.,                      Rep. 188 hrs.,           Rep. 1 hr., $66.90;
                                                                         five year study).                                          $334.50; RK 5                     $12,577; RK 188          RK 1 hr., $32.04
                                                                                                                                    hrs., $160.20.                    hrs., $6,023.
     R8 ..........................   188 (PC and TP) ..                1/5 (once for every                37.6 .............      Rep., 27 hrs.,                    Rep. 1,015 hrs.,         Rep., 5.4 hrs.,
                                                                         five year study).                                          $1,806.30; RK,                    $67,917; RK 790          $361.26; RK 4.2
                                                                                                                                    21 hrs., $672.84.                 hrs., $25,299.           hrs., $134.57
     R9 ..........................   188 (PC and TP) ..                1/5 (once for every                37.6 .............      Rep. 9 hrs.,                      Rep. 338 hrs.,           Rep. 1.8 hrs.,
                                                                         five year study).                                          $602.10; RK 7                     $22,639; RK 263          $120.42; RK 1.4
                                                                                                                                    hrs., $224.28.                    hrs., $8,432.            hrs., $44.85
     R10 ........................    280 (25% of 1,119)                1/5 (once for every                56 ................     Rep. 22 hrs.,                     Rep. 1,232 hrs.,         Rep. 4.4 hrs.,
                                       (GO and TO).                      five year study).                                          $1,471.80; RK                     $82,421; RK              $294.36; RK 3.6
                                                                                                                                    18 hrs., $576.72.                 1,008 hrs.,              hrs., $115.34
                                                                                                                                                                      $32,296.
     R11 ........................    188 (PC and TP) ..                1 (on-going report-                188 ..............      Rep. 10 hrs., $669;               Rep. 1,880 hrs.,         Rep. 10 hrs., $669;
                                                                         ing).                                                      RK. 10 hrs.,                      $125,772; RK             RK 10 hrs.,
                                                                                                                                    $320.40.                          1,880 hrs.,              $320.40
                                                                                                                                                                      $60,235.
     R12 ........................    188 (PC and TP) ..                1 (on-going report-                188 ..............      Rep. 10 hrs., $669;               Rep. 1,880 hrs.          Rep. 10 hrs., $669;
                                                                         ing).                                                      RK. 10 hrs.,                      $125,772; RK             RK 10 hrs.,
                                                                                                                                    320.40.                           1,880 hrs.,              $320.40
                                                                                                                                                                      $60,235.
     Total Additional                ...............................   ...............................    .....................   ...............................   Rep., 6,533 hrs.,
       Hrs. and Cost                                                                                                                                                 $437,057; RK
       (rounded), due to                                                                                                                                             6,009 hrs.,
       Final Rule in                                                                                                                                                 $192,528.
       RM18–8.



       Title: FERC–725N, Mandatory                                            implements the Congressional mandate                                          2, and made a determination that its
     Reliability Standards: TPL Reliability                                   of the Energy Policy Act of 2005 to                                           action is necessary to implement section
     Standards                                                                develop mandatory and enforceable                                             215 of the FPA. The Commission has
       Action: Revisions to an existing                                       Reliability Standards to better ensure                                        assured itself, by means of its internal
     collection of information                                                the reliability of the nation’s Bulk-                                         review, that there is specific, objective
       OMB Control No: 1902–0264                                              Power System. Specifically, these                                             support for the burden estimates
       Respondents: Business or other for                                     requirements address the threat posed                                         associated with the information
     profit, and not for profit institutions.                                 by GMD events to the Bulk-Power                                               requirements.
       Frequency of Responses: 85 Every five                                  System and conform to the                                                        70. Interested persons may obtain
     years (for Requirement R7–R10),                                          Commission’s directives to modify                                             information on the reporting
     annually (for Requirement R11 and                                        Reliability Standard TPL–007–1 as                                             requirements by contacting the Federal
     R12), and ongoing.                                                       directed in Order No. 830.                                                    Energy Regulatory Commission, Office
       Necessity of the Information:                                            Internal review: The Commission has                                         of the Executive Director, 888 First
     Reliability Standard TPL–007–2                                           reviewed Reliability Standard TPL–007–                                        Street NE, Washington, DC 20426
       81 Hourly costs are based on the Bureau of Labor                       existing requirements in Reliability Standard TPL–                            numbers), and the Compliance section details the
     Statistics (BLS) figures for May 2017 (Sector 22,                        007–1 (and in the current OMB-approved                                        related Recordkeeping Requirement.
     Utilities) for wages (https://www.bls.gov/oes/                           inventory), which would continue under Reliability                               84 While Reliability Standard TPL–007–2 extends
     current/naics2_22.htm) and benefits for December                         Standard TPL–007–2.                                                           the requirements in existing Reliability Standard
     2017 (https://www.bls.gov/news.release/                                    The requirements for NERC to provide reports to
     ecec.nr0.htm). We estimate that an Electrical                                                                                                          TPL–007–1, Requirements R1 through R3 to the
                                                                              the Commission and to develop and submit                                      newly required supplemental GMD event analyses,
     Engineer (NAICS code 17–2071) would perform the
                                                                              modifications to Reliability Standard TPL–007–2                               the obligation to conduct the supplemental GMD
     functions associated with reporting requirements, at
     an average hourly cost (for wages and benefits) of                       are already covered under FERC–725 (OMB Control                               event analyses is found in Reliability Standard
     $66.90 The functions associated with recordkeeping                       No. 1902–0225).
                                                                                82 Rep.=reporting requirements; RK-
                                                                                                                                                            TPL–007–2, Requirements R8 through R10.
     requirements, we estimate, would be performed by                                                                                                          85 The frequency of Requirements R1 through R6
     a File Clerk (NAICS code 43–4071) at an average                          recordkeeping requirements (Evidence Retention).
                                                                                                                                                            in Reliability Standard TPL–007–2 is unchanged
     hourly cost of $32.04 for wages and benefits.                              83 For each Reliability Standard, the Measure

                                                                              shows the acceptable evidence (Reporting                                      from the existing requirements in Reliability
       The estimated burden and cost are in addition to
     the burden and cost that are associated with the                         Requirement) for the associated Requirement (R                                Standard TPL–007–1.




VerDate Sep<11>2014        17:33 Nov 23, 2018         Jkt 247001       PO 00000       Frm 00026          Fmt 4700     Sfmt 4700      E:\FR\FM\26NOR1.SGM              26NOR1


                          Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations                                                         60359

     [Attention: Ellen Brown, email:                                   small utility (using SBA’s sub-sector                  www.ferc.gov) and in FERC’s Public
     DataClearance@ferc.gov, phone: (202)                              221) is based on the number of                         Reference Room during normal business
     502–8663, fax: (202) 273–0873].                                   employees for a concern and its                        hours (8:30 a.m. to 5:00 p.m. Eastern
       71. Comments concerning the                                     affiliates. As discussed above,                        time) at 888 First Street NE, Room 2A,
     collection of information and the                                 Reliability Standard TPL–007–2 applies                 Washington DC 20426.
     associated burden estimate should be                              to a total of 1,130 unique planning                       77. From FERC’s Home Page on the
     sent to the Commission in this docket                             coordinators, transmission planners,                   internet, this information is available on
     and may also be sent to the Office of                             transmission owners, and generation                    eLibrary. The full text of this document
     Information and Regulatory Affairs,                               owners.89 A small utility (and its                     is available on eLibrary in PDF and
     Office of Management and Budget, 725                              affiliates) is defined as having no more               Microsoft Word format for viewing,
     17th Street NW, Washington, DC 20503                              than the following number of                           printing, and/or downloading. To access
     [Attention: Desk Officer for the Federal                          employees:                                             this document in eLibrary, type the
     Energy Regulatory Commission]. Due to                                • For planning coordinators,                        docket number excluding the last three
     security concerns, comments should be                             transmission planners, and transmission                digits of this document in the docket
     sent electronically to the following                              owners (NAICS code 221121, Electric                    number field.
     email address: oira_submission@                                   Bulk Power Transmission and Control),
     omb.eop.gov. Comments submitted to                                a maximum of 500 employees                                78. User assistance is available for
     OMB should refer to FERC–725N and                                    • for generator owners, a maximum of                eLibrary and the FERC’s website during
     OMB Control No. 1902–0264.                                        750 employees.90                                       normal business hours from FERC
                                                                          74. As estimated in the NOPR, the                   Online Support at (202) 502–6652 (toll
     IV. Environmental Analysis                                        total cost to all entities (large and small)           free at 1–866–208–3676) or email at
        72. The Commission is required to                              is $629,585 annually (or an average of                 ferconlinesupport@ferc.gov, or the
     prepare an Environmental Assessment                               $1,345.27 for each of the estimated 468                Public Reference Room at (202) 502–
     or an Environmental Impact Statement                              entities affected annually). For the                   8371, TTY (202)502–8659. Email the
     for any action that may have a                                    estimated 280 generator owners and                     Public Reference Room at
     significant adverse effect on the human                           transmission owners affected annually,                 public.referenceroom@ferc.gov.
     environment.86 The Commission has                                 the average cost would be $409.70 per                  VII. Effective Date and Congressional
     categorically excluded certain actions                            year. For the estimated 188 planning                   Notification
     from this requirement as not having a                             coordinators and transmission planners,
     significant effect on the human                                   the estimated average annual cost would                  These regulations are effective
     environment. Included in the exclusion                            be $2,738.84. The estimated annual cost                January 25, 2019. The Commission has
     are rules that are clarifying, corrective,                        to each affected entity varies from                    determined, with the concurrence of the
     or procedural or that do not                                      $409.70 to $2,738.84 and is not                        Administrator of the Office of
     substantially change the effect of the                            considered significant. The Commission                 Information and Regulatory Affairs of
     regulations being amended.87 The                                  did not receive any comments regarding                 OMB that this rule is not a ‘‘major rule’’
     actions here fall within this categorical                         these burden and cost estimates.                       as defined in section 351 of the Small
     exclusion in the Commission’s                                        75. Accordingly, the Commission                     Business Regulatory Enforcement
     regulations.                                                      certifies that this final rule will not have           Fairness Act of 1996. The rule will be
                                                                       a significant economic impact on a                     provided to the Senate, House,
     V. Regulatory Flexibility Act
                                                                       substantial number of small entities.                  Government Accountability Office, and
       73. The Regulatory Flexibility Act of                                                                                  the SBA.
     1980 (RFA) 88 generally requires a                                VI. Document Availability
     description and analysis of proposed                                76. In addition to publishing the full                 By the Commission. Commissioner
                                                                                                                              McIntyre is not voting on this order.
     rules that will have significant                                  text of this document in the Federal                     Issued: November 15, 2018.
     economic impact on a substantial                                  Register, the Commission provides all
                                                                                                                              Kimberly D. Bose,
     number of small entities. The definition                          interested persons an opportunity to
     of small business is provided by the                              view and/or print the contents of this                 Secretary.
     Small Business Administration (SBA) at                            document via the internet through                        Note: The following appendix will not
     13 CFR 121.201. The threshold for a                               FERC’s Home Page (http://                              appear in the Code of Federal Regulations.

                                                                         APPENDIX—LIST OF COMMENTERS
                      Abbreviation                                                                               Commenter

     Bardin ..............................................   David Bardin.
     BPA .................................................   Bonneville Power Administration.
     Idaho Power ....................................        Idaho Power Company.
     ISO NE ............................................     ISO New England Inc.
     NERC ..............................................     North American Electric Reliability Corporation.
     Reclamation ....................................        Bureau of Reclamation.
     Resilient Societies ...........................         Foundation for Resilient Societies.
     Trade Associations .........................            American Public Power Association, Edison Electric Institute, Electricity Consumers Resource Council,
                                                               Large Public Power Council, National Rural Electric Cooperative Association.
     TVA .................................................   Tennessee Valley Authority.

       86 Regulations Implementing the National                          88 5 U.S.C. 601–12.                                    90 The maximum number of employees for a

     Environmental Policy Act of 1969, Order No. 486,                    89 In the NERC Registry, there are approximately     generator owner (and its affiliates) to be ‘‘small’’
     FERC Stats. & Regs. ¶ 30,783 (1987) (cross-                       65 PCs, 188 TPs, 944 GOs, and 330 TOs (in the          varies from 250 to 750 employees, depending on the
     referenced at 41 FERC ¶ 61,284).                                  United States), which will be affected by this final   type of generation (e.g., hydroelectric, nuclear,
       87 18 CFR 380.4(a)(2)(ii) (2018).                               rule. Because some entities serve in more than one     fossil fuel, wind). For this analysis, we use the most
                                                                       role, these figures involve some double counting.      conservative threshold of 750 employees.



VerDate Sep<11>2014        16:13 Nov 23, 2018        Jkt 247001   PO 00000   Frm 00027   Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM    26NOR1


     60360            Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Rules and Regulations

     [FR Doc. 2018–25678 Filed 11–23–18; 8:45 am]            COTP Captain of the Port                              IV. Discussion of the Rule
     BILLING CODE 6717–01–P                                  DHS Department of Homeland Security
                                                             FR Federal Register                                      This rule establishes a temporary
                                                             NPRM Notice of proposed rulemaking                    safety zone on November 19, 2018
                                                             § Section                                             through November 30, 2018, within 250
     DEPARTMENT OF HOMELAND                                                                                        yards of vessels and machinery being
                                                             U.S.C. United States Code
     SECURITY                                                                                                      used by personnel to conduct diving
                                                             II. Background Information and                        and equipment recovery operations, at
     Coast Guard                                             Regulatory History                                    approximately 39°49.3002′ N Latitude,
     33 CFR Part 165                                            The Coast Guard is issuing this                    ¥75°22.8966′ W Longitude, in the
                                                             temporary rule without prior notice and               Marcus Hook Range of the Delaware
     [Docket Number USCG–2018–0913]
                                                             opportunity to comment pursuant to                    River. During diving and equipment
                                                             authority under section 4(a) of the                   recovery operations, persons or vessels
     RIN 1625–AA00
                                                             Administrative Procedure Act (APA) (5                 will not be permitted to enter the safety
     Safety Zone; Delaware River, Dredging                                                                         zone without obtaining permission from
                                                             U.S.C. 553(b)). This provision
     Operation Equipment Recovery,                                                                                 the COTP or the COTP’s designated
                                                             authorizes an agency to issue a rule
     Marcus Hook Range, Chester, PA                                                                                representative. Vessels wishing to
                                                             without prior notice and opportunity to
                                                                                                                   transit the safety zone in the clear side
     AGENCY:    Coast Guard, DHS.                            comment when the agency for good
                                                                                                                   of the main navigational channel may
                                                             cause finds that those procedures are
     ACTION:   Temporary final rule.                                                                               do so if they can make satisfactory
                                                             ‘‘impracticable, unnecessary, or contrary
                                                                                                                   passing arrangements with dredge NEW
     SUMMARY:   The Coast Guard is                           to the public interest.’’ Under 5 U.S.C.
                                                                                                                   YORK or tug INDIAN DAWN in
     establishing a temporary safety zone for                553(b)(B), the Coast Guard finds that
                                                                                                                   accordance with the Navigational Rules
     navigable waters within a 250-yard                      good cause exists for not publishing a
                                                                                                                   in 33 CFR subchapter E via VHF–FM 88
     radius of Great Lakes Dredge & Dock                     notice of proposed rulemaking (NPRM)
                                                                                                                   at least 1 hour prior to arrival and at 30
     Company vessels and machinery                           with respect to this rule because it is
                                                                                                                   minutes prior to arrival to arrange safe
     conducting emergency diving and                         impracticable and contrary to the public              passage. If vessels are unable to make
     equipment removal operations in the                     interest to do so. The rule must be                   satisfactory passing arrangements with
     Delaware River within Marcus Hook                       established by November 18, 2018, to                  the dredge NEW YORK or tug INDIAN
     Range near Chester, Pennsylvania. The                   serve its purpose of providing safety                 DAWN, they may request permission
     safety zone is needed to protect                        during the recovery of a broken hydro-                from the COTP, or his designated
     personnel, vessels, and the marine                      hammer associated with dredging                       representative, to enter and transit the
     environment from potential hazards                      operations. The Coast Guard was                       safety zone on VHF–FM channel 16. All
     created by broken equipment removal                     notified of the recovery operation                    vessels must operate at the minimum
     operations. Entry of vessels or persons                 schedule on November 18, 2018, and a                  safe speed necessary to maintain
     into this zone is prohibited unless                     safety zone must be established by                    steerage and reduce wake while
     specifically authorized by the Captain of               November 18, 2018 to address the                      transiting the safety zone. The Coast
     the Port Delaware Bay or a designated                   hazards associated with diving and                    Guard will issue a Broadcast Notice to
     representative.                                         equipment removal operations.                         Mariners via VHF–FM marine channel
     DATES: This rule is effective without                      Under 5 U.S.C. 553(d)(3), the Coast                16 and Marine Safety Information
     actual notice from November 19, 2018                    Guard finds that good cause exists for                Bulletin further defining specific work
     through November 26, 2018. For the                      making this rule effective less than 30               locations and traffic patterns.
     purposes of enforcement, actual notice                  days after publication in the Federal
                                                                                                                   V. Regulatory Analyses
     will be used from November 26, 2018                     Register. Delaying the effective date of
     through November 30, 2018. This rule                    this rule would be impracticable and                    We developed this rule after
     may be withdrawn if the project is                      contrary to the public interest because               considering numerous statutes and
     completed before the stated end date.                   immediate action is needed to mitigate                Executive orders related to rulemaking.
     This rule will be enforced continuously                 the potential safety hazards associated               Below we summarize our analyses
     each day the rule is in effect.                         with diving and equipment removal                     based on a number of these statutes and
     ADDRESSES: To view documents                            operations.                                           Executive orders, and we discuss First
     mentioned in this preamble as being                                                                           Amendment rights of protestors.
                                                             III. Legal Authority and Need for Rule
     available in the docket, go to http://
     www.regulations.gov, type USCG–2018–                                                                          A. Regulatory Planning and Review
                                                               The Coast Guard is issuing this rule
     0913 in the ‘‘SEARCH’’ box and click                    under authority in 33 U.S.C. 1231. The                   Executive Orders 12866 and 13563
     ‘‘SEARCH.’’ Click on Open Docket                        Captain of the Port Delaware Bay                      direct agencies to assess the costs and
     Folder on the line associated with this                 (COTP) has determined that potential                  benefits of available regulatory
     rule.                                                   hazards associated with emergency                     alternatives and, if regulation is
     FOR FURTHER INFORMATION CONTACT: If                     diving and equipment recovery                         necessary, to select regulatory
     you have questions on this rule, call or                operations beginning November 19,                     approaches that maximize net benefits.
     email Petty Officer Thomas Welker, U.S.                 2018, will be a safety concern for                    Executive Order 13771 directs agencies
     Coast Guard, Sector Delaware Bay,                       anyone within a 250-yard radius of                    to control regulatory costs through a
     Waterways Management Division;                          diving and equipment recovery vessels                 budgeting process. This rule has not
     telephone (215) 271–4814, email                         and machinery. This rule is needed to                 been designated a ‘‘significant
     Thomas.J.Welker@uscg.mil.                               protect personnel, vessels, and the                   regulatory action,’’ under Executive
     SUPPLEMENTARY INFORMATION:                              marine environment in the navigable                   Order 12866. Accordingly, this rule has
                                                             waters within the safety zone while the               not been reviewed by the Office of
     I. Table of Abbreviations                               operations to recover the broken hydro-               Management and Budget (OMB), and
     CFR    Code of Federal Regulations                      hammer are being conducted.                           pursuant to OMB guidance it is exempt


VerDate Sep<11>2014   16:13 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00028   Fmt 4700   Sfmt 4700   E:\FR\FM\26NOR1.SGM   26NOR1



Document Created: 2018-11-24 00:51:39
Document Modified: 2018-11-24 00:51:39
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionRules and Regulations
ActionFinal rule.
DatesThis rule will become effective January 25, 2019.
Contact. Michael Gandolfo (Technical Information), Office of Electric Reliability, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, (202) 502-6817, [email protected] Matthew Vlissides (Legal Information), Office of the General Counsel, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, (202) 502-8408, [email protected]
FR Citation83 FR 60347 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR