83_FR_60647 83 FR 60420 - Notice of Application; Mountain Valley Pipeline, LLC

83 FR 60420 - Notice of Application; Mountain Valley Pipeline, LLC

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 227 (November 26, 2018)

Page Range60420-60421
FR Document2018-25637

Federal Register, Volume 83 Issue 227 (Monday, November 26, 2018)
[Federal Register Volume 83, Number 227 (Monday, November 26, 2018)]
[Notices]
[Pages 60420-60421]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-25637]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP19-14-000; PF18-4-000]


Notice of Application; Mountain Valley Pipeline, LLC

    Take notice that on November 6, 2018, Mountain Valley Pipeline, LLC 
(Mountain Valley), 625 Liberty Avenue, Suite 2000, Pittsburgh, 
Pennsylvania 15222, filed in Docket No. CP19-14-000 an application 
pursuant to section 7(c) of the Natural Gas Act (NGA) and Parts 157 and 
284 of the Commission's regulations for authorization to construct, own 
and operate its Southgate Project located in Virginia and North 
Carolina. Specifically, Mountain Valley proposes to construct: (i) 
Approximately 73 miles of new 24-inch and 16-inch-diameter pipeline, 
(ii) the 28,915 horsepower Lambert Compressor Station in Pittsylvania 
County, Virginia, and (iii) associated valves, piping, pig launching 
and receiving facilities, and appurtenant facilities. The proposed 
Southgate Project facilities commence near the City of Chatham, in 
Pittsylvania County, Virginia and terminate at a delivery point with 
Public Service Company of North Carolina, Inc. (PSNC) near the City of 
Graham in Alamance County, North Carolina. The Project is designed to 
create 375,000 dekatherms per day (Dth/d). Mountain Valley estimates 
the cost of the Southgate Project to be $468,459,509. Mountain Valley 
requests a separate rate zone and initial recourse rates for the 
Southgate Project facilities, all as more fully set forth in the 
application which is on file with the Commission and open to public 
inspection.
    Commission staff has determined that this project qualifies as a 
Major Infrastructure Project pursuant to the Memorandum of 
Understanding Implementing One Federal Decision Under Executive Order 
13807 (MOU) signed on April 10, 2018. Major Infrastructure Projects are 
defined as projects for which multiple authorizations by Federal 
agencies will be required and the lead Federal agency has determined 
that it will prepare an Environmental Impact Statement under the 
National Environmental Policy Act, 42 U.S.C. 4321 et seq.
    The filing is available for review at the Commission in the Public 
Reference Room or may be viewed on the Commission's website web at 
http://www.ferc.gov using the ``eLibrary'' link. Enter the docket 
number excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC at 
[email protected] or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    Any questions regarding this application should be directed to 
William Lavarco, NextEra Energy, Inc., 801 Pennsylvania Ave. NW, Suite 
220, Washington, DC 20004, by telephone at (202) 347-7127, or by email 
at [email protected].
    On May 15, 2018, the Commission staff granted Mountain Valley's 
request to utilize the Pre-Filing Process and assigned Docket No. PF18-
4-000 to staff activities involved in the Southgate Project. Now, as of 
the filing of the November 6, 2018 application, the Pre-Filing Process 
for this project has ended. From this time forward, this proceeding 
will be conducted in Docket No. CP19-14-000, as noted in the caption of 
this Notice.
    Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9), 
within 90 days of this Notice, the Commission staff will either: 
Complete its environmental impact statement (EIS) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final EIS for this proposal. The filing of the final EIS in the 
Commission's public record for this proceeding or the issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 3 copies of filings made with the Commission and must provide a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list and will be 
notified of any meetings associated with the Commission's environmental 
review process. Environmental commentors will not be required to serve 
copies of filed documents on all other parties. However, the non-party 
commentors will not receive copies of all documents filed by other 
parties or issued by the Commission and will not have the right to seek 
court review of the Commission's final order.
    As of the February 27, 2018 date of the Commission's order in 
Docket No. CP16-4-001, the Commission will apply its revised practice 
concerning out-of-time motions to intervene in any new Natural Gas Act 
section 3 or section

[[Page 60421]]

7 proceeding.\1\ Persons desiring to become a party to a certificate 
proceeding are to intervene in a timely manner. If seeking to intervene 
out-of-time, the movant is required to ``show good cause why the time 
limitation should be waived,'' and should provide justification by 
reference to factors set forth in Rule 214(d)(1) of the Commission's 
Rules and Regulations.\2\
---------------------------------------------------------------------------

    \1\ Tennessee Gas Pipeline Company, L.L.C., 162 FERC ]61,167 at 
]50 (2018).
    \2\ 18 CFR 385.214(d)(1).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 3 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE, Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on December 10, 2018.

    Dated: November 19, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-25637 Filed 11-23-18; 8:45 am]
 BILLING CODE 6717-01-P



     60420                      Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Notices

     receive email notification when a                       Under Executive Order 13807 (MOU)                     obtain legal status by becoming a party
     document is added to a subscribed                       signed on April 10, 2018. Major                       to the proceedings for this project
     docket(s). For assistance with any FERC                 Infrastructure Projects are defined as                should, on or before the comment date
     Online service, please email                            projects for which multiple                           stated below, file with the Federal
     FERCOnlineSupport@ferc.gov, or call                     authorizations by Federal agencies will               Energy Regulatory Commission, 888
     (866) 208–3676 (toll free). For TTY, call               be required and the lead Federal agency               First Street NE, Washington, DC 20426,
     (202) 502–8659.                                         has determined that it will prepare an                a motion to intervene in accordance
       Comment Date: 5:00 p.m. Eastern                       Environmental Impact Statement under                  with the requirements of the
     Time on November 28, 2018.                              the National Environmental Policy Act,                Commission’s Rules of Practice and
       Dated: November 16, 2018.                             42 U.S.C. 4321 et seq.                                Procedure (18 CFR 385.214 or 385.211)
                                                                The filing is available for review at              and the Regulations under the NGA (18
     Kimberly D. Bose,
                                                             the Commission in the Public Reference                CFR 157.10). A person obtaining party
     Secretary.                                              Room or may be viewed on the
     [FR Doc. 2018–25586 Filed 11–23–18; 8:45 am]
                                                                                                                   status will be placed on the service list
                                                             Commission’s website web at http://
                                                                                                                   maintained by the Secretary of the
     BILLING CODE 6717–01–P                                  www.ferc.gov using the ‘‘eLibrary’’ link.
                                                                                                                   Commission and will receive copies of
                                                             Enter the docket number excluding the
                                                                                                                   all documents filed by the applicant and
                                                             last three digits in the docket number
     DEPARTMENT OF ENERGY                                    field to access the document. For                     by all other parties. A party must submit
                                                             assistance, contact FERC at                           3 copies of filings made with the
     Federal Energy Regulatory                               FERCOnlineSupport@ferc.gov or call                    Commission and must provide a copy to
     Commission                                              toll-free, (886) 208–3676 or TYY, (202)               the applicant and to every other party in
     [Docket No. CP19–14–000; PF18–4–000]                    502–8659.                                             the proceeding. Only parties to the
                                                                Any questions regarding this                       proceeding can ask for court review of
     Notice of Application; Mountain Valley                  application should be directed to                     Commission orders in the proceeding.
     Pipeline, LLC                                           William Lavarco, NextEra Energy, Inc.,                   However, a person does not have to
                                                             801 Pennsylvania Ave. NW, Suite 220,                  intervene in order to have comments
        Take notice that on November 6,                      Washington, DC 20004, by telephone at
     2018, Mountain Valley Pipeline, LLC                                                                           considered. The second way to
                                                             (202) 347–7127, or by email at                        participate is by filing with the
     (Mountain Valley), 625 Liberty Avenue,                  William.Lavarco@nee.com.
     Suite 2000, Pittsburgh, Pennsylvania                                                                          Secretary of the Commission, as soon as
                                                                On May 15, 2018, the Commission                    possible, an original and two copies of
     15222, filed in Docket No. CP19–14–000                  staff granted Mountain Valley’s request
     an application pursuant to section 7(c)                                                                       comments in support of or in opposition
                                                             to utilize the Pre-Filing Process and                 to this project. The Commission will
     of the Natural Gas Act (NGA) and Parts                  assigned Docket No. PF18–4–000 to staff
     157 and 284 of the Commission’s                                                                               consider these comments in
                                                             activities involved in the Southgate
     regulations for authorization to                                                                              determining the appropriate action to be
                                                             Project. Now, as of the filing of the
     construct, own and operate its                                                                                taken, but the filing of a comment alone
                                                             November 6, 2018 application, the Pre-
     Southgate Project located in Virginia                                                                         will not serve to make the filer a party
                                                             Filing Process for this project has ended.
     and North Carolina. Specifically,                       From this time forward, this proceeding               to the proceeding. The Commission’s
     Mountain Valley proposes to construct:                  will be conducted in Docket No. CP19–                 rules require that persons filing
     (i) Approximately 73 miles of new 24-                   14–000, as noted in the caption of this               comments in opposition to the project
     inch and 16-inch-diameter pipeline, (ii)                Notice.                                               provide copies of their protests only to
     the 28,915 horsepower Lambert                              Pursuant to section 157.9 of the                   the party or parties directly involved in
     Compressor Station in Pittsylvania                      Commission’s rules (18 CFR 157.9),                    the protest.
     County, Virginia, and (iii) associated                  within 90 days of this Notice, the                       Persons who wish to comment only
     valves, piping, pig launching and                       Commission staff will either: Complete                on the environmental review of this
     receiving facilities, and appurtenant                   its environmental impact statement                    project should submit an original and
     facilities. The proposed Southgate                      (EIS) and place it into the Commission’s              two copies of their comments to the
     Project facilities commence near the                    public record (eLibrary) for this                     Secretary of the Commission.
     City of Chatham, in Pittsylvania County,                proceeding; or issue a Notice of                      Environmental commentors will be
     Virginia and terminate at a delivery                    Schedule for Environmental Review. If                 placed on the Commission’s
     point with Public Service Company of                    a Notice of Schedule for Environmental                environmental mailing list and will be
     North Carolina, Inc. (PSNC) near the                    Review is issued, it will indicate, among             notified of any meetings associated with
     City of Graham in Alamance County,                      other milestones, the anticipated date                the Commission’s environmental review
     North Carolina. The Project is designed                 for the Commission staff’s issuance of                process. Environmental commentors
     to create 375,000 dekatherms per day                    the final EIS for this proposal. The filing           will not be required to serve copies of
     (Dth/d). Mountain Valley estimates the                  of the final EIS in the Commission’s                  filed documents on all other parties.
     cost of the Southgate Project to be                     public record for this proceeding or the              However, the non-party commentors
     $468,459,509. Mountain Valley requests                  issuance of a Notice of Schedule for                  will not receive copies of all documents
     a separate rate zone and initial recourse               Environmental Review will serve to                    filed by other parties or issued by the
     rates for the Southgate Project facilities,             notify federal and state agencies of the              Commission and will not have the right
     all as more fully set forth in the                      timing for the completion of all                      to seek court review of the
     application which is on file with the                   necessary reviews, and the subsequent                 Commission’s final order.
     Commission and open to public                           need to complete all federal
     inspection.                                             authorizations within 90 days of the                     As of the February 27, 2018 date of
        Commission staff has determined that                 date of issuance of the Commission                    the Commission’s order in Docket No.
     this project qualifies as a Major                       staff’s FEIS.                                         CP16–4–001, the Commission will
     Infrastructure Project pursuant to the                     There are two ways to become                       apply its revised practice concerning
     Memorandum of Understanding                             involved in the Commission’s review of                out-of-time motions to intervene in any
     Implementing One Federal Decision                       this project. First, any person wishing to            new Natural Gas Act section 3 or section


VerDate Sep<11>2014   17:28 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00030   Fmt 4703   Sfmt 4703   E:\FR\FM\26NON1.SGM   26NON1


                                Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Notices                                                 60421

     7 proceeding.1 Persons desiring to                      long, 30-foot-wide channel; (2) an upper              www.ferc.gov/docs-filing/efiling.asp.
     become a party to a certificate                         reservoir with a surface area of 488.52               Commenters can submit brief comments
     proceeding are to intervene in a timely                 acres and a storage capacity of 43,633                up to 6,000 characters, without prior
     manner. If seeking to intervene out-of-                 acre-feet; (3) a 98.4-foot-long, 39.4-foot-           registration, using the eComment system
     time, the movant is required to ‘‘show                  high concrete upper intake/outlet                     at http://www.ferc.gov/docs-filing/
     good cause why the time limitation                      structure; (4) a 6,370-foot-long, 27.8-               ecomment.asp. You must include your
     should be waived,’’ and should provide                  foot-diameter steel and concrete                      name and contact information at the end
     justification by reference to factors set               headrace tunnel; (5) a 545-foot-long, 90-             of your comments. For assistance,
     forth in Rule 214(d)(1) of the                          foot-wide, 185.4-foot-high underground                please contact FERC Online Support at
     Commission’s Rules and Regulations.2                    concrete pumping station/powerhouse                   FERCOnlineSupport@ferc.gov, (866)
       The Commission strongly encourages                    containing four pump/generating units                 208–3676 (toll free), or (202) 502–8659
     electronic filings of comments, protests                with a total capacity of 1,200 megawatts;             (TTY). In lieu of electronic filing, please
     and interventions in lieu of paper using                (6) a 7,439-foot-long, 27.8-foot-diameter             send a paper copy to: Secretary, Federal
     the ‘‘eFiling’’ link at http://                         tailrace tunnel; (7) a 98.4-foot-long,                Energy Regulatory Commission, 888
     www.ferc.gov. Persons unable to file                    39.4-foot-high concrete lower intake/                 First Street NE, Washington, DC 20426.
     electronically should submit an original                outlet structure; (8) a 9,957-foot-long,              The first page of any filing should
     and 3 copies of the protest or                          52.5-foot-high earthen lower dam with a               include docket number P–14887–000.
     intervention to the Federal Energy                      33-foot-long, 13-foot-high emergency                     More information about this project,
     regulatory Commission, 888 First Street                 spillway with a 1,640-foot-long tunnel                including a copy of the application, can
     NE, Washington, DC 20426.                               to the Kiamichi River; (9) a lower                    be viewed or printed on the ‘‘eLibrary’’
       Comment Date: 5:00 p.m. Eastern                       reservoir with a surface area of 727                  link of Commission’s website at http://
     Time on December 10, 2018.                              acres, and a storage capacity of 37,965               www.ferc.gov/docs-filing/elibrary.asp.
       Dated: November 19, 2018.                             acre-feet; (10) two 20-inch-diameter,                 Enter the docket number (P–14887) in
     Kimberly D. Bose,                                       675-foot-long pipes with 110 kilowatt                 the docket number field to access the
     Secretary.                                              pumps from the lower reservoir to the                 document. For assistance, contact FERC
                                                             regulating reservoir; (11) a regulating               Online Support.
     [FR Doc. 2018–25637 Filed 11–23–18; 8:45 am]
                                                             reservoir with a surface area of 40 acres,
     BILLING CODE 6717–01–P                                                                                          Dated: November 16, 2018.
                                                             and a storage capacity of 1,216 acre-feet;
                                                             (12) two 20-inch-diameter, 690-foot-long              Kimberly D. Bose,
                                                             pipes with two 110 kilowatt pumps                     Secretary.
     DEPARTMENT OF ENERGY
                                                             from the Kiamichi River to the                        [FR Doc. 2018–25585 Filed 11–23–18; 8:45 am]
     Federal Energy Regulatory                               regulating reservoir; (13) a 40-foot-long,            BILLING CODE 6717–01–P
     Commission                                              40-foot-wide funnel shaped intake
                                                             structure on the Kiamichi River, located
     [Project No. 14887–000]                                 1.5-foot above the bottom of the                      DEPARTMENT OF ENERGY
                                                             Kiamichi River tapering down to 10-
     Southeast Oklahoma Power                                                                                      Federal Energy Regulatory
                                                             foot-long, 10-foot-wide section where it
     Corporation; Notice of Preliminary                                                                            Commission
                                                             connects to the two pipes; and (14) a
     Permit Application Accepted for Filing
                                                             124-mile-long transmission line to the                [Docket No. CP18–525–000]
     and Soliciting Comments, Motions To
                                                             Electric Reliability Council of Texas
     Intervene, and Competing Applications
                                                             grid.                                                 Notice of Schedule for Environmental
        1. On July 31, 2018, Southeast                          The proposed project would relocate                Review of the Gulf South Pipeline
     Oklahoma Power Corporation, filed an                    State Road 248 (Post Oar Road) and                    Company, LP—Willis Lateral Project
     application for a preliminary permit,                   583rd Street because the lower reservoir
     pursuant to section 4(f) of the Federal                 would otherwise inundate them. The                       On July 13, 2018, Gulf South Pipeline
     Power Act (FPA), proposing to study the                 proposed project would have an                        Company, LP (Gulf South) filed an
     feasibility of the Southeast Oklahoma                   estimated average annual generation of                application in Docket No. CP18–525–
     Pumped Storage Hydroelectric Project                    4,368,000 megawatt-hours.                             000 requesting a Certificate of Public
     (project) to be located on the Kiamichi                    Applicant Contact: Mr. John Bobenic,               Convenience and Necessity pursuant to
     River, near the town of Whitesboro, in                  Southeast Oklahoma Power                              section 7(c) of the Natural Gas Act to
     LeFlore County, Oklahoma. The sole                      Corporation, c/o Daytona Power Corp,                  construct and operate certain natural gas
     purpose of a preliminary permit, if                     1800, 421–7 Avenue SW, Calgary,                       pipeline facilities. The proposed project
     issued, is to grant the permit holder                   Alberta Canada T2P 4K9; phone: (578)                  is known as the Willis Lateral Project
     priority to file a license application                  433–4933.                                             (Project), and would provide about 200
     during the permit term. A preliminary                      FERC Contact: Michael Spencer, (202)               million cubic feet of natural gas per day
     permit does not authorize the permit                    502–6093, michael.spencer@ferc.gov.                   to Entergy Texas, Inc.’s Montgomery
     holder to perform any land-disturbing                      Deadline for filing comments, motions              County Power Station Project near
     activities or otherwise enter upon lands                to intervene, competing applications                  Willis, Texas.
     or waters owned by others without the                   (without notices of intent), or notices of               On July 26, 2018, the Federal Energy
     owners’ express permission.                             intent to file competing applications: 60             Regulatory Commission (Commission or
        2. The proposed project would consist                days from the issuance of this notice.                FERC) issued its Notice of Application
     of the following: (1) A 2,165-foot-long,                Competing applications and notices of                 for the Project. Among other things, that
     302-foot-high concrete-faced rockfill                   intent must meet the requirements of 18               notice alerted agencies issuing federal
     upper dam with a 196.85-foot-long                       CFR 4.36.                                             authorizations of the requirement to
     emergency spillway with a 600-foot-                        The Commission strongly encourages                 complete all necessary reviews and to
                                                             electronic filing. Please file comments,              reach a final decision on a request for
       1 Tennessee Gas Pipeline Company, L.L.C., 162         motions to intervene, notices of intent,              a federal authorization within 90 days of
     FERC ¶61,167 at ¶50 (2018).                             and competing applications using the                  the date of issuance of the Commission
       2 18 CFR 385.214(d)(1).                               Commission’s eFiling system at http://                staff’s Environmental Assessment (EA)


VerDate Sep<11>2014   17:28 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00031   Fmt 4703   Sfmt 4703   E:\FR\FM\26NON1.SGM   26NON1



Document Created: 2018-11-24 00:51:06
Document Modified: 2018-11-24 00:51:06
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Time on December 10, 2018.
FR Citation83 FR 60420 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR