83_FR_60648 83 FR 60421 - Notice of Schedule for Environmental Review of the Gulf South Pipeline Company, LP-Willis Lateral Project

83 FR 60421 - Notice of Schedule for Environmental Review of the Gulf South Pipeline Company, LP-Willis Lateral Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 227 (November 26, 2018)

Page Range60421-60422
FR Document2018-25641

Federal Register, Volume 83 Issue 227 (Monday, November 26, 2018)
[Federal Register Volume 83, Number 227 (Monday, November 26, 2018)]
[Notices]
[Pages 60421-60422]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-25641]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-525-000]


Notice of Schedule for Environmental Review of the Gulf South 
Pipeline Company, LP--Willis Lateral Project

    On July 13, 2018, Gulf South Pipeline Company, LP (Gulf South) 
filed an application in Docket No. CP18-525-000 requesting a 
Certificate of Public Convenience and Necessity pursuant to section 
7(c) of the Natural Gas Act to construct and operate certain natural 
gas pipeline facilities. The proposed project is known as the Willis 
Lateral Project (Project), and would provide about 200 million cubic 
feet of natural gas per day to Entergy Texas, Inc.'s Montgomery County 
Power Station Project near Willis, Texas.
    On July 26, 2018, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA)

[[Page 60422]]

for the Project. This instant notice identifies the FERC staff's 
planned schedule for the completion of the EA for the Project.

Schedule for Environmental Review

Issuance of EA--March 4, 2019
90-day Federal Authorization Decision Deadline--June 2, 2019

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    The Project would consist of the following facilities entirely 
within the state of Texas:
     Construction of approximately 19 miles of 24-inch-diameter 
pipeline in Montgomery and San Jacinto Counties;
     addition of a new 15,876 horsepower turbine engine to the 
existing Goodrich Compressor Station and construction of a new Meter 
and Regulator (M&R) station at the compressor station in Polk County;
     construction of the Index 129 tie-in and pig \1\ launcher 
facility in San Jacinto County;
---------------------------------------------------------------------------

    \1\ A ``pig'' is a tool that the pipeline company inserts into 
and pushes through the pipeline for cleaning the pipeline, 
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------

     construction of the new Willis M&R station at the terminus 
of the Project (including a pig receiver, filter separators with a 
liquid storage tank, and ancillary equipment) in Montgomery County; and
     construction of a mainline valve facility in Montgomery 
County.

Background

    On August 31, 2018, the Commission issued a Notice of Intent to 
Prepare an Environmental Assessment for the Proposed Willis Lateral 
Project, And Request for Comments on Environmental Issues (NOI). The 
NOI was sent to affected landowners; federal, state, and local 
government agencies; elected officials; environmental and public 
interest groups; Native American tribes; other interested parties; and 
local libraries and newspapers.
    In response to the Notice of Application, the Commission received 
comments from the Texas Parks and Wildlife Department regarding 
appropriate best management practices for construction and restoration, 
special status species, surface water, and impacts on vegetation and 
wildlife. All substantive comments will be addressed in the EA. No 
comments were received in response to the NOI.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the projects are available from the 
Commission's
    Office of External Affairs at (866) 208-FERC or on the FERC website 
(www.ferc.gov). Using the ``eLibrary'' link, select ``General Search'' 
from the eLibrary menu, enter the selected date range and ``Docket 
Number'' excluding the last three digits (i.e., CP18-525), and follow 
the instructions. For assistance with access to eLibrary, the helpline 
can be reached at (866) 208-3676, TTY (202) 502-8659, or at 
FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

    Dated: November 19, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-25641 Filed 11-23-18; 8:45 am]
 BILLING CODE 6717-01-P



                                Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Notices                                                 60421

     7 proceeding.1 Persons desiring to                      long, 30-foot-wide channel; (2) an upper              www.ferc.gov/docs-filing/efiling.asp.
     become a party to a certificate                         reservoir with a surface area of 488.52               Commenters can submit brief comments
     proceeding are to intervene in a timely                 acres and a storage capacity of 43,633                up to 6,000 characters, without prior
     manner. If seeking to intervene out-of-                 acre-feet; (3) a 98.4-foot-long, 39.4-foot-           registration, using the eComment system
     time, the movant is required to ‘‘show                  high concrete upper intake/outlet                     at http://www.ferc.gov/docs-filing/
     good cause why the time limitation                      structure; (4) a 6,370-foot-long, 27.8-               ecomment.asp. You must include your
     should be waived,’’ and should provide                  foot-diameter steel and concrete                      name and contact information at the end
     justification by reference to factors set               headrace tunnel; (5) a 545-foot-long, 90-             of your comments. For assistance,
     forth in Rule 214(d)(1) of the                          foot-wide, 185.4-foot-high underground                please contact FERC Online Support at
     Commission’s Rules and Regulations.2                    concrete pumping station/powerhouse                   FERCOnlineSupport@ferc.gov, (866)
       The Commission strongly encourages                    containing four pump/generating units                 208–3676 (toll free), or (202) 502–8659
     electronic filings of comments, protests                with a total capacity of 1,200 megawatts;             (TTY). In lieu of electronic filing, please
     and interventions in lieu of paper using                (6) a 7,439-foot-long, 27.8-foot-diameter             send a paper copy to: Secretary, Federal
     the ‘‘eFiling’’ link at http://                         tailrace tunnel; (7) a 98.4-foot-long,                Energy Regulatory Commission, 888
     www.ferc.gov. Persons unable to file                    39.4-foot-high concrete lower intake/                 First Street NE, Washington, DC 20426.
     electronically should submit an original                outlet structure; (8) a 9,957-foot-long,              The first page of any filing should
     and 3 copies of the protest or                          52.5-foot-high earthen lower dam with a               include docket number P–14887–000.
     intervention to the Federal Energy                      33-foot-long, 13-foot-high emergency                     More information about this project,
     regulatory Commission, 888 First Street                 spillway with a 1,640-foot-long tunnel                including a copy of the application, can
     NE, Washington, DC 20426.                               to the Kiamichi River; (9) a lower                    be viewed or printed on the ‘‘eLibrary’’
       Comment Date: 5:00 p.m. Eastern                       reservoir with a surface area of 727                  link of Commission’s website at http://
     Time on December 10, 2018.                              acres, and a storage capacity of 37,965               www.ferc.gov/docs-filing/elibrary.asp.
       Dated: November 19, 2018.                             acre-feet; (10) two 20-inch-diameter,                 Enter the docket number (P–14887) in
     Kimberly D. Bose,                                       675-foot-long pipes with 110 kilowatt                 the docket number field to access the
     Secretary.                                              pumps from the lower reservoir to the                 document. For assistance, contact FERC
                                                             regulating reservoir; (11) a regulating               Online Support.
     [FR Doc. 2018–25637 Filed 11–23–18; 8:45 am]
                                                             reservoir with a surface area of 40 acres,
     BILLING CODE 6717–01–P                                                                                          Dated: November 16, 2018.
                                                             and a storage capacity of 1,216 acre-feet;
                                                             (12) two 20-inch-diameter, 690-foot-long              Kimberly D. Bose,
                                                             pipes with two 110 kilowatt pumps                     Secretary.
     DEPARTMENT OF ENERGY
                                                             from the Kiamichi River to the                        [FR Doc. 2018–25585 Filed 11–23–18; 8:45 am]
     Federal Energy Regulatory                               regulating reservoir; (13) a 40-foot-long,            BILLING CODE 6717–01–P
     Commission                                              40-foot-wide funnel shaped intake
                                                             structure on the Kiamichi River, located
     [Project No. 14887–000]                                 1.5-foot above the bottom of the                      DEPARTMENT OF ENERGY
                                                             Kiamichi River tapering down to 10-
     Southeast Oklahoma Power                                                                                      Federal Energy Regulatory
                                                             foot-long, 10-foot-wide section where it
     Corporation; Notice of Preliminary                                                                            Commission
                                                             connects to the two pipes; and (14) a
     Permit Application Accepted for Filing
                                                             124-mile-long transmission line to the                [Docket No. CP18–525–000]
     and Soliciting Comments, Motions To
                                                             Electric Reliability Council of Texas
     Intervene, and Competing Applications
                                                             grid.                                                 Notice of Schedule for Environmental
        1. On July 31, 2018, Southeast                          The proposed project would relocate                Review of the Gulf South Pipeline
     Oklahoma Power Corporation, filed an                    State Road 248 (Post Oar Road) and                    Company, LP—Willis Lateral Project
     application for a preliminary permit,                   583rd Street because the lower reservoir
     pursuant to section 4(f) of the Federal                 would otherwise inundate them. The                       On July 13, 2018, Gulf South Pipeline
     Power Act (FPA), proposing to study the                 proposed project would have an                        Company, LP (Gulf South) filed an
     feasibility of the Southeast Oklahoma                   estimated average annual generation of                application in Docket No. CP18–525–
     Pumped Storage Hydroelectric Project                    4,368,000 megawatt-hours.                             000 requesting a Certificate of Public
     (project) to be located on the Kiamichi                    Applicant Contact: Mr. John Bobenic,               Convenience and Necessity pursuant to
     River, near the town of Whitesboro, in                  Southeast Oklahoma Power                              section 7(c) of the Natural Gas Act to
     LeFlore County, Oklahoma. The sole                      Corporation, c/o Daytona Power Corp,                  construct and operate certain natural gas
     purpose of a preliminary permit, if                     1800, 421–7 Avenue SW, Calgary,                       pipeline facilities. The proposed project
     issued, is to grant the permit holder                   Alberta Canada T2P 4K9; phone: (578)                  is known as the Willis Lateral Project
     priority to file a license application                  433–4933.                                             (Project), and would provide about 200
     during the permit term. A preliminary                      FERC Contact: Michael Spencer, (202)               million cubic feet of natural gas per day
     permit does not authorize the permit                    502–6093, michael.spencer@ferc.gov.                   to Entergy Texas, Inc.’s Montgomery
     holder to perform any land-disturbing                      Deadline for filing comments, motions              County Power Station Project near
     activities or otherwise enter upon lands                to intervene, competing applications                  Willis, Texas.
     or waters owned by others without the                   (without notices of intent), or notices of               On July 26, 2018, the Federal Energy
     owners’ express permission.                             intent to file competing applications: 60             Regulatory Commission (Commission or
        2. The proposed project would consist                days from the issuance of this notice.                FERC) issued its Notice of Application
     of the following: (1) A 2,165-foot-long,                Competing applications and notices of                 for the Project. Among other things, that
     302-foot-high concrete-faced rockfill                   intent must meet the requirements of 18               notice alerted agencies issuing federal
     upper dam with a 196.85-foot-long                       CFR 4.36.                                             authorizations of the requirement to
     emergency spillway with a 600-foot-                        The Commission strongly encourages                 complete all necessary reviews and to
                                                             electronic filing. Please file comments,              reach a final decision on a request for
       1 Tennessee Gas Pipeline Company, L.L.C., 162         motions to intervene, notices of intent,              a federal authorization within 90 days of
     FERC ¶61,167 at ¶50 (2018).                             and competing applications using the                  the date of issuance of the Commission
       2 18 CFR 385.214(d)(1).                               Commission’s eFiling system at http://                staff’s Environmental Assessment (EA)


VerDate Sep<11>2014   17:28 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00031   Fmt 4703   Sfmt 4703   E:\FR\FM\26NON1.SGM   26NON1


     60422                      Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Notices

     for the Project. This instant notice                     Additional Information                                Public comments were previously
     identifies the FERC staff’s planned                         In order to receive notification of the            requested via the Federal Register on
     schedule for the completion of the EA                    issuance of the EA and to keep track of               August 3, 2018 during a 60-day
     for the Project.                                         all formal issuances and submittals in                comment period. This notice allows for
                                                              specific dockets, the Commission offers               an additional 30 days for public
     Schedule for Environmental Review                                                                              comments. A fuller description of the
                                                              a free service called eSubscription. This
     Issuance of EA—March 4, 2019                             can reduce the amount of time you                     ICR is given below, including its
     90-day Federal Authorization Decision                    spend researching proceedings by                      estimated burden and cost to the public.
        Deadline—June 2, 2019                                 automatically providing you with                      An agency may not conduct or sponsor
        If a schedule change becomes                          notification of these filings, document               and a person is not required to respond
     necessary, additional notice will be                     summaries, and direct links to the                    to a collection of information unless it
     provided so that the relevant agencies                   documents. Go to www.ferc.gov/docs-                   displays a currently valid OMB control
     are kept informed of the Project’s                       filing/esubscription.asp.                             number.
     progress.                                                   Additional information about the                   DATES: Additional comments may be
                                                              projects are available from the                       submitted on or before December 26,
     Project Description                                                                                            2018.
                                                              Commission’s
        The Project would consist of the                         Office of External Affairs at (866) 208–           ADDRESSES: Submit your comments,
     following facilities entirely within the                 FERC or on the FERC website                           referencing Docket ID No. EPA–HQ–
     state of Texas:                                          (www.ferc.gov). Using the ‘‘eLibrary’’                OLEM–2018–0543, to (1) EPA, either
        • Construction of approximately 19                    link, select ‘‘General Search’’ from the              online using www.regulations.gov (our
     miles of 24-inch-diameter pipeline in                    eLibrary menu, enter the selected date                preferred method), or by email to rcra-
     Montgomery and San Jacinto Counties;                     range and ‘‘Docket Number’’ excluding                 docket@epa.gov, or by mail to: RCRA
        • addition of a new 15,876                            the last three digits (i.e., CP18–525), and           Docket (2822T), U.S. Environmental
     horsepower turbine engine to the                         follow the instructions. For assistance               Protection Agency, 1200 Pennsylvania
     existing Goodrich Compressor Station                     with access to eLibrary, the helpline can             Avenue NW, Washington, DC 20460;
     and construction of a new Meter and                      be reached at (866) 208–3676, TTY (202)               and (2) OMB via email to oira_
     Regulator (M&R) station at the                           502–8659, or at FERCOnlineSupport@                    submission@omb.eop.gov. Address
     compressor station in Polk County;                       ferc.gov. The eLibrary link on the FERC               comments to OMB Desk Officer for EPA.
        • construction of the Index 129 tie-in                website also provides access to the texts               EPA’s policy is that all comments
     and pig 1 launcher facility in San Jacinto               of formal documents issued by the                     received will be included in the public
     County;                                                  Commission, such as orders, notices,                  docket without change including any
        • construction of the new Willis M&R                  and rule makings.                                     personal information provided, unless
     station at the terminus of the Project                     Dated: November 19, 2018.                           the comment includes profanity, threats,
     (including a pig receiver, filter                                                                              information claimed to be Confidential
                                                              Kimberly D. Bose,
     separators with a liquid storage tank,                                                                         Business Information (CBI) or other
                                                              Secretary.
     and ancillary equipment) in                                                                                    information whose disclosure is
     Montgomery County; and                                   [FR Doc. 2018–25641 Filed 11–23–18; 8:45 am]
                                                                                                                    restricted by statute.
        • construction of a mainline valve                    BILLING CODE 6717–01–P
                                                                                                                    FOR FURTHER INFORMATION CONTACT:
     facility in Montgomery County.                                                                                 Peggy Vyas, Environmental Protection
     Background                                                                                                     Agency, 1200 Pennsylvania Ave. NW,
                                                              ENVIRONMENTAL PROTECTION                              Washington, DC 20460; telephone
        On August 31, 2018, the Commission                    AGENCY                                                number: 703–308–5477; fax number:
     issued a Notice of Intent to Prepare an                  [EPA–HQ–OLEM–2018–0543, FRL–9986–08–                  703–308–8433; email address:
     Environmental Assessment for the                         OEI]                                                  vyas.peggy@epa.gov.
     Proposed Willis Lateral Project, And                                                                           SUPPLEMENTARY INFORMATION:
     Request for Comments on                                  Agency Information Collection                         Supporting documents, which explain
     Environmental Issues (NOI). The NOI                      Activities; Submission to OMB for                     in detail the information that the EPA
     was sent to affected landowners; federal,                Review and Approval; Comment                          will be collecting, are available in the
     state, and local government agencies;                    Request; Hazardous Remediation                        public docket for this ICR. The docket
     elected officials; environmental and                     Waste Management Requirements                         can be viewed online at
     public interest groups; Native American                  (HWIR) Contaminated Media (Renewal)                   www.regulations.gov or in person at the
     tribes; other interested parties; and local                                                                    EPA Docket Center, WJC West, Room
     libraries and newspapers.                                AGENCY: Environmental Protection
                                                              Agency (EPA).                                         3334, 1301 Constitution Ave. NW,
        In response to the Notice of                                                                                Washington, DC. The telephone number
     Application, the Commission received                     ACTION: Notice.
                                                                                                                    for the Docket Center is 202–566–1744.
     comments from the Texas Parks and                        SUMMARY:   The Environmental Protection               For additional information about EPA’s
     Wildlife Department regarding                            Agency (EPA) has submitted an                         public docket, visit http://www.epa.gov/
     appropriate best management practices                    information collection request (ICR),                 dockets.
     for construction and restoration, special                Hazardous Remediation Waste                             Abstract: The Resource Conservation
     status species, surface water, and                       Management Requirements (HWIR)                        and Recovery Act (RCRA) requires EPA
     impacts on vegetation and wildlife. All                  Contaminated Media (EPA ICR No.                       to establish a national regulatory
     substantive comments will be addressed                   1775.08, OMB Control No. 2050–0161),                  program to ensure that hazardous
     in the EA. No comments were received                     to the Office of Management and Budget                wastes are managed in a manner
     in response to the NOI.                                  (OMB) for review and approval in                      protective of human health and the
       1 A ‘‘pig’’ is a tool that the pipeline company
                                                              accordance with the Paperwork                         environment. Under this program, EPA
     inserts into and pushes through the pipeline for
                                                              Reduction Act. This is a proposed                     regulates newly generated hazardous
     cleaning the pipeline, conducting internal               extension of the ICR, which is currently              wastes, as well as hazardous
     inspections, or other purposes.                          approved through November 30, 2018.                   remediation wastes (i.e., hazardous


VerDate Sep<11>2014   17:28 Nov 23, 2018   Jkt 247001    PO 00000   Frm 00032   Fmt 4703   Sfmt 4703   E:\FR\FM\26NON1.SGM   26NON1



Document Created: 2018-11-24 00:51:51
Document Modified: 2018-11-24 00:51:51
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 60421 