83_FR_60735 83 FR 60508 - Omaha Public Power District, Fort Calhoun Station, Unit No. 1, Partial Site Release

83 FR 60508 - Omaha Public Power District, Fort Calhoun Station, Unit No. 1, Partial Site Release

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 83, Issue 227 (November 26, 2018)

Page Range60508-60509
FR Document2018-25666

The U.S. Nuclear Regulatory Commission (NRC) is considering two requests from the Omaha Public Power District (OPPD) to approve the release of land areas, under the control of the NRC power reactor license for the Fort Calhoun Station, Unit No. 1 (FCS), License No. DPR-40, of portions of their owned-controlled property and an easement- controlled land area for unrestricted use. The NRC will review the requests and the result of NRC confirmatory surveys of the properties proposed for release. Approval of the request would allow OPPD to sell the released portion of the owner-controlled property, to the north and west of the plant in Nebraska, and to release the easement on the other property, to the north and east of the plant, in Iowa. The NRC is soliciting public comment on the requested actions and invites stakeholders and interested persons to participate. The NRC plans to hold a public meeting to promote full understanding of the requested actions and to facilitate public comment.

Federal Register, Volume 83 Issue 227 (Monday, November 26, 2018)
[Federal Register Volume 83, Number 227 (Monday, November 26, 2018)]
[Notices]
[Pages 60508-60509]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-25666]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-285; NRC-2018-0268]


Omaha Public Power District, Fort Calhoun Station, Unit No. 1, 
Partial Site Release

AGENCY: Nuclear Regulatory Commission.

ACTION: Partial site release; public meeting and request for comment.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is considering 
two requests from the Omaha Public Power District (OPPD) to approve the 
release of land areas, under the control of the NRC power reactor 
license for the Fort Calhoun Station, Unit No. 1 (FCS), License No. 
DPR-40, of portions of their owned-controlled property and an easement-
controlled land area for unrestricted use. The NRC will review the 
requests and the result of NRC confirmatory surveys of the properties 
proposed for release. Approval of the request would allow OPPD to sell 
the released portion of the owner-controlled property, to the north and 
west of the plant in Nebraska, and to release the easement on the other 
property, to the north and east of the plant, in Iowa. The NRC is 
soliciting public comment on the requested actions and invites 
stakeholders and interested persons to participate. The NRC plans to 
hold a public meeting to promote full understanding of the requested 
actions and to facilitate public comment.

DATES: Submit comments by December 26, 2018. Comments received after 
this date will be considered if it is practical to do so, but the 
Commission is able to ensure consideration only for comments received 
before this date. A public meeting will be held on November 28, 2018.

ADDRESSES: You may submit comments by any of the following methods:
     Federal Rulemaking website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0268. Address 
questions about Docket IDs in Regulations.gov to Jennifer Borges; 
telephone: 301-287-9127; email: [email protected]. For technical 
questions, contact the individual listed in the FOR FURTHER INFORMATION 
CONTACT section of this document.
     Mail comments to: May Ma, Office of Administration, Mail 
Stop: TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Jack Parrott, Office of Nuclear 
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001; telephone: 301-415-6634; email: 
[email protected].

SUPPLEMENTARY INFORMATION:

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2018-0268. You may obtain publicly-
available information related to this action by any of the following 
methods:
     Federal Rulemaking website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0268.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to [email protected]. The ``Fort Calhoun Station, Unit 1--
Request for Partial Site Release'' and ``Fort Calhoun Station, Unit 1--
Request for Partial Site Release Phase 2'' are available in ADAMS under 
Nos. ML18215A187 and ML18316A036, respectively.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments

    Please include Docket ID NRC-2018-0268. The NRC cautions you not to 
include identifying or contact information that you do not want to be 
publicly disclosed in your comment submission. The NRC will post all 
comment submissions at http://www.regulations.gov as well as enter the 
comment submissions into ADAMS. The NRC does not routinely edit comment 
submissions to remove identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment into ADAMS.

II. Background

    The NRC has received two requests for approval of partial site 
releases from the Omaha Public Power District (OPPD or licensee), by 
letters dated June 29, 2018 (ADAMS Accession No. ML18215A187) and 
November 12, 2018 (ADAMS Accession No. ML18316A036). The requests seek 
approval for release for unrestricted use of a portion of the Fort 
Calhoun Station, Unit No. 1 (FCS) site located at 9610 Power Lane, 
Blair, Nebraska. The first proposed release area is a 120-acre portion 
on the north

[[Page 60509]]

and west side of the licensee-controlled facility property, wholly 
within the State of Nebraska. The second proposed release area involves 
a 475-acre parcel of land north and east of the site, located on the 
banks of the Missouri River on the Iowa side of the Iowa-Nebraska 
border, on which the licensee currently has an easement and that is 
part of the exclusion area of the plant.
    The FCS license (NRC License No. DPR-40, Docket No. 50-285) is for 
a power reactor under part 50, ``Domestic Licensing of Production and 
Utilization Facilities,'' of title 10 of the Code of Federal 
Regulations (10 CFR). The facility was certified as permanently shut 
down, per NRC regulations in 10 CFR 50.82(a), by letter dated November 
13, 2016. FCS is currently in ``SAFSTOR'' decommissioning mode awaiting 
the termination of the power reactor license.
    The licensee requests release from the NRC license, for 
unrestricted use, of two portions of the site under 10 CFR 50.83, 
``Release of Part of a Power Reactor Facility or Site for Unrestricted 
Use.'' The licensee is declaring these portions of the site to be 
``non-impacted'' as defined in 10 CFR 50.2. Approval of the request 
would, for example, allow OPPD to sell a released portion to a non-OPPD 
controlled entity.
    As described in 10 CFR 50.83(c), the NRC will determine whether the 
licensee has adequately evaluated the effect of releasing the 
properties per the requirements of 10 CFR 50.83(a)(1), determine 
whether the licensee's classification of any released areas as ``non-
impacted'' is adequately justified, and if the NRC determines that the 
licensee's submittal is adequate, the NRC will inform the licensee in 
writing that the release is approved.

III. Public Meeting

    The NRC will conduct a public meeting to discuss OPPD's request for 
approval of the partial site release. The meeting will be held on 
Wednesday, November 28, 2018, from 7:00 p.m. until 8:30 p.m., Central 
Standard Time, at the Residence Inn Omaha Downtown/Old Market Area, 106 
South 15th St., Omaha, NE 68102.
    This is a Category 3 public meeting where stakeholders are invited 
to fully engage NRC staff to provide a range of views, information, 
concerns and suggestions with regard to regulatory issues. After the 
licensee and NRC staff presentation portion of the meeting, the public 
is allowed to speak and ask questions. Comments can be provided orally 
or in writing to the NRC staff present at the meeting.
    Stakeholders should monitor the NRC's public meeting website for 
information about the public meeting at: http://www.nrc.gov/public-involve/public-meetings/index.cfm. The agenda will be posted no later 
than 10 days prior to the meeting.

    Dated at Rockville, Maryland, this 20th day of November, 2018.

    For the Nuclear Regulatory Commission.
Andrea Kock,
Acting Director, Division of Decommissioning, Uranium Recovery, and 
Waste Programs, Office of Nuclear Material Safety and Safeguards.
[FR Doc. 2018-25666 Filed 11-23-18; 8:45 am]
BILLING CODE 7590-01-P



     60508                      Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Notices

     NRC is issuing the final Supplement 59                  Calhoun Station, Unit No. 1 (FCS),                       • Federal Rulemaking website: Go to
     to the GEIS regarding the renewal of                    License No. DPR–40, of portions of their              http://www.regulations.gov and search
     Entergy Operations, Inc. operating                      owned-controlled property and an                      for Docket ID NRC–2018–0268.
     license NPF–38 for an additional 20                     easement-controlled land area for                        • NRC’s Agencywide Documents
     years of operation for WF3. Draft                       unrestricted use. The NRC will review                 Access and Management System
     Supplement 59 to the GEIS was noticed                   the requests and the result of NRC                    (ADAMS): You may obtain publicly-
     by the NRC in the Federal Register on                   confirmatory surveys of the properties                available documents online in the
     August 23, 2018 (83 FR 42713), and                      proposed for release. Approval of the                 ADAMS Public Documents collection at
     noticed by the Environmental Protection                 request would allow OPPD to sell the                  http://www.nrc.gov/reading-rm/
     Agency on August 24, 2018 (83 FR                        released portion of the owner-controlled              adams.html. To begin the search, select
     42892). The public comment period on                    property, to the north and west of the                ‘‘Begin Web-based ADAMS Search.’’ For
     draft Supplement 59 to the GEIS ended                   plant in Nebraska, and to release the                 problems with ADAMS, please contact
     on October 9, 2018, and the comments                    easement on the other property, to the                the NRC’s Public Document Room (PDR)
     received are addressed in final                         north and east of the plant, in Iowa. The             reference staff at 1–800–397–4209, 301–
     Supplement 59 to the GEIS.                              NRC is soliciting public comment on the               415–4737, or by email to pdr.resource@
                                                             requested actions and invites                         nrc.gov. The ‘‘Fort Calhoun Station,
     II. Discussion                                                                                                Unit 1—Request for Partial Site Release’’
                                                             stakeholders and interested persons to
        As discussed in Chapter 5 of the final               participate. The NRC plans to hold a                  and ‘‘Fort Calhoun Station, Unit 1—
     Supplement 59 to the GEIS, the NRC                      public meeting to promote full                        Request for Partial Site Release Phase 2’’
     determined that the adverse                             understanding of the requested actions                are available in ADAMS under Nos.
     environmental impacts of license                        and to facilitate public comment.                     ML18215A187 and ML18316A036,
     renewal for WF3 are not so great that                                                                         respectively.
                                                             DATES: Submit comments by December
     preserving the option of license renewal                                                                         • NRC’s PDR: You may examine and
     for energy-planning decisionmakers                      26, 2018. Comments received after this
                                                                                                                   purchase copies of public documents at
     would be unreasonable. This                             date will be considered if it is practical
                                                                                                                   the NRC’s PDR, Room O1–F21, One
     recommendation is based on: (1) The                     to do so, but the Commission is able to
                                                                                                                   White Flint North, 11555 Rockville
     analysis and findings in the GEIS; (2)                  ensure consideration only for comments
                                                                                                                   Pike, Rockville, Maryland 20852.
     information provided in the                             received before this date. A public
                                                             meeting will be held on November 28,                  B. Submitting Comments
     environmental report and other
     documents submitted by Entergy                          2018.                                                   Please include Docket ID NRC–2018–
     Operations Inc.; (3) consultation with                  ADDRESSES: You may submit comments                    0268. The NRC cautions you not to
     Federal, State, local, and Tribal                       by any of the following methods:                      include identifying or contact
     agencies; (4) the NRC staff’s                              • Federal Rulemaking website: Go to                information that you do not want to be
     independent environmental review; and                   http://www.regulations.gov and search                 publicly disclosed in your comment
     (5) consideration of public comments                    for Docket ID NRC–2018–0268. Address                  submission. The NRC will post all
     received during the scoping process and                 questions about Docket IDs in                         comment submissions at http://
     on the draft supplemental                               Regulations.gov to Jennifer Borges;                   www.regulations.gov as well as enter the
     environmental impact statement.                         telephone: 301–287–9127; email:                       comment submissions into ADAMS.
                                                             Jennifer.Borges@nrc.gov. For technical                The NRC does not routinely edit
       Dated at Rockville, Maryland, this 20th day
     of November, 2018.                                      questions, contact the individual listed              comment submissions to remove
                                                             in the FOR FURTHER INFORMATION                        identifying or contact information.
       For the Nuclear Regulatory Commission.
                                                             CONTACT section of this document.                       If you are requesting or aggregating
     Emmanuel C. Sayoc,
                                                               • Mail comments to: May Ma, Office                  comments from other persons for
     Acting Chief, License Renewal Projects                  of Administration, Mail Stop: TWFN–7–                 submission to the NRC, then you should
     Branch, Division of Materials and License
     Renewal, Office of Nuclear Reactor
                                                             A60M, U.S. Nuclear Regulatory                         inform those persons not to include
     Regulation.                                             Commission, Washington, DC 20555–                     identifying or contact information that
     [FR Doc. 2018–25695 Filed 11–23–18; 8:45 am]
                                                             0001.                                                 they do not want to be publicly
                                                               For additional direction on obtaining               disclosed in their comment submission.
     BILLING CODE 7590–01–P
                                                             information and submitting comments,                  Your request should state that the NRC
                                                             see ‘‘Obtaining Information and                       does not routinely edit comment
     NUCLEAR REGULATORY                                      Submitting Comments’’ in the                          submissions to remove such information
     COMMISSION                                              SUPPLEMENTARY INFORMATION section of                  before making the comment
                                                             this document.                                        submissions available to the public or
     [Docket No. 50–285; NRC–2018–0268]                                                                            entering the comment into ADAMS.
                                                             FOR FURTHER INFORMATION CONTACT: Jack
     Omaha Public Power District, Fort                       Parrott, Office of Nuclear Material                   II. Background
     Calhoun Station, Unit No. 1, Partial Site               Safety and Safeguards, U.S. Nuclear
                                                             Regulatory Commission, Washington,                       The NRC has received two requests
     Release                                                                                                       for approval of partial site releases from
                                                             DC 20555–0001; telephone: 301–415–
     AGENCY:  Nuclear Regulatory                             6634; email: Jack.Parrott@nrc.gov.                    the Omaha Public Power District (OPPD
     Commission.                                                                                                   or licensee), by letters dated June 29,
                                                             SUPPLEMENTARY INFORMATION:
     ACTION: Partial site release; public
                                                                                                                   2018 (ADAMS Accession No.
     meeting and request for comment.                        I. Obtaining Information and                          ML18215A187) and November 12, 2018
                                                             Submitting Comments                                   (ADAMS Accession No. ML18316A036).
     SUMMARY:   The U.S. Nuclear Regulatory                                                                        The requests seek approval for release
     Commission (NRC) is considering two                     A. Obtaining Information                              for unrestricted use of a portion of the
     requests from the Omaha Public Power                      Please refer to Docket ID NRC–2018–                 Fort Calhoun Station, Unit No. 1 (FCS)
     District (OPPD) to approve the release of               0268. You may obtain publicly-available               site located at 9610 Power Lane, Blair,
     land areas, under the control of the NRC                information related to this action by any             Nebraska. The first proposed release
     power reactor license for the Fort                      of the following methods:                             area is a 120-acre portion on the north


VerDate Sep<11>2014   17:28 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00118   Fmt 4703   Sfmt 4703   E:\FR\FM\26NON1.SGM   26NON1


                                Federal Register / Vol. 83, No. 227 / Monday, November 26, 2018 / Notices                                                  60509

     and west side of the licensee-controlled                  Stakeholders should monitor the                       Section II identifies the docket
     facility property, wholly within the                    NRC’s public meeting website for                      number(s) associated with each Postal
     State of Nebraska. The second proposed                  information about the public meeting at:              Service request, the title of each Postal
     release area involves a 475-acre parcel                 http://www.nrc.gov/public-involve/                    Service request, the request’s acceptance
     of land north and east of the site,                     public-meetings/index.cfm. The agenda                 date, and the authority cited by the
     located on the banks of the Missouri                    will be posted no later than 10 days                  Postal Service for each request. For each
     River on the Iowa side of the Iowa-                     prior to the meeting.                                 request, the Commission appoints an
     Nebraska border, on which the licensee                    Dated at Rockville, Maryland, this 20th day         officer of the Commission to represent
     currently has an easement and that is                   of November, 2018.                                    the interests of the general public in the
     part of the exclusion area of the plant.                  For the Nuclear Regulatory Commission.              proceeding, pursuant to 39 U.S.C. 505
        The FCS license (NRC License No.                     Andrea Kock,                                          (Public Representative). Section II also
     DPR–40, Docket No. 50–285) is for a                     Acting Director, Division of                          establishes comment deadline(s)
     power reactor under part 50, ‘‘Domestic                 Decommissioning, Uranium Recovery, and                pertaining to each request.
     Licensing of Production and Utilization                 Waste Programs, Office of Nuclear Material
     Facilities,’’ of title 10 of the Code of                Safety and Safeguards.                                  The public portions of the Postal
     Federal Regulations (10 CFR). The                                                                             Service’s request(s) can be accessed via
                                                             [FR Doc. 2018–25666 Filed 11–23–18; 8:45 am]
     facility was certified as permanently                                                                         the Commission’s website (http://
                                                             BILLING CODE 7590–01–P
     shut down, per NRC regulations in 10                                                                          www.prc.gov). Non-public portions of
     CFR 50.82(a), by letter dated November                                                                        the Postal Service’s request(s), if any,
     13, 2016. FCS is currently in                                                                                 can be accessed through compliance
     ‘‘SAFSTOR’’ decommissioning mode                        POSTAL REGULATORY COMMISSION                          with the requirements of 39 CFR
     awaiting the termination of the power                   [Docket No. CP2019–22]                                3007.301.1
     reactor license.                                                                                                The Commission invites comments on
        The licensee requests release from the               New Postal Products
                                                                                                                   whether the Postal Service’s request(s)
     NRC license, for unrestricted use, of two                                                                     in the captioned docket(s) are consistent
                                                             AGENCY:   Postal Regulatory Commission.
     portions of the site under 10 CFR 50.83,                                                                      with the policies of title 39. For
     ‘‘Release of Part of a Power Reactor                    ACTION:   Notice.
                                                                                                                   request(s) that the Postal Service states
     Facility or Site for Unrestricted Use.’’                SUMMARY:   The Commission is noticing a               concern market dominant product(s),
     The licensee is declaring these portions                recent Postal Service filing for the                  applicable statutory and regulatory
     of the site to be ‘‘non-impacted’’ as                   Commission’s consideration concerning
     defined in 10 CFR 50.2. Approval of the                                                                       requirements include 39 U.S.C. 3622, 39
                                                             a negotiated service agreement. This                  U.S.C. 3642, 39 CFR part 3010, and 39
     request would, for example, allow OPPD                  notice informs the public of the filing,
     to sell a released portion to a non-OPPD                                                                      CFR part 3020, subpart B. For request(s)
                                                             invites public comment, and takes other               that the Postal Service states concern
     controlled entity.                                      administrative steps.
        As described in 10 CFR 50.83(c), the                                                                       competitive product(s), applicable
                                                             DATES: Comments are due: November                     statutory and regulatory requirements
     NRC will determine whether the
                                                             27, 2018.                                             include 39 U.S.C. 3632, 39 U.S.C. 3633,
     licensee has adequately evaluated the
     effect of releasing the properties per the              ADDRESSES: Submit comments                            39 U.S.C. 3642, 39 CFR part 3015, and
     requirements of 10 CFR 50.83(a)(1),                     electronically via the Commission’s                   39 CFR part 3020, subpart B. Comment
     determine whether the licensee’s                        Filing Online system at http://                       deadline(s) for each request appear in
     classification of any released areas as                 www.prc.gov. Those who cannot submit                  section II.
     ‘‘non-impacted’’ is adequately justified,               comments electronically should contact
                                                             the person identified in the FOR FURTHER              II. Docketed Proceeding(s)
     and if the NRC determines that the
     licensee’s submittal is adequate, the                   INFORMATION CONTACT section by
                                                                                                                     1. Docket No(s).: CP2019–22; Filing
     NRC will inform the licensee in writing                 telephone for advice on filing
                                                                                                                   Title: Notice of United States Postal
     that the release is approved.                           alternatives.
                                                                                                                   Service of Filing a Functionally
                                                             FOR FURTHER INFORMATION CONTACT:                      Equivalent Global Expedited Package
     III. Public Meeting
                                                             David A. Trissell, General Counsel, at                Services 8 Negotiated Service
        The NRC will conduct a public                        202–789–6820.                                         Agreement and Application for Non-
     meeting to discuss OPPD’s request for                   SUPPLEMENTARY INFORMATION:                            Public Treatment of Materials Filed
     approval of the partial site release. The
                                                             Table of Contents                                     Under Seal; Filing Acceptance Date:
     meeting will be held on Wednesday,
     November 28, 2018, from 7:00 p.m. until                                                                       November 19, 2018; Filing Authority: 39
                                                             I. Introduction                                       CFR 3015.5; Public Representative:
     8:30 p.m., Central Standard Time, at the                II. Docketed Proceeding(s)
     Residence Inn Omaha Downtown/Old                                                                              Lawrence Fenster; Comments Due:
     Market Area, 106 South 15th St.,                        I. Introduction                                       November 27, 2018.
     Omaha, NE 68102.                                           The Commission gives notice that the                 This Notice will be published in the
        This is a Category 3 public meeting                  Postal Service filed request(s) for the               Federal Register.
     where stakeholders are invited to fully                 Commission to consider matters related
                                                                                                                   Stacy L. Ruble,
     engage NRC staff to provide a range of                  to negotiated service agreement(s). The
     views, information, concerns and                        request(s) may propose the addition or                Secretary.
     suggestions with regard to regulatory                   removal of a negotiated service                       [FR Doc. 2018–25664 Filed 11–23–18; 8:45 am]
     issues. After the licensee and NRC staff                agreement from the market dominant or                 BILLING CODE 7710–FW–P
     presentation portion of the meeting, the                the competitive product list, or the
     public is allowed to speak and ask                      modification of an existing product                     1 See Docket No. RM2018–3, Order Adopting
     questions. Comments can be provided                     currently appearing on the market                     Final Rules Relating to Non-Public Information,
     orally or in writing to the NRC staff                   dominant or the competitive product                   June 27, 2018, Attachment A at 19–22 (Order No.
     present at the meeting.                                 list.                                                 4679).



VerDate Sep<11>2014   17:28 Nov 23, 2018   Jkt 247001   PO 00000   Frm 00119   Fmt 4703   Sfmt 9990   E:\FR\FM\26NON1.SGM   26NON1



Document Created: 2018-11-24 00:52:19
Document Modified: 2018-11-24 00:52:19
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionPartial site release; public meeting and request for comment.
DatesSubmit comments by December 26, 2018. Comments received after this date will be considered if it is practical to do so, but the Commission is able to ensure consideration only for comments received before this date. A public meeting will be held on November 28, 2018.
ContactJack Parrott, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-6634; email: [email protected]
FR Citation83 FR 60508 