83_FR_61063 83 FR 60835 - Cat Creek Energy, LLC; Notice of Successive Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

83 FR 60835 - Cat Creek Energy, LLC; Notice of Successive Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 228 (November 27, 2018)

Page Range60835-60836
FR Document2018-25813

Federal Register, Volume 83 Issue 228 (Tuesday, November 27, 2018)
[Federal Register Volume 83, Number 228 (Tuesday, November 27, 2018)]
[Notices]
[Pages 60835-60836]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-25813]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14655-001]


Cat Creek Energy, LLC; Notice of Successive Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On November 9, 2018, Cat Creek Energy, LLC (Cat Creek) filed an 
application for a successive preliminary permit, pursuant to section 
4(f) of the Federal Power Act (FPA), to study the feasibility of the 
proposed Cat Creek Energy Generation Facility Pumped Storage 
Hydroelectric Project (project) to be located at the U.S. Bureau of 
Reclamation's (Reclamation) Anderson Ranch Reservoir on the South Fork 
of the Boise River near Mountain Home in Elmore County, Idaho. The sole 
purpose of a preliminary permit, if issued, is to grant the permit 
holder priority to file a license application during the permit term. A 
preliminary permit does not authorize the permit holder to perform any 
land-disturbing activities or otherwise enter upon lands or waters 
owned by others without the owners' express permission.
    As stated in the original permit for the project, Reclamation 
retains jurisdiction over hydropower development at the Anderson Ranch 
dam, reservoir, and powerhouse, which are part of Reclamation's Boise 
Project. However, the Commission retains jurisdiction for hydropower 
facilities that would be located outside of Reclamation's development. 
Thus, an entity seeking to build a hydropower project that would use 
Reclamation's Boise Project facilities would need to obtain a lease of 
power privilege from Reclamation, but it also would need to obtain a 
license from the Commission for those facilities of the hydropower 
project that are not under Reclamation's jurisdiction.
    The proposed project would utilize Reclamation's existing Anderson 
Ranch Reservoir as a lower reservoir and would consist of the following 
new facilities: (1) A 4.3-mile-long, 80-foot-high earthen dam; (2) a 
63,500-acre-foot impoundment as an upper reservoir; (3) six 2,500-foot-
long, 14- to 16-foot-diameter steel penstocks; (4) two 100-foot-
diameter concrete silos; (5) twelve 60-megawatt (MW) ternary turbine/
generator units, for a total capacity of 720 MW; (6) an 8.1-mile-long, 
230-kilovolt transmission line interconnecting with the existing 
Bonneville Power Administration Dixie Substation; (7) an approximately 
2-mile-long access road; and (8) appurtenant facilities. The estimated 
annual generation of the project would be 1,965.4 gigawatt-hours.
    Applicant Contact: James T. Carkulis, Cat Creek Energy, LLC, 398 S 
9th Street Suite 240, Boise, ID 83702; phone: (208) 954-5090.
    FERC Contact: Karen Sughrue; phone: (202) 502-8556.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://

[[Page 60836]]

www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-14655-001.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of the 
Commission's website at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14655) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: November 20, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-25813 Filed 11-26-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                                         Federal Register / Vol. 83, No. 228 / Tuesday, November 27, 2018 / Notices                                            60835

                                              of the protest or intervention to the                   Commission in determining the                         the Boise River near Mountain Home in
                                              Federal Energy Regulatory Commission,                   appropriate action to be taken, but will              Elmore County, Idaho. The sole purpose
                                              888 First Street NE, Washington, DC                     not serve to make protestants parties to              of a preliminary permit, if issued, is to
                                              20426.                                                  the proceeding. Any person wishing to                 grant the permit holder priority to file
                                                 This filing is accessible online at                  become a party must file a notice of                  a license application during the permit
                                              http://www.ferc.gov, using the                          intervention or motion to intervene, as               term. A preliminary permit does not
                                              ‘‘eLibrary’’ link and is available for                  appropriate. The Respondent’s answer                  authorize the permit holder to perform
                                              review in the Commission’s Public                       and all interventions, or protests must               any land-disturbing activities or
                                              Reference Room in Washington, DC.                       be filed on or before the comment date.               otherwise enter upon lands or waters
                                              There is an ‘‘eSubscription’’ link on the               The Respondent’s answer, motions to                   owned by others without the owners’
                                              website that enables subscribers to                     intervene, and protests must be served                express permission.
                                              receive email notification when a                       on the Complainant.                                      As stated in the original permit for the
                                              document is added to a subscribed                          The Commission encourages                          project, Reclamation retains jurisdiction
                                              docket(s). For assistance with any FERC                 electronic submission of protests and                 over hydropower development at the
                                              Online service, please email                            interventions in lieu of paper using the              Anderson Ranch dam, reservoir, and
                                              FERCOnlineSupport@ferc.gov, or call                     ‘‘eFiling’’ link at http://www.ferc.gov.              powerhouse, which are part of
                                              (866) 208–3676 (toll free). For TTY, call               Persons unable to file electronically                 Reclamation’s Boise Project. However,
                                              (202) 502–8659.                                         should submit an original and 5 copies                the Commission retains jurisdiction for
                                                 Comment Date: 5 p.m. Eastern time                    of the protest or intervention to the                 hydropower facilities that would be
                                              on December 7, 2018.                                    Federal Energy Regulatory Commission,                 located outside of Reclamation’s
                                                                                                      888 First Street NE, Washington, DC                   development. Thus, an entity seeking to
                                                Dated: November 20, 2018.
                                                                                                      20426.                                                build a hydropower project that would
                                              Kimberly D. Bose,                                                                                             use Reclamation’s Boise Project
                                                                                                         This filing is accessible on-line at
                                              Secretary.                                                                                                    facilities would need to obtain a lease of
                                                                                                      http://www.ferc.gov, using the
                                              [FR Doc. 2018–25810 Filed 11–26–18; 8:45 am]
                                                                                                      ‘‘eLibrary’’ link and is available for                power privilege from Reclamation, but it
                                              BILLING CODE 6717–01–P                                  electronic review in the Commission’s                 also would need to obtain a license from
                                                                                                      Public Reference Room in Washington,                  the Commission for those facilities of
                                                                                                      DC. There is an ‘‘eSubscription’’ link on             the hydropower project that are not
                                              DEPARTMENT OF ENERGY                                                                                          under Reclamation’s jurisdiction.
                                                                                                      the website that enables subscribers to
                                                                                                      receive email notification when a                        The proposed project would utilize
                                              Federal Energy Regulatory                                                                                     Reclamation’s existing Anderson Ranch
                                              Commission                                              document is added to a subscribed
                                                                                                      docket(s). For assistance with any FERC               Reservoir as a lower reservoir and
                                              [Docket No. EL19–18–000]                                                                                      would consist of the following new
                                                                                                      Online service, please email
                                                                                                                                                            facilities: (1) A 4.3-mile-long, 80-foot-
                                                                                                      FERCOnlineSupport@ferc.gov, or call
                                              American Electric Power Service                                                                               high earthen dam; (2) a 63,500-acre-foot
                                                                                                      (866) 208–3676 (toll free). For TTY, call
                                              Corporation v. PJM Interconnection                                                                            impoundment as an upper reservoir; (3)
                                                                                                      (202) 502–8659.
                                              L.L.C.; Notice of Complaint                                                                                   six 2,500-foot-long, 14- to 16-foot-
                                                                                                         Comment Date: 5 p.m. Eastern Time
                                                                                                                                                            diameter steel penstocks; (4) two 100-
                                                 Take notice that on November 16,                     on December 6, 2018.
                                                                                                                                                            foot-diameter concrete silos; (5) twelve
                                              2018, pursuant to sections 206 and 306                    Dated: November 20, 2018.                           60-megawatt (MW) ternary turbine/
                                              of the Federal Power Act, 16 U.S.C. 824e                Kimberly D. Bose,                                     generator units, for a total capacity of
                                              and 825e, and Rule 206 of the Federal                   Secretary.                                            720 MW; (6) an 8.1-mile-long, 230-
                                              Energy Regulatory Commission’s                          [FR Doc. 2018–25808 Filed 11–26–18; 8:45 am]          kilovolt transmission line
                                              (Commission) Rules of Practice and                                                                            interconnecting with the existing
                                                                                                      BILLING CODE 6717–01–P
                                              Procedure, 18 CFR 385.206 (2018),                                                                             Bonneville Power Administration Dixie
                                              American Electric Power Service                                                                               Substation; (7) an approximately 2-mile-
                                              Corporation, on behalf of its PJM                       DEPARTMENT OF ENERGY                                  long access road; and (8) appurtenant
                                              transmission owners (Complainant)                                                                             facilities. The estimated annual
                                              filed a formal complaint against PJM                    Federal Energy Regulatory                             generation of the project would be
                                              Interconnection L.L.C. (PJM or                          Commission                                            1,965.4 gigawatt-hours.
                                              Respondent), alleging that PJM’s Open                                                                            Applicant Contact: James T. Carkulis,
                                              Access Transmission Tariff is unjust                    [Project No. 14655–001]
                                                                                                                                                            Cat Creek Energy, LLC, 398 S 9th Street
                                              and unreasonable because it does not                    Cat Creek Energy, LLC; Notice of                      Suite 240, Boise, ID 83702; phone: (208)
                                              include indemnifications provisions                     Successive Preliminary Permit                         954–5090.
                                              that are consistent with the                            Application Accepted for Filing and                      FERC Contact: Karen Sughrue; phone:
                                              Commission’s pro forma Large                            Soliciting Comments, Motions To                       (202) 502–8556.
                                              Generator Interconnection Agreement,                    Intervene, and Competing Applications                    Deadline for filing comments, motions
                                              as more fully explained in the                                                                                to intervene, competing applications
                                              complaint.                                                On November 9, 2018, Cat Creek                      (without notices of intent), or notices of
                                                 The Complainant certifies that copies                Energy, LLC (Cat Creek) filed an                      intent to file competing applications: 60
                                              of the complaint were served on the                     application for a successive preliminary              days from the issuance of this notice.
                                              contacts for Respondent, as listed on the               permit, pursuant to section 4(f) of the               Competing applications and notices of
amozie on DSK3GDR082PROD with NOTICES1




                                              Commission’s list of Corporate Officials.               Federal Power Act (FPA), to study the                 intent must meet the requirements of 18
                                                 Any person desiring to intervene or to               feasibility of the proposed Cat Creek                 CFR 4.36.
                                              protest this filing must file in                        Energy Generation Facility Pumped                        The Commission strongly encourages
                                              accordance with Rules 211 and 214 of                    Storage Hydroelectric Project (project) to            electronic filing. Please file comments,
                                              the Commission’s Rules of Practice and                  be located at the U.S. Bureau of                      motions to intervene, notices of intent,
                                              Procedure (18 CFR 385.211, 385.214).                    Reclamation’s (Reclamation) Anderson                  and competing applications using the
                                              Protests will be considered by the                      Ranch Reservoir on the South Fork of                  Commission’s eFiling system at http://


                                         VerDate Sep<11>2014   17:45 Nov 26, 2018   Jkt 247001   PO 00000   Frm 00015   Fmt 4703   Sfmt 4703   E:\FR\FM\27NON1.SGM   27NON1


                                              60836                      Federal Register / Vol. 83, No. 228 / Tuesday, November 27, 2018 / Notices

                                              www.ferc.gov/docs-filing/efiling.asp.                   DEPARTMENT OF ENERGY                                  document is added to a subscribed
                                              Commenters can submit brief comments                                                                          docket(s). For assistance with any FERC
                                              up to 6,000 characters, without prior                   Federal Energy Regulatory                             Online service, please email
                                              registration, using the eComment system                 Commission                                            FERCOnlineSupport@ferc.gov, or call
                                              at http://www.ferc.gov/docs-filing/                     [Docket No. EL19–17–000]                              (866) 208–3676 (toll free). For TTY, call
                                              ecomment.asp. You must include your                                                                           (202) 502–8659.
                                              name and contact information at the end                 Kansas Electric Power Cooperative,                      Comment Date: 5:00 p.m. Eastern
                                              of your comments. For assistance,                       Inc. v. Westar Energy, Inc.; Notice of                Time on December 6, 2018.
                                              please contact FERC Online Support at                   Complaint                                               Dated: November 20, 2018.
                                              FERCOnlineSupport@ferc.gov, (866)                          Take notice that on November 16,                   Kimberly D. Bose,
                                              208–3676 (toll free), or (202) 502–8659                 2018, pursuant to sections 206, 306, and              Secretary.
                                              (TTY). In lieu of electronic filing, please             309 of the Federal Power Act, 16 U.S.C.               [FR Doc. 2018–25807 Filed 11–26–18; 8:45 am]
                                              send a paper copy to: Secretary, Federal                824e, 825e, and 825h, and section 206                 BILLING CODE 6717–01–P
                                              Energy Regulatory Commission, 888                       of the Federal Energy Regulatory
                                              First Street NE, Washington, DC 20426.                  Commission’s (Commission) Rules of
                                              The first page of any filing should                     Practice and Procedure, 18 CFR 385.206                DEPARTMENT OF ENERGY
                                              include docket number P–14655–001.                      (2018), Kansas Electric Power
                                                                                                      Cooperative, Inc. (Complainant) filed a               Federal Energy Regulatory
                                                 More information about this project,                                                                       Commission
                                                                                                      formal complaint (complaint) against
                                              including a copy of the application, can
                                                                                                      Westar Energy, Inc. (Westar or
                                              be viewed or printed on the ‘‘eLibrary’’                                                                      Combined Notice of Filings
                                                                                                      Respondent), alleging that Westar is
                                              link of the Commission’s website at                     violating its generation formula rate,
                                              http://www.ferc.gov/docs-filing/                                                                                Take notice that the Commission has
                                                                                                      Commission orders, regulations, and                   received the following Natural Gas
                                              elibrary.asp. Enter the docket number                   generally applicable ratemaking                       Pipeline Rate and Refund Report filings:
                                              (P–14655) in the docket number field to                 policies, as more fully explained in the
                                              access the document. For assistance,                    complaint.                                            Filings Instituting Proceedings
                                              contact FERC Online Support.                               The Complainant certifies that copies                 Docket Numbers: RP19–300–000.
                                                Dated: November 20, 2018.                             of the complaint were served on the                      Applicants: Eastern Shore Natural Gas
                                              Kimberly D. Bose,
                                                                                                      contacts for Respondent and the Kansas                Company.
                                                                                                      Corporation Commission as listed on                      Description: § 4(d) Rate Filing:
                                              Secretary.
                                                                                                      the Commission’s list of Corporate                    Negotiated Rate—DCRC to be effective
                                              [FR Doc. 2018–25813 Filed 11–26–18; 8:45 am]            Officials.                                            1/1/2019.
                                              BILLING CODE 6717–01–P                                     Any person desiring to intervene or to                Filed Date: 11/19/18.
                                                                                                      protest this filing must file in                         Accession Number: 20181119–5182.
                                                                                                      accordance with Rules 211 and 214 of                     Comments Due: 5 p.m. ET 12/3/18.
                                              DEPARTMENT OF ENERGY                                    the Commission’s Rules of Practice and                   Docket Numbers: RP19–301–000.
                                                                                                      Procedure (18 CFR 385.211, 385.214).                     Applicants: Western Gas Interstate
                                              Federal Energy Regulatory                               Protests will be considered by the
                                              Commission                                                                                                    Company.
                                                                                                      Commission in determining the                            Description: eTariff filing per 1430:
                                                                                                      appropriate action to be taken, but will              Western Gas Interstate Company
                                              [EG18–117–000, EG18–119–000, EG18–120–                  not serve to make protestants parties to              Extension of Time Request Filing FERC
                                              000, EG18–121–000, EG18–122–000, EG18–                  the proceeding. Any person wishing to                 Form 501–G.
                                              123–000]                                                become a party must file a notice of                     Filed Date: 11/20/18.
                                                                                                      intervention or motion to intervene, as                  Accession Number: 20181120–5000.
                                              Notice of Effectiveness of Exempt                       appropriate. The Respondent’s answer                     Comments Due: 5 p.m. ET 11/26/18.
                                              Wholesale Generator Status:                             and all interventions, or protests must
                                              Persimmon Creek Wind Farm 1, LLC;                                                                                Docket Numbers: RP19–302–000.
                                                                                                      be filed on or before the comment date.
                                                                                                                                                               Applicants: Algonquin Gas
                                              Stillwater Wind, LLC; Crazy Mountain                    The Respondent’s answer, motions to
                                                                                                                                                            Transmission, LLC.
                                              Wind LLC; Blue Cloud Wind Energy,                       intervene, and protests must be served
                                                                                                                                                               Description: § 4(d) Rate Filing:
                                              LLC; Green River Wind Farm Phase 1,                     on the Complainant.
                                                                                                         The Commission encourages                          Negotiated rate—Amended Boston Gas
                                              LLC; Santa Rita East Wind Energy LLC                                                                          510807 eff 1–1–2019 to be effective
                                                                                                      electronic submission of protests and
                                                                                                      interventions in lieu of paper using the              1/1/2019.
                                                Take notice that during the month of
                                                                                                      ‘‘eFiling’’ link at http://www.ferc.gov.                 Filed Date: 11/20/18.
                                              October 2018, the status of the above-                                                                           Accession Number: 20181120–5034.
                                              captioned entities as Exempt Wholesale                  Persons unable to file electronically
                                                                                                      should submit an original and 5 copies                   Comments Due: 5 p.m. ET 12/3/18.
                                              Generators became effective by
                                                                                                      of the protest or intervention to the                    Docket Numbers: RP19–303–000.
                                              operation of the Commission’s
                                                                                                      Federal Energy Regulatory Commission,                    Applicants: Southern Star Central Gas
                                              regulations. 18 CFR 366.7(a) (2018).                                                                          Pipeline, Inc.
                                                                                                      888 First Street NE, Washington, DC
                                                Dated: November 16, 2018.                             20426.                                                   Description: Compliance filing
                                              Nathaniel J. Davis, Sr.,                                   This filing is accessible online at                Annual Cash-Out Activity Report 2018.
amozie on DSK3GDR082PROD with NOTICES1




                                              Deputy Secretary.                                       http://www.ferc.gov, using the                           Filed Date: 11/20/18.
                                              [FR Doc. 2018–25755 Filed 11–26–18; 8:45 am]            ‘‘eLibrary’’ link and is available for                   Accession Number: 20181120–5036.
                                                                                                      electronic review in the Commission’s                    Comments Due: 5 p.m. ET 12/3/18.
                                              BILLING CODE 6717–01–P
                                                                                                      Public Reference Room in Washington,                     The filings are accessible in the
                                                                                                      DC. There is an ‘‘eSubscription’’ link on             Commission’s eLibrary system by
                                                                                                      the website that enables subscribers to               clicking on the links or querying the
                                                                                                      receive email notification when a                     docket number.


                                         VerDate Sep<11>2014   17:45 Nov 26, 2018   Jkt 247001   PO 00000   Frm 00016   Fmt 4703   Sfmt 4703   E:\FR\FM\27NON1.SGM   27NON1



Document Created: 2018-11-27 01:24:29
Document Modified: 2018-11-27 01:24:29
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 60835 