83_FR_61899 83 FR 61668 - Notice of Availability of the Draft Environmental Impact Statement for the Sevier Playa Potash Project, Utah

83 FR 61668 - Notice of Availability of the Draft Environmental Impact Statement for the Sevier Playa Potash Project, Utah

DEPARTMENT OF THE INTERIOR
Bureau of Land Management

Federal Register Volume 83, Issue 231 (November 30, 2018)

Page Range61668-61670
FR Document2018-26076

In accordance with the National Environmental Policy Act (NEPA) of 1969, as amended, the Federal Land Policy and Management Act of 1976, as amended, the Mineral Leasing Act of 1920, as amended, and Secretarial Order 3355, the Bureau of Land Management (BLM) is releasing the Draft Environmental Impact Statement (EIS) for Crystal Peak Minerals Inc.'s (CPM) Sevier Playa Potash Project (Project), and by this notice is announcing the opening of the comment period.

Federal Register, Volume 83 Issue 231 (Friday, November 30, 2018)
[Federal Register Volume 83, Number 231 (Friday, November 30, 2018)]
[Notices]
[Pages 61668-61670]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-26076]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Land Management

[LLUTW02000-L51010000-ER0000-LVRWJ18J5120-18X--UTU-90095]


Notice of Availability of the Draft Environmental Impact 
Statement for the Sevier Playa Potash Project, Utah

AGENCY: Bureau of Land Management, Interior.

ACTION: Notice of availability.

-----------------------------------------------------------------------

SUMMARY: In accordance with the National Environmental Policy Act 
(NEPA) of 1969, as amended, the Federal Land Policy and Management Act 
of 1976, as amended, the Mineral Leasing Act of 1920, as amended, and 
Secretarial Order 3355, the Bureau of Land Management (BLM) is 
releasing the Draft Environmental Impact Statement (EIS) for Crystal 
Peak Minerals Inc.'s (CPM) Sevier Playa Potash Project (Project), and 
by this notice is announcing the opening of the comment period.

DATES: To ensure comments will be considered, the BLM must receive 
written comments on the Project Draft EIS within 45 days following the 
date the Environmental Protection Agency publishes its Notice of 
Availability in the Federal Register. The BLM will

[[Page 61669]]

announce future meetings or hearings and any other public involvement 
activities at least 15 days in advance through public notices, media 
releases, and/or mailings.

ADDRESSES: You may submit comments related to the Draft EIS for the 
Project by any of the following methods:
     Email: [email protected].
     Fax: (435) 743-3136.
     Mail: Bureau of Land Management Fillmore Field Office, 
Attn: Clara Stevens--Sevier Playa Potash Project Comments, 95 East 500 
North, Fillmore, UT 84631.
    Electronic versions of the Project Draft EIS, appendices, and 
supporting documents can be downloaded from ePlanning at https://bit.ly/2CZPeWy. Paper and digital copies of the Project Draft EIS and 
supporting documents are available for review at:
    (1) The BLM Fillmore Field Office at the above address;
    (2) The BLM West Desert District Office at 2370 South Decker Lake 
Blvd., West Valley City, UT;
    (3) The Fillmore City Library at 75 West Center, Fillmore, UT; and
    (4) The Delta City Library at 76 North 200 West, Delta, UT.

FOR FURTHER INFORMATION CONTACT: Clara Stevens, Project Manager, 
telephone (435) 743-3119; address 95 East 500 North, Fillmore, UT 
84631; email [email protected]. Persons who use a telecommunications 
device for the deaf (TDD) may call the Federal Relay Service (FRS) at 
1-800-877-8339 to contact the above individual during normal business 
hours. The FRS is available 24 hours a day, 7 days a week, to leave a 
message or question with the above individual. You will receive a reply 
during normal business hours.

SUPPLEMENTARY INFORMATION: On March 12, 2014, the BLM published a 
Notice of Intent to Prepare an EIS in the Federal Register (79 FR 
14078).
    The Project would be located in central Millard County in 
southwestern Utah. The Sevier Playa is a large terminal playa that is 
normally dry on the surface and contains subsurface potassium-bearing 
saline brines. The playa is approximately 26 miles long and averages 8 
miles wide.
    CPM holds or through agreement controls the rights to develop and 
operate potassium mineral leases on 117,814 acres of Federal lands 
administered by the BLM and an additional 6,409 acres of state lands. 
CPM proposes to exercise their lease rights by constructing and 
operating the Project, which would produce at its peak approximately 
372,000 tons per year of potassium sulfate 
(K2SO4), also known as sulfate of potash (SOP), 
and related minerals over the 32-year lifetime of the Project.
    The Project is a potash mine proposed on 124,223 acres of Federal 
and State mineral leases. The proposal includes mining facilities 
located on-lease with off-lease supporting infrastructure. On-lease 
facilities include evaporation ponds; a brine extraction system 
(trenches, wells, and conveyance canals); a recharge system (trenches, 
canals, and Sevier River diversion); a waste product storage area 
(purge brine and tailings); access roads, and processing facilities. 
The off-lease ROW facilities, proposed on approximately 4,135 acres, 
include power and communication lines, a natural gas pipeline, a rail 
loadout facility and rail spur; water supply wells; communication 
towers; preconcentration ponds; segments of recharge canals and the 
playa perimeter road; and access roads. Three gravel pits would also be 
developed.
    Potassium-bearing brines would be extracted from trenches and wells 
on the Sevier Playa, and routed through a series of ponds, using solar 
evaporation to concentrate the brine. The preconcentration ponds would 
concentrate the brine causing halite (NaCl, table salt) and other non-
commercial salts to precipitate. These salts would be stored in the 
preconcentration ponds. The saturated brine would be transferred to the 
production ponds for further evaporation, causing potassium-rich salts 
to precipitate. The production ponds would be harvested year-round, 
with the potassium-rich salts moved directly to a facility for 
processing into SOP. The SOP would be trucked to the rail loadout 
facility for distribution. Purge brine containing primarily magnesium 
chloride (MgCl2) would be removed from the production ponds 
before harvesting begins and would be piped to an on-playa purge brine 
storage pond. Process by-products (solid tailings) from the processing 
facility would be trucked to the on-playa tailings storage area.
    The Draft EIS analyzes CPM's Mining Plan, prepared for development 
of Federal potassium mineral leases acquired in 2011 and potash mineral 
leases acquired on State lands. These leases were amalgamated under BLM 
casefile number UTU-88387. In addition, the Draft EIS analyzes CPM's 
request for rights-of-way (ROWs) to construct various ancillary 
facilities on public lands in the vicinity of the mineral leases, but 
outside the lease boundary. CPM prepared a Plan of Development (POD) 
for the ROWs that they have requested. The Draft EIS also analyzes 
CPM's request to purchase mineral materials for gravel to support 
construction and operation of the Project. Although the BLM may only 
make decisions pertaining to public lands managed by the BLM, the EIS 
analyzes the complete Project including portions located on state and 
private lands.
    This Draft EIS evaluates, in detail, the no action alternative, the 
proposed action, and five action alternatives. Alternative 1 would 
route a cross-country segment of the off-lease 69-kV power and 
communication line to an alignment along existing roads, including SR 
257 and SR-257 Cutoff Road. Alternative 2 would route a cross-country 
segment of the off-lease 69-kV power and communication line to a more 
southern orientation along existing roads, including Crystal Peak Road 
and Crystal Peak Spur Road. Alternative 3 would route a segment of the 
off-lease natural gas pipeline entirely on BLM land to avoid crossing 
private lands. Alternative 4 would route a cross-country segment of the 
off-lease natural gas pipeline to a similar alignment as Alternative 2 
along existing roads, including Crystal Peak Road and Crystal Peak Spur 
Road. Alternative 5 is an alternative method of diverting flows from 
the Sevier River into the recharge system. This alternative would 
relocate the on-lease Sevier River diversion facilities, including 
diversion channel, recharge canal, diversion culvert and sump, and 
perimeter and access roads slightly to the west, within the boundary of 
the playa.
    Based on public scoping and internal review, the principal issues 
analyzed in the Draft EIS include: (1) Impacts to water resources and 
water quality including adverse effects to surface water and 
groundwater basins, as well as impacts to existing water rights 
holders; (2) adverse effects to air quality in the form of fugitive 
dust produced during construction and operation of the mine facilities; 
(3) impacts to cultural resources and historic properties, including 
rock art and subsurface features; (4) impacts to migratory bird 
populations; and (5) the socioeconomic effects of water right 
acquisition for recharge water. Analysis also includes impacts to the 
following resources: Visual, wildlife, access, range management, 
recreation, and soils.
    The BLM published a Notice of Intent for the Project on March 12, 
2014. Scoping was extended through August 31, 2015, due to Project 
delays. A public scoping meeting was held in Delta, Utah, on August 5, 
2015. The public

[[Page 61670]]

was offered the opportunity to provide written comments throughout the 
scoping process.
    In 2015, pursuant to Executive Order 13175, the BLM initiated 
government-to-government consultation with interested tribes, including 
the Confederated Tribes of the Goshute Reservation, the Hopi Tribe, the 
Kaibab Band of Paiute Indians, the Kanosh Band of Paiute Indians, the 
Navajo Nation, the Paiute Indian Tribe of Utah, the Skull Valley Band 
of Goshute, and the Ute Indian Tribe. Beginning in 2015, the BLM 
coordinated with the Utah State Historic Preservation Office and seven 
other consulting parties that requested to participate in the Section 
106 process, to develop a Programmatic Agreement to outline a process 
to be used to avoid, mitigate, or treat adverse effects to historic 
properties.
    In August 2015, the BLM invited agencies to participate as 
Cooperating Agencies in the Project. The following agencies accepted 
the invitation: The U.S. Department of Defense (Utah Test and Training 
Range), the U.S. Environmental Protection Agency, the U.S. Fish and 
Wildlife Service, the State of Utah, and Millard and Beaver Counties. 
These agencies and governments reviewed the Draft EIS before it was 
available to the public and their comments have been incorporated into 
the document.
    Before including your address, phone number, email address, or 
other personal identifying information in your comment, you should be 
aware that your entire comment--including your personal identifying 
information--may be made publicly available at any time. While you can 
ask us in your comment to withhold your personal identifying 
information from public review, we cannot guarantee that we will be 
able to do so.

    Authority: 40 CFR 1506.6, 40 CFR 1506.10.

Anita Bilbao,
Associate State Director.
[FR Doc. 2018-26076 Filed 11-29-18; 8:45 am]
 BILLING CODE 4310-DQ-P



                                              61668                       Federal Register / Vol. 83, No. 231 / Friday, November 30, 2018 / Notices

                                                 Authority: 5 U.S.C. Appendix 2.                      provide the requested data in the                     Institutions: U.S. nonfuel minerals
                                              David Hoskins,
                                                                                                      desired format.                                       producers and consumers of industrial
                                                                                                        A Federal Register notice with a 60-                minerals. Public sector: State and local
                                              Co-Chair, Aquatic Nuisance Species Task
                                                                                                      day public comment period soliciting                  governments.
                                              Force, Assistant Director for Fish and Aquatic
                                              Conservation.                                           comments on this collection of                          Total Estimated Number of Annual
                                                                                                      information was published on July 9,                  Responses: 17,533.
                                              [FR Doc. 2018–26019 Filed 11–27–18; 11:15 am]
                                                                                                      2018, 83 FR 31767. We did not receive                   Total Estimated Number of Annual
                                              BILLING CODE 4333–15–P
                                                                                                      any public comments in response to that               Burden Hours: 12,055 hours.
                                                                                                      notice.                                                 Total Estimated Number of Annual
                                                                                                        We are again soliciting comments on                 Respondents: 14,957.
                                              DEPARTMENT OF THE INTERIOR
                                                                                                      the proposed ICR that is described                      Estimated Completion Time per
                                              Geological Survey                                       below. We are especially interested in                Response: 10 minutes to 5 hours.
                                                                                                      public comment addressing the                           Respondent’s Obligation: Voluntary.
                                              [GX18LR000F60100; OMB Control Number                    following issues: (1) Is the collection                 Frequency of Collection: Monthly,
                                              1028–0062]                                              necessary for the USGS to perform its                 Quarterly, Semiannually, or Annually.
                                                                                                      duties, including whether the                           Total Estimated Annual Nonhour
                                              Agency Information Collection                           information is useful; (2) the accuracy of            Burden Cost: There are no ‘‘nonhour
                                              Activities; Submission to the Office of                 the agency’s estimate of the burden of                cost’’ burdens associated with this IC.
                                              Management and Budget for Review                        the proposed collection of information;                 The authorities for this action are the
                                              and Approval; Industrial Minerals                       (3) ways to enhance the quality,                      Paperwork Reduction Act of 1995 (44
                                              Surveys                                                 usefulness, and clarity of the                        U.S.C. 3501, et seq.), the National
                                                                                                      information to be collected; and (4) how              Materials and Minerals Policy, Research
                                              AGENCY:   U.S. Geological Survey (USGS),                to minimize the burden of this                        and Development Act of 1980 (30 U.S.C.
                                              Interior.                                               collection on the respondents, including              1601 et seq.), and the National Mining
                                              ACTION: Notice of information collection;               through the use of information                        and Minerals Policy Act of 1970 (30
                                              request for comment.                                    technology.                                           U.S.C. 21(a)).
                                                                                                        Comments that you submit in
                                              SUMMARY:   In accordance with the                       response to this notice are a matter of               Michael Magyar,
                                              Paperwork Reduction Act of 1995, the                    public record. Before including your                  Associate Director, National Minerals
                                              U.S. Geological Survey is proposing to                  address, phone number, email address,                 Information Center.
                                              renew an information collection.                        or other personal identifying                         [FR Doc. 2018–26053 Filed 11–29–18; 8:45 am]
                                              DATES: Interested persons are invited to                information in your comment, you                      BILLING CODE 4338–11–P
                                              submit comments on or before                            should be aware that your entire
                                              December 31, 2018.                                      comment—including your personal
                                              ADDRESSES: Send written comments on                     identifying information—may be made                   DEPARTMENT OF THE INTERIOR
                                              this information collection request (ICR)               publicly available at any time. While
                                                                                                      you can ask us in your comment to                     Bureau of Land Management
                                              to the Office of Management and
                                              Budget’s Desk Officer for the                           withhold your personal identifying                    [LLUTW02000–L51010000–ER0000–
                                              Department of the Interior by email at                  information from public review, we                    LVRWJ18J5120–18X—UTU–90095]
                                              OIRA_Submission@omb.eop.gov; or via                     cannot guarantee that we will be able to
                                              facsimile to (202) 395–5806. Please                     do so.                                                Notice of Availability of the Draft
                                              provide a copy of your comments to                        An agency may not conduct or                        Environmental Impact Statement for
                                              U.S. Geological Survey, Information                     sponsor and a person is not required to               the Sevier Playa Potash Project, Utah
                                              Collections Officer, 12201 Sunrise                      respond to a collection of information                AGENCY:   Bureau of Land Management,
                                              Valley Drive MS 159, Reston, VA 20192;                  unless it displays a currently valid OMB              Interior.
                                              or by email to gs-info_collections@                     control number.
                                                                                                        Abstract: Respondents to these forms                ACTION: Notice of availability.
                                              usgs.gov. Please reference OMB Control
                                              Number 1028–0062 in the subject line of                 supply the USGS with domestic                         SUMMARY:   In accordance with the
                                              your comments.                                          production and consumption data of                    National Environmental Policy Act
                                              FOR FURTHER INFORMATION CONTACT: To
                                                                                                      industrial mineral commodities, some of               (NEPA) of 1969, as amended, the
                                              request additional information about                    which are considered strategic and                    Federal Land Policy and Management
                                              this ICR, contact Elizabeth S. Sangine by               critical to assist in determining National            Act of 1976, as amended, the Mineral
                                              email at escottsangine@usgs.gov, or by                  Defense Stockpile goals. These data and               Leasing Act of 1920, as amended, and
                                              telephone at 703–648–7720. You may                      derived information will be published                 Secretarial Order 3355, the Bureau of
                                              also view the ICR at http://                            as chapters in Minerals Yearbooks,                    Land Management (BLM) is releasing
                                              www.reginfo.gov/public/do/PRAMain.                      monthly Mineral Industry Surveys,                     the Draft Environmental Impact
                                                                                                      annual Mineral Commodity Summaries,                   Statement (EIS) for Crystal Peak
                                              SUPPLEMENTARY INFORMATION: In
                                                                                                      and special publications, for use by                  Minerals Inc.’s (CPM) Sevier Playa
                                              accordance with the Paperwork                           Government agencies, industry
                                              Reduction Act of 1995, we provide the                                                                         Potash Project (Project), and by this
                                                                                                      education programs, and the general                   notice is announcing the opening of the
                                              general public and other Federal                        public.
                                              agencies with an opportunity to                                                                               comment period.
                                                                                                        Title of Collection: Industrial Minerals
amozie on DSK3GDR082PROD with NOTICES1




                                              comment on proposed, revised, and                       Surveys.                                              DATES: To ensure comments will be
                                              continuing collections of information.                    OMB Control Number: 1028–0062.                      considered, the BLM must receive
                                              This helps us assess the impact of our                    Form Number: Various, 38 forms.                     written comments on the Project Draft
                                              information collection requirements and                   Type of Review: Extension of a                      EIS within 45 days following the date
                                              minimize the public’s reporting burden.                 currently approved collection.                        the Environmental Protection Agency
                                              It also helps the public understand our                   Respondents/Affected Public:                        publishes its Notice of Availability in
                                              information collection requirements and                 Business or Other-For-Profit                          the Federal Register. The BLM will


                                         VerDate Sep<11>2014   17:00 Nov 29, 2018   Jkt 247001   PO 00000   Frm 00070   Fmt 4703   Sfmt 4703   E:\FR\FM\30NON1.SGM   30NON1


                                                                          Federal Register / Vol. 83, No. 231 / Friday, November 30, 2018 / Notices                                            61669

                                              announce future meetings or hearings                    year of potassium sulfate (K2SO4), also               Development (POD) for the ROWs that
                                              and any other public involvement                        known as sulfate of potash (SOP), and                 they have requested. The Draft EIS also
                                              activities at least 15 days in advance                  related minerals over the 32-year                     analyzes CPM’s request to purchase
                                              through public notices, media releases,                 lifetime of the Project.                              mineral materials for gravel to support
                                              and/or mailings.                                           The Project is a potash mine proposed              construction and operation of the
                                              ADDRESSES: You may submit comments                      on 124,223 acres of Federal and State                 Project. Although the BLM may only
                                              related to the Draft EIS for the Project by             mineral leases. The proposal includes                 make decisions pertaining to public
                                              any of the following methods:                           mining facilities located on-lease with               lands managed by the BLM, the EIS
                                                 • Email: blm_ut_fm_sevier_playa_                     off-lease supporting infrastructure. On-              analyzes the complete Project including
                                              potash_project@blm.gov.                                 lease facilities include evaporation                  portions located on state and private
                                                 • Fax: (435) 743–3136.                               ponds; a brine extraction system                      lands.
                                                 • Mail: Bureau of Land Management                    (trenches, wells, and conveyance                         This Draft EIS evaluates, in detail, the
                                              Fillmore Field Office, Attn: Clara                      canals); a recharge system (trenches,                 no action alternative, the proposed
                                              Stevens—Sevier Playa Potash Project                     canals, and Sevier River diversion); a                action, and five action alternatives.
                                              Comments, 95 East 500 North, Fillmore,                  waste product storage area (purge brine               Alternative 1 would route a cross-
                                              UT 84631.                                               and tailings); access roads, and                      country segment of the off-lease 69-kV
                                                 Electronic versions of the Project Draft             processing facilities. The off-lease ROW              power and communication line to an
                                              EIS, appendices, and supporting                         facilities, proposed on approximately                 alignment along existing roads,
                                              documents can be downloaded from                        4,135 acres, include power and                        including SR 257 and SR–257 Cutoff
                                              ePlanning at https://bit.ly/2CZPeWy.                    communication lines, a natural gas                    Road. Alternative 2 would route a cross-
                                              Paper and digital copies of the Project                 pipeline, a rail loadout facility and rail            country segment of the off-lease 69-kV
                                              Draft EIS and supporting documents are                  spur; water supply wells;                             power and communication line to a
                                              available for review at:                                communication towers;                                 more southern orientation along existing
                                                 (1) The BLM Fillmore Field Office at                 preconcentration ponds; segments of                   roads, including Crystal Peak Road and
                                              the above address;                                      recharge canals and the playa perimeter               Crystal Peak Spur Road. Alternative 3
                                                 (2) The BLM West Desert District                     road; and access roads. Three gravel pits             would route a segment of the off-lease
                                              Office at 2370 South Decker Lake Blvd.,                 would also be developed.                              natural gas pipeline entirely on BLM
                                              West Valley City, UT;                                      Potassium-bearing brines would be                  land to avoid crossing private lands.
                                                 (3) The Fillmore City Library at 75                  extracted from trenches and wells on                  Alternative 4 would route a cross-
                                              West Center, Fillmore, UT; and                          the Sevier Playa, and routed through a                country segment of the off-lease natural
                                                 (4) The Delta City Library at 76 North               series of ponds, using solar evaporation              gas pipeline to a similar alignment as
                                              200 West, Delta, UT.                                    to concentrate the brine. The                         Alternative 2 along existing roads,
                                                                                                      preconcentration ponds would                          including Crystal Peak Road and Crystal
                                              FOR FURTHER INFORMATION CONTACT:
                                                                                                      concentrate the brine causing halite                  Peak Spur Road. Alternative 5 is an
                                              Clara Stevens, Project Manager,                         (NaCl, table salt) and other non-                     alternative method of diverting flows
                                              telephone (435) 743–3119; address 95                    commercial salts to precipitate. These                from the Sevier River into the recharge
                                              East 500 North, Fillmore, UT 84631;                     salts would be stored in the                          system. This alternative would relocate
                                              email clsteven@blm.gov. Persons who                     preconcentration ponds. The saturated                 the on-lease Sevier River diversion
                                              use a telecommunications device for the                 brine would be transferred to the                     facilities, including diversion channel,
                                              deaf (TDD) may call the Federal Relay                   production ponds for further                          recharge canal, diversion culvert and
                                              Service (FRS) at 1–800–877–8339 to                      evaporation, causing potassium-rich                   sump, and perimeter and access roads
                                              contact the above individual during                     salts to precipitate. The production                  slightly to the west, within the
                                              normal business hours. The FRS is                       ponds would be harvested year-round,                  boundary of the playa.
                                              available 24 hours a day, 7 days a week,                with the potassium-rich salts moved                      Based on public scoping and internal
                                              to leave a message or question with the                 directly to a facility for processing into            review, the principal issues analyzed in
                                              above individual. You will receive a                    SOP. The SOP would be trucked to the                  the Draft EIS include: (1) Impacts to
                                              reply during normal business hours.                     rail loadout facility for distribution.               water resources and water quality
                                              SUPPLEMENTARY INFORMATION: On March                     Purge brine containing primarily                      including adverse effects to surface
                                              12, 2014, the BLM published a Notice of                 magnesium chloride (MgCl2) would be                   water and groundwater basins, as well
                                              Intent to Prepare an EIS in the Federal                 removed from the production ponds                     as impacts to existing water rights
                                              Register (79 FR 14078).                                 before harvesting begins and would be                 holders; (2) adverse effects to air quality
                                                 The Project would be located in                      piped to an on-playa purge brine storage              in the form of fugitive dust produced
                                              central Millard County in southwestern                  pond. Process by-products (solid                      during construction and operation of the
                                              Utah. The Sevier Playa is a large                       tailings) from the processing facility                mine facilities; (3) impacts to cultural
                                              terminal playa that is normally dry on                  would be trucked to the on-playa                      resources and historic properties,
                                              the surface and contains subsurface                     tailings storage area.                                including rock art and subsurface
                                              potassium-bearing saline brines. The                       The Draft EIS analyzes CPM’s Mining                features; (4) impacts to migratory bird
                                              playa is approximately 26 miles long                    Plan, prepared for development of                     populations; and (5) the socioeconomic
                                              and averages 8 miles wide.                              Federal potassium mineral leases                      effects of water right acquisition for
                                                 CPM holds or through agreement                       acquired in 2011 and potash mineral                   recharge water. Analysis also includes
                                              controls the rights to develop and                      leases acquired on State lands. These                 impacts to the following resources:
                                              operate potassium mineral leases on                     leases were amalgamated under BLM                     Visual, wildlife, access, range
amozie on DSK3GDR082PROD with NOTICES1




                                              117,814 acres of Federal lands                          casefile number UTU–88387. In                         management, recreation, and soils.
                                              administered by the BLM and an                          addition, the Draft EIS analyzes CPM’s                   The BLM published a Notice of Intent
                                              additional 6,409 acres of state lands.                  request for rights-of-way (ROWs) to                   for the Project on March 12, 2014.
                                              CPM proposes to exercise their lease                    construct various ancillary facilities on             Scoping was extended through August
                                              rights by constructing and operating the                public lands in the vicinity of the                   31, 2015, due to Project delays. A public
                                              Project, which would produce at its                     mineral leases, but outside the lease                 scoping meeting was held in Delta,
                                              peak approximately 372,000 tons per                     boundary. CPM prepared a Plan of                      Utah, on August 5, 2015. The public


                                         VerDate Sep<11>2014   17:00 Nov 29, 2018   Jkt 247001   PO 00000   Frm 00071   Fmt 4703   Sfmt 4703   E:\FR\FM\30NON1.SGM   30NON1


                                              61670                       Federal Register / Vol. 83, No. 231 / Friday, November 30, 2018 / Notices

                                              was offered the opportunity to provide                  ACTION:   Notice of availability.                     Department of Lands, the U.S. Army
                                              written comments throughout the                                                                               Corps of Engineers, and the Idaho
                                              scoping process.                                        SUMMARY:    In accordance with the                    Governor’s Office of Energy and Mineral
                                                 In 2015, pursuant to Executive Order                 National Environmental Policy Act of                  Resources are cooperating agencies.
                                              13175, the BLM initiated government-                    1969, as amended, the Bureau of Land                     P4 Production, LLC (P4), a subsidiary
                                              to-government consultation with                         Management (BLM) has prepared a Draft                 of Bayer AG, developed and submitted
                                              interested tribes, including the                        Environmental Impact Statement (EIS)                  a Mine and Reclamation Plan (M&RP),
                                              Confederated Tribes of the Goshute                      for the proposed Caldwell Canyon Mine                 the Proposed Action, for the Caldwell
                                              Reservation, the Hopi Tribe, the Kaibab                 Project, and by this notice is                        Canyon Mine. The Proposed Action
                                              Band of Paiute Indians, the Kanosh                      announcing the opening of the comment                 consists of mining Federal Phosphate
                                              Band of Paiute Indians, the Navajo                      period.                                               Leases IDI–02, IDI–014080, and IDI–
                                              Nation, the Paiute Indian Tribe of Utah,                DATES: To ensure the BLM considers all                13738 and State of Idaho Mineral Lease
                                              the Skull Valley Band of Goshute, and                   comments, the BLM must receive                        E07959. Portions of the mine’s waste
                                              the Ute Indian Tribe. Beginning in 2015,                written comments on the Draft EIS for                 rock would be placed into the nearby
                                              the BLM coordinated with the Utah                       the proposed Caldwell Canyon Mine                     inactive Dry Valley Mine on Federal
                                              State Historic Preservation Office and                  Project within 45 days following the                  Phosphate Lease IDI–014184. P4 will
                                              seven other consulting parties that                     date the Environmental Protection                     request modifications to enlarge the
                                              requested to participate in the Section                 Agency publishes this Notice of                       phosphate lease boundaries for the
                                              106 process, to develop a Programmatic                  Availability in the Federal Register. The             Caldwell Canyon leases, and obtain
                                              Agreement to outline a process to be                    BLM will announce public comment                      authorization for a haul road across
                                              used to avoid, mitigate, or treat adverse               meetings at least 15 days in advance                  BLM public land as outlined in the Draft
                                              effects to historic properties.                         through public notices, media release,                EIS. The BLM has fully evaluated
                                                 In August 2015, the BLM invited                      and/or mailings. To assist the BLM in                 alternatives to the Proposed Action,
                                              agencies to participate as Cooperating                  identifying issues and concerns related               including a No Action Alternative, in
                                              Agencies in the Project. The following                  to this project and the Draft EIS,                    the Draft EIS and addressed issues
                                              agencies accepted the invitation: The                   comments should be as specific as                     identified during scoping and analysis.
                                              U.S. Department of Defense (Utah Test                   possible.                                                The BLM will make decisions to
                                              and Training Range), the U.S.                                                                                 either approve, approve with
                                                                                                      ADDRESSES: You may submit comments
                                              Environmental Protection Agency, the                                                                          modifications, or deny the Caldwell
                                                                                                      related to the Caldwell Canyon Mine                   Canyon Mine M&RP and modification of
                                              U.S. Fish and Wildlife Service, the State               Project Draft EIS by any of the following
                                              of Utah, and Millard and Beaver                                                                               the Dry Valley Mine M&RP. In addition,
                                                                                                      methods:                                              the BLM will determine whether to
                                              Counties. These agencies and                               • Website: https://bit.ly/2SaxWcO.                 modify the lease boundaries, and
                                              governments reviewed the Draft EIS                         • Email: blm_id_caldwell_canyon_
                                              before it was available to the public and                                                                     whether to issue a right-of-way or
                                                                                                      mine_eis@blm.gov.
                                              their comments have been incorporated                      • Mail: Caldwell Canyon Mine EIS,                  phosphate use permit for a haul road on
                                              into the document.                                                                                            BLM lands. These decisions will
                                                                                                      c/o Tetra Tech, 2525 Palmer Street,
                                                 Before including your address, phone                                                                       consider public and agency input
                                                                                                      Suite 2, Missoula, MT 59808.
                                              number, email address, or other                            Please reference ‘‘Caldwell Canyon                 received on the Draft and Final EISs.
                                              personal identifying information in your                                                                         The BLM published a Notice of Intent
                                                                                                      Mine Draft EIS’’ on all correspondence.
                                              comment, you should be aware that                                                                             (NOI) to prepare this EIS in the Federal
                                                                                                      The BLM has made CD–ROM and print
                                              your entire comment—including your                                                                            Register on March 22, 2017, initiating a
                                                                                                      copies of the Caldwell Canyon Mine
                                              personal identifying information—may                                                                          30-day public scoping period for the
                                                                                                      Draft EIS available in the BLM Pocatello
                                              be made publicly available at any time.                                                                       Proposed Action during which the BLM
                                                                                                      Field Office at the following address:
                                              While you can ask us in your comment                                                                          accepted written comments. Public
                                                                                                      4350 Cliffs Drive, Pocatello, ID 83204. In            scoping identified concerns related to
                                              to withhold your personal identifying                   addition, the BLM has made an
                                              information from public review, we                                                                            the following topics: The potential
                                                                                                      electronic copy of the Draft EIS                      impacts to water quantity from
                                              cannot guarantee that we will be able to                available online at the BLM Land Use                  dewatering; potential impacts to water
                                              do so.                                                  Planning and NEPA Register website:                   quality from elevated levels of selenium
                                                 Authority: 40 CFR 1506.6, 40 CFR 1506.10.            http://bit.ly/2zuZ8Mn.                                and other constituents of concern;
                                                                                                      FOR FURTHER INFORMATION CONTACT: For                  potential effects of increased noise on
                                              Anita Bilbao,
                                                                                                      further information contact Bill Volk,                wildlife, safety, and socioeconomics;
                                              Associate State Director.                               Planning and NEPA Specialist, phone                   effects to tribal interests; cultural
                                              [FR Doc. 2018–26076 Filed 11–29–18; 8:45 am]            (208) 236–7503; address, BLM Pocatello                resources; wildlife; vegetation, visual
                                              BILLING CODE 4310–DQ–P                                  Field Office, 4350 Cliffs Drive,                      quality; reclamation and financial
                                                                                                      Pocatello, ID 83204; email, wvolk@                    assurance; and mitigation and
                                                                                                      blm.gov; and fax, (208) 478–6376.                     monitoring of mine operations.
                                              DEPARTMENT OF THE INTERIOR                              Persons who use a telecommunications                     Before including your phone number,
                                                                                                      device for the deaf (TDD) may call the                email address, or other personal
                                              Bureau of Land Management
                                                                                                      Federal Information Relay Service (FRS)               identifying information in your
                                              [18XL LLIDI00000.L71220000.EO0000.                      at (800) 877–8339 to contact Mr. Volk.                comment, you should be aware that
                                              LVTFDX402300 241A 4500129252]                           The FRS is available 24 hours a day, 7                your entire comment—including your
amozie on DSK3GDR082PROD with NOTICES1




                                                                                                      days a week, to leave a message or                    personal identifying information—may
                                              Notice of Availability of the Draft                     question for Mr. Volk. You will receive               be made publicly available at any time.
                                              Environmental Impact Statement for                      a reply during normal business hours.                 While you can ask us in your comment
                                              the Proposed Caldwell Canyon Mine
                                                                                                      SUPPLEMENTARY INFORMATION: The BLM,                   to withhold your personal identifying
                                              Project, Caribou County, Idaho
                                                                                                      as the Federal lease administrator, is the            information from public review, we
                                              AGENCY:     Bureau of Land Management,                  lead agency. The Idaho Department of                  cannot guarantee that we will be able to
                                              Interior.                                               Environmental Quality, Idaho                          do so.


                                         VerDate Sep<11>2014   17:00 Nov 29, 2018   Jkt 247001   PO 00000   Frm 00072   Fmt 4703   Sfmt 4703   E:\FR\FM\30NON1.SGM   30NON1



Document Created: 2018-11-30 04:35:33
Document Modified: 2018-11-30 04:35:33
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of availability.
DatesTo ensure comments will be considered, the BLM must receive written comments on the Project Draft EIS within 45 days following the date the Environmental Protection Agency publishes its Notice of Availability in the Federal Register. The BLM will announce future meetings or hearings and any other public involvement activities at least 15 days in advance through public notices, media releases, and/or mailings.
ContactClara Stevens, Project Manager,
FR Citation83 FR 61668 