83_FR_62954 83 FR 62720 - Findings of Failure To Submit Complete State Implementation Plans Required for the 1997, 2006, and 2012 PM2.5

83 FR 62720 - Findings of Failure To Submit Complete State Implementation Plans Required for the 1997, 2006, and 2012 PM2.5

ENVIRONMENTAL PROTECTION AGENCY

Federal Register Volume 83, Issue 234 (December 6, 2018)

Page Range62720-62724
FR Document2018-26359

The Environmental Protection Agency (EPA) is taking final action to find that California has failed to submit complete state implementation plans (SIPs) required under the Clean Air Act (CAA or ``Act'') to implement the 1997, 2006, and 2012 national ambient air quality standards (NAAQS or ``standards'') for fine particulate matter (PM<INF>2.5</INF>) in the San Joaquin Valley. For the 1997 annual and 24-hour PM<INF>2.5</INF> NAAQS, California was required to submit by December 31, 2016, a SIP submission that provides for, among other things, annual reductions in emissions of direct PM<INF>2.5</INF> or a PM<INF>2.5</INF> plan precursor pollutant within the area of not less than five percent of the amount of such emissions as reported in the most recent inventory for the area. For the 2006 24-hour PM<INF>2.5</INF> NAAQS, California was required to submit by August 21, 2017, a SIP submission that meets the requirements for Serious PM<INF>2.5</INF> nonattainment areas, including the requirement for best available control measures (BACM). For the 2012 annual PM<INF>2.5</INF> NAAQS, California was required to submit by October 15, 2016, a SIP submission that meets the requirements for Moderate PM<INF>2.5</INF> nonattainment areas, including the requirement for reasonably available control measures (RACM). California submitted substantial portions of each of these required SIP submissions as part of an integrated plan on November 16, 2018, but each of these submissions fails to meet the EPA's minimum criteria for completeness. If the EPA has not affirmatively found that the State has submitted complete SIPs that correct the deficiencies in each of these SIP submissions within 18 months of this finding, the offset sanction will apply in the area. If within 6 additional months the EPA still has not affirmatively determined that the State has submitted complete SIPs that correct the deficiencies, the highway funding sanction will apply in the area. No later than 2 years after the EPA makes these findings, if the State has not submitted, and the EPA has not approved, each of the required SIP submissions, the EPA must promulgate a federal implementation plan (FIP) to address any remaining requirements.

Federal Register, Volume 83 Issue 234 (Thursday, December 6, 2018)
[Federal Register Volume 83, Number 234 (Thursday, December 6, 2018)]
[Rules and Regulations]
[Pages 62720-62724]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-26359]


-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

40 CFR Part 52

[EPA-R09-OAR-2018-0778; FRL-9987-38-Region 9]


Findings of Failure To Submit Complete State Implementation Plans 
Required for the 1997, 2006, and 2012 PM2.5 NAAQS; California; San 
Joaquin Valley

AGENCY: Environmental Protection Agency (EPA).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: The Environmental Protection Agency (EPA) is taking final 
action to find that California has failed to submit complete state 
implementation plans (SIPs) required under the Clean Air Act (CAA or 
``Act'') to implement the 1997, 2006, and 2012 national ambient air 
quality standards (NAAQS or ``standards'') for fine particulate matter 
(PM2.5) in the San Joaquin Valley. For the 1997 annual and 
24-hour PM2.5 NAAQS, California was required to submit by 
December 31, 2016, a SIP submission that provides for, among other 
things, annual reductions in emissions of direct PM2.5 or a 
PM2.5 plan precursor pollutant within the area of not less 
than five percent of the amount of such emissions as reported in the 
most recent inventory for the area. For the 2006 24-hour 
PM2.5 NAAQS, California was required to submit by August 21, 
2017, a SIP submission that meets the requirements for Serious 
PM2.5 nonattainment areas, including the requirement for 
best available control measures (BACM). For the 2012 annual 
PM2.5 NAAQS, California was required to submit by October 
15, 2016, a SIP submission that meets the requirements for Moderate 
PM2.5 nonattainment areas, including the requirement for 
reasonably available control measures (RACM). California submitted 
substantial portions of each of these required SIP submissions as part 
of an integrated plan on November 16, 2018, but each of these 
submissions fails to meet the EPA's minimum criteria for completeness.
    If the EPA has not affirmatively found that the State has submitted 
complete SIPs that correct the deficiencies in each of these SIP 
submissions within 18 months of this finding, the offset sanction will 
apply in the area. If within 6 additional months the EPA still has not 
affirmatively determined that the State has submitted complete SIPs 
that

[[Page 62721]]

correct the deficiencies, the highway funding sanction will apply in 
the area. No later than 2 years after the EPA makes these findings, if 
the State has not submitted, and the EPA has not approved, each of the 
required SIP submissions, the EPA must promulgate a federal 
implementation plan (FIP) to address any remaining requirements.

DATES: This action will be effective on January 7, 2019.

ADDRESSES: The EPA has established a docket for this action under 
Docket ID No. EPA-R09-OAR-2018-0778. Generally, documents in the docket 
are listed and publicly available at http://www.regulations.gov. 
Although listed in the index, some information is not publicly 
available, i.e., Confidential Business Information or other information 
whose disclosure is restricted by statute. Certain other material, such 
as copyrighted material, is not placed on the internet and will be 
publicly available in hard copy form. Publicly available docket 
materials are available either electronically at http://www.regulations.gov or in hard copy at EPA Region IX, 75 Hawthorne 
Street, San Francisco, CA 94105-3901. To inspect the hard copy 
materials, please schedule an appointment during normal business hours 
with the contact listed in the FOR FURTHER INFORMATION CONTACT section.

FOR FURTHER INFORMATION CONTACT: Wienke Tax, EPA Region IX, (415) 947-
4192, [email protected].

SUPPLEMENTARY INFORMATION: Throughout this document, ``we,'' ``us'' and 
``our'' refer to the EPA.

Notice and Comment Under the Administrative Procedure Act (APA)

    Section 553 of the APA, 5 U.S.C. 553(b)(3)(B), provides that, when 
an agency for good cause finds that notice and public procedure are 
impracticable, unnecessary or contrary to the public interest, the 
agency may issue a rule without providing notice and an opportunity for 
public comment. The EPA has determined that there is good cause for 
taking this final agency action without prior proposal and opportunity 
for comment because no significant EPA judgment is involved in making a 
finding of failure to submit complete SIPs, or elements of SIPs, 
required by the CAA, where a state has made incomplete submissions, to 
meet the requirement. Thus, notice and public procedures are 
unnecessary. The EPA finds that this constitutes good cause under 5 
U.S.C. 553(b)(3)(B).

Table of Contents

I. Background
    A. Statutory Requirements
    B. Minimum Criteria for Completeness of a SIP Submission
    C. California's SIP Submissions
II. Consequences of Findings of Failure To Submit Complete SIPs
III. Final Action
IV. Statutory and Executive Order Reviews

I. Background

A. Statutory Requirements

1. 1997 PM2.5 NAAQS
    The EPA first promulgated NAAQS for PM2.5 on July 18, 
1997, setting the primary and secondary annual standards at 15 
micrograms per cubic meter ([mu]g/m\3\) and the primary and secondary 
24-hour standards at 65 [mu]g/m\3\.\1\ Effective April 5, 2005, the EPA 
designated the San Joaquin Valley as nonattainment for the 1997 
PM2.5 NAAQS.\2\ Following a January 4, 2013 decision of the 
U.S. Court of Appeals for the D.C. Circuit (``D.C. Circuit'') remanding 
the EPA's 2007 PM2.5 Implementation Rule for the 1997 
PM2.5 NAAQS,\3\ the EPA published a final rule on June 2, 
2014, classifying the San Joaquin Valley, among other areas, as a 
``Moderate'' nonattainment area for the 1997 PM2.5 NAAQS 
under subpart 4, part D of title I of the Act.\4\
---------------------------------------------------------------------------

    \1\ 62 FR 38652 (July 18, 1997) (codified at 40 CFR 50.7).
    \2\ 70 FR 944 (January 5, 2005).
    \3\ Natural Resources Defense Council v. EPA, 706 F.3d. 428 (DC 
Cir. 2013) (``NRDC''). In NRDC, the court held that the EPA erred in 
implementing the 1997 PM2.5 standards solely pursuant to 
the general implementation requirements of subpart 1, without also 
considering the requirements specific to nonattainment areas for 
particles less than or equal to 10 [mu]m in diameter 
(PM10) in subpart 4, part D of title I of the CAA. The 
court reasoned that the plain meaning of the CAA requires 
implementation of the 1997 PM2.5 standards under subpart 
4 because PM2.5 falls within the statutory definition of 
PM10 and is thus subject to the same statutory 
requirements as PM10. The court remanded the rule, 
without vacatur, and instructed the EPA ``to repromulgate these 
rules pursuant to Subpart 4 consistent with this opinion.''
    \4\ 79 FR 31566.
---------------------------------------------------------------------------

    Effective May 7, 2015, the EPA reclassified the San Joaquin Valley 
as a ``Serious'' nonattainment area for the 1997 PM 2.5 
NAAQS.\5\ Upon reclassification as a Serious Area, the San Joaquin 
Valley became subject to a December 31, 2015 deadline under CAA section 
188(c)(2) for attaining the 1997 PM2.5 NAAQS. On February 9, 
2016, the EPA proposed to grant the State's request for extensions of 
the December 31, 2015 attainment date under CAA section 188(e), to 
December 31, 2018, for the 1997 24-hour PM2.5 NAAQS and to 
December 31, 2020, for the 1997 annual PM2.5 NAAQS in the 
San Joaquin Valley.\6\ On October 6, 2016, after considering public 
comments, the EPA denied California's request for these extensions of 
the attainment date.\7\ Consequently, on November 23, 2016, the EPA 
determined that the San Joaquin Valley had failed to attain the 1997 
annual and 24-hour PM2.5 NAAQS by the December 31, 2015 
Serious Area attainment date.\8\ This determination triggered a 
requirement for California to submit, by December 31, 2016, a revised 
PM2.5 attainment plan that satisfies the requirements of CAA 
section 189(d).\9\
---------------------------------------------------------------------------

    \5\ 80 FR 18528 (April 7, 2015).
    \6\ 81 FR 6936. California's request for extension of the 
Serious Area attainment date for the San Joaquin Valley accompanied 
its Serious Area attainment plan for the 1997 PM2.5 NAAQS 
and related motor vehicle emission budgets, submitted June 25, 2015 
and August 13, 2015, respectively.
    \7\ 81 FR 69396.
    \8\ 81 FR 84481.
    \9\ CAA section 189(d).
---------------------------------------------------------------------------

    The section 189(d) plan must, among other things, demonstrate 
expeditious attainment of the 1997 PM2.5 NAAQS within the 
time period provided under CAA section 179(d) and provide for annual 
reductions in emissions of direct PM2.5 or a 
PM2.5 plan precursor pollutant within the area of not less 
than five percent per year from the most recent emissions inventory for 
the area until attainment.\10\ The section 189(d) plan must also 
include, among other things:
---------------------------------------------------------------------------

    \10\ Id. and 40 CFR 51.1010(c).
---------------------------------------------------------------------------

    1. A comprehensive, accurate, current inventory of actual emissions 
from all sources of PM2.5 and PM2.5 precursors in 
the area (CAA section 172(c)(3));
    2. plan provisions that require reasonable further progress (RFP) 
(CAA 172(c)(2));
    3. quantitative milestones which are to be achieved every 3 years 
until the area is redesignated attainment and which demonstrate RFP 
toward attainment by the applicable date (CAA section 189(c)); and
    4. contingency measures to be implemented if the area fails to meet 
RFP or to attain by the applicable attainment date (CAA section 
172(c)(9)).
2. 2006 PM2.5 NAAQS
    On October 17, 2006, the EPA revised the 24-hour PM2.5 
NAAQS by lowering it from 65 [micro]g/m\3\ to 35 [micro]g/m\3\.\11\ 
Effective December 14, 2009, the EPA designated the San Joaquin Valley 
as nonattainment for the 2006 24-hour PM2.5 NAAQS. The EPA 
initially classified the San Joaquin Valley area as a Moderate Area 
effective July 2, 2014, and reclassified the area as

[[Page 62722]]

a Serious Area for the 2006 PM2.5 NAAQS effective February 
19, 2016.\12\
---------------------------------------------------------------------------

    \11\ 71 FR 61144 (October 17, 2006) (codified at 40 CFR 50.13).
    \12\ 79 FR 31566 (June 2, 2014), 81 FR 2993 (January 20, 2016), 
and 81 FR 42263 (June 29, 2016) (correcting amendment).
---------------------------------------------------------------------------

    Upon the area's reclassification as a Serious Area for the 2006 
PM2.5 NAAQS, California was required to submit additional 
SIP revisions by August 21, 2017, to satisfy the statutory requirements 
that apply to Serious PM2.5 nonattainment areas, including 
the requirements of subpart 4 of part D, title I of the Act.\13\
---------------------------------------------------------------------------

    \13\ Id.
---------------------------------------------------------------------------

    The Serious Area plan must include, among other things:
    1. A comprehensive, accurate, current inventory of actual emissions 
from all sources of PM2.5 and PM2.5 precursors in 
the area (CAA section 172(c)(3));
    2. provisions for the implementation of BACM, including best 
available control technology (BACT), for sources of direct 
PM2.5 and all PM2.5 plan precursors no later than 
4 years after the area is reclassified (CAA section 189(b)(1)(B));
3. a demonstration (including air quality modeling) that the plan 
provides for attainment as expeditiously as practicable but no later 
than December 31, 2019, or where the State is seeking an extension of 
the attainment date under section 188(e), a demonstration that 
attainment by December 31, 2019, is impracticable and that the plan 
provides for attainment by the most expeditious alternative date 
practicable and no later than December 31, 2024, (CAA sections 
188(c)(2) and 189(b)(1)(A)); \14\
---------------------------------------------------------------------------

    \14\ A state seeking an extension of a Serious Area attainment 
date under section 188(e) must also meet additional requirements 
under that provision, including the requirement to demonstrate that 
the SIP for the area includes the most stringent measures that are 
included in any SIP or are achieved in practice in any state, and 
can feasibly be implemented in the area. CAA section 188(e).
---------------------------------------------------------------------------

    4. plan provisions that require RFP (CAA 172(c)(2));
    5. quantitative milestones which are to be achieved every 3 years 
until the area is redesignated attainment and which demonstrate RFP 
toward attainment by the applicable date (CAA section 189(c));
    6. provisions to assure that control requirements applicable to 
major stationary sources of PM2.5 also apply to major 
stationary sources of PM2.5 precursors, except where the 
state demonstrates to the EPA's satisfaction that such sources do not 
contribute significantly to PM2.5 levels that exceed the 
standard in the area (CAA section 189(e));
    7. contingency measures to be implemented if the area fails to meet 
RFP or to attain by the applicable attainment date (CAA section 
172(c)(9)); and
    8. a revision to the nonattainment NSR program to lower the 
applicable ``major stationary source'' thresholds from 100 tpy to 70 
tpy (CAA section 189(b)(3)).
    3. 2012 PM2.5 NAAQS
    On December 14, 2012, the EPA revised the primary annual 
PM2.5 standard by lowering it from 15.0 to 12.0 [micro]g/
m\3\.\15\ Effective April 15, 2015, the EPA designated and classified 
the San Joaquin Valley as a Moderate nonattainment area for the 2012 
annual PM2.5 NAAQS.\16\ This designation and classification 
triggered a requirement for California to submit a Moderate Area plan 
addressing attainment of the 2012 annual PM2.5 NAAQS in the 
San Joaquin Valley no later than 18 months after the designation, i.e., 
by October 15, 2016.\17\
---------------------------------------------------------------------------

    \15\ 78 FR 3086 (January 15, 2013) (codified at 40 CFR 50.18).
    \16\ 80 FR 2206 (January 15, 2015).
    \17\ CAA section 189(a)(2)(B).
---------------------------------------------------------------------------

    The Moderate Area plan must include, among other things:
    1. A comprehensive, accurate, current inventory of actual emissions 
from all sources of PM2.5 and PM2.5 precursors in 
the area (CAA section 172(c)(3));
    2. provisions for the implementation of RACM, including reasonably 
available control technology (RACT), for sources of direct 
PM2.5 and all PM2.5 plan precursors no later than 
4 years after designation (CAA section 189(a)(1)(C));
    3. a demonstration (including air quality modeling) that the plan 
provides for attainment as expeditiously as practicable but no later 
than December 31, 2021, or a demonstration that attainment by that date 
is impracticable (CAA section 189(a)(1)(B));
    4. plan provisions that require RFP (CAA 172(c)(2));
    5. quantitative milestones which are to be achieved every 3 years 
until the area is redesignated attainment and which demonstrate RFP 
toward attainment by the applicable date (CAA section 189(c));
    6. provisions to assure that control requirements applicable to 
major stationary sources of PM2.5 also apply to major 
stationary sources of PM2.5 precursors, except where the 
state demonstrates to the EPA's satisfaction that such sources do not 
contribute significantly to PM2.5 levels that exceed the 
standard in the area (CAA section 189(e));
    7. contingency measures to be implemented if the area fails to meet 
RFP or to attain by the applicable attainment date (CAA section 
172(c)(9)); and
    8. Any revisions to the nonattainment NSR program necessary to 
implement the requirements of CAA section 189(a)(1)(A) for the 2012 
PM2.5 NAAQS.

B. Minimum Criteria for Completeness of a SIP Submission

    Section 110(k)(1)(A) of the CAA requires that the EPA promulgate 
minimum criteria that any plan submission must meet before the EPA is 
required to act on such submission. The EPA has promulgated these 
criteria at 40 CFR part 51, appendix V. We refer to these requirements 
as the ``completeness criteria.'' Section 2.1 of the completeness 
criteria requires that each plan submission include, among other 
things: (1) Evidence that the State has adopted the plan in the State 
code or body of regulations, including the date of adoption or final 
issuance as well as the effective date of the plan, if different from 
the adoption/issuance date, and (2) evidence that the State followed 
all of the procedural requirements of the State's laws and constitution 
in conducting and completing the adoption/issuance of the plan. Section 
2.2 of the completeness criteria requires that each plan submission 
contain certain technical support, including (1) a demonstration that 
the SIP will protect RFP if approved, and (2) modeling to support the 
proposed revision. The completeness criteria also identify other 
administrative materials and technical support documentation that must 
be included in each plan submission.\18\
---------------------------------------------------------------------------

    \18\ See generally 40 CFR part 51, appendix V, sections 2.1 and 
2.2.
---------------------------------------------------------------------------

    Section 110(k)(2) of the CAA requires the EPA to act on a SIP 
submission only after the State has submitted a SIP submission (or part 
thereof) that meets the completeness criteria, either by EPA 
determination or by operation of law under CAA section 110(k)(1)(B).

C. California's SIP Submissions

    On November 16, 2018, California submitted to the EPA a draft of 
the ``2018 Plan for the 1997, 2006, and 2012 PM2.5 
Standards'' (``2018 PM2.5 Plan''), a comprehensive plan for 
attainment of the PM2.5 NAAQS in the San Joaquin Valley. 
This submission includes substantial portions of a section 189(d) plan 
addressing attainment of the 1997 PM2.5 NAAQS, a Serious 
Area plan addressing attainment of the 2006 PM2.5 NAAQS, and 
a Moderate Area plan addressing attainment of the 2012 PM2.5 
NAAQS in the San Joaquin Valley. The

[[Page 62723]]

San Joaquin Valley Air Pollution Control District adopted the 2018 
PM2.5 Plan on November 15, 2018.
    As a threshold matter, however, the California Air Resources Board 
(CARB) noted in its letter transmitting the SIP submission to the EPA 
that CARB had not yet presented the 2018 PM2.5 Plan to its 
Board or adopted it for submission to the EPA as a revision to the 
California SIP. CARB stated that it was providing the submission to the 
EPA now so that EPA staff can begin its review while CARB completes the 
final step in plan development when it considers approval of the 2018 
PM2.5 Plan at its hearing scheduled for January 24-25, 
2019.\19\
---------------------------------------------------------------------------

    \19\ Letter dated November 16, 2018, from Kurt Karperos, Deputy 
Executive Officer, CARB, to Mike Stoker, Regional Administrator, EPA 
Region IX.
---------------------------------------------------------------------------

    Accordingly, the EPA cannot at this time find that California has 
submitted the required complete PM2.5 SIP revisions for the 
San Joaquin Valley nonattainment area. CARB's November 16, 2018 SIP 
submission does not include evidence that the State has adopted the 
plan in the State code or body of regulations or evidence that the 
State followed all of the procedural requirements of the State's laws 
and constitution in conducting and completing the adoption/issuance of 
the plan, as required by 40 CFR part 51, appendix V, section 2.1. Based 
on these deficiencies alone, the SIP submission fails to meet the EPA's 
minimum completeness criteria. In addition, until we receive the formal 
SIP submission, we cannot determine whether the plan that CARB 
ultimately adopts will contain all of the necessary components of the 
required PM2.5 attainment plans for the San Joaquin Valley 
and the associated technical support required for each submission under 
40 CFR part 51, appendix V, section 2.2.
    We note, however, that CARB's submission represents a significant 
step in the State's and District's multi-year effort to address the 
Act's attainment planning requirements for the PM2.5 NAAQS 
in the San Joaquin Valley, and we commit to continue working closely 
with both agencies as they implement and enforce the requirements of 
these plans going forward.

II. Consequences of Findings of Failure To Submit Complete SIPs

    Under section 110(k)(1)(C) of the Act, where the EPA determines 
that a SIP submission (or part thereof) does not meet the EPA's minimum 
completeness criteria established in 40 CFR part 51, appendix V, the 
state shall be treated as not having made the submission (or part 
thereof). Sections 179(a) and 110(c) of the CAA establish specific 
consequences for failure to submit complete SIP submissions or SIP 
elements required under part D of title I of the Act, including the 
eventual imposition of mandatory sanctions in the affected area.
    In accordance with the EPA's sanctions sequencing rule in 40 CFR 
52.31, the offset sanction identified in CAA section 179(b)(2) would 
apply in the San Joaquin Valley area 18 months after the effective date 
of these findings, if the EPA has not affirmatively determined by that 
date that the State has submitted a complete SIP addressing the 
deficiency that is the basis for these findings. If, within 6 months 
after the offset sanction applies, the EPA still has not affirmatively 
determined that the State has submitted a complete SIP addressing the 
deficiency that is the basis for the findings, the highway funding 
sanction identified in CAA section 179(b)(1) would also apply in the 
San Joaquin Valley. Under 40 CFR 52.31(d)(5), neither sanction would 
apply if the EPA determines within 18 months after the effective date 
of these findings that the State has submitted a complete SIP 
submission addressing the deficiency that is the basis for these 
findings.
    Additionally, a finding of failure to submit a complete SIP 
submission triggers an obligation under CAA section 110(c) for the EPA 
to promulgate a FIP no later than 2 years after the finding, unless the 
state has submitted, and the EPA has approved, the required SIP 
submittal. Thus, the EPA would be required to promulgate a 
PM2.5 FIP for the San Joaquin Valley, in relevant part, if 
California does not submit and the EPA does not approve all of the 
necessary SIP submissions within 2 years after the effective date of 
these findings.

III. Final Action

    The EPA is finding that California has failed to submit complete 
SIP revisions for implementation of the 1997, 2006, and 2012 
PM2.5 NAAQS in the San Joaquin Valley as required under 
subparts 1 and 4 of part D, title I of the CAA and the PM2.5 
SIP Requirements Rule. The consequences of these findings are discussed 
above in section II of this notice.

IV. Statutory and Executive Order Reviews

A. Executive Order 12866: Regulatory Planning and Executive Order 
13563: Improving Regulation and Regulatory Review

    This action is not a significant regulatory action and was, 
therefore, not submitted to the Office of Management and Budget (OMB) 
for review.

B. Executive Order 13771: Reducing Regulation and Controlling 
Regulatory Costs

    This action is not an Executive Order 13771 regulatory action 
because this action is not significant under Executive Order 12866.

C. Paperwork Reduction Act (PRA)

    This action does not impose an information collection burden under 
the provisions of the PRA. This final rule does not establish any new 
information collection requirement apart from what is already required 
by law. This rule relates to the requirements in the CAA for states to 
submit SIPs under sections 172, 188 and 189 which address the statutory 
requirements that apply to areas designated as nonattainment for the 
PM2.5 NAAQS.

D. Regulatory Flexibility Act (RFA)

    I certify that this rule will not have a significant economic 
impact on a substantial number of small entities under the RFA. This 
action will not impose any requirements on small entities. The rule is 
a finding that California has not submitted the necessary SIP 
revisions.

E. Unfunded Mandates Reform Act of 1995 (UMRA)

    This action does not contain any unfunded mandate as described in 
UMRA 2 U.S.C. 1531-1538, and does not significantly or uniquely affect 
small governments. The action imposes no enforceable duty on any state, 
local or tribal governments or the private sector.

F. Executive Order 13132: Federalism

    This action does not have federalism implications. It will not have 
substantial direct effects on the states, on the relationship between 
the national government and the states, or on the distribution of power 
and responsibilities among the various levels of government.

G. Executive Order 13175: Consultation and Coordination With Indian 
Tribal Governments

    This action does not have tribal implications as specified in 
Executive

[[Page 62724]]

Order 13175. This rule finds that California has failed to submit SIP 
revisions that satisfy certain nonattainment area planning requirements 
under sections 172, 188 and 189 of the CAA for the 1997, 2006, and 2012 
PM2.5 NAAQS for the San Joaquin Valley nonattainment area. 
No tribe is subject to the requirement to submit an implementation plan 
under section 172 or under subpart 4 of part D of Title I of the CAA. 
Thus, Executive Order 13175 does not apply to this action.

H. Executive Order 13045: Protection of Children From Environmental 
Health and Safety Risks

    The EPA interprets Executive Order 13045 as applying only to those 
regulatory actions that concern health or safety risks that the EPA has 
reason to believe may disproportionately affect children, per the 
definition of ``covered regulatory action'' in section 2-202 of the 
Executive Order. This action is not subject to Executive Order 13045 
because it is a finding that California has failed to submit certain 
SIP revisions that satisfy the nonattainment area planning requirements 
under sections 172, 188 and 189 of the CAA for the 1997, 2006, and 2012 
PM2.5 NAAQS for the San Joaquin Valley nonattainment area 
and does not directly or disproportionately affect children.

I. Executive Order 13211: Actions That Significantly Affect Energy 
Supply, Distribution or Use

    This action is not subject to Executive Order 13211, because it is 
not a significant regulatory action under Executive Order 12866.

J. National Technology Transfer and Advancement Act

    This rulemaking does not involve technical standards.

K. Executive Order 12898: Federal Actions To Address Environmental 
Justice in Minority Populations and Low-Income Populations

    The EPA believes the human health or environmental risk addressed 
by this action will not have potential disproportionately high and 
adverse human health or environmental effects on minority, low-income, 
or indigenous populations. In finding that California has failed to 
submit SIP revisions that satisfy certain nonattainment area planning 
requirements under sections 172, 188 and 189 of the CAA for the1997, 
2006, and 2012 PM2.5 NAAQS for the San Joaquin Valley 
nonattainment area, this action does not directly affect the level of 
protection provided to human health or the environment.

L. Congressional Review Act (CRA)

    The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the 
Small Business Regulatory Enforcement Fairness Act of 1996, generally 
provides that before a rule may take effect, the agency promulgating 
the rule must submit a rule report, which includes a copy of the rule, 
to each House of the Congress and to the Comptroller General of the 
United States. The EPA will submit a report containing this action and 
other required information to the U.S. Senate, the U.S. House of 
Representatives, and the Comptroller General of the United States prior 
to publication of the rule in the Federal Register. A major rule cannot 
take effect until 60 days after it is published in the Federal 
Register. This action is not a ``major rule'' as defined by 5 U.S.C. 
804(2).

M. Judicial Review

    Under section 307(b)(1) of the Clean Air Act, petitions for 
judicial review of this action must be filed in the United States Court 
of Appeals for the appropriate circuit by February 4, 2019. Filing a 
petition for reconsideration by the Administrator of this final rule 
does not affect the finality of this action for the purposes of 
judicial review nor does it extend the time within which a petition for 
judicial review may be filed, and shall not postpone the effectiveness 
of such rule or action. This action may not be challenged later in 
proceedings to enforce its requirements (see section 307(b)(2)).

List of Subjects in 40 CFR Part 52

    Environmental protection, Administrative practice and procedures, 
Air pollution control, Approval and promulgation of implementation 
plans, Administrative practice and procedures, Incorporation by 
reference, Intergovernmental relations, Particulate matter, and 
Reporting and recordkeeping requirements.

    Dated: November 19, 2018.
Deborah Jordan,
Acting Regional Administrator, Region IX.
[FR Doc. 2018-26359 Filed 12-4-18; 8:45 am]
 BILLING CODE 6560-50-P



                                             62720            Federal Register / Vol. 83, No. 234 / Thursday, December 6, 2018 / Rules and Regulations

                                             methods, under Executive Order 12898                          States prior to publication of the rule in                    Dated: November 26, 2018.
                                             (59 FR 7629, February 16, 1994).                              the Federal Register. A major rule                          Anne Idsal,
                                             In addition, the SIP is not approved to                       cannot take effect until 60 days after it                   Regional Administrator, Region 6.
                                             apply on any Indian reservation land or                       is published in the Federal Register.                            40 CFR part 52 is amended as follows:
                                             in any other area where EPA or an                             This action is not a ‘‘major rule’’ as
                                             Indian tribe has demonstrated that a                          defined by 5 U.S.C. 804(2).                                 PART 52—APPROVAL AND
                                             tribe has jurisdiction. In those areas of                        Under section 307(b)(1) of the Clean                     PROMULGATION OF
                                             Indian country, the rule does not have                        Air Act, petitions for judicial review of                   IMPLEMENTATION PLANS
                                             tribal implications and will not impose                       this action must be filed in the United
                                             substantial direct costs on tribal                            States Court of Appeals for the                             ■ 1. The authority citation for part 52
                                             governments or preempt tribal law as                          appropriate circuit by February 4, 2019.                    continues to read as follows:
                                             specified by Executive Order 13175 (65                        Filing a petition for reconsideration by                         Authority: 42 U.S.C. 7401 et seq.
                                             FR 67249, November 9, 2000).                                  the Administrator of this final rule does
                                                The Congressional Review Act, 5                            not affect the finality of this action for                  Subpart SS—Texas
                                             U.S.C. 801 et seq., as added by the Small                     the purposes of judicial review nor does
                                             Business Regulatory Enforcement                               it extend the time within which a                           ■  2. In § 52.2270(e) the second table
                                             Fairness Act of 1996, generally provides                      petition for judicial review may be filed,                  titled ‘‘EPA Approved Nonregulatory
                                             that before a rule may take effect, the                       and shall not postpone the effectiveness                    Provisions and Quasi-Regulatory
                                             agency promulgating the rule must                             of such rule or action. This action may                     Measures in the Texas SIP’’ is amended
                                             submit a rule report, which includes a                        not be challenged later in proceedings to                   by revising the entry for ‘‘Infrastructure
                                             copy of the rule, to each House of the                        enforce its requirements. (See section                      and Interstate Transport for the 1997
                                             Congress and to the Comptroller General                       307(b)(2).)                                                 Ozone and the 1997 and 2006 PM2.5
                                             of the United States. EPA will submit a                                                                                   NAAQS’’ to read as follows:
                                             report containing this action and other                       List of Subjects in 40 CFR Part 52
                                             required information to the U.S. Senate,                        Environmental protection, Air                             § 52.2270       Identification of plan
                                             the U.S. House of Representatives, and                        pollution control, Air pollution control,                   *        *    *        *       *
                                             the Comptroller General of the United                         Incorporation by reference, Ozone.                               (e) * * *
                                                          EPA-APPROVED NONREGULATORY PROVISIONS AND QUASI-REGULATORY MEASURES IN THE TEXAS SIP
                                                                               Applicable geographic                 State submittal/
                                                 Name of SIP provision                                                                                  EPA approval date                         Explanation
                                                                               or nonattainment area                  effective date


                                                                  *                  *                            *                   *                      *                     *                      *
                                             Infrastructure and Interstate    Statewide ....................   12/12/2007, 3/11/2008, 4/4/       12/28/2011, 76 FR 81371 ....    Approval for CAA elements 110(a)(2)(A),
                                                Transport for the 1997                                           2008, 5/1/2008, 11/23/                                            (B), (E), (F), (G), (H), (K), (L), and (M).
                                                Ozone and the 1997 and                                           2009.                                                             Full    approval    for     CAA     elements
                                                2006 PM2.5 NAAQS..                                                                                                                 110(a)(2)(C), (D)(i)(II), (D)(ii) and (J) with
                                                                                                                                                                                   approval of the GHG PSD revision (11/
                                                                                                                                                                                   10/2014, 79 FR66626). 1997 and 2006
                                                                                                                                                                                   PM2.5 element D(i)(I) approved 5/14/
                                                                                                                                                                                   2018, 83 FR 22208. 1997 ozone element
                                                                                                                                                                                   D(i)(I) approved 12/6/2018, [Insert Fed-
                                                                                                                                                                                   eral Register citation].

                                                                 *                     *                         *                      *                      *                   *                      *



                                             [FR Doc. 2018–26287 Filed 12–4–18; 8:45 am]                   complete state implementation plans                         control measures (BACM). For the 2012
                                             BILLING CODE 6560–50–P                                        (SIPs) required under the Clean Air Act                     annual PM2.5 NAAQS, California was
                                                                                                           (CAA or ‘‘Act’’) to implement the 1997,                     required to submit by October 15, 2016,
                                                                                                           2006, and 2012 national ambient air                         a SIP submission that meets the
                                             ENVIRONMENTAL PROTECTION                                      quality standards (NAAQS or                                 requirements for Moderate PM2.5
                                             AGENCY                                                        ‘‘standards’’) for fine particulate matter                  nonattainment areas, including the
                                                                                                           (PM2.5) in the San Joaquin Valley. For                      requirement for reasonably available
                                             40 CFR Part 52                                                the 1997 annual and 24-hour PM2.5                           control measures (RACM). California
                                             [EPA–R09–OAR–2018–0778; FRL–9987–38–                          NAAQS, California was required to                           submitted substantial portions of each
                                             Region 9]                                                     submit by December 31, 2016, a SIP                          of these required SIP submissions as
                                                                                                           submission that provides for, among                         part of an integrated plan on November
                                             Findings of Failure To Submit                                 other things, annual reductions in                          16, 2018, but each of these submissions
                                             Complete State Implementation Plans                           emissions of direct PM2.5 or a PM2.5 plan                   fails to meet the EPA’s minimum
                                             Required for the 1997, 2006, and 2012                         precursor pollutant within the area of                      criteria for completeness.
                                             PM2.5 NAAQS; California; San Joaquin                          not less than five percent of the amount                       If the EPA has not affirmatively found
                                             Valley                                                        of such emissions as reported in the                        that the State has submitted complete
khammond on DSK30JT082PROD with RULES




                                             AGENCY:  Environmental Protection                             most recent inventory for the area. For                     SIPs that correct the deficiencies in each
                                             Agency (EPA).                                                 the 2006 24-hour PM2.5 NAAQS,                               of these SIP submissions within 18
                                             ACTION: Final rule.                                           California was required to submit by                        months of this finding, the offset
                                                                                                           August 21, 2017, a SIP submission that                      sanction will apply in the area. If within
                                             SUMMARY:   The Environmental Protection                       meets the requirements for Serious                          6 additional months the EPA still has
                                             Agency (EPA) is taking final action to                        PM2.5 nonattainment areas, including                        not affirmatively determined that the
                                             find that California has failed to submit                     the requirement for best available                          State has submitted complete SIPs that


                                        VerDate Sep<11>2014    16:05 Dec 04, 2018   Jkt 247001      PO 00000     Frm 00032   Fmt 4700       Sfmt 4700   E:\FR\FM\06DER1.SGM      06DER1


                                                              Federal Register / Vol. 83, No. 234 / Thursday, December 6, 2018 / Rules and Regulations                                                  62721

                                             correct the deficiencies, the highway                      A. Statutory Requirements                           Valley.6 On October 6, 2016, after
                                             funding sanction will apply in the area.                   B. Minimum Criteria for Completeness of             considering public comments, the EPA
                                             No later than 2 years after the EPA                           a SIP Submission                                 denied California’s request for these
                                             makes these findings, if the State has                     C. California’s SIP Submissions                     extensions of the attainment date.7
                                             not submitted, and the EPA has not                      II. Consequences of Findings of Failure To
                                                                                                                                                            Consequently, on November 23, 2016,
                                                                                                           Submit Complete SIPs
                                             approved, each of the required SIP                                                                             the EPA determined that the San
                                                                                                     III. Final Action
                                             submissions, the EPA must promulgate                    IV. Statutory and Executive Order Reviews              Joaquin Valley had failed to attain the
                                             a federal implementation plan (FIP) to                                                                         1997 annual and 24-hour PM2.5 NAAQS
                                             address any remaining requirements.                     I. Background                                          by the December 31, 2015 Serious Area
                                             DATES: This action will be effective on                 A. Statutory Requirements                              attainment date.8 This determination
                                             January 7, 2019.                                                                                               triggered a requirement for California to
                                             ADDRESSES: The EPA has established a                    1. 1997 PM2.5 NAAQS                                    submit, by December 31, 2016, a revised
                                             docket for this action under Docket ID                                                                         PM2.5 attainment plan that satisfies the
                                                                                                        The EPA first promulgated NAAQS                     requirements of CAA section 189(d).9
                                             No. EPA–R09–OAR–2018–0778.                              for PM2.5 on July 18, 1997, setting the
                                             Generally, documents in the docket are                                                                            The section 189(d) plan must, among
                                                                                                     primary and secondary annual
                                             listed and publicly available at http://                                                                       other things, demonstrate expeditious
                                                                                                     standards at 15 micrograms per cubic
                                             www.regulations.gov. Although listed in                                                                        attainment of the 1997 PM2.5 NAAQS
                                                                                                     meter (mg/m3) and the primary and
                                             the index, some information is not                                                                             within the time period provided under
                                                                                                     secondary 24-hour standards at 65 mg/
                                             publicly available, i.e., Confidential                                                                         CAA section 179(d) and provide for
                                                                                                     m3.1 Effective April 5, 2005, the EPA
                                             Business Information or other                                                                                  annual reductions in emissions of direct
                                                                                                     designated the San Joaquin Valley as
                                             information whose disclosure is                                                                                PM2.5 or a PM2.5 plan precursor
                                                                                                     nonattainment for the 1997 PM2.5
                                             restricted by statute. Certain other                                                                           pollutant within the area of not less
                                                                                                     NAAQS.2 Following a January 4, 2013
                                             material, such as copyrighted material,                                                                        than five percent per year from the most
                                                                                                     decision of the U.S. Court of Appeals for
                                             is not placed on the internet and will be                                                                      recent emissions inventory for the area
                                                                                                     the D.C. Circuit (‘‘D.C. Circuit’’)
                                             publicly available in hard copy form.                                                                          until attainment.10 The section 189(d)
                                                                                                     remanding the EPA’s 2007 PM2.5
                                             Publicly available docket materials are                                                                        plan must also include, among other
                                                                                                     Implementation Rule for the 1997 PM2.5
                                             available either electronically at http://                                                                     things:
                                                                                                     NAAQS,3 the EPA published a final rule
                                             www.regulations.gov or in hard copy at
                                                                                                     on June 2, 2014, classifying the San                      1. A comprehensive, accurate, current
                                             EPA Region IX, 75 Hawthorne Street,
                                                                                                     Joaquin Valley, among other areas, as a                inventory of actual emissions from all
                                             San Francisco, CA 94105–3901. To
                                                                                                     ‘‘Moderate’’ nonattainment area for the                sources of PM2.5 and PM2.5 precursors in
                                             inspect the hard copy materials, please
                                                                                                     1997 PM2.5 NAAQS under subpart 4,                      the area (CAA section 172(c)(3));
                                             schedule an appointment during normal
                                                                                                     part D of title I of the Act.4                            2. plan provisions that require
                                             business hours with the contact listed in
                                             the FOR FURTHER INFORMATION CONTACT                        Effective May 7, 2015, the EPA                      reasonable further progress (RFP) (CAA
                                             section.                                                reclassified the San Joaquin Valley as a               172(c)(2));
                                                                                                     ‘‘Serious’’ nonattainment area for the                    3. quantitative milestones which are
                                             FOR FURTHER INFORMATION CONTACT:
                                                                                                     1997 PM 2.5 NAAQS.5 Upon                               to be achieved every 3 years until the
                                             Wienke Tax, EPA Region IX, (415) 947–
                                                                                                     reclassification as a Serious Area, the                area is redesignated attainment and
                                             4192, tax.wienke@epa.gov.
                                                                                                     San Joaquin Valley became subject to a                 which demonstrate RFP toward
                                             SUPPLEMENTARY INFORMATION:                              December 31, 2015 deadline under CAA
                                             Throughout this document, ‘‘we,’’ ‘‘us’’                                                                       attainment by the applicable date (CAA
                                                                                                     section 188(c)(2) for attaining the 1997               section 189(c)); and
                                             and ‘‘our’’ refer to the EPA.                           PM2.5 NAAQS. On February 9, 2016, the
                                             Notice and Comment Under the                            EPA proposed to grant the State’s                         4. contingency measures to be
                                             Administrative Procedure Act (APA)                      request for extensions of the December                 implemented if the area fails to meet
                                                                                                     31, 2015 attainment date under CAA                     RFP or to attain by the applicable
                                                Section 553 of the APA, 5 U.S.C.                                                                            attainment date (CAA section 172(c)(9)).
                                             553(b)(3)(B), provides that, when an                    section 188(e), to December 31, 2018, for
                                             agency for good cause finds that notice                 the 1997 24-hour PM2.5 NAAQS and to                    2. 2006 PM2.5 NAAQS
                                             and public procedure are impracticable,                 December 31, 2020, for the 1997 annual
                                                                                                     PM2.5 NAAQS in the San Joaquin                            On October 17, 2006, the EPA revised
                                             unnecessary or contrary to the public
                                                                                                                                                            the 24-hour PM2.5 NAAQS by lowering
                                             interest, the agency may issue a rule
                                                                                                       1 62 FR 38652 (July 18, 1997) (codified at 40 CFR    it from 65 mg/m3 to 35 mg/m3.11 Effective
                                             without providing notice and an
                                                                                                     50.7).                                                 December 14, 2009, the EPA designated
                                             opportunity for public comment. The                       2 70 FR 944 (January 5, 2005).
                                                                                                                                                            the San Joaquin Valley as nonattainment
                                             EPA has determined that there is good                     3 Natural Resources Defense Council v. EPA, 706
                                                                                                                                                            for the 2006 24-hour PM2.5 NAAQS. The
                                             cause for taking this final agency action               F.3d. 428 (DC Cir. 2013) (‘‘NRDC’’). In NRDC, the
                                                                                                                                                            EPA initially classified the San Joaquin
                                             without prior proposal and opportunity                  court held that the EPA erred in implementing the
                                                                                                     1997 PM2.5 standards solely pursuant to the general    Valley area as a Moderate Area effective
                                             for comment because no significant EPA
                                                                                                     implementation requirements of subpart 1, without      July 2, 2014, and reclassified the area as
                                             judgment is involved in making a                        also considering the requirements specific to
                                             finding of failure to submit complete                   nonattainment areas for particles less than or equal      6 81 FR 6936. California’s request for extension of
                                             SIPs, or elements of SIPs, required by                  to 10 mm in diameter (PM10) in subpart 4, part D
                                                                                                     of title I of the CAA. The court reasoned that the     the Serious Area attainment date for the San
                                             the CAA, where a state has made                                                                                Joaquin Valley accompanied its Serious Area
                                                                                                     plain meaning of the CAA requires implementation
                                             incomplete submissions, to meet the                     of the 1997 PM2.5 standards under subpart 4            attainment plan for the 1997 PM2.5 NAAQS and
khammond on DSK30JT082PROD with RULES




                                             requirement. Thus, notice and public                    because PM2.5 falls within the statutory definition    related motor vehicle emission budgets, submitted
                                                                                                                                                            June 25, 2015 and August 13, 2015, respectively.
                                             procedures are unnecessary. The EPA                     of PM10 and is thus subject to the same statutory
                                                                                                                                                               7 81 FR 69396.
                                             finds that this constitutes good cause                  requirements as PM10. The court remanded the rule,
                                                                                                                                                               8 81 FR 84481.
                                                                                                     without vacatur, and instructed the EPA ‘‘to
                                             under 5 U.S.C. 553(b)(3)(B).                            repromulgate these rules pursuant to Subpart 4            9 CAA section 189(d).

                                                                                                     consistent with this opinion.’’                           10 Id. and 40 CFR 51.1010(c).
                                             Table of Contents                                         4 79 FR 31566.                                          11 71 FR 61144 (October 17, 2006) (codified at 40

                                             I. Background                                             5 80 FR 18528 (April 7, 2015).                       CFR 50.13).



                                        VerDate Sep<11>2014   16:05 Dec 04, 2018   Jkt 247001   PO 00000   Frm 00033   Fmt 4700   Sfmt 4700   E:\FR\FM\06DER1.SGM   06DER1


                                             62722            Federal Register / Vol. 83, No. 234 / Thursday, December 6, 2018 / Rules and Regulations

                                             a Serious Area for the 2006 PM2.5                          7. contingency measures to be                      RFP or to attain by the applicable
                                             NAAQS effective February 19, 2016.12                    implemented if the area fails to meet                 attainment date (CAA section 172(c)(9));
                                                Upon the area’s reclassification as a                RFP or to attain by the applicable                    and
                                             Serious Area for the 2006 PM2.5                         attainment date (CAA section 172(c)(9));                 8. Any revisions to the nonattainment
                                             NAAQS, California was required to                       and                                                   NSR program necessary to implement
                                             submit additional SIP revisions by                         8. a revision to the nonattainment                 the requirements of CAA section
                                             August 21, 2017, to satisfy the statutory               NSR program to lower the applicable                   189(a)(1)(A) for the 2012 PM2.5 NAAQS.
                                             requirements that apply to Serious PM2.5                ‘‘major stationary source’’ thresholds
                                                                                                                                                           B. Minimum Criteria for Completeness
                                             nonattainment areas, including the                      from 100 tpy to 70 tpy (CAA section
                                                                                                     189(b)(3)).                                           of a SIP Submission
                                             requirements of subpart 4 of part D, title
                                             I of the Act.13                                            3. 2012 PM2.5 NAAQS                                   Section 110(k)(1)(A) of the CAA
                                                The Serious Area plan must include,                     On December 14, 2012, the EPA                      requires that the EPA promulgate
                                             among other things:                                     revised the primary annual PM2.5                      minimum criteria that any plan
                                                1. A comprehensive, accurate, current                standard by lowering it from 15.0 to                  submission must meet before the EPA is
                                             inventory of actual emissions from all                  12.0 mg/m3.15 Effective April 15, 2015,               required to act on such submission. The
                                             sources of PM2.5 and PM2.5 precursors in                the EPA designated and classified the                 EPA has promulgated these criteria at 40
                                                                                                     San Joaquin Valley as a Moderate                      CFR part 51, appendix V. We refer to
                                             the area (CAA section 172(c)(3));
                                                                                                     nonattainment area for the 2012 annual                these requirements as the
                                                2. provisions for the implementation
                                                                                                     PM2.5 NAAQS.16 This designation and                   ‘‘completeness criteria.’’ Section 2.1 of
                                             of BACM, including best available
                                                                                                     classification triggered a requirement for            the completeness criteria requires that
                                             control technology (BACT), for sources
                                                                                                     California to submit a Moderate Area                  each plan submission include, among
                                             of direct PM2.5 and all PM2.5 plan
                                                                                                     plan addressing attainment of the 2012                other things: (1) Evidence that the State
                                             precursors no later than 4 years after the
                                                                                                     annual PM2.5 NAAQS in the San Joaquin                 has adopted the plan in the State code
                                             area is reclassified (CAA section                       Valley no later than 18 months after the
                                             189(b)(1)(B));                                                                                                or body of regulations, including the
                                                                                                     designation, i.e., by October 15, 2016.17             date of adoption or final issuance as
                                             3. a demonstration (including air quality                  The Moderate Area plan must                        well as the effective date of the plan, if
                                             modeling) that the plan provides for                    include, among other things:                          different from the adoption/issuance
                                             attainment as expeditiously as                             1. A comprehensive, accurate, current              date, and (2) evidence that the State
                                             practicable but no later than December                  inventory of actual emissions from all                followed all of the procedural
                                             31, 2019, or where the State is seeking                 sources of PM2.5 and PM2.5 precursors in              requirements of the State’s laws and
                                             an extension of the attainment date                     the area (CAA section 172(c)(3));                     constitution in conducting and
                                             under section 188(e), a demonstration                      2. provisions for the implementation               completing the adoption/issuance of the
                                             that attainment by December 31, 2019,                   of RACM, including reasonably
                                                                                                                                                           plan. Section 2.2 of the completeness
                                             is impracticable and that the plan                      available control technology (RACT), for
                                                                                                                                                           criteria requires that each plan
                                             provides for attainment by the most                     sources of direct PM2.5 and all PM2.5
                                                                                                                                                           submission contain certain technical
                                             expeditious alternative date practicable                plan precursors no later than 4 years
                                                                                                                                                           support, including (1) a demonstration
                                             and no later than December 31, 2024,                    after designation (CAA section
                                                                                                                                                           that the SIP will protect RFP if
                                             (CAA sections 188(c)(2) and                             189(a)(1)(C));
                                                                                                        3. a demonstration (including air                  approved, and (2) modeling to support
                                             189(b)(1)(A)); 14                                                                                             the proposed revision. The
                                                                                                     quality modeling) that the plan provides
                                                4. plan provisions that require RFP                  for attainment as expeditiously as                    completeness criteria also identify other
                                             (CAA 172(c)(2));                                        practicable but no later than December                administrative materials and technical
                                                5. quantitative milestones which are                 31, 2021, or a demonstration that                     support documentation that must be
                                             to be achieved every 3 years until the                  attainment by that date is impracticable              included in each plan submission.18
                                             area is redesignated attainment and                     (CAA section 189(a)(1)(B));                              Section 110(k)(2) of the CAA requires
                                             which demonstrate RFP toward                               4. plan provisions that require RFP                the EPA to act on a SIP submission only
                                             attainment by the applicable date (CAA                  (CAA 172(c)(2));                                      after the State has submitted a SIP
                                             section 189(c));                                           5. quantitative milestones which are               submission (or part thereof) that meets
                                                                                                     to be achieved every 3 years until the                the completeness criteria, either by EPA
                                                6. provisions to assure that control
                                                                                                     area is redesignated attainment and                   determination or by operation of law
                                             requirements applicable to major
                                                                                                     which demonstrate RFP toward                          under CAA section 110(k)(1)(B).
                                             stationary sources of PM2.5 also apply to
                                             major stationary sources of PM2.5                       attainment by the applicable date (CAA                C. California’s SIP Submissions
                                             precursors, except where the state                      section 189(c));
                                                                                                        6. provisions to assure that control                  On November 16, 2018, California
                                             demonstrates to the EPA’s satisfaction                                                                        submitted to the EPA a draft of the
                                             that such sources do not contribute                     requirements applicable to major
                                                                                                     stationary sources of PM2.5 also apply to             ‘‘2018 Plan for the 1997, 2006, and 2012
                                             significantly to PM2.5 levels that exceed                                                                     PM2.5 Standards’’ (‘‘2018 PM2.5 Plan’’), a
                                             the standard in the area (CAA section                   major stationary sources of PM2.5
                                                                                                     precursors, except where the state                    comprehensive plan for attainment of
                                             189(e));                                                                                                      the PM2.5 NAAQS in the San Joaquin
                                                                                                     demonstrates to the EPA’s satisfaction
                                                                                                     that such sources do not contribute                   Valley. This submission includes
                                                12 79 FR 31566 (June 2, 2014), 81 FR 2993
                                                                                                     significantly to PM2.5 levels that exceed             substantial portions of a section 189(d)
                                             (January 20, 2016), and 81 FR 42263 (June 29, 2016)
                                             (correcting amendment).                                 the standard in the area (CAA section                 plan addressing attainment of the 1997
                                                                                                     189(e));                                              PM2.5 NAAQS, a Serious Area plan
khammond on DSK30JT082PROD with RULES




                                                13 Id.
                                                14 A state seeking an extension of a Serious Area
                                                                                                        7. contingency measures to be                      addressing attainment of the 2006 PM2.5
                                             attainment date under section 188(e) must also meet     implemented if the area fails to meet                 NAAQS, and a Moderate Area plan
                                             additional requirements under that provision,                                                                 addressing attainment of the 2012 PM2.5
                                             including the requirement to demonstrate that the
                                             SIP for the area includes the most stringent
                                                                                                       15 78 FR 3086 (January 15, 2013) (codified at 40    NAAQS in the San Joaquin Valley. The
                                             measures that are included in any SIP or are            CFR 50.18).
                                                                                                       16 80 FR 2206 (January 15, 2015).
                                             achieved in practice in any state, and can feasibly                                                             18 See generally 40 CFR part 51, appendix V,

                                             be implemented in the area. CAA section 188(e).           17 CAA section 189(a)(2)(B).                        sections 2.1 and 2.2.



                                        VerDate Sep<11>2014   16:05 Dec 04, 2018   Jkt 247001   PO 00000   Frm 00034   Fmt 4700   Sfmt 4700   E:\FR\FM\06DER1.SGM   06DER1


                                                              Federal Register / Vol. 83, No. 234 / Thursday, December 6, 2018 / Rules and Regulations                                         62723

                                             San Joaquin Valley Air Pollution                        thereof). Sections 179(a) and 110(c) of               IV. Statutory and Executive Order
                                             Control District adopted the 2018 PM2.5                 the CAA establish specific                            Reviews
                                             Plan on November 15, 2018.                              consequences for failure to submit
                                                As a threshold matter, however, the                                                                        A. Executive Order 12866: Regulatory
                                                                                                     complete SIP submissions or SIP                       Planning and Executive Order 13563:
                                             California Air Resources Board (CARB)                   elements required under part D of title
                                             noted in its letter transmitting the SIP                                                                      Improving Regulation and Regulatory
                                                                                                     I of the Act, including the eventual                  Review
                                             submission to the EPA that CARB had                     imposition of mandatory sanctions in
                                             not yet presented the 2018 PM2.5 Plan to                the affected area.                                      This action is not a significant
                                             its Board or adopted it for submission to                                                                     regulatory action and was, therefore, not
                                             the EPA as a revision to the California                    In accordance with the EPA’s                       submitted to the Office of Management
                                             SIP. CARB stated that it was providing                  sanctions sequencing rule in 40 CFR                   and Budget (OMB) for review.
                                             the submission to the EPA now so that                   52.31, the offset sanction identified in
                                                                                                     CAA section 179(b)(2) would apply in                  B. Executive Order 13771: Reducing
                                             EPA staff can begin its review while
                                                                                                     the San Joaquin Valley area 18 months                 Regulation and Controlling Regulatory
                                             CARB completes the final step in plan
                                                                                                     after the effective date of these findings,           Costs
                                             development when it considers
                                             approval of the 2018 PM2.5 Plan at its                  if the EPA has not affirmatively                        This action is not an Executive Order
                                             hearing scheduled for January 24–25,                    determined by that date that the State                13771 regulatory action because this
                                             2019.19                                                 has submitted a complete SIP                          action is not significant under Executive
                                                Accordingly, the EPA cannot at this                  addressing the deficiency that is the                 Order 12866.
                                             time find that California has submitted                 basis for these findings. If, within 6                C. Paperwork Reduction Act (PRA)
                                             the required complete PM2.5 SIP                         months after the offset sanction applies,
                                             revisions for the San Joaquin Valley                    the EPA still has not affirmatively                      This action does not impose an
                                             nonattainment area. CARB’s November                                                                           information collection burden under the
                                                                                                     determined that the State has submitted
                                             16, 2018 SIP submission does not                                                                              provisions of the PRA. This final rule
                                                                                                     a complete SIP addressing the
                                             include evidence that the State has                                                                           does not establish any new information
                                                                                                     deficiency that is the basis for the                  collection requirement apart from what
                                             adopted the plan in the State code or                   findings, the highway funding sanction
                                             body of regulations or evidence that the                                                                      is already required by law. This rule
                                                                                                     identified in CAA section 179(b)(1)                   relates to the requirements in the CAA
                                             State followed all of the procedural
                                                                                                     would also apply in the San Joaquin                   for states to submit SIPs under sections
                                             requirements of the State’s laws and
                                                                                                     Valley. Under 40 CFR 52.31(d)(5),                     172, 188 and 189 which address the
                                             constitution in conducting and
                                                                                                     neither sanction would apply if the EPA               statutory requirements that apply to
                                             completing the adoption/issuance of the
                                             plan, as required by 40 CFR part 51,                    determines within 18 months after the                 areas designated as nonattainment for
                                             appendix V, section 2.1. Based on these                 effective date of these findings that the             the PM2.5 NAAQS.
                                             deficiencies alone, the SIP submission                  State has submitted a complete SIP
                                                                                                     submission addressing the deficiency                  D. Regulatory Flexibility Act (RFA)
                                             fails to meet the EPA’s minimum
                                             completeness criteria. In addition, until               that is the basis for these findings.                   I certify that this rule will not have a
                                             we receive the formal SIP submission,                      Additionally, a finding of failure to              significant economic impact on a
                                             we cannot determine whether the plan                    submit a complete SIP submission                      substantial number of small entities
                                             that CARB ultimately adopts will                                                                              under the RFA. This action will not
                                                                                                     triggers an obligation under CAA
                                             contain all of the necessary components                                                                       impose any requirements on small
                                                                                                     section 110(c) for the EPA to promulgate
                                             of the required PM2.5 attainment plans                                                                        entities. The rule is a finding that
                                                                                                     a FIP no later than 2 years after the                 California has not submitted the
                                             for the San Joaquin Valley and the                      finding, unless the state has submitted,
                                             associated technical support required                                                                         necessary SIP revisions.
                                                                                                     and the EPA has approved, the required
                                             for each submission under 40 CFR part                   SIP submittal. Thus, the EPA would be                 E. Unfunded Mandates Reform Act of
                                             51, appendix V, section 2.2.                            required to promulgate a PM2.5 FIP for                1995 (UMRA)
                                                We note, however, that CARB’s
                                                                                                     the San Joaquin Valley, in relevant part,                This action does not contain any
                                             submission represents a significant step
                                                                                                     if California does not submit and the                 unfunded mandate as described in
                                             in the State’s and District’s multi-year
                                             effort to address the Act’s attainment                  EPA does not approve all of the                       UMRA 2 U.S.C. 1531–1538, and does
                                             planning requirements for the PM2.5                     necessary SIP submissions within 2                    not significantly or uniquely affect small
                                             NAAQS in the San Joaquin Valley, and                    years after the effective date of these               governments. The action imposes no
                                             we commit to continue working closely                   findings.                                             enforceable duty on any state, local or
                                             with both agencies as they implement                                                                          tribal governments or the private sector.
                                                                                                     III. Final Action
                                             and enforce the requirements of these                                                                         F. Executive Order 13132: Federalism
                                             plans going forward.                                       The EPA is finding that California has
                                                                                                                                                             This action does not have federalism
                                                                                                     failed to submit complete SIP revisions
                                             II. Consequences of Findings of Failure                                                                       implications. It will not have substantial
                                             To Submit Complete SIPs                                 for implementation of the 1997, 2006,                 direct effects on the states, on the
                                                                                                     and 2012 PM2.5 NAAQS in the San                       relationship between the national
                                                Under section 110(k)(1)(C) of the Act,               Joaquin Valley as required under
                                             where the EPA determines that a SIP                                                                           government and the states, or on the
                                                                                                     subparts 1 and 4 of part D, title I of the            distribution of power and
                                             submission (or part thereof) does not                   CAA and the PM2.5 SIP Requirements
                                             meet the EPA’s minimum completeness                                                                           responsibilities among the various
khammond on DSK30JT082PROD with RULES




                                                                                                     Rule. The consequences of these                       levels of government.
                                             criteria established in 40 CFR part 51,
                                                                                                     findings are discussed above in section
                                             appendix V, the state shall be treated as                                                                     G. Executive Order 13175: Consultation
                                                                                                     II of this notice.
                                             not having made the submission (or part                                                                       and Coordination With Indian Tribal
                                                                                                                                                           Governments
                                               19 Letter dated November 16, 2018, from Kurt

                                             Karperos, Deputy Executive Officer, CARB, to Mike                                                               This action does not have tribal
                                             Stoker, Regional Administrator, EPA Region IX.                                                                implications as specified in Executive


                                        VerDate Sep<11>2014   16:05 Dec 04, 2018   Jkt 247001   PO 00000   Frm 00035   Fmt 4700   Sfmt 4700   E:\FR\FM\06DER1.SGM   06DER1


                                             62724            Federal Register / Vol. 83, No. 234 / Thursday, December 6, 2018 / Rules and Regulations

                                             Order 13175. This rule finds that                       directly affect the level of protection               ENVIRONMENTAL PROTECTION
                                             California has failed to submit SIP                     provided to human health or the                       AGENCY
                                             revisions that satisfy certain                          environment.
                                             nonattainment area planning                                                                                   40 CFR Part 180
                                             requirements under sections 172, 188                    L. Congressional Review Act (CRA)
                                                                                                                                                           [EPA–HQ–OPP–2017–0372; FRL–9985–83]
                                             and 189 of the CAA for the 1997, 2006,                    The Congressional Review Act, 5
                                             and 2012 PM2.5 NAAQS for the San                        U.S.C. 801 et seq., as added by the Small             Clomazone; Pesticide Tolerances
                                             Joaquin Valley nonattainment area. No
                                                                                                     Business Regulatory Enforcement                       AGENCY:  Environmental Protection
                                             tribe is subject to the requirement to
                                                                                                     Fairness Act of 1996, generally provides              Agency (EPA).
                                             submit an implementation plan under
                                                                                                     that before a rule may take effect, the               ACTION: Final rule.
                                             section 172 or under subpart 4 of part
                                             D of Title I of the CAA. Thus, Executive                agency promulgating the rule must
                                                                                                     submit a rule report, which includes a                SUMMARY:   This regulation establishes
                                             Order 13175 does not apply to this                                                                            tolerances for residues of clomazone in
                                             action.                                                 copy of the rule, to each House of the
                                                                                                     Congress and to the Comptroller General               or on multiple commodities which are
                                             H. Executive Order 13045: Protection of                 of the United States. The EPA will                    identified and discussed later in this
                                             Children From Environmental Health                      submit a report containing this action                document. Interregional Research
                                             and Safety Risks                                        and other required information to the                 Project No. 4 (IR–4) requested these
                                               The EPA interprets Executive Order                                                                          tolerances under the Federal Food,
                                                                                                     U.S. Senate, the U.S. House of
                                             13045 as applying only to those                                                                               Drug, and Cosmetic Act (FFDCA).
                                                                                                     Representatives, and the Comptroller
                                             regulatory actions that concern health or                                                                     DATES: This regulation is effective
                                                                                                     General of the United States prior to
                                             safety risks that the EPA has reason to                                                                       December 6, 2018. Objections and
                                                                                                     publication of the rule in the Federal
                                             believe may disproportionately affect                                                                         requests for hearings must be received
                                                                                                     Register. A major rule cannot take effect
                                             children, per the definition of ‘‘covered                                                                     on or before February 4, 2019, and must
                                                                                                     until 60 days after it is published in the
                                             regulatory action’’ in section 2–202 of                                                                       be filed in accordance with the
                                                                                                     Federal Register. This action is not a                instructions provided in 40 CFR part
                                             the Executive Order. This action is not                 ‘‘major rule’’ as defined by 5 U.S.C.
                                             subject to Executive Order 13045                                                                              178 (see also Unit I.C. of the
                                                                                                     804(2).                                               SUPPLEMENTARY INFORMATION).
                                             because it is a finding that California
                                             has failed to submit certain SIP                        M. Judicial Review                                    ADDRESSES: The docket for this action,
                                             revisions that satisfy the nonattainment                                                                      identified by docket identification (ID)
                                             area planning requirements under                           Under section 307(b)(1) of the Clean               number EPA–HQ–OPP–2017–0372, is
                                             sections 172, 188 and 189 of the CAA                    Air Act, petitions for judicial review of             available at http://www.regulations.gov
                                             for the 1997, 2006, and 2012 PM2.5                      this action must be filed in the United               or at the Office of Pesticide Programs
                                             NAAQS for the San Joaquin Valley                        States Court of Appeals for the                       Regulatory Public Docket (OPP Docket)
                                             nonattainment area and does not                         appropriate circuit by February 4, 2019.              in the Environmental Protection Agency
                                             directly or disproportionately affect                   Filing a petition for reconsideration by              Docket Center (EPA/DC), West William
                                             children.                                               the Administrator of this final rule does             Jefferson Clinton Bldg., Rm. 3334, 1301
                                                                                                     not affect the finality of this action for            Constitution Ave. NW, Washington, DC
                                             I. Executive Order 13211: Actions That                                                                        20460–0001. The Public Reading Room
                                                                                                     the purposes of judicial review nor does
                                             Significantly Affect Energy Supply,                                                                           is open from 8:30 a.m. to 4:30 p.m.,
                                             Distribution or Use                                     it extend the time within which a
                                                                                                     petition for judicial review may be filed,            Monday through Friday, excluding legal
                                                This action is not subject to Executive              and shall not postpone the effectiveness              holidays. The telephone number for the
                                             Order 13211, because it is not a                        of such rule or action. This action may               Public Reading Room is (202) 566–1744,
                                             significant regulatory action under                     not be challenged later in proceedings to             and the telephone number for the OPP
                                             Executive Order 12866.                                                                                        Docket is (703) 305–5805. Please review
                                                                                                     enforce its requirements (see section
                                             J. National Technology Transfer and                                                                           the visitor instructions and additional
                                                                                                     307(b)(2)).
                                             Advancement Act                                                                                               information about the docket available
                                                                                                     List of Subjects in 40 CFR Part 52                    at http://www.epa.gov/dockets.
                                                This rulemaking does not involve                                                                           FOR FURTHER INFORMATION CONTACT:
                                             technical standards.                                      Environmental protection,                           Michael Goodis, Registration Division
                                             K. Executive Order 12898: Federal                       Administrative practice and procedures,               (7505P), Office of Pesticide Programs,
                                             Actions To Address Environmental                        Air pollution control, Approval and                   Environmental Protection Agency, 1200
                                             Justice in Minority Populations and                     promulgation of implementation plans,                 Pennsylvania Ave. NW, Washington, DC
                                             Low-Income Populations                                  Administrative practice and procedures,               20460–0001; main telephone number:
                                                                                                     Incorporation by reference,                           (703) 305–7090; email address:
                                               The EPA believes the human health or                  Intergovernmental relations, Particulate
                                             environmental risk addressed by this                                                                          RDFRNotices@epa.gov.
                                                                                                     matter, and Reporting and                             SUPPLEMENTARY INFORMATION:
                                             action will not have potential
                                                                                                     recordkeeping requirements.
                                             disproportionately high and adverse                                                                           I. General Information
                                             human health or environmental effects                     Dated: November 19, 2018.
                                             on minority, low-income, or indigenous                  Deborah Jordan,                                       A. Does this action apply to me?
                                             populations. In finding that California                 Acting Regional Administrator, Region IX.                You may be potentially affected by
khammond on DSK30JT082PROD with RULES




                                             has failed to submit SIP revisions that                 [FR Doc. 2018–26359 Filed 12–4–18; 8:45 am]           this action if you are an agricultural
                                             satisfy certain nonattainment area                                                                            producer, food manufacturer, or
                                                                                                     BILLING CODE 6560–50–P
                                             planning requirements under sections                                                                          pesticide manufacturer. The following
                                             172, 188 and 189 of the CAA for                                                                               list of North American Industrial
                                             the1997, 2006, and 2012 PM2.5 NAAQS                                                                           Classification System (NAICS) codes is
                                             for the San Joaquin Valley                                                                                    not intended to be exhaustive, but rather
                                             nonattainment area, this action does not                                                                      provides a guide to help readers


                                        VerDate Sep<11>2014   16:05 Dec 04, 2018   Jkt 247001   PO 00000   Frm 00036   Fmt 4700   Sfmt 4700   E:\FR\FM\06DER1.SGM   06DER1



Document Created: 2018-12-05 02:35:50
Document Modified: 2018-12-05 02:35:50
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionRules and Regulations
ActionFinal rule.
DatesThis action will be effective on January 7, 2019.
ContactWienke Tax, EPA Region IX, (415) 947- 4192, [email protected]
FR Citation83 FR 62720 
CFR AssociatedEnvironmental Protection; Administrative Practice and Procedures; Air Pollution Control; Approval and Promulgation of Implementation Plans; Incorporation by Reference; Intergovernmental Relations; Particulate Matter and Reporting and Recordkeeping Requirements

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR