83_FR_63093 83 FR 62859 - Tallassee Shoals, LLC; Notice Approving Use of the Traditional Licensing Process

83 FR 62859 - Tallassee Shoals, LLC; Notice Approving Use of the Traditional Licensing Process

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 234 (December 6, 2018)

Page Range62859-62860
FR Document2018-26456

Federal Register, Volume 83 Issue 234 (Thursday, December 6, 2018)
[Federal Register Volume 83, Number 234 (Thursday, December 6, 2018)]
[Notices]
[Pages 62859-62860]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-26456]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 6951-018]


Tallassee Shoals, LLC; Notice Approving Use of the Traditional 
Licensing Process

    a. Type of Filing: Notice Approving the Use of the Traditional 
Licensing Process.
    b. Project No.: 6951-018.
    c. Date Filed: September 28, 2018.
    d. Submitted By: Tallassee Shoals, LLC.
    e. Name of Project: Tallassee Shoals Project.
    f. Location: On the Middle Oconee River near the city of Athens, in 
Clarke, and Jackson Counties, Georgia. The project does not occupy 
federal lands.
    g. Filed Pursuant to: 18 CFR part 5 of the Commission's 
Regulations.
    h. Applicant Contact: Mr. Walt Puryear, Tallassee Shoals, LLC, 2399 
Tallassee Road, Athens, GA 30607, (706) 540-7621.

[[Page 62860]]

    i. FERC Contact: Michael Spencer at (202) 502-6093 or email at 
[email protected].
    j. In a letter dated November 29, 2018, the Director of the 
Division of Hydropower Licensing approved Tallassee Shoals, LLC's 
request to use the Traditional Licensing Process.
    k. With this notice, we are initiating informal consultation with 
the U.S. Fish and Wildlife Service and/or NOAA Fisheries under section 
7 of the Endangered Species Act and the joint agency regulations 
thereunder at 50 CFR, Part 402; and NOAA Fisheries under section 305(b) 
of the Magnuson-Stevens Fishery Conservation and Management Act and 
implementing regulations at 50 CFR 600.920. We are also initiating 
consultation with the Georgia State Historic Preservation Officer, as 
required by section 106, National Historic Preservation Act, and the 
implementing regulations of the Advisory Council on Historic 
Preservation at 36 CFR 800.2.
    l. Tallassee Shoals LLC filed a Pre-Application Document (PAD; 
including a proposed process plan and schedule) with the Commission, 
pursuant to 18 CFR 5.6 of the Commission's regulations.
    m. A copy of the PAD is available for review at the Commission in 
the Public Reference Room or may be viewed on the Commission's website 
(http://www.ferc.gov), using the ``eLibrary'' link. Enter the docket 
number, excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). A copy is also available for inspection and reproduction at 
the address in paragraph h.
    n. The licensee states its unequivocal intent to submit an 
application for a new license for Project No. 3102. Pursuant to 18 CFR 
16.8, 16.9, and 16.10 each application for a new license and any 
competing license applications must be filed with the Commission at 
least 24 months prior to the expiration of the existing license. All 
applications for license for this project must be filed by September 
30, 2021.
    o. Register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.

    Dated: November 29, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-26456 Filed 12-4-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                                          Federal Register / Vol. 83, No. 234 / Thursday, December 6, 2018 / Notices                                                  62859

                                               eComment system at http://                              For assistance, contact FERC Online                       p. Waiver of deadline to file
                                               www.ferc.gov/docs-filing/                               Support.                                               competing applications filed pursuant
                                               ecomment.asp. You must include your                        n. Anyone may submit comments, a                    to a notice of intent (NOI):
                                               name and contact information at the end                 protest, or a motion to intervene in                      Any qualified applicant desiring to
                                               of your comments. For assistance,                                                                              file a competing application must
                                                                                                       accordance with the requirements of
                                               please contact FERC Online Support at                                                                          submit to the Commission, on or before
                                                                                                       Rules of Practice and Procedure, 18 CFR
                                               FERCOnlineSupport@ferc.gov, (866)                                                                              the specified intervention deadline date,
                                                                                                       385.210, .211, and .214. In determining
                                               208–3676 (toll free), or (202) 502–8659                                                                        a competing development application or
                                                                                                       the appropriate action to take, the
                                               (TTY). In lieu of electronic filing, please                                                                    an NOI to file such an application.
                                                                                                       Commission will consider all protests or
                                               send a paper copy to: Secretary, Federal                                                                       Section 4.36(b)(2) of the Commission’s
                                                                                                       other comments filed, but only those
                                               Energy Regulatory Commission, 888                                                                              regulations, which allows 120 days from
                                                                                                       who file a motion to intervene in
                                               First Street NE, Washington, DC 20426.                                                                         the specified intervention deadline date
                                                                                                       accordance with the Commission’s
                                               The first page of any filing should                                                                            for interested parties to file competing
                                                                                                       Rules may become a party to the
                                               include docket number P–13511–003.                                                                             development applications in which
                                                                                                       proceeding. Any comments, protests, or
                                                  The Commission’s Rules of Practice                                                                          timely NOIs have been submitted, is
                                                                                                       motions to intervene must be received                  hereby waived. Due to the expedited
                                               require all intervenors filing documents                on or before the specified comment date
                                               with the Commission to serve a copy of                                                                         nature of the pilot project licensing
                                                                                                       for the particular application.                        procedures, the submission of a timely
                                               that document on each person on the
                                               official service list for the project.                     All filings must (1) bear in all capital            NOI will instead allow an interested
                                               Further, if an intervenor files comments                letters the title ‘‘PROTEST’’, ‘‘MOTION                person to file the competing
                                               or documents with the Commission                        TO INTERVENE’’, ‘‘COMMENTS,’’                          development application no later than
                                               relating to the merits of an issue that                 ‘‘REPLY COMMENTS,’’                                    30 days after the specified intervention
                                               may affect the responsibilities of a                    ‘‘RECOMMENDATIONS,’’ ‘‘TERMS                           deadline date. Applications for
                                               particular resource agency, they must                   AND CONDITIONS,’’ or ’’ FISHWAY                        preliminary permits will not be
                                               also serve a copy of the document on                    PRESCRIPTIONS;’’ (2) set forth in the                  accepted in response to this notice.
                                               that resource agency.                                   heading the name of the applicant and                     An NOI must specify the exact name,
                                                  k. This application has been accepted                the project number of the application to               business address, and telephone number
                                               for filing and is now ready for                         which the filing responds; (3) furnish                 of the prospective applicant, and must
                                               environmental analysis.                                 the name, address, and telephone                       include an unequivocal statement of
                                                  l. The proposed Igiugig Hydrokinetic                 number of the person protesting or                     intent to submit a development
                                               Project would consist of: (1) An in-                    intervening; and (4) otherwise comply                  application. An NOI must be served on
                                               stream 35-kilowatt (kW), 52-foot-long,                  with the requirements of 18 CFR                        the applicant named in this public
                                               12-foot-high, 47-foot-wide pontoon-                     385.2001 through 385.2005. All                         notice.
                                               mounted RivGen Power System Turbine                     comments, recommendations, terms and                     Dated: November 29, 2018.
                                               Generator Unit (TGU) in Phase 1; (2) an                 conditions or prescriptions must set                   Kimberly D. Bose,
                                               additional in-stream 35-kW pontoon-                     forth their evidentiary basis and                      Secretary.
                                               mounted TGU in Phase 2; (3) two                         otherwise comply with the requirements
                                                                                                                                                              [FR Doc. 2018–26457 Filed 12–4–18; 8:45 am]
                                               anchoring systems each consisting of a                  of 18 CFR 4.34(b). Agencies may obtain
                                                                                                                                                              BILLING CODE 6717–01–P
                                               6,600-pound anchor, chain, shackles,                    copies of the application directly from
                                               and 200 feet of mooring; (4) a 375-foot-                the applicant. A copy of any protest or
                                               long, coated and weighted combined                      motion to intervene must be served                     DEPARTMENT OF ENERGY
                                               power, data, and environmental                          upon each representative of the
                                               monitoring cable from the TGU for                       applicant specified in the particular                  Federal Energy Regulatory
                                               Phase 1; and a 675-foot-long cable from                 application. A copy of all other filings               Commission
                                               the TGU for Phase 2; (5) an existing 10-                in reference to this application must be
                                                                                                       accompanied by proof of service on all                 [Project No. 6951–018]
                                               foot-long by 8-foot-wide shore station
                                               for housing project electronics and                     persons listed in the service list                     Tallassee Shoals, LLC; Notice
                                               controls; and (6) appurtenant facilities.               prepared by the Commission in this                     Approving Use of the Traditional
                                               The project is estimated to have an                     proceeding, in accordance with 18 CFR                  Licensing Process
                                               annual generation of 404,000 megawatt-                  4.34(b) and 385.2010.
                                               hours per year.                                            o. Procedural Schedule:                               a. Type of Filing: Notice Approving
                                                  m. A copy of the application is                                                                             the Use of the Traditional Licensing
                                                                                                          The application will be processed                   Process.
                                               available for review at the Commission                  according to the following Hydro                         b. Project No.: 6951–018.
                                               in the Public Reference Room or may be                  Licensing Schedule. Revisions to the                     c. Date Filed: September 28, 2018.
                                               viewed on the Commission’s website at                   schedule may be made as appropriate.                     d. Submitted By: Tallassee Shoals,
                                               http://www.ferc.gov using the                                                                                  LLC.
                                               ‘‘eLibrary’’ link. Enter the docket                                Milestone                     Target date     e. Name of Project: Tallassee Shoals
                                               number excluding the last three digits in                                                                      Project.
                                               the docket number field to access the                   Filing of recommendations,          December 31,         f. Location: On the Middle Oconee
                                               document. For assistance, contact FERC                     preliminary terms and con-         2018.            River near the city of Athens, in Clarke,
                                               Online Support. A copy is also available                   ditions, and preliminary
khammond on DSK30JT082PROD with NOTICES




                                                                                                                                                              and Jackson Counties, Georgia. The
                                               for inspection and reproduction at the                     fishway prescriptions.                              project does not occupy federal lands.
                                               address in item h above.                                Filing of response comments         January 29,          g. Filed Pursuant to: 18 CFR part 5 of
                                                  Register online at http://                                                                 2019.
                                                                                                                                                              the Commission’s Regulations.
                                               www.ferc.gov/docs-filing/                               Commission issues EA .........      February 27,         h. Applicant Contact: Mr. Walt
                                                                                                                                             2019.
                                               esubscription.asp to be notified via                                                                           Puryear, Tallassee Shoals, LLC, 2399
                                                                                                       Comments on EA or EIS ......        March 29,
                                               email of new filings and issuances                                                            2019.
                                                                                                                                                              Tallassee Road, Athens, GA 30607, (706)
                                               related to this or other pending projects.                                                                     540–7621.


                                          VerDate Sep<11>2014   20:35 Dec 04, 2018   Jkt 247001   PO 00000   Frm 00027   Fmt 4703   Sfmt 4703    E:\FR\FM\06DEN1.SGM   06DEN1


                                               62860                      Federal Register / Vol. 83, No. 234 / Thursday, December 6, 2018 / Notices

                                                  i. FERC Contact: Michael Spencer at                    Dated: November 29, 2018.                           review period if the EPA has not
                                               (202) 502–6093 or email at                              Kimberly D. Bose,                                     objected on its own initiative. Petitions
                                               michael.spencer@ferc.gov.                               Secretary.                                            must be based only on objections to the
                                                  j. In a letter dated November 29, 2018,              [FR Doc. 2018–26456 Filed 12–4–18; 8:45 am]           permit that were raised with reasonable
                                               the Director of the Division of                         BILLING CODE 6717–01–P                                specificity during the public comment
                                               Hydropower Licensing approved                                                                                 period provided by the state, unless the
                                                                                                                                                             petitioner demonstrates that it was
                                               Tallassee Shoals, LLC’s request to use
                                                                                                       ENVIRONMENTAL PROTECTION                              impracticable to raise these issues
                                               the Traditional Licensing Process.
                                                                                                       AGENCY                                                during the comment period or unless
                                                  k. With this notice, we are initiating                                                                     the grounds for the issue arose after this
                                               informal consultation with the U.S. Fish                [FRL–9987–44–Region 10]                               period.
                                               and Wildlife Service and/or NOAA                                                                                 The EPA received the Petition from
                                               Fisheries under section 7 of the                        Clean Air Act Operating Permit                        Bill Green of Richland, Washington,
                                               Endangered Species Act and the joint                    Program; Petition for Objection To                    dated September 1, 2016, requesting
                                               agency regulations thereunder at 50                     State Operating Permit for the U.S.                   that the EPA object to the issuance of
                                               CFR, Part 402; and NOAA Fisheries                       Department of Energy-Hanford                          title V operating permit no. 00–05–006,
                                                                                                       Operations, Benton County,                            Renewal 2, Revision B, issued by
                                               under section 305(b) of the Magnuson-
                                                                                                       Washington                                            Ecology to DOE for the Hanford site in
                                               Stevens Fishery Conservation and
                                               Management Act and implementing                         AGENCY:  Environmental Protection                     Benton County, Washington.
                                               regulations at 50 CFR 600.920. We are                   Agency (EPA).                                            The Petition claims that Ecology did
                                               also initiating consultation with the                   ACTION: Notice of final Order on Petition             not, as required by 40 CFR 70.7(h)(2),
                                               Georgia State Historic Preservation                     for objection to Clean Air Act title V                make available during the public
                                               Officer, as required by section 106,                    operating permit.                                     comment process all of the information
                                               National Historic Preservation Act, and                                                                       that the permitting authority had
                                               the implementing regulations of the                     SUMMARY:   The Environmental Protection               deemed to be relevant by using it in the
                                               Advisory Council on Historic                            Agency (EPA) Administrator signed an                  permitting process.
                                               Preservation at 36 CFR 800.2.                           Order, dated October 15, 2018, granting                  On October 15, 2018, the EPA
                                                                                                       a petition dated September 1, 2016, filed             Administrator issued an Order granting
                                                  l. Tallassee Shoals LLC filed a Pre-                 by Bill Green of Richland, Washington.                the Petition. The Order explains the
                                               Application Document (PAD; including                    The Petition requested that the EPA                   basis for EPA’s decision.
                                               a proposed process plan and schedule)                   object to a Clean Air Act (CAA) title V                  Sections 307(b) and 505(b)(2) of the
                                               with the Commission, pursuant to 18                     operating permit (Permit No. 00–05–                   CAA provide that a petitioner may ask
                                               CFR 5.6 of the Commission’s                             006, Renewal 2, Revision B) issued by                 for judicial review of those portions of
                                               regulations.                                            the Washington State Department of                    an order that deny issues raised in a
                                                  m. A copy of the PAD is available for                Ecology (Ecology) to the U.S.                         petition. Any petition for review shall
                                               review at the Commission in the Public                  Department of Energy-Hanford                          be filed in the United States Court of
                                               Reference Room or may be viewed on                      Operations (DOE) for the Hanford site                 Appeals for the appropriate circuit no
                                               the Commission’s website (http://                       located in Benton County, Washington.                 later than February 4, 2019.
                                               www.ferc.gov), using the ‘‘eLibrary’’                   ADDRESSES: The EPA requests that you                    Dated: November 21, 2018.
                                               link. Enter the docket number,                          contact the individual listed in the FOR              Michelle L. Pirzadeh,
                                               excluding the last three digits in the                  FURTHER INFORMATION CONTACT section to
                                                                                                                                                             Acting Regional Administrator, EPA Region
                                               docket number field to access the                       view copies of the final Order, the                   10.
                                               document. For assistance, contact FERC                  Petition, and other supporting
                                                                                                                                                             [FR Doc. 2018–26482 Filed 12–4–18; 8:45 am]
                                               Online Support at                                       information. You may view hard copies
                                                                                                                                                             BILLING CODE 6560–50–P
                                               FERCONlineSupport@ferc.gov, (866)                       of these documents Monday through
                                               208–3676 (toll free), or (202) 502–8659                 Friday, from 9 a.m. to 3 p.m., excluding
                                               (TTY). A copy is also available for                     federal holidays, at EPA Region 10, 1200
                                                                                                                                                             ENVIRONMENTAL PROTECTION
                                               inspection and reproduction at the                      Sixth Avenue, Seattle, Washington. If
                                                                                                                                                             AGENCY
                                               address in paragraph h.                                 you wish to examine these documents,
                                                                                                       you should make an appointment at                     [FRL–9987–53–OAR]
                                                  n. The licensee states its unequivocal               least 24 hours before the visiting day.
                                               intent to submit an application for a                   Additionally, the final Order and                     Allocations of Cross-State Air
                                               new license for Project No. 3102.                       Petition are available electronically at:             Pollution Rule Allowances From New
                                               Pursuant to 18 CFR 16.8, 16.9, and 16.10                http://www.epa.gov/title-v-operating-                 Unit Set-Asides for 2018 Control
                                               each application for a new license and                  permits/title-v-petition-database.                    Periods
                                               any competing license applications                      FOR FURTHER INFORMATION CONTACT:
                                               must be filed with the Commission at                                                                          AGENCY: Environmental Protection
                                                                                                       Kelly McFadden, EPA Region 10, (206)                  Agency (EPA).
                                               least 24 months prior to the expiration                 553–1679, McFadden.Kelly@epa.gov.
                                               of the existing license. All applications                                                                     ACTION: Notice of data availability
                                                                                                       SUPPLEMENTARY INFORMATION: The CAA                    (NODA).
                                               for license for this project must be filed
                                                                                                       affords the EPA a 45-day period to
                                               by September 30, 2021.
                                                                                                       review and object to, as appropriate, a               SUMMARY:   The Environmental Protection
khammond on DSK30JT082PROD with NOTICES




                                                  o. Register online at http://                        title V operating permit proposed by a                Agency (EPA) is providing notice of the
                                               www.ferc.gov/docs-filing/                               state permitting authority under title V              availability of preliminary lists of units
                                               esubscription.asp to be notified via                    of the CAA. Section 505(b)(2) of the                  eligible for second-round allocations of
                                               email of new filing and issuances                       CAA authorizes any person to petition                 emission allowances for the 2018
                                               related to this or other pending projects.              the EPA Administrator to object to a                  control periods from the new unit set-
                                               For assistance, contact FERC Online                     title V operating permit within 60 days               asides (NUSAs) established under the
                                               Support.                                                after the expiration of the EPA’s 45-day              Cross-State Air Pollution Rule (CSAPR)


                                          VerDate Sep<11>2014   20:35 Dec 04, 2018   Jkt 247001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\06DEN1.SGM   06DEN1



Document Created: 2018-12-05 02:36:17
Document Modified: 2018-12-05 02:36:17
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 62859 