83_FR_805 83 FR 800 - Notice of Intent To Prepare an Environmental Assessment for the Transcontinental Gas Pipe Line Company LLC Proposed Gateway Expansion Project, and Request for Comments on Environmental Issues

83 FR 800 - Notice of Intent To Prepare an Environmental Assessment for the Transcontinental Gas Pipe Line Company LLC Proposed Gateway Expansion Project, and Request for Comments on Environmental Issues

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 5 (January 8, 2018)

Page Range800-801
FR Document2018-00091

Federal Register, Volume 83 Issue 5 (Monday, January 8, 2018)
[Federal Register Volume 83, Number 5 (Monday, January 8, 2018)]
[Notices]
[Pages 800-801]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-00091]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-18-000]


Notice of Intent To Prepare an Environmental Assessment for the 
Transcontinental Gas Pipe Line Company LLC Proposed Gateway Expansion 
Project, and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Gateway Expansion Project 
involving construction and operation of facilities Transcontinental Gas 
Pipe Line Company (Transco) in Essex and Passaic Counties, New Jersey. 
The Commission will use this EA in its decision-making process to 
determine whether the project is in the public convenience and 
necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. You can make a difference by providing us with 
your specific comments or concerns about the project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before February 2, 2018.
    If you sent comments on this project to the Commission before the 
opening of this docket on November 16, 2017, you will need to file 
those comments in Docket No. CP18-18-000 to ensure they are considered 
as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Transco provided landowners with a fact sheet prepared by the FERC 
entitled An Interstate Natural Gas Facility On My Land? What Do I Need 
To Know? This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC website (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or [email protected]. Please carefully follow 
these instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's website (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's website (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
eRegister. If you are filing a comment on a particular project, please 
select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
CP18-18-000 with your submission: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, 
DC 20426.

Summary of the Proposed Project

    Transco proposes to perform the following activities for 
construction of the project.

Compressor Station (CS) 303 (Essex County, New Jersey)

     Expansion of the existing building to include one new 
33,000 horsepower (hp) electric-motor driven compression unit and 
ancillary equipment;
     Install gas cooling equipment;
     Extend existing security fencing to encompass new 
equipment; and
     A new driveway to connect the new gas cooler location with 
CS 303.

Roseland Meter and Regulator (M&R), Essex County, New Jersey

     One new 36-inch ML block valve with automation controls; 
and
     Actuator modification on existing ML block valve.

Paterson M&R, Passaic County, New Jersey

     Remove existing 12-inch headers, meter skid, building, and 
associated equipment;
     Install a meter skid with two 6-inch ultrasonic meters 
with 12-inch inlet and outlet headers;
     Install a new M&R building;
     Install new remote terminal unit (RTU)/gas chromatograph 
building;
     Install new flow computer, radio, and an antenna/pole; and
     Install a new condensate tank.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called eLibrary or from the Commission's Public 
Reference Room, 888 First Street NE, Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb 9.43 acres of 
land, with 9.06 acres being utilized for the CS 303 site and the 
remaining 0.37 acres utilized for the Paterson M&R site. All proposed 
land affected is currently in use as Transco existing property. No new 
land would need to be acquired for operational use.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a

[[Page 801]]

Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ We, us, and our refer to the environmental staff of the 
Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species;
     public safety; and
     cumulative impacts
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. We will 
consider all comments on the EA before making our recommendations to 
the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\3\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice. Currently, no agency has 
expressed intention to participate as a cooperating agency in the 
preparation of the EA.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\4\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the ``Document-less Intervention Guide'' under the ``e-filing'' link on 
the Commission's website. Motions to intervene are more fully described 
at http://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP18-
18). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.

    Dated: January 2, 2018.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2018-00091 Filed 1-5-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                800                            Federal Register / Vol. 83, No. 5 / Monday, January 8, 2018 / Notices

                                                20426, in accordance with Rule 214 of                   notify their constituents of this                      Regulatory Commission, 888 First Street
                                                the Commission’s Rules of Practice and                  proposed project and encourage them to                 NE, Room 1A, Washington, DC 20426.
                                                Procedure, 18 CFR 385.214, within 21                    comment on their areas of concern.
                                                                                                          If you are a landowner receiving this                Summary of the Proposed Project
                                                days of the date of issuance of the order.
                                                                                                        notice, a pipeline company                               Transco proposes to perform the
                                                  Dated: January 2, 2018.
                                                                                                        representative may contact you about                   following activities for construction of
                                                Kimberly D. Bose,
                                                                                                        the acquisition of an easement to                      the project.
                                                Secretary.                                              construct, operate, and maintain the
                                                [FR Doc. 2018–00092 Filed 1–5–18; 8:45 am]                                                                     Compressor Station (CS) 303 (Essex
                                                                                                        proposed facilities. The company would
                                                                                                                                                               County, New Jersey)
                                                BILLING CODE 6717–01–P                                  seek to negotiate a mutually acceptable
                                                                                                        agreement. However, if the Commission                    • Expansion of the existing building
                                                                                                        approves the project, that approval                    to include one new 33,000 horsepower
                                                DEPARTMENT OF ENERGY                                    conveys with it the right of eminent                   (hp) electric-motor driven compression
                                                                                                        domain. Therefore, if easement                         unit and ancillary equipment;
                                                Federal Energy Regulatory                                                                                        • Install gas cooling equipment;
                                                                                                        negotiations fail to produce an
                                                Commission                                              agreement, the pipeline company could                    • Extend existing security fencing to
                                                [Docket No. CP18–18–000]                                initiate condemnation proceedings                      encompass new equipment; and
                                                                                                        where compensation would be                              • A new driveway to connect the new
                                                Notice of Intent To Prepare an                          determined in accordance with state                    gas cooler location with CS 303.
                                                Environmental Assessment for the                        law.                                                   Roseland Meter and Regulator (M&R),
                                                Transcontinental Gas Pipe Line                            Transco provided landowners with a                   Essex County, New Jersey
                                                Company LLC Proposed Gateway                            fact sheet prepared by the FERC entitled
                                                Expansion Project, and Request for                      An Interstate Natural Gas Facility On                    • One new 36-inch ML block valve
                                                Comments on Environmental Issues                        My Land? What Do I Need To Know?                       with automation controls; and
                                                                                                        This fact sheet addresses a number of                    • Actuator modification on existing
                                                   The staff of the Federal Energy                      typically asked questions, including the               ML block valve.
                                                Regulatory Commission (FERC or                          use of eminent domain and how to
                                                Commission) will prepare an                                                                                    Paterson M&R, Passaic County, New
                                                                                                        participate in the Commission’s                        Jersey
                                                environmental assessment (EA) that will                 proceedings. It is also available for
                                                discuss the environmental impacts of                    viewing on the FERC website                              • Remove existing 12-inch headers,
                                                the Gateway Expansion Project                           (www.ferc.gov).                                        meter skid, building, and associated
                                                involving construction and operation of                                                                        equipment;
                                                facilities Transcontinental Gas Pipe Line               Public Participation                                     • Install a meter skid with two 6-inch
                                                Company (Transco) in Essex and Passaic                     For your convenience, there are three               ultrasonic meters with 12-inch inlet and
                                                Counties, New Jersey. The Commission                    methods you can use to submit your                     outlet headers;
                                                will use this EA in its decision-making                 comments to the Commission. The                          • Install a new M&R building;
                                                process to determine whether the                        Commission encourages electronic filing                  • Install new remote terminal unit
                                                project is in the public convenience and                of comments and has expert staff                       (RTU)/gas chromatograph building;
                                                necessity.                                              available to assist you at (202) 502–8258                • Install new flow computer, radio,
                                                   This notice announces the opening of                 or FercOnlineSupport@ferc.gov. Please                  and an antenna/pole; and
                                                the scoping process the Commission                      carefully follow these instructions so                   • Install a new condensate tank.
                                                will use to gather input from the public                that your comments are properly                          The general location of the project
                                                and interested agencies on the project.                 recorded.                                              facilities is shown in appendix 1.1
                                                You can make a difference by providing                     (1) You can file your comments                      Land Requirements for Construction
                                                us with your specific comments or                       electronically using the eComment
                                                concerns about the project. Your                        feature on the Commission’s website                       Construction of the proposed facilities
                                                comments should focus on the potential                  (www.ferc.gov) under the link to                       would disturb 9.43 acres of land, with
                                                environmental effects, reasonable                       Documents and Filings. This is an easy                 9.06 acres being utilized for the CS 303
                                                alternatives, and measures to avoid or                  method for submitting brief, text-only                 site and the remaining 0.37 acres
                                                lessen environmental impacts. Your                      comments on a project;                                 utilized for the Paterson M&R site. All
                                                input will help the Commission staff                       (2) You can file your comments                      proposed land affected is currently in
                                                determine what issues they need to                      electronically by using the eFiling                    use as Transco existing property. No
                                                evaluate in the EA. To ensure that your                 feature on the Commission’s website                    new land would need to be acquired for
                                                comments are timely and properly                        (www.ferc.gov) under the link to                       operational use.
                                                recorded, please send your comments so                  Documents and Filings. With eFiling,                   The EA Process
                                                that the Commission receives them in                    you can provide comments in a variety
                                                Washington, DC on or before February                    of formats by attaching them as a file                   The National Environmental Policy
                                                2, 2018.                                                with your submission. New eFiling                      Act (NEPA) requires the Commission to
                                                   If you sent comments on this project                 users must first create an account by                  take into account the environmental
                                                to the Commission before the opening of                 clicking on eRegister. If you are filing a             impacts that could result from an action
                                                this docket on November 16, 2017, you                   comment on a particular project, please                whenever it considers the issuance of a
                                                will need to file those comments in
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                        select ‘‘Comment on a Filing’’ as the                    1 The appendices referenced in this notice will
                                                Docket No. CP18–18–000 to ensure they                   filing type; or                                        not appear in the Federal Register. Copies of
                                                are considered as part of this                             (3) You can file a paper copy of your               appendices were sent to all those receiving this
                                                proceeding.                                             comments by mailing them to the                        notice in the mail and are available at www.ferc.gov
                                                   This notice is being sent to the                     following address. Be sure to reference                using the link called eLibrary or from the
                                                                                                                                                               Commission’s Public Reference Room, 888 First
                                                Commission’s current environmental                      the project docket number CP18–18–000                  Street NE, Washington, DC 20426, or call (202) 502–
                                                mailing list for this project. State and                with your submission: Kimberly D.                      8371. For instructions on connecting to eLibrary,
                                                local government representatives should                 Bose, Secretary, Federal Energy                        refer to the last page of this notice.



                                           VerDate Sep<11>2014   16:29 Jan 05, 2018   Jkt 244001   PO 00000   Frm 00018   Fmt 4703   Sfmt 4703   E:\FR\FM\08JAN1.SGM   08JAN1


                                                                                Federal Register / Vol. 83, No. 5 / Monday, January 8, 2018 / Notices                                                          801

                                                Certificate of Public Convenience and                   implementing regulations for section                      official party to the Commission’s
                                                Necessity. NEPA also requires us 2 to                   106 of the National Historic                              proceeding. Intervenors play a more
                                                discover and address concerns the                       Preservation Act, we are using this                       formal role in the process and are able
                                                public may have about proposals. This                   notice to initiate consultation with the                  to file briefs, appear at hearings, and be
                                                process is referred to as ‘‘scoping.’’ The              applicable State Historic Preservation                    heard by the courts if they choose to
                                                main goal of the scoping process is to                  Office (SHPO), and to solicit their views                 appeal the Commission’s final ruling.
                                                focus the analysis in the EA on the                     and those of other government agencies,                   An intervenor formally participates in
                                                important environmental issues. By this                 interested Indian tribes, and the public                  the proceeding by filing a request to
                                                notice, the Commission requests public                  on the project’s potential effects on                     intervene. Instructions for becoming an
                                                comments on the scope of the issues to                  historic properties.4 We will define the                  intervenor are in the ‘‘Document-less
                                                address in the EA. We will consider all                 project-specific Area of Potential Effects                Intervention Guide’’ under the ‘‘e-filing’’
                                                filed comments during the preparation                   (APE) in consultation with the SHPO as                    link on the Commission’s website.
                                                of the EA.                                              the project develops. On natural gas                      Motions to intervene are more fully
                                                   In the EA we will discuss impacts that               facility projects, the APE at a minimum                   described at http://www.ferc.gov/
                                                could occur as a result of the                          encompasses all areas subject to ground                   resources/guides/how-to/intervene.asp.
                                                construction and operation of the                       disturbance (examples include
                                                proposed project under these general                    construction right-of-way, contractor/                    Additional Information
                                                headings:                                               pipe storage yards, compressor stations,                     Additional information about the
                                                   • Geology and soils;                                 and access roads). Our EA for this                        project is available from the
                                                   • land use;                                          project will document our findings on                     Commission’s Office of External Affairs,
                                                   • water resources, fisheries, and                    the impacts on historic properties and                    at (866) 208–FERC, or on the FERC
                                                wetlands;                                               summarize the status of consultations                     website at www.ferc.gov using the
                                                   • cultural resources;
                                                                                                        under section 106.                                        ‘‘eLibrary’’ link. Click on the eLibrary
                                                   • vegetation and wildlife;
                                                   • air quality and noise;                                                                                       link, click on ‘‘General Search’’ and
                                                                                                        Environmental Mailing List
                                                   • endangered and threatened species;                                                                           enter the docket number, excluding the
                                                   • public safety; and                                    The environmental mailing list                         last three digits in the Docket Number
                                                   • cumulative impacts                                 includes federal, state, and local                        field (i.e., CP18–18). Be sure you have
                                                   We will also evaluate reasonable                     government representatives and                            selected an appropriate date range. For
                                                alternatives to the proposed project or                 agencies; elected officials;                              assistance, please contact FERC Online
                                                portions of the project, and make                       environmental and public interest                         Support at FercOnlineSupport@ferc.gov
                                                recommendations on how to lessen or                     groups; Native American Tribes; other                     or toll free at (866) 208–3676, or for
                                                avoid impacts on the various resource                   interested parties; and local libraries                   TTY, contact (202) 502–8659. The
                                                areas.                                                  and newspapers. This list also includes                   eLibrary link also provides access to the
                                                   The EA will present our independent                  all affected landowners (as defined in                    texts of formal documents issued by the
                                                analysis of the issues. The EA will be                  the Commission’s regulations) who are                     Commission, such as orders, notices,
                                                available in the public record through                  potential right-of-way grantors, whose                    and rulemakings.
                                                eLibrary. We will consider all comments                 property may be used temporarily for                         In addition, the Commission offers a
                                                on the EA before making our                             project purposes, or who own homes                        free service called eSubscription which
                                                recommendations to the Commission.                      within certain distances of aboveground                   allows you to keep track of all formal
                                                To ensure we have the opportunity to                    facilities, and anyone who submits                        issuances and submittals in specific
                                                consider and address your comments,                     comments on the project. We will                          dockets. This can reduce the amount of
                                                please carefully follow the instructions                update the environmental mailing list as                  time you spend researching proceedings
                                                in the Public Participation section,                    the analysis proceeds to ensure that we                   by automatically providing you with
                                                beginning on page 2.                                    send the information related to this                      notification of these filings, document
                                                   With this notice, we are asking                      environmental review to all individuals,                  summaries, and direct links to the
                                                agencies with jurisdiction by law and/                  organizations, and government entities                    documents. Go to www.ferc.gov/docs-
                                                or special expertise with respect to the                interested in and/or potentially affected                 filing/esubscription.asp.
                                                environmental issues of this project to                 by the proposed project.
                                                formally cooperate with us in the                                                                                   Dated: January 2, 2018.
                                                                                                           If we publish and distribute the EA,
                                                preparation of the EA.3 Agencies that                   copies will be sent to the environmental                  Kimberly D. Bose,
                                                would like to request cooperating                       mailing list for public review and                        Secretary.
                                                agency status should follow the                         comment. If you would prefer to receive                   [FR Doc. 2018–00091 Filed 1–5–18; 8:45 am]
                                                instructions for filing comments                        a paper copy of the document instead of                   BILLING CODE 6717–01–P
                                                provided under the Public Participation                 the CD version or would like to remove
                                                section of this notice. Currently, no                   your name from the mailing list, please
                                                agency has expressed intention to                       return the attached Information Request                   DEPARTMENT OF ENERGY
                                                participate as a cooperating agency in                  (appendix 2).
                                                the preparation of the EA.                                                                                        Federal Energy Regulatory
                                                                                                        Becoming an Intervenor                                    Commission
                                                Consultations Under Section 106 of the
                                                                                                          In addition to involvement in the EA                    [Docket No. CP18–33–000]
                                                National Historic Preservation Act
                                                                                                        scoping process, you may want to
sradovich on DSK3GMQ082PROD with NOTICES




                                                  In accordance with the Advisory                       become an ‘‘intervenor’’ which is an                      Notice of Application; Florida Gas
                                                Council on Historic Preservation’s                                                                                Transmission Company, LLC
                                                                                                          4 The Advisory Council on Historic Preservation’s
                                                  2 We, us, and our refer to the environmental staff    regulations are at Title 36, Code of Federal                Take notice that on December 18,
                                                of the Commission’s Office of Energy Projects.          Regulations, Part 800. Those regulations define           2017, Florida Gas Transmission
                                                  3 The Council on Environmental Quality                historic properties as any prehistoric or historic
                                                regulations addressing cooperating agency               district, site, building, structure, or object included
                                                                                                                                                                  Company, LLC (Florida Gas), 1300 Main
                                                responsibilities are at Title 40, Code of Federal       in or eligible for inclusion in the National Register     Street, Houston, Texas 77002, filed in
                                                Regulations, Part 1501.6.                               of Historic Places.                                       Docket No. CP18–33–000 an application


                                           VerDate Sep<11>2014   16:29 Jan 05, 2018   Jkt 244001   PO 00000   Frm 00019   Fmt 4703   Sfmt 4703   E:\FR\FM\08JAN1.SGM     08JAN1



Document Created: 2018-01-06 02:32:04
Document Modified: 2018-01-06 02:32:04
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 800 

2025 Federal Register | Disclaimer | Privacy Policy