The Secretary of the Interior (Secretary), through the Division of Energy and Mineral Development (DEMD), Office of Indian Energy and Economic Development (IEED), is soliciting ...

Department of the Interior
Bureau of Indian Affairs
  1. [201D0102DR/DS5A300000/DR.5A311.IA000118]

AGENCY:

Bureau of Indian Affairs, Interior.

ACTION:

Notice.

SUMMARY:

The Secretary of the Interior (Secretary), through the Division of Energy and Mineral Development (DEMD), Office of Indian Energy and Economic Development (IEED), is soliciting grant proposals from federally recognized Indian Tribes to build Tribal capacity for energy resource regulation and management under the Tribal Energy Development Capacity (TEDC) grant program.

DATES:

Applications will be accepted until 11:59 p.m. EST on September 1, 2020.

ADDRESSES:

Email applications to in accordance with the directions at Step 4 of this notice.

( printed page 34222)

FOR FURTHER INFORMATION CONTACT:

Mr. Payton Batliner, Economic Development Specialist, Division of Energy and Mineral Development, 13922 Denver West Pkwy., Suite 200, Lakewood, CO 80401; telephone: (720) 999-1414; email: .

SUPPLEMENTARY INFORMATION:

I. General Information

II. Number of Projects Funded

III. Background

IV. Eligibility for Funding

V. Who May Perform Feasibility Studies Funded by TEDC Grants

VI. Applicant Procurement Procedures

VII. Limitations

VIII. TEDC Application Guidance

IX. Review and Selection Process

X. Evaluation Criteria

XI. Transfer of Funds

XII. Reporting Requirements for Award Recipients

XIII. Conflicts of Interest

XIV. Questions and Requests for IEED Assistance

XV. Separate Document(s)

XVI. Paperwork Reduction Act

XVII. Authority

I. General Information

Award Ceiling: 1,000,000.

Award Floor: 10,000.

CFDA Number: 15.148.

Cost Sharing or Matching Requirement: No.

Number of Awards: 15.

Category: Energy and Minerals.

II. Number of Projects Funded

DEMD anticipates award of approximately fifteen (15) grants under this announcement ranging in value from approximately $10,000 to $1,000,000. The program can fund projects only one year at a time. DEMD will use a competitive evaluation process based on criteria described in section X of this notice.

III. Background

DEMD administers the TEDC grant program. This solicitation seeks proposals for increasing the technical capacity of federally recognized Tribes to manage and regulate their energy resources. The energy project(s) for which the applicant seeks to build Tribal capacity can be existing or planned, Tribally owned or privately owned.

Capacity developing activities include, but are not limited to:

The funding periods and amounts referenced in this solicitation are subject to the availability of funds at the time of award, as well as the Department of the Interior (DOI) and Indian Affairs priorities at the time of the award. Neither DOI nor Indian Affairs will be held responsible for proposal or application preparation costs. Publication of this solicitation does not obligate DOI or Indian Affairs to award any specific grant or to obligate all or any part of available funds. Future funding is subject to the availability of appropriations and cannot be guaranteed. DOI or Indian Affairs may cancel or withdraw this solicitation at any time.

IV. Eligibility for Funding

Only Indian Tribes, as defined at 25 U.S.C. 5304(e), are eligible to receive TEDC grants. Under that statutory definition, eligible entities include any Indian Tribe, band, nation, or other organized group or community, including any Alaska Native village or regional or village corporation as defined in or established pursuant to the Alaska Native Claims Settlement Act, 43 U.S.C. 1601 et seq., which is recognized as eligible for the special programs and services provided by the United States to Indians because of their status as Indians. Indian Tribes are referred to using the term “Tribe” throughout this notice.

V. Who May Perform Studies Funded by TEDC Grants

The applicant determines who will conduct its study. An applicant has several choices, including but not limited to:

VI. Applicant Procurement Procedures

The applicant is subject to the procurement standards in 2 CFR 200.318 through 200.326. In accordance with 2 CFR 200.318, an applicant must use its own documented procurement procedures which reflect Tribal laws and regulations, provided that the procurements conform to applicable Federal law and standards identified in Part 2 of the Code of Federal Regulations.

VII. Limitations

TEDC grant funding must be expended in accordance with applicable statutory and regulatory requirements, including 2 CFR part 200. As part of the grant application review process, DEMD may conduct a review of an applicant's prior DEMD grant award(s).

Applicants that are currently under BIA sanction Level 2 or higher resulting from non-compliance with the Single Audit Act are ineligible for a TEDC award. Applicants at Sanction Level 1 will be considered for funding.

DEMD will not usually consider funding new TEDC proposals where the applicant has open TEDC projects, granted under any previous funding cycle. The DEMD does, however, understand that delays beyond the control of the applicant sometimes occur. The DEMD will consider any explanation provided in conjunction with the new TEDC grant proposal. The explanation should describe the reasons why the previous project is delayed and successfully justify or demonstrate that the delay is at no fault of the applicant.

DEMD will accept multi-project proposals. Multi-project proposals must be submitted as one application. Multi-project proposals may contain proposals to develop and enhance both business and regulatory infrastructure. Applicants may also submit multi-project proposals in just one area, such as two separate purposes, with each proposing to develop or enhance the regulatory structure for two separate purposes. For instance, an applicant may submit a proposal for funding to form a Tribal utility authority and a separate and distinct proposal to develop a Tribal secured transactions code.

Each project in the application requires its own stand-alone proposal, budget, and designated Tribal project lead. Multi-project proposals require that the applicant submit a Tribal resolution that identifies and describes each project being proposed authorizing the Tribe to submit the proposal for a TEDC grant. Each proposal in the application will be evaluated based on ( printed page 34223) its own merits as a stand-alone project. The DEMD will evaluate each individual project proposal using the same standards as those evaluated as a single-project proposal.

The purpose of TEDC grants is to increase Tribal technical capacity to manage and regulate energy resources only. TEDC awards may not be used for:

VIII. TEDC Application Guidance

All TEDC applicants must use the standard forms Application for Federal Assistance SF-424 and the Project Narrative Attachment Form. These forms can be found at www.grants.gov. A complete proposal must contain the five mandatory components as described below.

Step 1. Complete the Application for Federal Assistance SF-424

Instructions to Download the Application for Federal Assistance SF-424

1. Go to www.grants.gov.

2. Select the “forms” tab. This will open a page with a table titled “SF-424 FAMILY FORMS.”

3. Under the column “Agency Owner,” third row down, is listed, Grants.gov —Application for Federal Assistance SF-424.

4. Click on the blue PDF letters to download the three-page document.

Application for Federal Assistance SF-424 (Mandatory Component 1)

Within the Application for Federal Assistance SF-424, please complete the following sections:

Save the Application for Federal Assistance SF-424 and name the file using the following format: Tribal Name TEDC Grant Application SF-424.

Example for naming the SF-424 Application for Federal Assistance file: Pueblo of Laguna TEDC Grant Application SF-424.

Step 2. Prepare the Project Narrative, Budget, Critical Information Documents, and Obtain a Tribal Resolution

Project Narrative (Mandatory Component 2)

The Project Narrative must not exceed 20 pages. At a minimum, it should include:

a. An Executive Summary that is an overview and technical summary of the project, no longer than one page, that has a description of the elements of the proposed project, reasons for the project, description of the objectives and anticipated outcomes that will result if the project were to be funded, total funding amount requested, and a designated Tribal project lead authorized to make decisions on the day-to-day grant activities.

b. The Project Objective, Technical Description, and Scope of Work. Describe the Tribe's current business and/or regulatory capacity for energy development, including regulations and other measures already in place and the extent to which they are being implemented. If the proposal is related to establishing organizational business entity structures, describe the extent to which the Tribe is capable of engaging in development or management activities, and to what extent the proposed project will increase the Tribe's capacity to manage and/or regulate its energy resources. Describe which business and/or regulatory capacities need enhancement, such as: Tribal code development, regulation or ordinance development, commercial code development, financial and revenue management, land lease management (including evaluation, negotiation, and enforcement of terms), and regulatory monitoring (Federal, State, and Tribal environmental and safety regulations). Describe how the project would assist the Tribe in developing the capacity needed to maximize the economic impact of energy or mineral resource development on Indian land, and to what extent that would affect the overall economy of the Tribe. List all previous or ongoing energy or mineral resource development capacity-building projects involving the Tribe. Describe the Tribe's motivation to implement the business or regulatory framework that would be developed or enhanced through TEDC funding. Describe project goals and objectives. Include a detailed scope of work describing the project phases and timeline, method of measurement of meeting objectives of the proposed project, and expected outcomes. Describe how and why the particular ( printed page 34224) methods being applied will achieve the stated goals.

c. If the project is focused on studying the feasibility of a Tribal Utility Authority (TUA), or some other electric utility structure including micro grids, please provide a brief discussion (one page or less) that includes the following: Reason/need for chartering a TUA or micro grid formation, the relationship between the Tribe and incumbent utility, annual expenditure by the Tribe on electricity, electricity pricing ($/kWh) and/or power quality issues, utility policy issues that are hindering the Tribe from proper management of its energy assets or hindering the development of energy projects ( i.e. net metering policies) and how these can potentially be overcome by a tribally owned TUA, and any other relevant information that would highlight the need for the establishment of a TUA or micro grid.

d. Describe all deliverable products that the proposed TEDC project is to generate, including all regulations, codes, ordinances or processes and procedures. Discuss the content of any planned status reports as well as the final TEDC project report.

e. Provide the resumes (with areas of expertise) of key consultants and personnel to be retained, if available, and the nature of their involvement, including their relationship to the applicant as Tribal staff, consultant, subcontractor, etc. This information may be included as an attachment to the application and will not be counted towards the 20-page limitation.

Budget SF424a and Budget Narrative (Mandatory Component 3)

Please complete the SF424a and provide a budget narrative that clearly describes all major line item grant expenditures. High ranking budgets will provide a budget narrative that correlates to the project scope of work and clearly breaks the project down into defined tasks with an associated budget line item for each task. Tasks and costs should include justification in the budget narrative.

Critical Information Page (Mandatory Component 4)

Applicants must include a critical information page that includes:

Tribal Resolution Attachment (Mandatory Component 5)

Applicants must include as an attachment to their application a Tribal resolution authorizing the submission of a FY 2020 TEDC grant application. It must be signed by authorized Tribal representative(s). The Tribal resolution must also include:

Tribal Energy Development Organization applicants are required to have a Tribal resolution authorizing the Tribe participating in the organization to apply for this grant.

Step 3. Prepare the Project Narrative Attachment Form for Submission

Note: Mandatory components 2-5 must be submitted using the Project Narrative Attachment Form.

Instructions To download the Project Narrative Attachment Form:

When the applicant has successfully downloaded the Project Narrative Attachment Form, follow the next steps to upload documents:

When the applicant has completed uploading the Project Narrative and the attachments (Budget, Tribal Resolution, and Critical Information Page) to the Project Narrative Attachment Form, the applicant will save and name the file using the following format: Tribal Name TEDC Grant Attachments.

Example for naming the Project Narrative Attachment Form file: Pueblo of Laguna TEDC Grant Attachments.

Step 4. Submit the Completed TEDC Grant Proposal

Applicants must submit the Application for Federal Assistance SF-424 form and the Project Narrative Attachment Form in a single email to the email listed in the ADDRESSES section of this notice and:

Applications and mandatory attachments received and date stamped after the time listed in the DATES section of this notice will not be considered by the Awarding Official. DEMD will accept applications at any time before the deadline and will send a notification of receipt to the return email address on the application package, along with a determination of whether the application is complete.

Incomplete Applications. Applications submitted without one or more of the five mandatory components described above will be returned to the applicant with an explanation. The applicant will then be allowed to correct any deficiencies and resubmit the proposal for consideration on or before the deadline. This option will not be available to an applicant once the deadline has passed.

IX. Review and Selection Process

Upon receiving a TEDC application, DEMD will determine whether the application is complete and that the proposed project does not duplicate or overlap previous or currently funded DEMD technical assistance projects. Any proposal that is received after the date and time in the DATES section of this notice will not be reviewed. If an application is not complete and the submission deadline has not passed, the applicant will be notified and given an opportunity to resubmit its application.

The DEMD Review Committee (Committee), comprised of DEMD staff, staff from other Federal agencies, and subject matter experts, will evaluate the proposals against the ranking criteria. Proposals will be evaluated using the four criteria listed below, with a ( printed page 34225) maximum achievable total of 100 points.

Final award selections will be approved by the Assistant Secretary—Indian Affairs and the Associate Deputy Secretary, U.S. Department of the Interior. Applicants not selected for award will be notified in writing.

X. Evaluation Criteria

Executive Summary: 10 points. Proposals will be evaluated based on the clarity of the proposal's Executive Summary as discussed in Step 2, part A.

Project Objective, Technical Description, and Scope of Work: 35 points. This criterion will be evaluated based on the project objective, technical description and scope of work as described in Step 2, part B. The clarity of the described work and the appropriateness of the project in terms of meeting the intent and goals of the TEDC program will be evaluated.

Deliverable Products: 30 points. DEMD will rate the extent to which the expected outcome of the project meets the applicant's stated goals, based on the deliverables described. This section will be evaluated based on Step 2, part C.

Key Personnel: 25 points. The Committee understands that applicants may intend that the consultant(s) they retain to prepare the grant proposal will also conduct the feasibility study if the grant is awarded. This does not prejudice an applicant's chances of being selected as a grantee. However, the Committee will view unfavorably proposals that show little evidence of communication between the consultant(s) and the applicant or scant regard for the applicant community's unique circumstances. Facsimile applications prepared by the same consultant(s) and submitted by multiple applicants will receive particular scrutiny in this regard. DEMD will also evaluate the extent to which key personnel have the expertise to perform the functions under the scope of work, and produce quality deliverables. See Step 2, part D for more information.

XI. Transfer of Funds

DEMD's obligation under this solicitation is contingent on receipt of congressionally appropriated funds. No liability on the part of the U.S. Government for any payment may arise until funds are made available to the awarding officer for this grant and until the recipient receives notice of such availability, to be confirmed in writing by the grant officer.

All payments under this agreement will be made by electronic funds transfer through the ASAP. All award recipients are required to have a current and accurate DUNS number to receive funds. All payments will be deposited to the banking information designated by the applicant in the System for Award Management (SAM).

XII. Reporting Requirements for Award Recipients

The applicant must deliver all products and data required by the signed Grant Agreement for the proposed TEDC feasibility study project to DEMD within 30 days of the end of each quarter and 90 days after completion of the project.

DEMD requires that deliverable products be provided in both digital format and printed hard copies. Reports can be provided in either Microsoft Word or Adobe Acrobat PDF format. Spreadsheet data can be provided in Microsoft Excel, Microsoft Access, or Adobe PDF formats. All vector figures should be converted to PDF format. Raster images can be provided in PDF, JPEG, TIFF, or any of the Windows metafile formats. The contract between the grantee and the consultant conducting the TEDC-funded feasibility study must include deliverable products and require that the products be prepared in the format described above.

The contract should include budget amounts for all printed and digital copies to be delivered in accordance with the grant agreement. In addition, the contract must specify that all products generated by a consultant belong to the grantee and cannot be released to the public without the grantee's written approval. Products include, but are not limited to, all reports and technical data obtained, maps, status reports, and the final report.

In addition, this funding opportunity and financial assistance award must adhere to the following provisions:

XIII. Conflicts of Interest

Applicability

Requirements

Notification

Data Availability

o The scientific data relied upon;

o The analysis relied upon; and

o The methodology, including models, used to gather and analyze data.

XIV. Questions and Requests for DEMD Assistance

DEMD staff may provide technical consultation, upon written request by an applicant. The request must clearly identify the type of assistance sought. Technical consultation does not include funding to prepare a grant proposal, grant writing assistance, or pre-determinations as to the likelihood that a proposal will be awarded. The applicant is solely responsible for preparing its grant proposal. Technical consultation may include clarifying application requirements, confirming whether an applicant previously submitted the same or similar proposal, and registration information for SAM or ASAP.

XV. Separate Document(s)

XVI. Paperwork Reduction Act

The information collection requirements contained in this notice have been reviewed and approved by the Office of Management and Budget (OMB) under the Paperwork Reduction Act, 44 U.S.C. 3504(h). The OMB control number is 1076-0177. The authorization expires on October 31, 2020. An agency may not conduct or sponsor, and you are not required to respond to, any information collection that does not display a currently valid OMB Control Number.

XVII. Authority

TEDC grants are funded through non-recurring appropriations made by the United States Congress in the Federal budget. These funds are provided on a year-to-year basis, and may or may not be provided in future years. DEMD implements the Indian Energy Resource Development Program, under the Energy Policy Act of 2005, (503(a), Aug. 8, 2005, 119 Stat. 764) to assist Indian Tribes in the development of energy resources and to further the goal of Indian self-determination. The Energy Policy Act of 2005 (25 U.S.C. 3501 et seq.) requires the Secretary to:

“establish and implement an Indian energy resource development program to assist consenting Indian Tribes and Tribal energy resource development organizations.”

It also requires the Secretary to provide development grants to Indian Tribes and Tribal energy resource development organizations for use in developing or obtaining the managerial and technical capacity needed to develop energy resources on Indian land, and to properly account for resulting energy production and revenues; and to:

“provide grants to Indian Tribes and Tribal energy resource development organizations for the use in carrying out projects to promote the integration of energy resources, and to process, use, or develop those energy resources on Indian land . . .”

Additional authorizing Statutes for the program include:

Tara Sweeney,

Assistant Secretary—Indian Affairs.

[FR Doc. 2020-11975 Filed 6-2-20; 8:45 am]

BILLING CODE 4337-15-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

85 FR 34221

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Tribal Energy Development Capacity (TEDC) Grant; Solicitation of Proposals,” thefederalregister.org (June 3, 2020), https://thefederalregister.org/documents/2020-11975/tribal-energy-development-capacity-tedc-grant-solicitation-of-proposals.