Document

Green Mountain Power Corporation; Notice of Waiver Period for Water Quality Certification Application

Department of Energy Federal Energy Regulatory Commission [Project No. 5261-023] On June 6, 2022, Green Mountain Power Corporation submitted to the Federal Energy Regulatory Com...

Department of Energy
Federal Energy Regulatory Commission
  1. [Project No. 5261-023]

On June 6, 2022, Green Mountain Power Corporation submitted to the Federal Energy Regulatory Commission (Commission) a copy of its application for a Clean Water Act section 401(a)(1) water quality certification filed with Vermont Department of Environmental Conservation (Vermont DEC), in conjunction with the above captioned project. Pursuant to 40 CFR 121.6 and section [4.34(b)(5), 5.23(b), 153.4, or 157.22] of the Commission's regulations,[1] we hereby notify the Vermont DEC of the following:

Date of Receipt of the Certification Request: June 3, 2022.

Reasonable Period of Time To Act on the Certification Request: June 3, 2023.

If Vermont DEC fails or refuses to act on the water quality certification request on or before the above date, then the agency certifying authority is deemed waived pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1).

Dated: June 14, 2022.

Kimberly D. Bose,

Secretary.

Footnotes

1.  18 CFR [4.34(b)(5)/5.23(b)/153.4/157.22].

Back to Citation

[FR Doc. 2022-13283 Filed 6-21-22; 8:45 am]

BILLING CODE 6717-01-P

Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

87 FR 37330

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“Green Mountain Power Corporation; Notice of Waiver Period for Water Quality Certification Application,” thefederalregister.org (June 22, 2022), https://thefederalregister.org/documents/2022-13283/green-mountain-power-corporation-notice-of-waiver-period-for-water-quality-certification-application.