Department of Energy
Federal Energy Regulatory Commission
- [Project No. 5596-020]
On April 30, 2021, the Town of Bedford, Virginia filed an application for a new major license for the 5.0-megawatt Bedford Hydroelectric Project No. 5596 (Bedford Project or project). On August 17, 2023, Commission staff issued a notice of intent to prepare an Environmental Assessment (EA) to evaluate the effects of relicensing the Bedford Project. The notice of intent included a schedule for preparing a single EA.
By this notice, Commission staff is updating the procedural schedule for completing the EA. The revised schedule is shown below. Further revisions to the schedule may be made as appropriate.
| Milestone | Target date |
|---|---|
| Issue EA | July 2024.1 |
Any questions regarding this notice may be directed to Andy Bernick at (202) 502-8660 or andrew.bernick@ferc.gov.
Dated: April 11, 2024.
Debbie-Anne A. Reese,
Acting Secretary.