Department of Energy
Federal Energy Regulatory Commission
- [Project No. 9821-109]
Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.
a. Type of Application: New License.
b. Project No.: 9821-109.
c. Date Filed: May 30, 2025.
d. Applicant: Ampersand Ogdensburg Hydro, LLC (Ampersand).
e. Name of Project: Ogdensburg Hydroelectric Project.
f. Location: On the Oswegatchie River in the city of Ogdensburg, St. Lawrence County, New York.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Jason Huang, Director, 717 Atlantic Avenue, Suite 1A, Boston, MA 02111; telephone at (617) 933-7200; email at jasonh@ampersandenergy.com.
i. FERC Contact: Joshua Dub, Project Coordinator, Great Lakes Branch, Division of Hydropower Licensing; telephone at (202) 502-8138; email at Joshua.Dub@ferc.gov.
j. Deadline for filing motions to intervene and protests: December 4, 2026 by 5:00 p.m. Eastern Daylight Time.
The Commission strongly encourages electronic filing. Please file motions to intervene and protests using the Commission's eFiling system at ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit brief comments up to 10,000 characters, without prior registration, using the eComment system at ferconline.ferc.gov/QuickComment.aspx. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Debbie Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. All filings must clearly identify the project name and docket number on the first ( printed page 64367) page: Ogdensburg Hydroelectric Project (P-9821-109).
The Commission's Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.
k. This application has been accepted for filing but is not ready for environmental analysis at this time.
l. Project Description: The project consists of a 504.5-foot-long, 12-foot-high concrete dam that includes: (1) a 130-foot-long, 76-foot-wide powerhouse that includes: (a) an intake structure with five stoplog gates and trashracks with 1-inch clear bar spacing; and (b) five 596-kilowatt (kW) horizontal Kaplan turbine-generator units (Units 1 to 5), for a total installed capacity of 2,980 kW; (2) a 38.5-foot-long non-overflow section with three 9-foot-long sluice gates; (3) a 330-foot-long ogee spillway with a crest elevation of 258.0 feet above the National Geodetic Vertical Datum of 1929 (NGVD 29); and (4) a 6-foot-long east abutment. The dam creates an impoundment that has a surface area of 290 acres at a normal maximum surface elevation of 258 feet NGVD 29.
Water from the impoundment flows to Units 1 through 4, and then to a 235-foot-long tailrace that empties into the Oswegatchie River immediately downstream of the dam. Water also flows from the impoundment to Unit 5, and then to a 75-foot-long tailrace that empties into the Oswegatchie River approximately 620 feet downstream of the dam.
Electricity generated at the powerhouse is transmitted to the electric grid via 150-foot-long, 4.16-kilovolt (kV) generator lead lines, a 4.16/13.2-kV step-up transformer, and a 75-foot-long, 13.2-kV transmission line.
Project recreation facilities include a trailer boat access site and parking area on the east shore of the impoundment approximately 750-feet-upstream of the dam and a park on the east bank of the tailrace approximately 135-feet-downstream of the dam.
Ampersand proposes to continue operating the project in a run-of-river mode, and discharge up to 730 cfs through Unit 5, when Unit 5 is operating; or discharge 730 cfs or inflow, whichever is less, over the spillway when Unit 5 is not operating.
m. A copy of the application can be viewed on the Commission's website at www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at 19 Mill Street, Ogdensburg, NY 13669.
You may also register online at ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.
n. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, contact the Office of Public Participation at (202) 502-6595 or OPP@ferc.gov.
o. Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application.
All filings must (1) bear in all capital letters the title “PROTEST” or “MOTION TO INTERVENE;” (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application.
p. Procedural Schedule: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate.
| Milestone | Target date |
|---|---|
| Issue Scoping Notice | October 2026. |
| Scoping Comments Due | November 2026. |
| Filing of Motions to Intervene and Protests | December 2026. |
| Issue Notice of Ready for Environmental Analysis | January 2027. |
| Filing of Comments, Recommendations, Terms, Conditions, and Prescriptions | March 2027. |
| Filing of Reply Comments | April 2027. |
(Authority: 18 CFR 2.1)
Dated: October 5, 2026.
Debbie-Anne A. Reese,