DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
[Docket No. CP99-118-000]


NorAm Gas Transmission Company; Notice of Request Under Blanket 
Authorization

December 23, 1998.
    Take notice that on December 16, 1998, NorAm Gas Transmission 
Company (NGT), 1111 Louisiana, Houston, Texas 77002-5231, filed in 
Docket No. CP99-118-000 a request pursuant to Sections 157.205 and 
157.211 of the Commission's Regulations under the Natural Gas Act (18 
CFR 157.205 and 157.211) for authorization to construct and operate 
certain facilities in Louisiana under NGT's blanket certificate issued 
in Docket No. CP82-384-000 and CP82-384-001 pursuant to Section 7 of 
the Natural Gas Act, all as more fully set forth in the request that is 
on file with the Commission and open to public inspection.
    NGT specifically proposes to construct and operate a 1-inch 
delivery tap and first-cut regulator to serve ARKLA, a division of 
NorAm Energy Corp. (ARKLA). The proposed tap to be installed on NGT's 
Line R-1-N will be located in Desoto Parish, Louisiana. The total 
estimated volume is 65 Dth annually and 0.5 Dth on a peak day. The tap 
and first cut regulator will be constructed at an estimated cost of 
$2,212 and ARKLA will reimburse NGT $1,751 of the construction costs.
    Any person or the Commission's staff may, within 45 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to Section 157.205 of 
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
the request. If no protest is filed within the time allowed therefor, 
the proposed activity shall be deemed to be authorized effective the 
day after the time allowed for filing a protest. If a protest is filed 
and not withdrawn within 30 days after the time allowed for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to Section 7 of the Natural Gas Act.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 98-34611 Filed 12-30-98; 8:45 am]
BILLING CODE 6717-01-M


Legal Citation

Federal Register Citation

Use this for formal legal and research references to the published document.

63 FR 72297

Web Citation

Suggested Web Citation

Use this when citing the archival web version of the document.

“NorAm Gas Transmission Company; Notice of Request Under Blanket Authorization,” thefederalregister.org (December 31, 1998), https://thefederalregister.org/documents/98-34611/noram-gas-transmission-company-notice-of-request-under-blanket-authorization.