80_FR_15259 80 FR 15204 - FFP Missouri 2, LLC; Notice of Application Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions

80 FR 15204 - FFP Missouri 2, LLC; Notice of Application Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 80, Issue 55 (March 23, 2015)

Page Range15204-15205
FR Document2015-06524

Federal Register, Volume 80 Issue 55 (Monday, March 23, 2015)
[Federal Register Volume 80, Number 55 (Monday, March 23, 2015)]
[Notices]
[Pages 15204-15205]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2015-06524]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13702-002]


FFP Missouri 2, LLC; Notice of Application Ready for 
Environmental Analysis, and Soliciting Comments, Recommendations, Terms 
and Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original Major License--Existing Dam.
    b. Project No.: 13702-002.
    c. Date filed: November 13, 2013.
    d. Applicant: FFP Missouri 2, LLC.
    e. Name of Project: Grenada Lake Hydroelectric Project.
    f. Location: The proposed project would be located at the U.S. Army 
Corps of Engineers' (Corps) existing Grenada Lake Dam, on the Yalobusha 
River, near the Town of Grenada,

[[Page 15205]]

Grenada County, Mississippi. The proposed project would occupy 
approximately 35.5 acres of federal land administered by the Corps.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Ramya Swaminathan, Rye Development, 745 
Atlantic Avenue, 8th Floor, Boston, MA 02111; telephone (617) 804-1326.
    i. FERC Contact: Jeanne Edwards, telephone (202) 502-6181 and email 
[email protected]; or Patti Leppert, telephone (202) 502-6034 and 
email [email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
http://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-13702-002.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted for filing and is now ready 
for environmental analysis.
    l. The proposed Grenada Lake Project would utilize the following 
existing Corps' Grenada Lake Dam facilities: (1) A 13,900-foot-long, 
80-foot-high earth fill embankment dam; (2) a reservoir; and (3) outlet 
works consisting of a concrete intake tower, three gated inlets that 
combine to direct flow through a 377.5-foot-long, 17-foot-diameter 
concrete outlet conduit, and a stilling basin.
    The proposed Grenada Lake Project would consist of the following 
new facilities: (1) A 327.5-foot-long, 16-foot-diameter steel liner 
installed within the existing outlet conduit; (2) a 50-foot-long, 
variable width steel-lined, concrete bifurcation chamber containing two 
hydraulically-operated gates used to control the amount of flow 
diverted from the existing stilling basin to the powerhouse; (3) a 260-
foot-long, 14-foot-diameter steel penstock; (4) a 78-foot wide, 50-
foot-long, 86-foot-high steel and reinforced concrete forebay housing 
trashracks and a fish bypass outlet gate; (5) a 120-foot-long, 60-foot-
wide concrete powerhouse containing two vertical Kaplan turbine-
generator units having a combined installed capacity of 9.0 megawatts; 
(6) a 150-foot-long, 70-foot-wide tailrace; (7) a 670-foot-long, 4.16-
kilovolt (kV) buried cable; (8) a substation; and (9) a 1,980-foot-
long, 12.5-kV overhead transmission line extending from the substation 
to a utility-owned distribution line. The average annual generation 
would be 31,000 megawatt-hours.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room, or may be viewed on the 
Commission's Web site at http://www.ferc.gov, using the ``eLibrary'' 
link. Enter the docket number, excluding the last three digits in the 
docket number field, to access the document. For assistance, contact 
FERC Online Support. A copy is available for inspection and 
reproduction at the address in item h above.
    Register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    All filings must: (1) Bear in all capital letters the title 
``COMMENTS,'' ``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND 
CONDITIONS,'' or ``PRESCRIPTIONS''; (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person submitting the filing; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, recommendations, terms and conditions or prescriptions must 
set forth their evidentiary basis and otherwise comply with the 
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
application directly from the applicant. Each filing must be 
accompanied by proof of service on all persons listed on the service 
list prepared by the Commission in this proceeding, in accordance with 
18 CFR 4.34(b) and 385.2010.
    n. Procedural Schedule:
    The application will be processed according to the following 
revised hydro licensing schedule. Revisions to the schedule may be made 
as appropriate.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Filing of recommendations, terms and        May 2015.
 conditions, and prescriptions.
Commission issues Draft EA................  December 2015.
Comments on Draft EA Due..................  January 2016.
Commission Issues Final EA................  May 2016.
------------------------------------------------------------------------

    o. Public notice of the filing of the initial development 
application, which has already been given, established the due date for 
filing competing applications or notices of intent. Under the 
Commission's regulations, any competing development application must be 
filed in response to and in compliance with public notice of the 
initial development application. No competing applications or notices 
of intent may be filed in response to this notice.

    Dated: March 16, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-06524 Filed 3-20-15; 8:45 am]
 BILLING CODE 6717-01P



                                                  15204                         Federal Register / Vol. 80, No. 55 / Monday, March 23, 2015 / Notices

                                                  DEPARTMENT OF ENERGY                                    release 5 cubic feet per second (cfs) into            ‘‘MOTION TO INTERVENE’’ as
                                                                                                          the bypassed reach of Power Creek in                  applicable; (2) set forth in the heading
                                                  Federal Energy Regulatory                               order to study accretion flow, the                    the name of the applicant and the
                                                  Commission                                              environmental effects to fish, and to                 project number of the application to
                                                  [Project No. 11243–075]                                 potentially develop a proposal to                     which the filing responds; (3) furnish
                                                                                                          permanently suspend the requirements                  the name, address, and telephone
                                                  Cordova Electric Cooperative, Inc.;                     of Article 404 in order to generate                   number of the person protesting or
                                                  Notice of Application Accepted for                      additional power at a reduced cost with               intervening; and (4) otherwise comply
                                                  Filing and Soliciting Comments,                         less emissions compared to the                        with the requirements of 18 CFR
                                                  Motions To Intervene and Protests                       alternative of diesel power generation                385.2001 through 385.2005. All
                                                                                                          during the low flow period. The                       comments, motions to intervene, or
                                                     Take notice that the following                       licensee states that preliminary studies              protests must set forth their evidentiary
                                                  hydroelectric application has been filed                have indicated that the bypassed reach                basis and otherwise comply with the
                                                  with the Commission and is available                    has an average accretion flow 20 cfs                  requirements of 18 CFR 4.34(b).
                                                  for public inspection:                                  during low flow periods with a                        Agencies may obtain copies of the
                                                     a. Application Type: Request for two                 minimum measured flow of 7.79 cfs in                  application directly from the applicant.
                                                  year temporary variance of license                      March as measured just upstream of the                A copy of any protest or motion to
                                                  Article 404.                                            powerhouse. Therefore, the licensee’s                 intervene must be served upon each
                                                     b. Project No: 11243–075.                            request is not expected to dewater the                representative of the applicant specified
                                                     c. Date Filed: February 17, 2015.                    bypass reach, as it should still receive              in the particular application. If an
                                                     d. Applicant: Cordova Electric                       the intended 5 cfs from accretion flow.               intervener files comments or documents
                                                  Cooperative, INC (licensee).                               l. Locations of the Application: A                 with the Commission relating to the
                                                     e. Name of Project: Power Creek                      copy of the application is available for              merits of an issue that may affect the
                                                  Project.                                                inspection and reproduction at the                    responsibilities of a particular resource
                                                     f. Location: The Power Creek Project                 Commission’s Public Reference Room,                   agency, they must also serve a copy of
                                                  is located on Power Creek near the town                 located at 888 First Street, NE., Room                the document on that resource agency.
                                                  of Cordova, Alaska. The project is                      2A, Washington, DC 20426, or by calling               A copy of all other filings in reference
                                                  located entirely on Eyak Corporation                    202–502–8371. This filing may also be                 to this application must be accompanied
                                                  lands and is adjacent to Chugach                        viewed on the Commission’s Web site at                by proof of service on all persons listed
                                                  National Forest.                                        http://www.ferc.gov/docs-filing/
                                                     g. Filed Pursuant to: Federal Power                                                                        in the service list prepared by the
                                                                                                          efiling.asp. Enter the docket number                  Commission in this proceeding, in
                                                  Act, 16 U.S.C. 791a–825r.                               excluding the last three digits in the
                                                     h. Applicant Contact: Mr. Clay                                                                             accordance with 18 CFR 4.34(b) and
                                                                                                          docket number field to access the                     385.2010.
                                                  Koplin, CEO—Cordova Electric                            document. You may also register online
                                                  Cooperative, INC, 705 Second Street,                    at http://www.ferc.gov/docs-filing/                     Dated: March 16, 2015.
                                                  P.O. Box 20 Cordova, AK 99574, (907)                    esubscription.asp to be notified via                  Kimberly D. Bose,
                                                  424–5555.                                               email of new filings and issuances                    Secretary.
                                                     i. FERC Contact: Mr. Michael T.                      related to this or other pending projects.            [FR Doc. 2015–06522 Filed 3–20–15; 8:45 am]
                                                  Calloway, (202) 502–8041,                               For assistance, call 866–208–3676 or                  BILLING CODE 6717–01–P
                                                  michael.calloway@ferc.gov.                              email FERCOnlineSupport@ferc.gov, for
                                                     j. Deadline for filing comments,                     TTY, call 202–502–8659. A copy is also
                                                  motions to intervene, and protests is 30                available for inspection and                          DEPARTMENT OF ENERGY
                                                  days from the issuance date of this                     reproduction at the address in item (h)
                                                  notice by the Commission.                               above.                                                Federal Energy Regulatory
                                                     All documents may be filed                              m. Individuals desiring to be included             Commission
                                                  electronically via the Internet. See, 18                on the Commission’s mailing list should               [Project No. 13702–002]
                                                  CFR 385.2001(a)(1)(iii) and the                         so indicate by writing to the Secretary
                                                  instructions on the Commission’s Web                    of the Commission.                                    FFP Missouri 2, LLC; Notice of
                                                  site at http://www.ferc.gov/docs-filing/                   n. Comments, Protests, or Motions to               Application Ready for Environmental
                                                  efiling.asp. If unable to be filed                      Intervene: Anyone may submit                          Analysis, and Soliciting Comments,
                                                  electronically, documents may be paper-                 comments, a protest, or a motion to                   Recommendations, Terms and
                                                  filed. To paper-file, an original and                   intervene in accordance with the                      Conditions, and Prescriptions
                                                  seven copies should be mailed to:                       requirements of Rules of Practice and
                                                  Secretary, Federal Energy Regulatory                    Procedure, 18 CFR 385.210, .211, .214.                  Take notice that the following
                                                  Commission, 888 First Street NE.,                       In determining the appropriate action to              hydroelectric application has been filed
                                                  Washington, DC 20426. Commenters                        take, the Commission will consider all                with the Commission and is available
                                                  can submit brief comments up to 6,000                   protests or other comments filed, but                 for public inspection.
                                                  characters, without prior registration,                 only those who file a motion to                         a. Type of Application: Original Major
                                                  using the eComment system at http://                    intervene in accordance with the                      License—Existing Dam.
                                                  www.ferc.gov/docs-filing/                               Commission’s Rules may become a                         b. Project No.: 13702–002.
                                                  ecomment.asp. You must include your                     party to the proceeding. Any comments,                  c. Date filed: November 13, 2013.
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  name and contact information at the end                 protests, or motions to intervene must                  d. Applicant: FFP Missouri 2, LLC.
                                                  of your comments.                                       be received on or before the specified                  e. Name of Project: Grenada Lake
                                                     Please include the project number                    comment date for the particular                       Hydroelectric Project.
                                                  (P–11243–075) on any comments,                          application.                                            f. Location: The proposed project
                                                  motions, or recommendations filed.                         o. Filing and Service of Responsive                would be located at the U.S. Army
                                                     k. Description of Request: The                       Documents: Any filing must (1) bear in                Corps of Engineers’ (Corps) existing
                                                  licensee is requesting to suspend the                   all capital letters the title                         Grenada Lake Dam, on the Yalobusha
                                                  Article 404 requirement to continuously                 ‘‘COMMENTS’’; ‘‘PROTESTS’’, or                        River, near the Town of Grenada,


                                             VerDate Sep<11>2014   16:51 Mar 20, 2015   Jkt 235001   PO 00000   Frm 00019   Fmt 4703   Sfmt 4703   E:\FR\FM\23MRN1.SGM   23MRN1


                                                                                Federal Register / Vol. 80, No. 55 / Monday, March 23, 2015 / Notices                                                   15205

                                                  Grenada County, Mississippi. The                           The proposed Grenada Lake Project                  the service list prepared by the
                                                  proposed project would occupy                           would consist of the following new                    Commission in this proceeding, in
                                                  approximately 35.5 acres of federal land                facilities: (1) A 327.5-foot-long, 16-foot-           accordance with 18 CFR 4.34(b) and
                                                  administered by the Corps.                              diameter steel liner installed within the             385.2010.
                                                     g. Filed Pursuant to: Federal Power                  existing outlet conduit; (2) a 50-foot-                  n. Procedural Schedule:
                                                  Act, 16 U.S.C. 791 (a)–825(r).                          long, variable width steel-lined,                        The application will be processed
                                                     h. Applicant Contact: Ramya                          concrete bifurcation chamber containing               according to the following revised hydro
                                                  Swaminathan, Rye Development, 745                       two hydraulically-operated gates used to              licensing schedule. Revisions to the
                                                  Atlantic Avenue, 8th Floor, Boston, MA                  control the amount of flow diverted                   schedule may be made as appropriate.
                                                  02111; telephone (617) 804–1326.                        from the existing stilling basin to the
                                                     i. FERC Contact: Jeanne Edwards,                     powerhouse; (3) a 260-foot-long, 14-foot-                       Milestone                Target date
                                                  telephone (202) 502–6181 and email                      diameter steel penstock; (4) a 78-foot
                                                  jeanne.edwards@ferc.gov; or Patti                       wide, 50-foot-long, 86-foot-high steel                Filing of recommendations,       May 2015.
                                                  Leppert, telephone (202) 502–6034 and                                                                            terms and conditions, and
                                                                                                          and reinforced concrete forebay housing
                                                  email patricia.leppert@ferc.gov.                                                                                 prescriptions.
                                                                                                          trashracks and a fish bypass outlet gate;             Commission issues Draft EA       December
                                                     j. Deadline for filing comments,                     (5) a 120-foot-long, 60-foot-wide                                                        2015.
                                                  recommendations, terms and                              concrete powerhouse containing two                    Comments on Draft EA Due         January 2016.
                                                  conditions, and prescriptions: 60 days                  vertical Kaplan turbine-generator units               Commission Issues Final EA       May 2016.
                                                  from the issuance date of this notice;                  having a combined installed capacity of
                                                  reply comments are due 105 days from                    9.0 megawatts; (6) a 150-foot-long, 70-                 o. Public notice of the filing of the
                                                  the issuance date of this notice.                       foot-wide tailrace; (7) a 670-foot-long,              initial development application, which
                                                     The Commission strongly encourages                   4.16-kilovolt (kV) buried cable; (8) a                has already been given, established the
                                                  electronic filing. Please file comments,                substation; and (9) a 1,980-foot-long,                due date for filing competing
                                                  recommendations, terms and                              12.5–kV overhead transmission line                    applications or notices of intent. Under
                                                  conditions, and prescriptions using the                 extending from the substation to a                    the Commission’s regulations, any
                                                  Commission’s eFiling system at http://                  utility-owned distribution line. The                  competing development application
                                                  www.ferc.gov/docs-filing/efiling.asp.                   average annual generation would be                    must be filed in response to and in
                                                  Commenters can submit brief comments                    31,000 megawatt-hours.                                compliance with public notice of the
                                                  up to 6,000 characters, without prior                      m. A copy of the application is                    initial development application. No
                                                  registration, using the eComment system                 available for review at the Commission                competing applications or notices of
                                                  at http://www.ferc.gov/docs-filing/                     in the Public Reference Room, or may be               intent may be filed in response to this
                                                  ecomment.asp. You must include your                     viewed on the Commission’s Web site at                notice.
                                                  name and contact information at the end                 http://www.ferc.gov, using the
                                                  of your comments. For assistance,                                                                               Dated: March 16, 2015.
                                                                                                          ‘‘eLibrary’’ link. Enter the docket
                                                  please contact FERC Online Support at                   number, excluding the last three digits               Kimberly D. Bose,
                                                  FERCOnlineSupport@ferc.gov, (866)                       in the docket number field, to access the             Secretary.
                                                  208–3676 (toll free), or (202) 502–8659                 document. For assistance, contact FERC                [FR Doc. 2015–06524 Filed 3–20–15; 8:45 am]
                                                  (TTY). In lieu of electronic filing, please             Online Support. A copy is available for               BILLING CODE 6717–01P
                                                  send a paper copy to: Secretary, Federal                inspection and reproduction at the
                                                  Energy Regulatory Commission, 888                       address in item h above.
                                                  First Street NE., Washington, DC 20426.                    Register online at http://                         DEPARTMENT OF ENERGY
                                                  The first page of any filing should                     www.ferc.gov/docs-filing/                             [Certification Notice—233]
                                                  include docket number P–13702–002.                      esubscription.asp to be notified via
                                                     The Commission’s Rules of Practice                   email of new filings and issuances                    Notice of Filing of Self-Certification of
                                                  require all intervenors filing documents                related to this or other pending projects.            Coal Capability Under the Powerplant
                                                  with the Commission to serve a copy of                  For assistance, contact FERC Online                   and Industrial Fuel Use Act
                                                  that document on each person on the                     Support.
                                                  official service list for the project.                     All filings must: (1) Bear in all capital          AGENCY: Office of Electricity Delivery
                                                  Further, if an intervenor files comments                letters the title ‘‘COMMENTS,’’ ‘‘REPLY               and Energy Reliability, DOE.
                                                  or documents with the Commission                        COMMENTS,’’                                           ACTION: Notice of Filing.
                                                  relating to the merits of an issue that                 ‘‘RECOMMENDATIONS,’’ ‘‘TERMS
                                                  may affect the responsibilities of a                    AND CONDITIONS,’’ or                                  SUMMARY:    On March 2, 2015, NTE
                                                  particular resource agency, they must                   ‘‘PRESCRIPTIONS’’; (2) set forth in the               Carolinas, LLC, as owner and operator
                                                  also serve a copy of the document on                    heading the name of the applicant and                 of a new base load electric powerplant,
                                                  that resource agency.                                   the project number of the application to              submitted a coal capability self-
                                                     k. This application has been accepted                which the filing responds; (3) furnish                certification to the Department of
                                                  for filing and is now ready for                         the name, address, and telephone                      Energy (DOE) pursuant to § 201(d) of the
                                                  environmental analysis.                                 number of the person submitting the                   Powerplant and Industrial Fuel Use Act
                                                     l. The proposed Grenada Lake Project                 filing; and (4) otherwise comply with                 of 1978 (FUA), as amended, and DOE
                                                  would utilize the following existing                    the requirements of 18 CFR 385.2001                   regulations in 10 CFR 501.60, 61. FUA
                                                  Corps’ Grenada Lake Dam facilities: (1)                 through 385.2005. All comments,                       and regulations thereunder require DOE
                                                                                                                                                                to publish a notice of filing of self-
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  A 13,900-foot-long, 80-foot-high earth                  recommendations, terms and conditions
                                                  fill embankment dam; (2) a reservoir;                   or prescriptions must set forth their                 certification in the Federal Register. 42
                                                  and (3) outlet works consisting of a                    evidentiary basis and otherwise comply                U.S.C. 8311(d) and 10 CFR 501.61(c).
                                                  concrete intake tower, three gated inlets               with the requirements of 18 CFR 4.34(b).              ADDRESSES: Copies of coal capability
                                                  that combine to direct flow through a                   Agencies may obtain copies of the                     self-certification filings are available for
                                                  377.5-foot-long, 17-foot-diameter                       application directly from the applicant.              public inspection, upon request, in the
                                                  concrete outlet conduit, and a stilling                 Each filing must be accompanied by                    Office of Electricity Delivery and Energy
                                                  basin.                                                  proof of service on all persons listed on             Reliability, Mail Code OE–20, Room


                                             VerDate Sep<11>2014   16:51 Mar 20, 2015   Jkt 235001   PO 00000   Frm 00020   Fmt 4703   Sfmt 4703   E:\FR\FM\23MRN1.SGM   23MRN1



Document Created: 2018-02-21 09:47:42
Document Modified: 2018-02-21 09:47:42
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation80 FR 15204 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR