81_FR_10651 81 FR 10611 - Clark Canyon Hydro, LLC ; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Terms and Conditions, Recommendations, and Prescriptions

81 FR 10611 - Clark Canyon Hydro, LLC ; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Terms and Conditions, Recommendations, and Prescriptions

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 40 (March 1, 2016)

Page Range10611-10612
FR Document2016-04392

Federal Register, Volume 81 Issue 40 (Tuesday, March 1, 2016)
[Federal Register Volume 81, Number 40 (Tuesday, March 1, 2016)]
[Notices]
[Pages 10611-10612]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-04392]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14677-001]


Clark Canyon Hydro, LLC ; Notice of Application Accepted for 
Filing, Soliciting Motions To Intervene and Protests, Ready for 
Environmental Analysis, and Soliciting Comments, Terms and Conditions, 
Recommendations, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original License for a Major Water Power 
Project at an Existing Dam, 5 Megawatts or Less.
    b. Project No.: 14677-001.
    c. Date filed: November 23, 2015.
    d. Applicant: Clark Canyon Hydro, LLC.
    e. Name of Project: Clark Canyon Dam Hydroelectric Project.
    f. Location: On the River, in the Town of Dillon, Beaverhead 
County, Montana. The project would occupy 62.1 acres of land owned by 
the U.S. Bureau of Reclamation and 0.2 acres of land owned by the U.S. 
Bureau of Land Management.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: John Gangemi, (406) 249-3972, email at 
[email protected].
    i. FERC Contact: Kelly Wolcott, (202) 502-6480, email at 
[email protected].
    j. Deadline for filing motions to intervene and protests, comments, 
terms and conditions, recommendations, and prescriptions: 30 days from 
the issuance date of this notice; reply comments are due 45 days from 
the issuance date of this notice.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene and protests, comments, terms and conditions, 
recommendations, and prescriptions using the Commission's eFiling 
system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can

[[Page 10612]]

submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. The first page of any filing should 
include docket number P-14677-001.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted for filing and is now ready 
for environmental analysis.
    l. The Clark Canyon Dam Hydroelectric Project would utilize the 
U.S. Bureau of Reclamation's Clark Canyon Dam and outlet works 
including an intake structure and concrete conduit in the reservoir. 
The project would consist of the following new facilities: (1) A 360-
foot-long, 8-foot-diameter steel penstock within the existing concrete 
conduit, ending in a trifurcation; (2) two 35-foot-long, 8-foot-
diameter penstocks extending from the trifurcation to the powerhouse, 
transitioning to 6-foot-diameter before entering the powerhouse; (3) a 
10-foot-long, 8-foot-diameter steel penstock leaving the trifurcation 
and ending in a 7-foot-diameter cone valve and reducer to control 
discharge into the existing outlet stilling basin; (4) a 65-foot-long, 
46-foot-wide reinforced concrete powerhouse containing two vertical 
Francis-type turbine/generator units with a total capacity of 4.7 
megawatts; (5) two 25-foot-long steel draft tubes transitioning to 
concrete draft tube/tailrace section; (6) a 17-foot-long, 15-foot-
diameter tailrace channel connecting with the existing spillway 
stilling basin; (7) a 45-foot-long, 10-foot-wide aeration basin 
downstream of the powerhouse with three frames containing 330 
diffusers; (8) a 1,100-foot-long, 4.16-kilovolt (kV) buried 
transmission line from the powerhouse to a substation; (9) a substation 
containing step-up transformers and switchgear; (10) a 7.9-mile-long, 
69-kV transmission line extending from the project substation to the 
Peterson Flat substation (the point of interconnection); and (11) 
appurtenant facilities. The estimated annual generation of the Clark 
Canyon Dam Project would be 15.4 gigawatt-hours. All project facilities 
would be located on federal lands owned by the U.S. Bureau of 
Reclamation and the U.S. Bureau of Land Management. The applicant 
proposes to operate the project as run-of-release.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    Register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Any qualified applicant desiring to file a competing application 
must submit to the Commission, on or before the specified intervention 
deadline date, a competing development application, or a notice of 
intent to file such an application. Submission of a timely notice of 
intent allows an interested person to file the competing development 
application no later than 120 days after the specified intervention 
deadline date. Applications for preliminary permits will not be 
accepted in response to this notice.
    A notice of intent must specify the exact name, business address, 
and telephone number of the prospective applicant, and must include an 
unequivocal statement of intent to submit a development application. A 
notice of intent must be served on the applicant(s) named in this 
public notice.
    Anyone may submit comments, a protest, or a motion to intervene in 
accordance with the requirements of Rules of Practice and Procedure, 18 
CFR 385.210, .211, and .214. In determining the appropriate action to 
take, the Commission will consider all protests or other comments 
filed, but only those who file a motion to intervene in accordance with 
the Commission's Rules may become a party to the proceeding. Any 
comments, protests, or motions to intervene must be received on or 
before the specified comment date for the particular application.
    All filings must (1) bear in all capital letters the title 
``PROTEST'', ``MOTION TO INTERVENE'', ``NOTICE OF INTENT TO FILE 
COMPETING APPLICATION,'' ``COMPETING APPLICATION,'' ``COMMENTS,'' 
``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND CONDITIONS,'' or 
``PRESCRIPTIONS;'' (2) set forth in the heading the name of the 
applicant and the project number of the application to which the filing 
responds; (3) furnish the name, address, and telephone number of the 
person protesting or intervening; and (4) otherwise comply with the 
requirements of 18 CFR 385.2001 through 385.2005. All comments, 
recommendations, terms and conditions or prescriptions must set forth 
their evidentiary basis and otherwise comply with the requirements of 
18 CFR 4.34(b). Agencies may obtain copies of the application directly 
from the applicant. A copy of any protest or motion to intervene must 
be served upon each representative of the applicant specified in the 
particular application. A copy of all other filings in reference to 
this application must be accompanied by proof of service on all persons 
listed in the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    o. A license applicant must file no later than 60 days following 
the date of issuance of this notice: (1) A copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification.

    Dated: February 23, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-04392 Filed 2-29-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                   Federal Register / Vol. 81, No. 40 / Tuesday, March 1, 2016 / Notices                                                  10611

                                                       • The options and implications for,                  Kent Carter (Legal Information), Office                 For more information contact Nicole
                                                    and potential benefits or drawbacks of,                   of General Counsel, Federal Energy                  Cramer, Office of Energy Market
                                                    ARR allocation based on more frequent                     Regulatory Commission, 888 First                    Regulation, Federal Energy Regulatory
                                                    updates of the Simultaneous Feasibility                   Street NE., Washington, DC 20426,                   Commission at (202) 502–6775 or
                                                    Test model, which could, for example,                     (202) 502–8604, Kent.Carter@ferc.gov                nicole.cramer@ferc.gov.
                                                    allow for seasonal variations of line                   Daniel Kheloussi (Technical                             Dated: February 23, 2016.
                                                    ratings, as well as more timely                           Information), Office of Energy Policy               Nathaniel J. Davis, Sr.,
                                                    recognition and modeling of                               and Innovation, Federal Energy
                                                                                                                                                                  Deputy Secretary.
                                                    transmission outages and upgrades                         Regulatory Commission, 888 First
                                                    placed into service.                                                                                          [FR Doc. 2016–04388 Filed 2–29–16; 8:45 am]
                                                                                                              Street NE., Washington, DC 20426,
                                                       • The options to update PJM’s                          (202) 502–6391, Daniel.Kheloussi@                   BILLING CODE 6717–01–P
                                                    Simultaneous Feasibility Test model,                      ferc.gov
                                                    including source points and sink points,
                                                                                                              Dated: February 23, 2016.                           DEPARTMENT OF ENERGY
                                                    to reflect current system usage and
                                                    topology; concerns about updating the                   Nathaniel J. Davis, Sr.
                                                    model; the potential benefits or                        Deputy Secretary.                                     Federal Energy Regulatory
                                                    drawbacks for updating the model; and                   [FR Doc. 2016–04387 Filed 2–29–16; 8:45 am]           Commission
                                                    processes for allowing more frequent                    BILLING CODE 6717–01–P                                [Project No. 14677–001]
                                                    updates. If the Simultaneous Feasibility
                                                    Test model were to be updated more                                                                            Clark Canyon Hydro, LLC ; Notice of
                                                    frequently, would infeasible ARRs                       DEPARTMENT OF ENERGY                                  Application Accepted for Filing,
                                                    continue to exist?                                                                                            Soliciting Motions To Intervene and
                                                       • Whether the incentives for                         Federal Energy Regulatory                             Protests, Ready for Environmental
                                                    Transmission Owners to schedule                         Commission                                            Analysis, and Soliciting Comments,
                                                    outages and conduct timely work align                                                                         Terms and Conditions,
                                                    with ARR/FTR construct, and whether                     Notice of Commission Staff                            Recommendations, and Prescriptions
                                                    there are any proposals that can                        Attendance
                                                    improve this alignment; and the                                                                                  Take notice that the following
                                                                                                               The Federal Energy Regulatory                      hydroelectric application has been filed
                                                    effectiveness of the current reporting                  Commission (Commission) hereby gives
                                                    requirements for Transmission Owners                                                                          with the Commission and is available
                                                                                                            notice that members of the                            for public inspection.
                                                    to share information with PJM.                          Commission’s staff may attend the
                                                       • Whether continuing to include                                                                               a. Type of Application: Original
                                                                                                            following meetings related to the                     License for a Major Water Power Project
                                                    balancing congestion 1 in the definition                transmission planning activities of
                                                    of FTRs is appropriate (and why), or                                                                          at an Existing Dam, 5 Megawatts or Less.
                                                                                                            Public Service Company of Colorado,                      b. Project No.: 14677–001.
                                                    whether FTRs should be defined and                      Tucson Electric Power Company, UNS
                                                    settled only including day-ahead                                                                                 c. Date filed: November 23, 2015.
                                                                                                            Electric, Inc., Public Service Company                   d. Applicant: Clark Canyon Hydro,
                                                    congestion. Are there any aspect(s) of                  of New Mexico, Arizona Public Service
                                                    balancing congestion that should be                                                                           LLC.
                                                                                                            Company, El Paso Electric Company,                       e. Name of Project: Clark Canyon Dam
                                                    included in the definition of FTRs, and,                Black Hills Power, Inc., Black Hills
                                                    if so, what are they and why they                                                                             Hydroelectric Project.
                                                                                                            Colorado Electric Utility Company, LP,                   f. Location: On the River, in the Town
                                                    should be included?                                     Cheyenne Light, Fuel, & Power
                                                       Commenters need not address every                                                                          of Dillon, Beaverhead County, Montana.
                                                                                                            Company, Arizona Public Service                       The project would occupy 62.1 acres of
                                                    question and may provide comments on                    Company, and NV Energy, Inc.:
                                                    relevant issues other than those listed                                                                       land owned by the U.S. Bureau of
                                                    above. These comments are due no later                  Regional Stakeholder Meeting                          Reclamation and 0.2 acres of land
                                                    than 5:00 p.m. Eastern Standard Time                                                                          owned by the U.S. Bureau of Land
                                                                                                            February 24, 2016, 1 p.m.–4:30 p.m.                   Management.
                                                    (EST) on March 15, 2016. Reply                            (MST)
                                                    comments are due on or before 5:00                                                                               g. Filed Pursuant to: Federal Power
                                                    p.m. EST on March 29, 2016. The                         Planning Management Committee                         Act 16 U.S.C. 791(a)–825(r).
                                                    written comments will be included in                    Meeting                                                  h. Applicant Contact: John Gangemi,
                                                    the formal record for the proceeding,                                                                         (406) 249–3972, email at john.gangemi@
                                                                                                            April 5, 2016, 9 a.m.–12 p.m. (PST)
                                                    which, together with the record                                                                               erm.com.
                                                    developed to date, will form the basis                     The above-referenced meetings will                    i. FERC Contact: Kelly Wolcott, (202)
                                                    for further Commission action.                          be held at: SRP PERA Club, 1 E.                       502–6480, email at kelly.wolcott@
                                                       For more information about this                      Continental Drive, Tempe, Arizona                     ferc.gov.
                                                    Notice, please contact:                                 85281.                                                   j. Deadline for filing motions to
                                                    Pamela Quinlan (Technical                                  The above-referenced meetings will                 intervene and protests, comments, terms
                                                       Information), Office of Energy Market                be available via web conference and                   and conditions, recommendations, and
                                                       Regulation, Federal Energy Regulatory                teleconference.                                       prescriptions: 30 days from the issuance
                                                       Commission, 888 First Street NE.,                       The above-referenced meetings are                  date of this notice; reply comments are
                                                                                                            open to stakeholders.                                 due 45 days from the issuance date of
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                       Washington, DC 20426, (202) 502–
                                                       6179, Pamela.Quinlan@ferc.gov                           Further information may be found at                this notice.
                                                                                                            http://www.westconnect.com/                              The Commission strongly encourages
                                                       1 Negative balancing congestion occurs when real-    index.php.                                            electronic filing. Please file motions to
                                                    time transmission capacity is less than day-ahead          The discussions at the meetings                    intervene and protests, comments, terms
                                                    transmission capacity. FTRs are allocated negative      described above may address matters at                and conditions, recommendations, and
                                                    balancing congestion charges, which in turn can
                                                    result in FTR underfunding because the revenues
                                                                                                            issue in the following proceeding:                    prescriptions using the Commission’s
                                                    allocated for meeting the FTR funding target               ER16–912, Arizona Public Service                   eFiling system at http://www.ferc.gov/
                                                    amount are decreased.                                   Company.                                              docs-filing/efiling.asp. Commenters can


                                               VerDate Sep<11>2014   20:18 Feb 29, 2016   Jkt 238001   PO 00000   Frm 00047   Fmt 4703   Sfmt 4703   E:\FR\FM\01MRN1.SGM   01MRN1


                                                    10612                          Federal Register / Vol. 81, No. 40 / Tuesday, March 1, 2016 / Notices

                                                    submit brief comments up to 6,000                       extending from the project substation to                 All filings must (1) bear in all capital
                                                    characters, without prior registration,                 the Peterson Flat substation (the point of            letters the title ‘‘PROTEST’’, ‘‘MOTION
                                                    using the eComment system at http://                    interconnection); and (11) appurtenant                TO INTERVENE’’, ‘‘NOTICE OF
                                                    www.ferc.gov/docs-filing/                               facilities. The estimated annual                      INTENT TO FILE COMPETING
                                                    ecomment.asp. You must include your                     generation of the Clark Canyon Dam                    APPLICATION,’’ ‘‘COMPETING
                                                    name and contact information at the end                 Project would be 15.4 gigawatt-hours.                 APPLICATION,’’ ‘‘COMMENTS,’’
                                                    of your comments. For assistance,                       All project facilities would be located               ‘‘REPLY COMMENTS,’’
                                                    please contact FERC Online Support at                   on federal lands owned by the U.S.                    ‘‘RECOMMENDATIONS,’’ ‘‘TERMS
                                                    FERCOnlineSupport@ferc.gov, (866)                       Bureau of Reclamation and the U.S.                    AND CONDITIONS,’’ or
                                                    208–3676 (toll free), or (202) 502–8659                 Bureau of Land Management. The                        ‘‘PRESCRIPTIONS;’’ (2) set forth in the
                                                    (TTY). In lieu of electronic filing, please             applicant proposes to operate the                     heading the name of the applicant and
                                                    send a paper copy to: Secretary, Federal                project as run-of-release.                            the project number of the application to
                                                    Energy Regulatory Commission, 888                          m. A copy of the application is                    which the filing responds; (3) furnish
                                                    First Street NE., Washington, DC 20426.                 available for review at the Commission                the name, address, and telephone
                                                    The first page of any filing should                     in the Public Reference Room or may be                number of the person protesting or
                                                    include docket number P–14677–001.                      viewed on the Commission’s Web site at                intervening; and (4) otherwise comply
                                                       The Commission’s Rules of Practice                   http://www.ferc.gov using the                         with the requirements of 18 CFR
                                                    require all intervenors filing documents                ‘‘eLibrary’’ link. Enter the docket                   385.2001 through 385.2005. All
                                                    with the Commission to serve a copy of                  number excluding the last three digits in             comments, recommendations, terms and
                                                    that document on each person on the                     the docket number field to access the                 conditions or prescriptions must set
                                                    official service list for the project.                  document. For assistance, contact FERC                forth their evidentiary basis and
                                                    Further, if an intervenor files comments                Online Support. A copy is also available              otherwise comply with the requirements
                                                    or documents with the Commission                        for inspection and reproduction at the                of 18 CFR 4.34(b). Agencies may obtain
                                                    relating to the merits of an issue that                 address in item h above.                              copies of the application directly from
                                                    may affect the responsibilities of a                       Register online at http://                         the applicant. A copy of any protest or
                                                    particular resource agency, they must                   www.ferc.gov/docs-filing/                             motion to intervene must be served
                                                    also serve a copy of the document on                    esubscription.asp to be notified via                  upon each representative of the
                                                    that resource agency.                                   email of new filings and issuances                    applicant specified in the particular
                                                       k. This application has been accepted                                                                      application. A copy of all other filings
                                                                                                            related to this or other pending projects.
                                                    for filing and is now ready for                                                                               in reference to this application must be
                                                                                                            For assistance, contact FERC Online
                                                    environmental analysis.                                                                                       accompanied by proof of service on all
                                                       l. The Clark Canyon Dam                              Support.
                                                                                                               n. Any qualified applicant desiring to             persons listed in the service list
                                                    Hydroelectric Project would utilize the
                                                                                                            file a competing application must                     prepared by the Commission in this
                                                    U.S. Bureau of Reclamation’s Clark
                                                                                                            submit to the Commission, on or before                proceeding, in accordance with 18 CFR
                                                    Canyon Dam and outlet works including
                                                    an intake structure and concrete conduit                the specified intervention deadline date,             4.34(b) and 385.2010.
                                                    in the reservoir. The project would                     a competing development application,                     o. A license applicant must file no
                                                    consist of the following new facilities:                or a notice of intent to file such an                 later than 60 days following the date of
                                                    (1) A 360-foot-long, 8-foot-diameter steel              application. Submission of a timely                   issuance of this notice: (1) A copy of the
                                                    penstock within the existing concrete                   notice of intent allows an interested                 water quality certification; (2) a copy of
                                                    conduit, ending in a trifurcation; (2) two              person to file the competing                          the request for certification, including
                                                    35-foot-long, 8-foot-diameter penstocks                 development application no later than                 proof of the date on which the certifying
                                                    extending from the trifurcation to the                  120 days after the specified intervention             agency received the request; or (3)
                                                    powerhouse, transitioning to 6-foot-                    deadline date. Applications for                       evidence of waiver of water quality
                                                    diameter before entering the                            preliminary permits will not be                       certification.
                                                    powerhouse; (3) a 10-foot-long, 8-foot-                 accepted in response to this notice.                    Dated: February 23, 2016.
                                                    diameter steel penstock leaving the                        A notice of intent must specify the                Nathaniel J. Davis, Sr.,
                                                    trifurcation and ending in a 7-foot-                    exact name, business address, and                     Deputy Secretary.
                                                    diameter cone valve and reducer to                      telephone number of the prospective                   [FR Doc. 2016–04392 Filed 2–29–16; 8:45 am]
                                                    control discharge into the existing outlet              applicant, and must include an
                                                                                                                                                                  BILLING CODE 6717–01–P
                                                    stilling basin; (4) a 65-foot-long, 46-foot-            unequivocal statement of intent to
                                                    wide reinforced concrete powerhouse                     submit a development application. A
                                                    containing two vertical Francis-type                    notice of intent must be served on the                DEPARTMENT OF ENERGY
                                                    turbine/generator units with a total                    applicant(s) named in this public notice.
                                                    capacity of 4.7 megawatts; (5) two 25-                     Anyone may submit comments, a                      Federal Energy Regulatory
                                                    foot-long steel draft tubes transitioning               protest, or a motion to intervene in                  Commission
                                                    to concrete draft tube/tailrace section;                accordance with the requirements of
                                                                                                            Rules of Practice and Procedure, 18 CFR               [ Docket No. PF15–32–000]
                                                    (6) a 17-foot-long, 15-foot-diameter
                                                    tailrace channel connecting with the                    385.210, .211, and .214. In determining               Northern Natural Gas Company; Notice
                                                    existing spillway stilling basin; (7) a 45-             the appropriate action to take, the                   of Intent To Prepare an Environmental
                                                    foot-long, 10-foot-wide aeration basin                  Commission will consider all protests or
asabaliauskas on DSK5VPTVN1PROD with NOTICES




                                                                                                                                                                  Assessment for the Planned Cedar
                                                    downstream of the powerhouse with                       other comments filed, but only those                  Station Upgrade Project, Request for
                                                    three frames containing 330 diffusers;                  who file a motion to intervene in                     Comments on Environmental Issues,
                                                    (8) a 1,100-foot-long, 4.16-kilovolt (kV)               accordance with the Commission’s                      and Notice of Public Scoping Meeting
                                                    buried transmission line from the                       Rules may become a party to the
                                                    powerhouse to a substation; (9) a                       proceeding. Any comments, protests, or                  The staff of the Federal Energy
                                                    substation containing step-up                           motions to intervene must be received                 Regulatory Commission (FERC or
                                                    transformers and switchgear; (10) a 7.9-                on or before the specified comment date               Commission) will prepare an
                                                    mile-long, 69-kV transmission line                      for the particular application.                       environmental assessment (EA) that will


                                               VerDate Sep<11>2014   20:18 Feb 29, 2016   Jkt 238001   PO 00000   Frm 00048   Fmt 4703   Sfmt 4703   E:\FR\FM\01MRN1.SGM   01MRN1



Document Created: 2018-02-02 15:00:09
Document Modified: 2018-02-02 15:00:09
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 10611 