82_FR_15411 82 FR 15353 - Gulf South Pipeline Company, LP; Notice Extending Comment Date

82 FR 15353 - Gulf South Pipeline Company, LP; Notice Extending Comment Date

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 58 (March 28, 2017)

Page Range15353-15354
FR Document2017-06066

Federal Register, Volume 82 Issue 58 (Tuesday, March 28, 2017)
[Federal Register Volume 82, Number 58 (Tuesday, March 28, 2017)]
[Notices]
[Pages 15353-15354]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-06066]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-62-000]


Gulf South Pipeline Company, LP; Notice Extending Comment Date

    On March 1, 2017, the Commission issued a notice of application 
(March 1 Notice) in the above captioned proceeding.\1\ To give 
interested parties who were not on the original landowner list an 
opportunity to comment, the comment due date on the March 1 Notice is 
hereby extended from March 22, 2017 to April 12, 2017.
---------------------------------------------------------------------------

    \1\ Gulf South Pipeline Co., LP, 82 FR 12,814 (2017).
---------------------------------------------------------------------------

    As stated in the March 1 Notice, in its application, Gulf South 
Pipeline Company, LP requests to amend its certificate issued by the 
Commission in Docket No. CP15-517-000 to (i) install a gas-fired Solar 
Titan 130 turbine compressor unit in place of the currently 
certificated gas-fired Solar Mars 100 turbine compressor unit at the 
Magasco Compressor Station, located in Sabine County, Texas, increasing 
the horsepower from 15,748 hp to 20,482 hp and (ii) modify the 
emergency generator from an 800 brake-horsepower (bhp) unit to a 691 
bhp unit. This amendment will not require any additional workspace or 
land disturbance beyond what has been approved by the Commission. The 
estimated cost of the amendment is approximately $3 million, all as 
more fully set forth in the application which is on file with the 
Commission and open to public inspection. The filing is available for 
review at the Commission in the Public Reference Room or may be viewed 
on the Commission's Web site web at http://www.ferc.gov using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC at [email protected] or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.
    Any questions regarding this application may be directed to Kathy 
D. Fort, Manager, Certificates & Tariffs, Gulf South Pipeline Company, 
LP, 9 Greenway Plaza, Suite 2800, Houston, Texas 77046, by telephone at 
(713) 479-8252, or by email to [email protected].
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice \2\ the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the EA for this proposal. The filing of the EA in the Commission's 
public record for this proceeding or the issuance of a

[[Page 15354]]

Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's EA.
---------------------------------------------------------------------------

    \2\ The 90-day timeframe restarts from the date of this notice.
---------------------------------------------------------------------------

    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit seven copies of filings made in the proceeding with the 
Commission and must mail a copy to the applicant and to every other 
party. Only parties to the proceeding can ask for court review of 
Commission orders in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 7 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on April 12, 2017.

    Dated: March 22, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-06066 Filed 3-27-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                              Federal Register / Vol. 82, No. 58 / Tuesday, March 28, 2017 / Notices                                                    15353




                                                [FR Doc. 2017–06107 Filed 3–27–17; 8:45 am]             a gas-fired Solar Titan 130 turbine                   toll-free, (886) 208–3676 or TYY, (202)
                                                BILLING CODE 6450–01–C                                  compressor unit in place of the                       502–8659.
                                                                                                        currently certificated gas-fired Solar                   Any questions regarding this
                                                                                                        Mars 100 turbine compressor unit at the               application may be directed to Kathy D.
                                                DEPARTMENT OF ENERGY                                    Magasco Compressor Station, located in                Fort, Manager, Certificates & Tariffs,
                                                                                                        Sabine County, Texas, increasing the                  Gulf South Pipeline Company, LP, 9
                                                Federal Energy Regulatory                                                                                     Greenway Plaza, Suite 2800, Houston,
                                                Commission                                              horsepower from 15,748 hp to 20,482 hp
                                                                                                        and (ii) modify the emergency generator               Texas 77046, by telephone at (713) 479–
                                                [Docket No. CP17–62–000]                                from an 800 brake-horsepower (bhp)                    8252, or by email to kathy.fort@
                                                                                                        unit to a 691 bhp unit. This amendment                bwpmlp.com.
                                                Gulf South Pipeline Company, LP;                                                                                 Pursuant to section 157.9 of the
                                                                                                        will not require any additional
                                                Notice Extending Comment Date                                                                                 Commission’s rules, 18 CFR 157.9,
                                                                                                        workspace or land disturbance beyond
                                                   On March 1, 2017, the Commission                     what has been approved by the                         within 90 days of this Notice 2 the
                                                issued a notice of application (March 1                 Commission. The estimated cost of the                 Commission staff will either: Complete
                                                Notice) in the above captioned                                                                                its environmental assessment (EA) and
                                                                                                        amendment is approximately $3
                                                proceeding.1 To give interested parties                                                                       place it into the Commission’s public
                                                                                                        million, all as more fully set forth in the
                                                who were not on the original landowner                                                                        record (eLibrary) for this proceeding; or
                                                                                                        application which is on file with the
                                                list an opportunity to comment, the                                                                           issue a Notice of Schedule for
                                                                                                        Commission and open to public                         Environmental Review. If a Notice of
                                                comment due date on the March 1                         inspection. The filing is available for
                                                Notice is hereby extended from March                                                                          Schedule for Environmental Review is
                                                                                                        review at the Commission in the Public                issued, it will indicate, among other
                                                22, 2017 to April 12, 2017.
                                                                                                        Reference Room or may be viewed on
sradovich on DSK3GMQ082PROD with NOTICES




                                                   As stated in the March 1 Notice, in its                                                                    milestones, the anticipated date for the
                                                application, Gulf South Pipeline                        the Commission’s Web site web at                      Commission staff’s issuance of the EA
                                                Company, LP requests to amend its                       http://www.ferc.gov using the                         for this proposal. The filing of the EA
                                                certificate issued by the Commission in                 ‘‘eLibrary’’ link. Enter the docket                   in the Commission’s public record for
                                                Docket No. CP15–517–000 to (i) install                  number excluding the last three digits in             this proceeding or the issuance of a
                                                                                                        the docket number field to access the
                                                  1 Gulf South Pipeline Co., LP, 82 FR 12,814           document. For assistance, contact FERC                  2 The 90-day timeframe restarts from the date of
                                                                                                                                                                                                                   EN28MR17.004</GPH>




                                                (2017).                                                 at FERCOnlineSupport@ferc.gov or call                 this notice.



                                           VerDate Sep<11>2014   17:14 Mar 27, 2017   Jkt 241001   PO 00000   Frm 00040   Fmt 4703   Sfmt 4703   E:\FR\FM\28MRN1.SGM   28MRN1


                                                15354                         Federal Register / Vol. 82, No. 58 / Tuesday, March 28, 2017 / Notices

                                                Notice of Schedule for Environmental                    filed by other parties or issued by the                 January 2017. With this Supplemental
                                                Review will serve to notify federal and                 Commission (except for the mailing of                   Notice of Intent (NOI) we2 are
                                                state agencies of the timing for the                    environmental documents issued by the                   specifically seeking comments on
                                                completion of all necessary reviews, and                Commission) and will not have the right                 additional facilities planned by Midship
                                                the subsequent need to complete all                     to seek court review of the                             Pipeline and recently identified as part
                                                federal authorizations within 90 days of                Commission’s final order.                               of the MIDSHIP Project, specifically the
                                                the date of issuance of the Commission                     The Commission strongly encourages                   Velma Lateral and Sholem Booster
                                                staff’s EA.                                             electronic filings of comments, protests                Station. Your comments should focus
                                                   There are two ways to become                         and interventions in lieu of paper using                on the potential environmental effects,
                                                involved in the Commission’s review of                  the ‘‘eFiling’’ link at http://                         reasonable alternatives, and measures to
                                                this project. First, any person wishing to              www.ferc.gov. Persons unable to file
                                                obtain legal status by becoming a party                                                                         avoid or lessen environmental impacts
                                                                                                        electronically should submit an original
                                                to the proceedings for this project                                                                             from these facilities. Your input will
                                                                                                        and 7 copies of the protest or
                                                should, on or before the comment date                   intervention to the Federal Energy                      help the Commission staff determine
                                                stated below file with the Federal                      Regulatory Commission, 888 First Street                 what issues we need to evaluate in the
                                                Energy Regulatory Commission, 888                       NE., Washington, DC 20426.                              EIS. To ensure that your comments are
                                                First Street NE., Washington, DC 20426,                    Comment Date: 5:00 p.m. Eastern                      timely and properly recorded, please
                                                a motion to intervene in accordance                     Time on April 12, 2017.                                 send your comments so that the
                                                with the requirements of the                                                                                    Commission receives them in
                                                                                                          Dated: March 22, 2017.
                                                Commission’s Rules of Practice and                                                                              Washington, DC on or before April 21,
                                                                                                        Kimberly D. Bose,
                                                Procedure (18 CFR 385.214 or 385.211)                                                                           2017. If you have already submitted
                                                and the Regulations under the NGA (18                   Secretary.
                                                                                                                                                                comments for the MIDSHIP Project prior
                                                CFR 157.10). A person obtaining party                   [FR Doc. 2017–06066 Filed 3–27–17; 8:45 am]
                                                                                                                                                                to this Supplemental NOI, you do not
                                                status will be placed on the service list               BILLING CODE 6717–01–P
                                                                                                                                                                need to resubmit your comments.
                                                maintained by the Secretary of the
                                                                                                                                                                   This notice is being sent to the
                                                Commission and will receive copies of
                                                all documents filed by the applicant and                DEPARTMENT OF ENERGY                                    Commission’s current environmental
                                                by all other parties. A party must submit                                                                       mailing list for this project, including
                                                                                                        Federal Energy Regulatory                               the newly affected landowners along the
                                                seven copies of filings made in the
                                                                                                        Commission                                              planned Velma Lateral and Sholem
                                                proceeding with the Commission and
                                                must mail a copy to the applicant and                   [Docket No. PF17–3–000]                                 Booster Station. State and local
                                                to every other party. Only parties to the                                                                       government representatives should
                                                proceeding can ask for court review of                  Midship Pipeline Company, LLC;                          notify their constituents of this planned
                                                Commission orders in the proceeding.                    Supplemental Notice of Intent To                        project and encourage them to comment
                                                   However, a person does not have to                   Prepare an Environmental Impact                         on their areas of concern.
                                                intervene in order to have comments                     Statement for the Planned
                                                                                                                                                                   If you are a newly affected landowner
                                                considered. The second way to                           Midcontinent Supply Header Interstate
                                                                                                                                                                receiving this notice, a pipeline
                                                participate is by filing with the                       Pipeline Project and Request for
                                                                                                        Comments on Environmental Issues                        company representative may have
                                                Secretary of the Commission, as soon as
                                                                                                        Related to New Pipeline Lateral and                     already contacted you or may contact
                                                possible, an original and two copies of
                                                comments in support of or in opposition                 Booster Station                                         you soon about the acquisition of an
                                                to this project. The Commission will                                                                            easement to construct, operate, and
                                                                                                          As previously noticed on January 27,                  maintain the planned facilities. The
                                                consider these comments in
                                                                                                        2017, and supplemented herein, the                      company would seek to negotiate a
                                                determining the appropriate action to be
                                                                                                        staff of the Federal Energy Regulatory                  mutually acceptable agreement.
                                                taken, but the filing of a comment alone
                                                                                                        Commission (FERC or Commission) will                    However, if the Commission approves
                                                will not serve to make the filer a party
                                                                                                        prepare an environmental impact                         the project, that approval conveys with
                                                to the proceeding. The Commission’s
                                                                                                        statement (EIS) that will discuss the                   it the right of eminent domain.
                                                rules require that persons filing
                                                                                                        environmental impacts of the                            Therefore, if the easement negotiations
                                                comments in opposition to the project
                                                provide copies of their protests only to                Midcontinent Supply Header Interstate
                                                                                                                                                                fail to produce an agreement, the
                                                the party or parties directly involved in               Pipeline Project (MIDSHIP Project)
                                                                                                                                                                pipeline company could initiate
                                                the protest.                                            involving construction and operation of
                                                                                                        facilities by Midship Pipeline Company,                 condemnation proceedings where
                                                   Persons who wish to comment only                                                                             compensation would be determined in
                                                on the environmental review of this                     LLC (Midship Pipeline) 1 in Kingfisher,
                                                                                                        Canadian, Grady, Garvin, Stephens,                      accordance with state law.
                                                project should submit an original and
                                                two copies of their comments to the                     Carter, Johnston, and Bryan Counties,                      A fact sheet prepared by the FERC
                                                Secretary of the Commission.                            Oklahoma and leased capacity on                         entitled ‘‘An Interstate Natural Gas
                                                Environmental commentors will be                        existing pipeline infrastructure in                     Facility on My Land? What Do I Need
                                                placed on the Commission’s                              Oklahoma, Texas, and Louisiana. The                     To Know?’’ is available for viewing on
                                                environmental mailing list, will receive                Commission will use this EIS in its                     the FERC Web site (www.ferc.gov). This
                                                copies of the environmental documents,                  decision-making process to determine                    fact sheet addresses a number of
                                                and will be notified of meetings                        whether the project is in the public                    typically asked questions, including the
sradovich on DSK3GMQ082PROD with NOTICES




                                                associated with the Commission’s                        convenience and necessity.                              use of eminent domain and how to
                                                environmental review process.                             The Commission previously solicited                   participate in the Commission’s
                                                Environmental commentors will not be                    public input on the MIDSHIP Project in                  proceedings.
                                                required to serve copies of filed                         1 The sponsor of the Midcontinent Supply Header
                                                documents on all other parties.                         Interstate Pipeline Project, previously identified as     2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the

                                                However, the non-party commentors                       Cheniere Midstream Holdings, Inc., has changed its      environmental staff of the FERC’s Office of Energy
                                                will not receive copies of all documents                name to Midship Pipeline Company, LLC.                  Projects.



                                           VerDate Sep<11>2014   17:14 Mar 27, 2017   Jkt 241001   PO 00000   Frm 00041   Fmt 4703   Sfmt 4703   E:\FR\FM\28MRN1.SGM    28MRN1



Document Created: 2017-03-28 00:31:54
Document Modified: 2017-03-28 00:31:54
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Time on April 12, 2017.
FR Citation82 FR 15353 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR